MONTHYEARML21070A0502021-03-11011 March 2021 Notice of Pre-Application Meeting for the Crystal River 3 Reactor Pressure Vessel Package Project stage: Meeting PMNS20210594, 5/25/21 Notice of Pre-Application Meeting for the Crystal River 3 Reactor Pressure Vessel Package2021-05-0404 May 2021 5/25/21 Notice of Pre-Application Meeting for the Crystal River 3 Reactor Pressure Vessel Package Project stage: Meeting ML21160A0812021-06-0909 June 2021 Summary of May 25, 2021 Meeting with Orano Federal Services Encl 1 Meeting Attendees Project stage: Meeting ML21160A0822021-06-11011 June 2021 Encl 2: Public Presentation - CR3MP Crystal River 3 Middle Package 2nd NRC Meeting Project stage: Meeting ML21244A4852021-08-31031 August 2021, 1 September 2021 Orano Federal Services, LLC, Submittal of Safety Analysis Report for the CR3MP Package, Rev. 0 Project stage: Request ML21244A4892021-08-31031 August 2021 Orano Federal Services, LLC, CR3MP Safety Analysis Report, Revision 0 Project stage: Other ML21244A4862021-09-0101 September 2021 Orano Federal Services, LLC, Submittal of Safety Analysis Report for the CR3MP Package, Rev. 0 Project stage: Other ML21244A4872021-09-0101 September 2021 Orano Federal Services, LLC, Affidavit Project stage: Other ML21286A8002021-10-15015 October 2021 Enclosure 1 - Request for Supplemental Information and Observation for the Model No. CR3MP Package Project stage: Other ML21286A7982021-10-15015 October 2021 Request for Supplemental Information for the Review of the CR3MP Package Project stage: Request ML21286A7992021-10-15015 October 2021 Request for Supplemental Information for the Review of the CR3MP Package Project stage: Approval ML22006A3662021-12-22022 December 2021 Enclosure 1: Affidavit Pursuant to 10 CFR 2.390 Project stage: Other ML22006A3652022-01-0606 January 2022 Orano Federal Services, LLC, Response to Request for Supplemental Information for the Review of the Model No. CR3MP Package Project stage: Supplement ML22033A5412022-01-31031 January 2022 Orano Federal Services, LLC, Table of Changes for CR3MP Safety Analysis Report, Revision 2 Project stage: Other ML22006A3692022-01-31031 January 2022 Enclosure 4: CR3MP Transport Package Safety Analysis Report, Revision 1 Project stage: Other ML22006A3702022-01-31031 January 2022 Enclosure 5: Table of Changes for CR3MP SAR Revision 1 Project stage: Other ML22033A5372022-02-0202 February 2022 Review of the Orano Federal Services Updated Safety Analysis Report (Revision 2) for the Model No. CR3MP Package Project stage: Other ML22175A0442022-06-24024 June 2022 Letter Request for Additional Information for the Review of the Model No. CR3MP Package Project stage: RAI ML22356A3132022-12-19019 December 2022 Orano Federal Services, LLC Submittal of RAI Responses and SAR Revision 3 for the CR3MP Package Project stage: Other ML22356A3182022-12-19019 December 2022 Enclosure 5 - Table of Changes for CR3MP SAR Revision 3 Project stage: Other ML22356A3142022-12-19019 December 2022 Enclosure 1 - Responses to NRC Request for Additional Information on the Model No. CR3MP License Project stage: Response to RAI ML22356A3162022-12-31031 December 2022 Enclosure 3 - CR3MP Transport Package Safety Analysis Report, Revision 3 Project stage: Other ML23113A0122023-05-0202 May 2023 Encl 1 - Request for Additional Information CR3MP Project stage: RAI ML23159A2772023-05-31031 May 2023 Enclosure 4: CR3MP Transport Package Safety Analysis Report, Revision 4 (Non-Proprietary Version) Project stage: Other ML23159A2752023-06-0808 June 2023 Enclosure 2 - Non-Proprietary Responses to NRCs Second Request for Additional Information on the Model No. CR3MP License Application Project stage: Request ML23159A2732023-06-0808 June 2023 Orano Federal Services, LLC Response to Second Round Request for Additional Information for the Review of the Model No. CR3MP Package Project stage: Request ML23208A1472023-08-0404 August 2023 Special Package Authorization for the CR3 Middle Package(CR3MP) - Docket No. 71-9393 Project stage: Other ML23208A1442023-08-0404 August 2023 Special Authorization for the Crystal River 3 Middle Package CR3MP Project stage: Request ML24109A2992024-04-18018 April 2024 Orano Federal Services, LLC - Request for Extension of CR3MP Special Package Authorization, EPID L-2021-NEW-0003 Project stage: Request 2022-01-06
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 15, 2021 Mr. Philip W. Noss Licensing Manager Orano Federal Services LLC 505 S. 336th Street Suite 400 Federal Way, WA 98003
SUBJECT:
REQUEST FOR SUPPLEMENTAL INFORMATION FOR THE REVIEW OF THE MODEL NO. CR3MP PACKAGE
Dear Mr. Noss:
By letter dated September 1, 2021 (Agencywide Documents Access and Management System
[ADAMS] Accession No. ML21244A485), Orano Federal Services LLC submitted an application for approval of the CR3 Middle Package (CR3MP). Staff performed an acceptance review of your application to determine whether it contains sufficient technical information in scope and depth to allow the staff to complete a detailed technical review.
The information needed to continue our review is described as a request for supplemental information (RSI) in the enclosure to this letter. Please note that addressing these RSIs does not preclude the staff from issuing further requests for additional information (RAIs) during the course of the detailed technical review of this application. The RSI responses should be provided by December 3, 2021. If the RSI responses are not received by this date, the application may not be accepted for review and the staff may discontinue any further review.
Please reference Docket No. 71-9393 and Enterprise Project Identifier (EPID) No. L2021-NEW-0003 in future correspondence related to this request.
Sincerely, Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 71-9393 EPID L-2021-NEW-0003
Enclosure:
RSI Pierre M.
Saverot Digitally signed by Pierre M. Saverot Date: 2021.10.15 13:55:03
-04'00'
ML21286A798 (pkg), ML21286A799 (ltr), ML21286A800 (encl)
E=With attachment/enclosure N=No copy C=Without attachment/enclosure OFFICE DFM E
DFM C
DFM DFM C
DFM C
DFM C
NAME PSaverot JBorowski ZCruzPerez WWheatley JMcKirgan DATE 09/22/2021 09/23/2021 09/23/2021 10/14/2021 10/14/2021