Construction Reactor Oversight Process Resources Report August 2021ML21216A194 |
Person / Time |
---|
Issue date: |
08/04/2021 |
---|
From: |
NRC/NRR/VPOB |
---|
To: |
|
---|
Gaslevic J |
References |
---|
Download: ML21216A194 (5) |
|
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21216A1942021-08-0404 August 2021 Construction Reactor Oversight Process Resources Report August 2021 ML21064A3652021-03-0101 March 2021 Dashboard Report 3-1-2021 ML21036A0812021-02-0101 February 2021 Dashboard Report 2-1-2021 ML20343A0742020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20314A0962020-11-0202 November 2020 Dashboard Report 11/02/2020 ML20162A1242020-07-18018 July 2020 NRC Staff Presentation for June 18, 2020, Public Meeting ML19295D4672019-10-30030 October 2019 Public Meeting for ITAAC Hearing Process, October 30, 2019 ML19297E9612019-10-30030 October 2019 ITAAC Hearing Process - Final Public Presentation 10-30-19 ML19297E9292019-10-30030 October 2019 Pager for 10-30-19 Public Meeting - ITAAC Hearing Process for New Reactors 2023-02-02
[Table view]Some use of "" in your query was not closed by a matching "". Category:Slides and Viewgraphs
MONTHYEARML23291A0352023-12-31031 December 2023 2023 Hfes NRC Slides Digital and Conventional MCR Designs ML23268A4002023-09-18018 September 2023 Application of Digitization in Regulated Inspection Activities ML23156A2432023-06-0505 June 2023 Issued Amendments List for Vogtle Electric Generating Plant Units 3 and 4 (Updated 6-2-23) ML23072A1802023-03-13013 March 2023 2023 RIC Powerpoint Slide Presentation, Vogtle 3: Journey from Construction to Operations ML23033A0232023-02-0202 February 2023 Dashboard Report 2-2-2023 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22319A1242022-11-15015 November 2022 NRC Slides for November 15, 2022 Public Meeting on Part 52 Lessons Learned ML22278A0382022-10-0505 October 2022 Dashboard Report 10-5-2022 ML22265A0982022-09-22022 September 2022 NRC Slides on Part 52 Lessons Learned Construction Initiative for Public Meeting on 9/27/2022 ML22206A1682022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1712022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22201A0442022-07-20020 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 20, 2022 ML22144A0492022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22144A0502022-05-24024 May 2022 Dashboard Report 5-24-2022 ML22060A0072022-02-28028 February 2022 4Q 2021 Performance Summary U4 ML22060A0062022-02-28028 February 2022 4Q 2021 Performance Summary U3 ML22026A0582022-01-26026 January 2022 Dashboard Report 1-26-2022 ML21333A2172021-11-29029 November 2021 Readiness Group Presentation During 12-2-21 Public Meeting ML21216A1942021-08-0404 August 2021 Construction Reactor Oversight Process Resources Report August 2021 ML21188A3592021-07-0606 July 2021 1Q 2021 Performance Summary U3 ML21188A3612021-07-0606 July 2021 1Q 2021 Performance Summary U4 ML21188A3622021-07-0606 July 2021 Archives ML21064A3652021-03-0101 March 2021 Dashboard Report 3-1-2021 ML21036A0782021-02-0101 February 2021 Dashboard Report 02/01/2021 ML21036A0812021-02-0101 February 2021 Dashboard Report 2-1-2021 ML21008A0042021-01-0404 January 2021 Dashboard Report 1-4-2021 ML21008A0052021-01-0404 January 2021 Dashboard Report 1-4-2021 ML20343A0742020-12-0202 December 2020 Dashboard Report 12-2-2020 ML20314A0962020-11-0202 November 2020 Dashboard Report 11/02/2020 ML20162A1242020-07-18018 July 2020 NRC Staff Presentation for June 18, 2020, Public Meeting ML19295D4672019-10-30030 October 2019 Public Meeting for ITAAC Hearing Process, October 30, 2019 ML19297E9612019-10-30030 October 2019 ITAAC Hearing Process - Final Public Presentation 10-30-19 2023-09-18
[Table view]Some use of "" in your query was not closed by a matching "". Category:Status Report
MONTHYEARML22348A0872023-07-25025 July 2023 Enclosure - VEGP Unit 4 - 103g - Final Memorandum Table ML23093A0872023-04-0303 April 2023 ITAAC Review Status Report 04/03/2023 ML23093A0862023-04-0303 April 2023 Dashboard Report 4-3-2023 ML23060A0602023-03-0101 March 2023 Dashboard Report 3-1-2023 ML23060A0642023-03-0101 March 2023 ITAAC Review Status Report 3-1-2023 ML23045A0882023-02-14014 February 2023 3Q 2022 Performance Summary Vogtle Unit 4 ML23045A0072023-02-13013 February 2023 Archives ML23038A0082023-02-0707 February 2023 Construction Reactor Oversight Process Resources Report February 7, 2023 ML23033A0242023-02-0202 February 2023 ITAAC Review Status Report 2-2-2023 ML23003A0192023-01-0303 January 2023 ITAAC Review Status Report 1-3-2023 ML23003A0202023-01-0303 January 2023 Dashboard Report 1-3-2023 ML22335A0332022-12-0101 December 2022 ITAAC Review Status Report 12-1-2022 ML22335A0372022-12-0101 December 2022 Dashboard Report 12-1-2022 ML22335A0432022-12-0101 December 2022 Construction Reactor Oversight Process Resources Report December 1, 2022 ML22307A0332022-11-0303 November 2022 ITAAC Review Status Report 11-3-2022 ML22307A0352022-11-0303 November 2022 Dashboard Report 11-3-2022 ML22284A0192022-10-11011 October 2022 Construction Reactor Oversight Process Resources Report October 11, 2022 ML22278A0372022-10-0505 October 2022 ITAAC Review Status Report 10-5-2022 ML22244A0642022-09-0101 September 2022 Dashboard Report 9-1-2022 ML22244A1472022-09-0101 September 2022 ITAAC Review Status Report 9-1-2022 ML22230C5532022-08-18018 August 2022 ITAAC Review Status Report 8-18-2022 ML22224A1272022-08-12012 August 2022 Dashboard Report 8-12-2022 ML22224A1282022-08-12012 August 2022 ITAAC Review Status Report 8-12-2022 ML22214A0822022-08-0202 August 2022 2Q 2022 Performance Summary Vogtle Unit 4 ML22210A0422022-07-29029 July 2022 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Review Status Report Final ML22208A1002022-07-27027 July 2022 ITAAC Review Status Report 7-27-2022 ML22206A1682022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1712022-07-25025 July 2022 Dashboard Report 7-25-2022 ML22206A1822022-07-25025 July 2022 ITAAC Review Status Report 7-25-2022 ML22206A1862022-07-25025 July 2022 ITAAC Review Status Report 7-25-2022 ML22201A0422022-07-20020 July 2022 Icn Review Status for Vogtle Unit 3 as of July 20, 2022 ML22201A0442022-07-20020 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 20, 2022 ML22200A0162022-07-19019 July 2022 Icn Review Status for Vogtle Unit 3 as of July 19, 2022 ML22200A0222022-07-19019 July 2022 Icn Review Status for Vogtle Unit 4 as of July 19, 2022 ML22200A0232022-07-19019 July 2022 Voices Dashboard Report for Vogtle Unit 3 as of July 19, 2022 ML22200A0262022-07-19019 July 2022 Voices Dashboard Report for Vogtle Unit 4 as of July 19, 2022 ML22192A0282022-07-11011 July 2022 ITAAC Review Status Report 7-11-2022 ML22192A0272022-07-11011 July 2022 ITAAC Review Status Report 7-11-2022 ML22192A0232022-07-11011 July 2022 Dashboard Report 7-11-2022 ML22192A0202022-07-11011 July 2022 Dashboard Report 7-11-2022 ML22187A0212022-07-0606 July 2022 Construction Reactor Oversight Process Resources Report July 6, 2022 ML22186A0392022-07-0505 July 2022 ITAAC Review Status Report 7-5-2022 ML22186A0412022-07-0505 July 2022 ITAAC Review Status Report 7-5-2022 ML22186A0342022-07-0505 July 2022 Dashboard Report 7-5-2022 ML22186A0332022-07-0505 July 2022 Dashboard Report 7-5-2022 ML22178A0902022-06-27027 June 2022 ITAAC Review Status Report 6-27-2022 ML22178A0892022-06-27027 June 2022 ITAAC Review Status Report 06/27/2022 ML22178A0752022-06-27027 June 2022 Dashboard Report 6-27-2022 ML22178A0742022-06-27027 June 2022 Dashboard Report 06/27/2022 ML22173A0132022-06-22022 June 2022 Dashboard Report 6-22-2022 2023-07-25
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
CONSTRUCTION REACTOR OVERSIGHT PROCESS RESOURCES The U.S. Nuclear Regulatory Commission (NRC) staff originally estimated that direct inspection will require 35,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> per unit over the course of a 5-year nuclear power plant construction project. As of August 4, 2021, revised estimates are approximately 42,100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> for Vogtle Unit 3 and 28,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for Vogtle Unit 4. These revised estimates include:
- 19,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for inspections related to ITAAC for Vogtle Unit 3, and 11,100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> for Vogtle Unit 4;
- 12,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> for construction and operational program inspections for Vogtle Unit 3, and 6,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> for Vogtle Unit 4;
- 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events;
- and 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for technical support of construction inspections.
Table 1 and figure 1 show the total number of direct inspection hours expended through August 4, 2021, for Vogtle Units 3 and 4.
Table 1: Actual Total Construction Inspection Program Resource Expenditures Unit ITAAC Inspection Program Reactive/Allegation- Technical Total Hours/Percentage Inspections Related Inspections Support*
of Planned Inspections Vogtle, 17,202 / 90% 10,631 663 2,200 30,696 Unit 3 Vogtle, 8,006 / 72% 5,862 454 1,397 15,719 Unit 4
- To date, NRC Headquarters technical staff inspection support has not been linked to a specific docket and has not been fee billable. Therefore, it is not possible to distinguish the technical support hours expended by the Office of Nuclear Reactor Regulation on each unit. In Table 1, the total hours expended on technical support have been split between the units.
August 4, 2021 35000 30000 25000 20000 15000 10000 5000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2021 Proj Hours Vogtle, Unit 3, Cumulative Data Vogtle, Unit 4, Cumulative Data Figure 1 Total cumulative direct inspection hours for Vogtle, Unit 3 and 4 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2021 Vogtle, Unit 3, ITAAC direct inspections Proj Hours Vogtle, Unit 4, ITAAC direct inspections Figure 2 Cumulative ITAAC-related direct inspection hours for Vogtle, Units 3 and 4 Figure 2 summarizes the direct inspection hours expended for inspections related to ITAAC since the start of construction at Vogtle Units 3 and 4. The staff estimates that there will be approximately 19,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> of direct inspection related to ITAAC for Unit 3 and 11,100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> of direct inspection related to ITAAC for Unit 4.
18000 16000 14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2021 Proj Hours Vogtle, Unit 4, Program direct inspection Vogtle, Unit 4, QA direct inspection Vogtle, Unit 3, Program direct inspection Vogtle, Unit 3, QA direct inspection Figure 3 Cumulative quality assurance and program inspection for Vogtle, Units 3 and 4 Figure 3 summarizes the NRC staff resources in hours expended for programmatic inspection since the start of construction at Vogtle, Units 3 and 4. Based on Vogtles schedule, total cumulative program inspections are estimated at 12,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> for Vogtle Unit 3, and 6,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> for Unit 4.
3000 2500 2000 1500 1000 500 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2021 Proj Hours Vogtle, Unit 3, Reactive and Allegations Vogtle, Unit 3, HQ Technical Support Vogtle, Unit 4, Reactive and Allegations Vogtle, Unit 4, HQ Technical Support Figure 4 Cumulative reactive and technical support hours for Vogtle, Units 3 and 4 Figure 4 summarizes the direct inspection hours expended for reactive and allegation inspections and hours spent providing technical support for inspections since the start of construction at Vogtle, Units 3 and 4. The staff has not identified a need to revise the estimate of 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events, or the 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> estimated for technical support for construction inspections.