AGENDA 2
LICENSING Evaluating Design Changes During Construction 3
198 Completed Actions 5 Licensing Actions Under Review 3 Future Licensing Actions Licensing Actions for Vogtle 3 and 4 (Amendments, Exemptions, and Code Alternatives)
ITAAC Inspections, Tests, Analyses, and Acceptance Criteria 4
UIN: Uncompleted ITAAC Notification ICN: ITAAC Closure Notification
ITAAC Inspections, Tests, Analyses, and Acceptance Criteria 5
UIN: Uncompleted ITAAC Notification ICN: ITAAC Closure Notification
Inspection: Verifying ITAAC completion Over 25,000 Hours of Direct Inspection at Unit 3 6
0 10,000 20,000 30,000 TECHNICAL SUPPORT REACTIVE PROGRAMS ITAAC INSPECTION TOTAL DIRECT INSPECTION HOURS
Inspection:
The Reactor Oversight Process for an AP1000
Passive design resulted in an inspection procedure reassessment.
7
Next Steps Towards A 52.103(g) Finding
- Dates estimated based upon Unit 3 fuel load of November 23, 2020
- Assumes all prerequisites for Final Commission Memorandum and 52.103(g) Finding are met
N R C. G O V (301) 415-7000 or 1-800-368-5642 Key Search Terms: NRC - VRG - ITAAC - SAFETY Contact Us! Stay Informed!