ML20162A124 AGENDA 2
LICENSING Evaluating Design Changes During Construction 3
Licensing Actions for Vogtle 3 and 4 (Amendments, Exemptions, and Code Alternatives) 5 Licensing Actions Under Review 198 Completed Actions 3 Future Licensing Actions
ITAAC Inspections, Tests, Analyses, and Acceptance Criteria 4
UIN: Uncompleted ITAAC Notification ICN: ITAAC Closure Notification
ITAAC Inspections, Tests, Analyses, and Acceptance Criteria 5
UIN: Uncompleted ITAAC Notification ICN: ITAAC Closure Notification
Inspection: Verifying ITAAC completion Over 25,000 Hours of Direct Inspection at Unit 3 6
T O TAL I TAAC I N S P E C T I O N P R O G R AM S R E AC T I V E T E C H N I C AL S U P P O R T 0
10,000 20,000 DIRECT INSPECTION HOURS 30,000
Inspection:
The Reactor Oversight Process for an AP1000 7
Passive design resulted in an inspection procedure reassessment.
Next Steps Towards A 52.103(g) Finding
- Dates estimated based upon Unit 3 fuel load of November 23, 2020
- Assumes all prerequisites for Final Commission Memorandum and 52.103(g) Finding are met