IEMA Response to GE Hitachi Morris Draft Ea. Review of the Draft Environmental Assessment and Finding of No Significant Impact for the Morris Operation Decommissioning Funding Plans
ML21166A206
Person / Time
Site: 07200001
Issue date: 06/04/2021
From: Horn K
State of IL, Emergency Management Agency
To: John Mckirgan
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
Download: ML21166A206 (2)


Text

ILLINOIS EMERGENCY MANAGEMENT AGENCY JB Pritzker Alicia Tate-Nadeau Governor D irector June 4, 2021 John McKirgan, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S Nuclear Regulatory Commission Washington, DC 20555

Subject:

REVIEW OF THE DRAFT ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT FOR THE MORRIS OPERATION DECOMMISSIONING FUNDING PLANS

Dear Mr. McKirgan:

The Illinois Emergency Management Agency (!EMA/Agency) appreciates the U.S. Nuclear Regulatory Commission (NRC) providing our Agency the opportunity to review and comment on the Draft Environmental Assessment and Finding of No Significant Impact for the Morris Operation Decommissioning Funding Plan (EA) . IEMA reviewed both the EA and the GE Hitachi Nuclear Energy Americas, LLC, Morris Operation, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan, Revision 4 (DFP) to determine potential impacts to the state of Illinois. As such, IEMA would like to make the following comments:

  • The DFP, as presented, lacks an estimation for the total volume of low-level radioactive waste (LLRW) to be generated during the decommissioning process. Therefore, is not clear to IEMA how GE Hitachi determined an estimated cost associated with transportation and disposal of LLRW.
  • Section 13 of the Illinois Low-Level Radioactive Waste Management Act establishes a fee schedule for LLRW generated within Illinois. Because the DFP lacks granularity, IEMA is unable to determine if GE Hitachi has included an estimated cost associated with LLRW fees to be assessed by the IEMA.

1035 0L"TI.R P ARK DR IVE I SPRIN Cl*ll :LD, IL 62704 I 217.782.2700 illino is.gov / iema I ready.illinois.gov

Page 2 of 2 In genera l, IEMA believes the EA and DFP to be sufficient in context; however, until the NRC provides IEMA with clarification to our comments, we cannot concur with the NRC's Finding of No Significant Impact.

Again, IEMA would like to thank the NRC for the opportunity to review and provide comment on the EA and DFP for the GE Hitachi Morris Facility. We look forward to working w ith you on the resolution of our comments in order to achieve our common goal - the health and safety of the public and the environment through the safe and secure use of radioactive material.

Since rely,

!~

Head of Environmental Management Division of Nuclear Safety Illinois Emergency Management Agency Cc: Kristina Banovac/ NRC Adnan G Khayyat/ IEMA 11.1.JNOIS E~IERCF.NCY :'IL\N,\GF.MF.NT .-\GisNCY 1035 0LTF.R P A RK DRI VI \ I S PRIN(;l-11*:LD, IL 62704 I 217.782.2700 illinois.gov / iema I ready.illi.nois.gov