Technical Assistance Request - Review of Physical Security Plan for the Three Mile Island Unit 1 Power Station Independent Spent Fuel Storage Installation
ML21166A118
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 06/15/2021
From: Bruce Watson
Reactor Decommissioning Branch
To: Alison Rivera
NRC/NSIR/DPCP/MSB
Ted Smith, 301-415-6721
References
CAC 000078, EPID L-2021-SPR-0004
Download: ML21166A118 (3)


Text

June 15, 2021 MEMORANDUM TO: Alison L. Rivera, Chief Materials Security Branch Division of Physical and Cyber Security Policy Office of Nuclear Security and Incident Response Signed by Watson, Bruce FROM: Bruce A. Watson, Chief on 06/15/21 Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards

SUBJECT:

TECHNICAL ASSISTANCE REQUEST - REVIEW OF PHYSICAL SECURITY PLAN FOR THE THREE MILE ISLAND UNIT 1 POWER STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION The Division of Decommissioning, Uranium Recovery and Waste Programs (DUWP), Office of Nuclear Material Safety and Safeguards (NMSS), requests technical assistance from the Division of Physical and Cyber Security Policy (DPCP), Nuclear Security and Incident Response (NSIR), for the completion of the following project:

PROJECT: Review Three Mile Island Unit 1 Station (TMI-1) Independent Spent Fuel Storage Installation (ISFSI) Only Physical Security Plan and license amendment request (Agencywide Documents Access and Management System Accession No. ML21127A173).

DOCKET NO .: 50-289 CAC/EPID NO: 000078/05000289/L-2021-SPR-0004 REQUESTED ACTION: NMSS/DUWP requests NSIR/DPCP review of the Physical Security Plan for the TMI-1 Station ISFSI only, following completion of their dry storage campaign.

Prepare a memorandum documenting the results of NSIRs review.

CONTACT: Ted Smith, NMSS/DUWP 301-415-6721

A. Rivera Please provide the information requested below and return a completed copy to the DUWP/RDB Project Manager designated below.

Name of NSIR/DPCP assigned Reviewer: Douglas Garner NSIR/DPCP Project Completion Date:

NSIR/DPCP Branch Chief Signature: _________________________________

The above CAC/EPID No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.

The above CAC/EPID No. should be referenced in future correspondence related to this request and in the Human Resources Management System for recording staff time expended on this effort.

Memo ML21166A118 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NAME TSmith TS BWatson BW DATE Jun 15, 2021 Jun 15, 2021