ML20244C800

From kanterella
Jump to navigation Jump to search
Insp Rept 50-298/89-19 on 890501-05 & 15-19.Violation Noted. Major Areas Inspected:Licensee Actions in Response to NRC Requirements for Motor Operated Valve Testing & Programs for Instrument Calibr & Piping Supports
ML20244C800
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/02/1989
From: Singh A, Stetka T, Wagner P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20244C796 List:
References
50-298-89-19, IEB-85-003, IEB-85-3, IEIN-87-004, IEIN-87-4, NUDOCS 8906150143
Download: ML20244C800 (23)


See also: IR 05000298/1989019

Text

- _ _ _ ..

..

,

.

,

'

.

,

APPENDIX 8

,

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-298/89-19

Operating License: DPR-46'

Docket: 50-298

Licensee:

Nebraska Public Power District (NPPD)

P.O.' Box 499

-Columbus. NE . 68602-0499

Facility Name: Cooper Nuclear Station (CNS)

cInspection At: CNS. Brownsville, Nebraska

Inspection Conducted: May 1-5 and 15-19, 1989

Inspectors:

W Me

'

G,- 2- 69

'

P. C. Wagner, Reactor Inspector, Plant Systems

Date

Section.-Division of Reactor Safety

\\i b L d

shhv

A. S'ingh, Rfactor Inspect (r. Plant Systems

Datb

Section, Division of Reactor Safety-

[LYW

J

.

N Idl24

2 cf7

Approved:

T. F. Stetka, Chief, Plant Systems Section

Date

Division of Reactor Safety

Inspection Summary

Inspection Conducted May 1-5 and 15-19,'1989 (Report 50-298/89-19)

Areas Inspected: Routine, unannounced inspection of the licensee's actions in

response to NRC requirements for motor operated valve (MOV) testing and the -

licensee's programs for instrument calibration and piping supports. The

inspection included gathering survey information related to drywell

~

,

'

temperatures and diesel fuel oil storage and handling, and discussions of the

implementation of Regulatory Guide 1.97 instrumentation. The NRC inspectors

also reviewed the corrective actions related to the Type SJO electrical cable

problems and the actions completed in response to previous NRC inspection-

findings.

I

h

O

. _ - _ .

-

-

.

..

,

'

'

i

,

~2-

,

Results: Within the scope of the inspection, one violation of_NRC requirements

was identified (paragraph 3.b). The violation involved two examples where

component testing was performed utilizing instrumentation which had not been

calibrated. The NRC inspectors found the MOV testing program to'be good but

limited in scope in that only' those valves covered by IE Bulletin' 85-03 were -

being tested. .The NRC inspectors also considered the basis for the repair of

the SJO cable to be less substantial than would have been desirable.

The NRC inspectors determined that the calibration program'for instruments

listed in the Technical Specifications to be a good program.

l

l

l

l

l

1

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _

._

__

_ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _

_

_ _ _ _ _ _ _

-

_-

_ - _ _ _ _ _ -_

_-

.

.

. ; .i

'

'

s

L:

..

1

,l

i

e

-3-

-

p.

.

e

s

J

,

!

DETAILS

t

'

~

%

l.

Persons Contacted

-

3

,

'

NPPD

++L. Bray, Regulatory Compliance Specialist

+ R. Brungardt, Operations Manager

4

"

+ B. Fehrman, Project Manager

  • J. Flaherty, Plant Engineering Supervisor

+*S. Freborg, Assistant Plant Engineering Supervisor-

+*R. Gardner, Maintenance Manager

B._ Jansky, Outage and Modification Manager

  • J. Hall', Mechanical Supervisor
+*G. Horn, Plant Manager, Nuclear Operations

+ H. Jantzen. Instrument and Controls (I&C) Supervisor

+ L. Kohles, Nuclear Project and Construction Manager

+*E. Mace, Engineering Manager

+*J. Meacham, Senior Manager of Operations

  • D. Robinson, Quality Assurance (QA) Supervisor ^

+ G. Smith, QA Manager, CNS

NPPD - Columbus Office (via telephone)

4 J. Branch, Supervisor, Engineering

+ A. Heymer, Manager, Configuration Management

+ S. McClure Manager, Nuclear Engineering

+ H. Parris, Vice President Production

+ G. Smith, Licensing Supervisor

+ G. Trevors Division Manager, Nuclear Support

+ K. Walden, Licensing Manager

'

+ R. Wilber, Division Manager, Nuclear Engineering and Construction

+ V. Wolstenholm, Division Manager. QA

NRC, Region IV

+ J. Jaudon, Deputy Division Director, Division of Reactor. Safety.

  • L. Ellershew, Reactor Inspector
  • W. McNeill, Reactor Inspector

.

+ L. Gilbert, Reactor Inspector

  • G. Pick, Resident Inspector

+ W. Bennett, Senior Resident Inspector

'

'

  • Denotes personnel present at the May 5, 1989, exit meeting.

+ Denotes personnel present at the May 19, 1989, exit meeting.

The NRC inspectors also contacted and interviewed other NPPD personnel

'

during the performance of this inspection.

,

i

.

> .

]

, .

1

.-

,

J

-

.

-

.<.

.

,

)

.

i

2.

Motor Operated Valves (25573)

Because of problems identified with the torque switch and limit switch

settings of important motor operated valve (MOV) actuators, the NRC issued

IE Bulletin (IEB) 85-03. The.IEB was provided to ensure that switches

l

were set and maintained so as to accomodate the most severe loadings

expected during a design basis event. NRC inspection guidance was

a

provided in Temporary Instruction (TI) 2515/73.

.

NRC inspection of the licensee's response to IEB 85-03 was initiated in

l

,

~ November 1987 and documented in NRC Inspection Report 50-298/87-30. The

i

-

IEB remained open pending completion of the MOV testing. The MOV testing

at CNS was performed utilizing the "M0 VATS" system and equipment.

Subsequent to the initial NRC inspection, NPPD provided additional'

information in response to IEB 85-03 in letters dated June 2 and

September 20, 1988. The NRC requested some clarification to the NPPD

submittals by letter dated November 9,1988, which NPPD provided in their

January 9, 1989, respcnse.

The NRC technical review of the licensee's response is contained in-

subparagraph a. below. The NRC inspection of the remaining requirements of

i

TI 2515/73 are contained in subparagraphs b. through d. below. 'A

i

discussion of NPPD review results related to NRC Information Notices is

contained in subparagraph e. below,

a.

Technical Review of IEB 85-03 Submittals,

,

Review of the licensee's January 9,1989, response and their letter

i

of June 2,1988, in response to Supplement 1 of IEB 85-03, indicates

that their selection of the applicable safety-related valves to be

l

addressed and the valves' maximum differential pressures meet the

requirements of the IEB and that the program to assure valve

~

operability requested by action item e. of the 'IEB and its supplement

is now acceptable.

.

b.

Procedure Review

-

The NRC inspector reviewed the Maintenance Procedures (MP) related; to

MOVs listed in Attachment 1 to this report. The NRC inspector found

all of the procedures to contain easily understood, detailed,

step-by-step instructions. The procedures also included frequent

requirements for independent verification of actions. There were a.

total of 96 MOVs listed in MP-7.3.36, but only 19 of these MOVs were

included in the IEB 85-03 testing program. The 19 MOVs included in

l

the IEB 85-03 program consisted of.10 Reactor Core Isolation

Cooling (RCIC) system and 9 High Pressure Coolant Injection (HPCI)

system valves; all of the valves except 1 RCIC and 1 HPCI were DC

motor operated. During discussions with licensee personnel about the

l

M0 VATS program, the NRC inspector was informed that the remaining DC

l

MOVs will be MOVATS tested in the fall of 1989 (see paragraph e.

!

below).

!

!

1

!

4

4

_ __

~~

l

..

.

,

'

.

_$

>

'

.

!

c.

,T_rai ni ng

Since paragraph 6.5 of MP-7.3.~a5-1 required qualified personnel to

perform or supervise the MOVATS testing, the NRC inspector reviewed

the training program. lesson plans listed in Attachment 1.

The three

M0V lessons, along with their related 1sberatory exercises, were

prerequisites for the M0 VATS training course. The NPC inspector

found all of the lesson plans to contain sufficient detail for the

functions to Le performed.

The NRC inspector also noted that EQP-011-02-03 included maintenance

update information from Limitorque Corporation (the MOV vendor) and

information on DC motor cable sizing (see paragraph e. below).

d.

MOV Testing

NRC Inspection Report 50-298/87-30 stated that 6 of the 19 IEB 85-03

listed MOVs would be required to be tested under pressure. This

statement was based on an August 3.1987, letter to NPFD f rom M0 VATS

Incorporated; subsequently, NPPD provided MOVATS additional

information, and by letter dated March 22, 1988 MOVATS rescinded

their earlier recommendation on the need to test the valves at

pressure.

The NRC inspector reviewed the records for the MOV testing completed

in April and May 1968, on 10 of the 19 MOVs listed in NP?D's

January 9, 1989, submittal to ensure that prcoer testing had been

performed. While the HRC inspector found the testing records to be

'

properly completed with acceptable results, he noted that two valves

had new actuators installed prior to the tests and that five other

valves had the actuator spring packs replaced.

In eddition, all of

f

the MOV actuators were cleaned and lubricated prior to testing.

!

Therefore, the NRC inspector questioned how the operability prior to

{

testing designated in the NPPD letter had been determined.

NPPD

l

,

personnel stated that the initial operability determination was based

3

on the testing performed in 1986; the questions arising from any

abnormal indications during those tests and the results of

evaluations performed subsequent to those tests led to the

replacements noted in the 1988 test records.

The replacement

-

activities were performed to enhance the MOV operations not to

provide operability.

The NRC inspector also questioned how the MOVs had been relubricated,

specifically concerning the possibility of mixing the old and new

lubricants. The licensee personnel stated that the lubrication had

properly consisted of cleaning all of the old grease from the

mechanism and then applying fresh, approved grease.

l

._

_____---___ _ - -

.

.

.

.

.

-

-6-

,

,

e.

DC Motor MOV Activit,ies

i

The NRC issued Information Notices (ins) 88-72, " Inadequacies.in the

l

Design of DC Motor Operated Valves;" and 89-11. " Failure of DC Motor-

l

Operated Valves to Develop Rated Torque Because'of Improper Cable

Sizing," to alert licensees of potential problems. The NRC inspector

discussed the. status of NPPD's efforts to evaluate the conditions

l

presented in the ins with the responsible corporate engineer. The

NRC inspector was informed that NPPD had evaluated the active valves

included in the IEB 85-03 listing (i.e., those valves required to

reposition during an accident) and had found them to be acceptable.

The 125VDC valves were evaluated in calculations NED 89-131C and D;

the 250VDC valves in NED 89-131A and B.. The NRC inspector briefly

reviewed those preliminary calculations and found 'them to contain

conservative assumptions. The calculations concluded that adequate

current would be provideo'to the actuator motors to produce the

required torque for valve operation. The torque values were stated .

to have been calculated in accordance with vendor methodology and the

current values were calculated using the presently installed motor

.

feeder cables. NPPD engineering personnel stated that some DC motor

starting _ resistors had been previously removed based on a Limitorque

maintenance recommendation. The NPPD engineering. personnel also

stated that the remaining DC motor MOVs would be evaluated after the

in progress refueling outage, and that those evaluations were expected

to be completed in the fall of 1989.

The NRC inspector found the MOV testing program that had been implemented

at the CNS in response to IEB 85-03 to be a good program. The NRC

inspector, however, recommended that NPPD consider expanding the scope of

that program to include additional safety-related valves.

No violations or deviations were identified.

3.

Cal.brations

(56700)

In order to ascertain if the licensee had implemented a program for the

calibration of installed plant instrumentation that was in accordance with

regulatory requirements and accepted industry guidance, the NRC inspector

reviewed selected plant documents. The documents reviewed included

calibration, surveillance and testing procedures, and the. records of the

completion of those procedures. A partial listing of the documents

reviewed is contained in Attachment I to this report.

.

a.

Technical Specification Instruments

The NRC inspector reviewed a number of Calibration and Function Test

procedures for Technical Specification (TS) listed instruments and

found them to be acceptable. The majority of the procedures had been

revised within the preceding year into a new, more easily followed,

format. The NRC inspector noted attributes such as: readability;

l

i

'

.

{

+

.

.

-7-

,

.

easily understood, step-by-step instructions; clearly stated caution

statements, limits and tolerances; and requirements for independent

verification for return to service and for documenting any noted out

of tolerance conditions.

The NRC inspector also noted that the procedures required a

management review of the post-test / calibration data. The NRC

inspector questioned how trending of data was accomplished and was

informed that the systems engineers informally tracked and trended

test results.

l

The NRC inspector also noted that most of the TS listed instruments

were required to be functionally tested once per month and calibrated

once per 3 months.

Further, the functional test procedures usually

performed a calibration check.(e.g., a pressure source was connected

to the pressure transmitter and varied to ensure proper response).

The NRC inspector found both the calibration frequency and the

functional test complexity.to be more than usually experienced.

The NRC inspector reviewed the 1988 and 1989 test and calibration

records for those instrument procedures that had been reviewed. The

records were all complete, containing such attributes as proper

sign-offs for completed evolutions and postimplementation

i

verifications and' reviews, documentation of the test equipment

utilized, and the initiation of nonconformance reports for out of -

tolerance conditions when discovered. The NRC inspector questioned

how the three times normal setpoint for the Main Steam Radiation

Monitor (Surveillance Procedure (SP) 6.1.4) was determined and was

directed to SP 9.4.3.

Review of SP 9.4.3 indicated that the detector

was calibrated by exposure to a traceable radiation source and that

the normal,100 percent power, background radiation level, in the

area of the main steam line monitor, was determined prior to return

,

to service from each refueling outage by calculating an average from

!

the previous cycle data.

{

The NRC inspector also questioned how the HPCI pump low discharge

,

flow setpoint of 2.4 inches water gauge (wg) contained in

i

.

SP 6.2.2.3.13 was determined. A review of the scaling factors showed

j

!

that the TS setpoint of 400 gpm was calculated to represent a

l

1.92-inch wg differential pressure at the flow transmitter based on

the flow element curves. The procedure setpoint of 2.4-inch wg

provided an acceptable margin to ensure flows greater than the IS

required minimum.

I

Based on the sample reviewed, the NRC inspector found the calibration

program for those instruments listed in the TS to be a good program.

l

The NRC inspector had no further questions on the program and no

violations or deviations were identified,

i

I

. _ _ - _ _ . _ _ . _ . _ _ _

. _ _ _ _ _

_.~

'

.

,

I

,

.

-8-

,

.

b.

Nontechnical Specification Instruments

l

In order to ensure that the licensee was implementing an acceptable

j

calibration program for those instruments which were utilized in

j

safety-related functicas but were not specifically identified in the

i

1

TS..the NRC inspector reviewed operating.and surveillance procedures

and selected a sample.of instruments utilized therein to detemine

f

proper equipment operability.

(1) Emergency Diesel Generator (EDG) Operability

The NRC inspector reviewed the EDG Operability. Test Procedure

(SP 6.3.12.1) and selected five parameters listed on the data

sheets for review of the calibration status of the instruments

utilized during the testing of No. 2 EDG. The review of the

calibration records disclosed the following:

Jacket Water Temperature - Temperature Indicator DG-JW-3145

was calibrated on a 4-year interval in accordance with

Preventative Maintenance Procedure (PM) 01470.

Lube Oil Filter Inlet and Outlet - Pressure Gauges PI-3143

and -3145 were not on a scheduled calibration program,

but had been calibrated in November 1986 as part of another

work item.

Voltage, Frequency, and Current - Local electrical meters

i

were not on a scheduled calibration program and had not had

their calibration checked since initial startup in 1973.

l

The NRC inspector reviewed applicable procedures and records and

verified that the protective functions (e.g., low lube oil

pressure, overcurrent, differential overcurrent, etc.) were

calibrated on an acceptable frequency. However, the NRC

inspector also reviewed the procedure for shutdown outside the

control room (Emergency Procedure 5.2.1) and noted that the

local meters and gauges discussed above were utilized to operate

and protect the EDGs during the performance of that procedure.

j

Violation (298/8919-01): The failure to have a procedure which

ensured the proper, routine calibration of the local instrumentation

utilized to verify the proper operation of the EDGs is an

apparent violation of TS 6.3.3.D.

(2) Core Spray (CS) System Operability

i

The NRC inspector selected another system to evaluate if the.

J

instruments utilized during the surveillance test were being

calibrated. The CS Operability Test (6.3.4.1) contained data

!

sheets for the inservice test of CS pumps A and B which

I

specified the instruments to be utilized during the test. The

l

NRC inspector selected pump discharge flow, inlet pressure,

I

1

)

l

_

-

.

l

q

.

.

.

-9-

.

.

outlet pressure, and motor current as the parameters-important

to operation.

Review of calibration records disclosed the

following:

1

i

Discharge Flow - FI-50B was calibrated on a quarterly

frequency..

,

1

Pump Pressures - PI-36B and -48B were calibrated on'an

q

annual frequency.

j

,

Motor Current - CSP 1B Ammeter was not included in a

i

,

l

scheduled calibration program.

!

The NRC inspector reviewed the calibration records for the pump

.

discharge flow and pressures and found them to be acceptable;;

l

however, the motor ammeters had not had calibration verified

i

since the initial startup testing in 1973.

The failure to have a procedure to calibrate routinely

instrumentation used during the performance of surveillance

testing of the CS system is an additional example of the

apparent violation described in paragraph 3.b(1) above.

,

4.

Electrical Cable Repairs

(92701)

The NRC insper, tor questioried'if the preliminary notifications

(PNO-ADSP-89-01) issued on March 23, 1989, for a problem identified at--the

Browns Ferry Nuclear Facility was applicable to the CNS. The problem

involved the deterioration of the Buna-S rubber insulatior. on the Type SJO

electrical cable provided by General Electric Company (GE). . The conductor

insulation had become hard and brittle and had developed cracks. .NPPD

personnel stated that they had been informed of the problem by both GE and

the Institute of Nuclear Power Operations (INPO) and had identified

approximately 89 installations of the SJO ceble at.the CNS..

l

The SJO cables at the CNS were either 2 or 3 conductor, 18 AWG wire size,

and usually provided as interconnecting wire. The cable had the

appearance of normal appliance cord, similar to what would be used on an

electric drill. The problems with the cable at the'CNS included instances .

in which the insulation was completely missing from both conductors. The

exposed portions of the conductor insulation had been brittle and in most

cases had developed radial cracks; however, the portions of the insulation

that had remained covered by the cable's PVC outer jacket material had not

become brittle and remained flexible. NPPD had samples of the removed

cable analyzed by GE and were verbally informed that the unexposed

portions of the Buna-S insulation remained acceptable for continued used.

NPPD evaluated the cable problem and determined that continued use of the

SJO cable pending final corrective action recommendations by GE was ,

acceptable provided the cables were reterminated. The determination

_ _ _ _ _ _ _ - _ _

-

.

'

, . .

y

,

,

.

'

-10-

,

,

.

process included the removal'ofLpreviously exposed portions of Buna-S'

insulation -stripping the cable' jacket back to allow relugging of the

freshly exposed conductors, then reterminating. ,The NRC inspector was

informed that=these interim actions were in accordance with GE

.

recommendations. . NPPD also referenced the 3-year expected shelf-storage.. -

life for'SJO cable ~ listed in Military Standardization Handbook for Rubber

Products (MIL-HDBK-695C, 27 March 1985) 'as additional bases for~the

i

continued'use of reterminated cables;

Inspector Followup Item-(298/8919-02): While the NRC 'nspector dId not

i

determine that continued interim use of SJO ' cable would. be detrimental to

_

safe plant operations, followup inspection of the long-term corrective-

actions will.be performed to ensure that the SJO cables are replaced prior

,

L

to exceeding their expected service lifetime.

,i

5.'

Postaccident Monitoring Instrumentation -(25587)

'

By letter dated December 17,1982,(Generic' Letter 82-33)theNRCprovided

H

all reactor licensees and applicants with the " Requirements for Emergency

)

Response Capability."

Included in these requirements was.the application

l

of. RG 1.97 " Instrumentation for Light Water Cooled Nuclear Power Plants -

to Assess Plant and Environs Conditions During and Following an Accident."

,

The provisions for the instrumentation described in RG I.97 were endorsed

1

by the NRC to ensure that nuclear power plant operators w9uld havel

j

l

sufficient and reliable information available for preventing and/or

!

mitigating the consequences of a reactor accident. The NRC inspector

d

initiated the inspection of this instrumentation in accordance with

TI 2515/87.

j

!

The NRC inspector reviewed the NRC Safety Evaluation' dated October 27.

l

L

1986, and noted that some of the instrumentation being utilized at the CNS

j

'

differed from that described in NPPD's December.4, 1985, submittal. NPPD

1

engineering personnel discussed the changes and indicated that the

!

installed instrumentation was an enhancement to that originally proposed. .

-!

NPPD personnel had consnitted' to have the RG 1.97 instrumentation operable

>

l-

prior to restart from the in-progress refueling outage and stated that the

]

commitment would be met.

l

l

The NRC inspector made'a brief tour of the control room to verify that all

!

!

of the RG 1.97, Category I, instruments were installed, including required

redundancy and recorders. The NRC inspector found that the licensee had'

!

installed appropriate instrumentation; however, additional inspection

i

activity will be required to ensure that the implementation of RG 1.97 at.

I

the CNS meets the NRC acceptance criteria. -NPPD personnel agreed to

update their December 4,1985, response to indicate clearly which

instruments were being utilized to fulfill the CNS commitments. The

updated. response will be submitted by August 21, 1989.

!

No violations or deviations were identified.

1

>

e

-____m_________..__s.____

_ _ _ _ _ . _ _ . _ _ _ _ _

_

e

>

i

4

<

j

.

.

,

,

.

~

-11-

, ,

6 .'

Information on Drywell Temperatures '(25598)'

Because of occurrences of higher than anticipated temperatures inside

]

containments (PWRs) and drywells'.(BWRs), the NRC issued TI 2515/98 to

obtain plant specific data. The average temperature profiles requested in

Exhibit I to TI 2515/98 were to be'used to determine if the high-

temperatures previously identified were plant specific problems or.

l

indicative of a'more generic problem.

!

The NRC inspector compiled the data requested by the' TI and attached a

copy of the completed Exhibit I as Attachment 2 to this report.

No violations or deviations were identified.

7.

Information on Diesel Fuel Oil

(255100)

In order to verify that the licensee had implemented a program to maintain

adequate quality of the fuel oil for the EDGs, the NRC inspector

implemented TI 2515/100. This TI also requested information in the form

of appended questions. The survey was completed and is included as

'

l

Attachment 3.

The NRC inspector found the CNS programs to be acceptable but' questioned

the normal alignment of running both portions of the duplex fuel filter in

parallel instead of one side or the other. Licensee personnel stated that

no fuel oil problems had ever been encountered at the CNS.

I

No violations or deviations were identified.

,

8.

Testing of Piping Support and Restraint' Systems (70370)

The purpose of this inspection was to ascertain whether the licensee had

established an adequate program and procedures pertaining to the

examination and testing,of piping and restraint systems;"

1

e.

Procedure Review

'

The NRC inspector reviewed the CNS second 10-year Inservice

Inspection (ISI) Plan submitted to, and approved by, the NRC on

January- 27, 1986. The NRC inspector also reviewed the implementing

procedures for the ISI plan listed below:

Procedure No.

Title

Date

1

6.3.10.9.1

Surveillance Procedure, Snubber

02/28/89

1

Revision 15

Operability

7.2.34.1

Snubber Inspection

'02/09/89

Revision 1

,

-

,

1-

,

'

..

,

.

-12-

,

,

-

,

7.2.34.2

Pipe Snubbers Removal and

01/17/89

Revision 1

Installation

IV3-W812

Visual Examination VT-3

02/19/88

)

Revision 3

l

1

IV4-W812

Visual Examination VT-4

,.02/18/87

Revision 2

ED-88-C4

InserviceInspection(ISI) Activities

03/28/89

]

Revision 1

)

,

'7.2.57

Maintenance Procedure for ASME

08/30/88

l

Revision 1

Category F-A, F-B, and F-C Components

Supports, Inspection, and Adjustment

7.2.34.7

Grinnell Figure 200/201 Hydraulic

03/15/88

Revision 0

Snubber Functional ~ Test

7.2.34,8

Pacific Scientific Snubber Functional

03/15/88

Revision 0

Test

l

60-1

Receipt, Review, and Recording

01/20/89

I

Revision 0

Calculations

60-2

Preconstruction Review of Proposed

01/20/89

Revision 0'

Pipe Support Modifications

60-3

Large Bore Piping and Pipe Support

01/20/89

Revision 0

Design Criteria

60-4

Piping Analysis Procedure

01/20/89

Revision 0

Procedures reviewed by the NRC inspector appeared to be adequate.

b.

Field Observations of Pipe Supports

The NRC inspector examined approximately 50 snubbers and pipe

supports of various types and on various systems. Attributes

selected for visual examination were:

deterioration, corrosion, physical damage, or deformations were

not evident;

all required bolts, locking devices, nuts, and washers were

installed;

l

1

extension rods, support plates, and connecting joints were not

j

deformed, or loose;

J

i

l

- _ _ _ _ _ _

l

,

'F

V

,

-

M

" .'

'

'

"

.

,

,

,

/~

'

,

,

'

', . ,

.-13 =

n

.

..

,

snubber, settings;

,

pipes supports, or other associated equipment or components-

were not restricted or in contact with other surfaces 1 as a-

. result.of thermal expansion;

-

springs in hangers were not obstructed by foreign' material; .

,

indicators or spring hangers show either " cold"'or " hot"

'-

position, consistent with plant condition;-and-

3

,

threaded connections'were secured by locknuts, fasteners, and

'

cotter pins.

Snubbers and supports examined are listed below:.

~

Snubbers

<

MS-SIB

MS-S16A

RH-59

RH-SIO

_ _

SW-H23A through H23H

RH-552

,

RH-536

RH-537

MS-513A

MS-S13B

MS-S17-

Supports

RH-H47A

RF-HSS.

MS-H101A

l

RCC-S86

SW-S29A

RCC-S67-

SW-H149

RH-H56B

RH-H41A'

BS-H92

RCC-S61

RH-H74

RF-H42A-

RH-H17A

RH-H75

HP-H34

RH-H61A

RCC-S69

SW-H137

MS-H104-

RCC-H65

CRD-BB5

RH-H96A

- RCC-H69~

MS-H113

CS-H19A

RH-H50

'

RCC-H137-

SW-H184

,

RCC-H138

SW-H181

RCC-H139

RH-H71

Overall', the pipe supports examined a'ppeared acceptable. The NRC

l

inspector also noted, during the walkdown, that several modifications

I

were in progress.

&

a

_ _ _ _ _ _ - _ _ _

'

>

.

.

-14-

.

.

c.

Inservice Tests for Snubbers

The NRC inspector witnessed functional testing on the snubbers.

Observations by the NRC inspector indicated the following:

Personnel performing the testing were qualified.

Proper instructions and procedures were followed.

The functional ~ test machine and accessories were calibrated as

required.

As-found drag force, activation / acceleration and as-left drag

force were within acceptable limits.

The licensee's testing program was being conducted by NPPD personnel

and was found to be adequate.

The licensee has established an adequate program and implementing

procedures for the examination and testing of pipe supports,

d.

Operability Evaluation of Essential Piping Systems for CNS

During this inspection, the-NRC inspector also reviewed the

licensee's long-term plan for achieving full code qualification of

all essential large bore pipe supports. The licensee committed to

this plan in a letter to the NRC dated August 12, 1988. The licensee

submitted a contractor prepared report (CYGNA Report 88037A) which

contained a detailed evaluation of 122 supports. This report showed

that those Class IN pipe supports met the design criteria for full

code qualification. However, on May 12, 1989, the licensee reported

that they had been informed by their contractor ~ (CYGNA) that they had

identified two pipe supports included in the above report which

required modifications to satisfy the design criteria. Based upon

this report, the NRC inspector stated his concern about the code

qualification of the remaining supports. As the result of this

concern, the licensee committed to rereview all the remaining

calculations to ensure that they meet the design criteria and, if

required, to implement modifications prior to plant startup.

No violations or deviations were identified.

9.

Action on Previous Inspection Findinos

(Closed) Open Item (298/8627-01):

Completion of design change

package (DCP) reviews for final closecut. An NRC inspector reviewed six

DCPs and noted that they had not been closed even though the physical

modification effort had been completed. The NRC' inspector reviewed the

completion records of the previously reviewed DCPs and found them to be

..

__-

_

1,9

'

.

.-. w

,F

+-

.

,

,

4

,

,

,

,

'

-15-

,

,

.

.

I

acceptable. However, the completion of these DCPs appeared to be

protracted (e.g., the work on DCP 83-023.was finished in Apr11'1986, but-

the DCP was not closed until April 1989). Since the DCPs' referenced in.

the earlier NRC inspection report had been properly. closed, this open-item.

is closed.

'

,

,

,

.

.-

(Closed) Violation (298/8817-01): The use:of " green tags".during the

performance of an integrated. leak rate test (ILRT) was: not" properly -

,

implemented (green tags.were used to designate proper alignments for

testingconditions).

In response'to this NRC' finding, NPPD committed'to

. provide, training on the use of the green equipment tags. .The NRC

inspector reviewed the General Employee Industry Safety.Trainir.g Lesson

Plan (Revision 2) and noted the inclusion of a discussion on the reasons.

for, and proper'use of, the_. green tags. The NRC inspector also verified,

through a review of training plans, that the required training had been-

conducted..

10. Exit Meetings (30703)

The NRC inspectors summarized the scope and-findings of the inspection

during exit meetings conducted on May 5 and 19,1989, with the personnel

identified in paragraph 1 above. The licensee acknowledged the NRC

inspectors' findings and agreed to provide the submittals discussed in

paragraphs 5 and 8, of this report. The licensee did not identify as

proprietary any of the material provided to, or reviewed-by,' the NRC;

inspectors during this inspection.

., -

,

,

$

>

-_A__--__-___-_-__-..___.__-

.-

-

- .__ ____ ________ _________ _ _ _ _ -

'

I

.

.

ATTACHMENT 1

.

LIST OF DOCUMENTS REVIEWED

M_otor Operated Valves Procedures-

7.3.35.1, " Testing of Motor Operated Valves Using Motor Operated Valve

Analysis and Testing System (M0 VATS)," Revision 1

7.3.35.2, " Periodic Monitoring of Motor Operated Valves Using M0 VATS Motor

Load Unit," Revision 0

l

7.3.35.3, " Periodic Monitoring of Motor Operated Valves Using M0 VATS Motor

l

Torque Unit," Revision 0

7.3.36, " Limit and Torque Switch Checkout and Adjustment for Rising Stem

Limitorque MOVs," Revision 3

M0 VATS Training Lesson Plans

Troubleshooting and Repair of MOVs:

EQP 011-02-01 and related laboratory - 051

"

EQP 011-02-02 and related laboratory - 052

EQP 011-02-03 and related laboratory - 053

MOVATS Data Acquisition:

EQP 011-05-01

Calibration and Function Test Procedures

6.1.4, " Main Steam Line Radiation Monitor," Revision 40

6.1.5, "High Reactor Pressure Transmitter," Revision 16

i 9, "Lw Reactor Vessel Transmitter," Revision 23

6.1.4.1, " Main Steam Line Process. Radiation Monitor," Revision 2

6.2.2.3.4, " Emergency CST Level Transmitter," Revision 19

6.2.2.3.13. "SPCI Pump Low Flow Transmitter," Revision 17

7.3.6.2, " Diesel Generator Annual Electrical Inspection," Revision 1

7.3.1.2 " Timed and Instantaneous Overcurrent Relay Testing and

Calibration," Revision 3

7.3.1.3, " Differential Current Reley Testing and Calibration," Revision 2

9.4.3 " Main Steam Line Process Radiation Monitor," Revision 6

__-

- _ - - - - . _ - .

.__

_-

_,

'

ii

'

.

,

,1

,

i

-.-

,-

,

1

.

,

'

-2--

, , . .

.

1

System / Component Surveillance Procedures

6.3.4.1, " Core: Spray System.0perability Test,"iRevision 25

. _

.

1

-

6.3.4.3, " Sequential Loading of Emergency Diesel Generators," Revision 26:

1

6.3.12.1, " Diesel Generator Operability: Test," Revision 27

i

6.3.12.3, " Diesel Fuel _ Oil Quality Test," Revision 10

'l

7.2.53.1, " Diesel Generator Engine Mechanical Inspection," . Revision ~ 0

1

14.17.1, "DG-1 Annual. Inspection," Revision 0

'

Operating / Emergency Procedures

.

1

>

5.2.1,"ShutdownfromOutsidetheControlRoom," Revision 718(

,

<

!

i

!

l

l

i

_!

'a..

I

_mm--__m-_A-__.__._

_ - - _ ______-

'

,

.

.

.

'

ATTACHMENT 2

.

Tl 2516/98 - Exhibit 1

1.

Plant Name: Cooper Nuclear Station (CNS)

l

2.

Unit and Docket Number:

50-298

'

3.

What are the average containment /drywell (C/D) temperatures during power

operation as recorded by the licensee? Note: We are interested in the

peak operating temperatures during the hottest summer months.

Average weighted temperatures from July 18 through September 27, 1988,

ranged from approximated 130'F to 148'F. These weighted averages were

calculated in accordance with the Daily Surveillance Log

n

(Procedure 6.2.4.1).

A discussion of deywell temperatures is included in

3

paragraph 3.1.1 of NRC Inspection Report 50-298/88-200.

4.

Containment temperature at which the plant is licensed to operate (i.e..

operating temperature specified in.the FSAR).

The CNS USAR Section V.2.3.2 states that the drywell is designed for an

internal pressure of 56 psig coincident with a temperature of 281*F.

l

5.

Review the temperature readings and provide your assessment n to whether

or not you believe the average temperature readings accurately reflect

y

containment /drywell conditions, or if there is a significant difference,

-

due to temperature sensor location or stratification of containment

atmosphere which could produce hot spots.

The temperature readings are a weighted average of the temp'eratures at

five points within the drywell; in addition, seven other drywell

temperature points are recorded.

Temperature sensing locations are

denoted on Figure 1 attached.

6.

What temperature (s) is used by the licensee in its equipment environmental

qualification program when calculating the remaining qualified lifetime

for all equipment inside C/D, and are these temperatures consistent with

temperatures being experienced?

A temperature of 150*F was used in the equipment qualification program. A

review of temperature data showed that some local areas exceed the 150 F

by up to 25 F during the period discussed in 3 above.

7.

Administrative temperature limit for the containment /drywell, if no-

technical specification limit exists.

Although the temperature instruments are listed in the Technical

Specifications, no temperature restrictions are included. An

administrative limit on average temperature is 150*F.

8.

Recent history of temperatures inside containment.

Provide C/D average

air temperature in addition to the containment air temperatures used to

_ _ _ _ - _ _ - _ _ _

.___

. _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .__ __ _ -

_ _ _ _

r

..

.

e

'

-2-

,

,,

.

compute the averaga C/D temperatures for the months of April, May, June,

July, August, and September 1987, if the plant has not operated during

those months, uro an operating period close to these months.

Temperature Element

l

l

1987 : 505A

505B

505C

5050

505E

Apr :

132

129

137

130

143

May :

142

140

147

141

153

Jun :

141'

139

148

142

161

Jul

148

146

155

148

156

Aug :

154

154

163

155

164

Sep :

137

136

146

140

145

t

_ -__- - _ _ _ - - _ _ _ . _ _ . . - _

. , '

a

$

i

s

.. ,

.

7%.

Ro,

"

" ;p

gx

,

y 3.

J-z

e

- y--

-

-g-

-.

..

==

.:,

-

"

"

% % '# %

"

"

"

m

,,,

2A

2A

/

2B

,,

2B

-

/e

,_

-

d*

c._

% lw 4Wl

.A::;1

>

_

-

,.. _

--

_

-

X

/

3

"

l

%

,/ %,[

/

.

+--@

ka

kA

@T*

j

1

-

--

r w__

AIR RING HEADER

DRYWELL VENTILATION RECIRCULATION

FIGURE 1

- _ _ _ _ - _ _ _ - _ _ _

- _ .

-

_-______ __- - -

.

.

,

'

.

' ' '

ATTACHMENT 3

.

i

SURVEY OF LICENSEE'S RESULTS TO

SELECTED EDG F0 ISSUES

PLANT NAME AND UNIT:

Cooper Nuclear Station

1.

Has the licensee adequately reviewed and evaluated IE Information Notice 87-04 issued on January 16, 1987, as a result of the AND Unit 2 EDG

F0 starvation event which occurred on June 27, 19867

Review of the NPPD engineering response dated March 6, 1987, and the

Operating Experience Review Transmittal which was closed on March 31,

1987, indicated on adequate review and evaluation.

,

2.

Does the licensee have a permanent F0 storage tank recirculation system

which allows for complete F0 inventory cleaning by filtering each

refueling outage to remove accumulated particulate?

No.

3.

Are all F0 storage tanks being cleaned and inspected at a minimum of

10-year intervals in accordance with of Regulatory Guide 1.137?

Yes, in accordance with Section VIII.C.2 of Reference 2.

4.

Does the licensee's F0 program include a regular analysis of F0 samples

and bottom testing for accumulated water, at the lowest point in the F0

day tanks and F0 storage tanks?

Yes, monthly and after use in accordance with Reference 2.

5.

Is a fuel additive being used as a fuel stabilizer which will function to

prevent oxidation and bacterial growth?

Yes, a stabilizer (Power Service Diesel Fuel Supplement) is added in

accordance with Reference 1.

6.

Does the licersee effectively ensure that periodic F0 bottom sampling and

analysis are heing performed to detect high particulate concentrations in

the F0 supply which occurs over long-term storage due to the effects of

oxidaticn, and biological contamination in accordance with ASTM D270-19757

Yes, every 6 months in accordance with Section VIII.C.1 of Reference 2.

7.

Are day tanks and integral tanks being checked for water monthly, as a

minimum, and after each operation of the diesel where the period of

operation was I hour or longer?

Yes, in accordance with Section V.B.5 of Reference 2.

. . .

.

___ _-______ - _ - -

s

'

,

a

-2-

,.

.

8.

Is accumulated water removed immediately if it is determined that water is

present in the storage, integral or day tanks?

Yes, in accordance with Section VIII.A.3 of Reference 2.

'

9.

Is the licensee replacing F0 in a short period of time (about a week) if

it is determined that the F0 does not meet the applicable specifications?

Yes, in accordance with Section V.B.2 of Reference 2.

10. Are F0 components which may be prone to fouling being routinely monitored

for indications of~ fouling?

Fuel injector nozzles are tested and the fuel filters are replaced during

the performance of Reference 3.

11. Are F0 filters and strainers being cleaned and inspected on a periodic

basis per the vendor recommendations?

Fuel filters are replaced annually (see No.10 above) and fuel strainers

are inspected each cycle in accordance with PM 04779.

12. Does the F0 system utilize dual element filters and strainers which

permits on line cleaning of the elements, in the event of fouling, to

allow continuous operation of the EDG7

There is a single strainer in the suction to each pump)with a duplex

filter in the common discharge line (mounted on engine .

13.

Is there a differential pressure indicator for each duplex filter / strainer

for indication of fouling in accordance with ANSI N195-19767

No.

14. Are F0 alams annunciated in the main control room or incorporated into a

general control room trouble alarm with local individual alams, in

accordance with ANSI N195-1976?

Fuel oil alams are annunciated in the control room and locally.

15. Are any of the instruments that perform a control function and provide an

alarm seismically qualified in accordance with the IEEE Recommended

Practices for Seismic Qualification of Class IE Equipment for Nuclear

Power Generating Station, IEEE-344-1975?

The criginal design did not include seismic qualification; however,

replacement parts are being qualified.

. _ _ _ _ _ _ _ _ _

___

3;

'

,

,

,,

'

j;>:

g

,

i*

>

f.-

.

<

< s

.

.

-t

,

-3 ~ '

,s.'

,

, _

,

I

6

References:

>

.

j .

1.-

OP 2.1.16 Revision 11; " Heating Boiler andiDiesel Fuel Oil Unloading" ,

SP 6.3.12.3. Revision 10, " Diesel Fuel Oil-Quality Test" .. l. Inspection"-

2.

SP 7.2.53.1, Revision 0, " Diesel. Generator Engine Mechanica

3.

4.

Drawing 2011, Sheet 1,;" Diesel Oil System"' .

,

'

5.

Drawing 2077, " Flow Diagram - Diesel Generator Auxiliary Systems"

,,

,

u

,

, ,

'p

s

W

t

1

I, t

l'

1

,

i

I

,

'1

a

-

i

[-