Responds to 861208 Request for Review of Util Revised Licensed Operator Requalification Program for Facilities. Discrete Programs Submitted Comply W/Either App a to 10CFR50 or HR Denton
ML20215K687
Person / Time
Site: Millstone, Haddam Neck, 05000000
Issue date: 06/22/1987
From: Stolz J
Office of Nuclear Reactor Regulation
To: Mroczka E
CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO.
References
TAC-64137, TAC-64138, TAC-64620, NUDOCS 8706250416
Download: ML20215K687 (3)


Text

_

J June 22,1987 Docket Hos.: 50-213, 50-245 and 50-336 Mr. Edward J. Mroczka Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company and Connecticut Yankee Atomic Power Company Post Office Box 270 l

Hartford, Connecticut 06141-0270

Dear Mr. Mroczka:

SUBJECT:

LICENSED OPERATOR REQUALIFICATION PROGRAMS FOR MILLSTONE UNITS 1 AND 2 AND HADDAM NECK PLANT (TAC Nos. 64137, 64138 and 64620)

]

By letter dated Decemb'er 8,1986, Northeast Utilities, in accordance with J

10 CFR 50.54, requested a review of their revised licensed operator requalification programs for the Haddam Neck Plant and Millstone Nuclear Power Station, Units 1 and 2.

Additional information was submitted by your letter dated April 15, 1987 which was provided in response to our request dated February 24, 1987.

J Based upon our review of your December 8,1986 and April 15, 1987 submittals, I

we conclude that the three discrete programs submitted for review meet the 1

criteria of either 10 CFR 55, Appendix A or the H. R. Denton letter of I

March 28, 1980. The above criteria are in effect until the new 10 CFR 55 1s effective.

Sincerely,

{

{

{

/s/

John F. Stolz, Director Project Directorate I-4 Division of Reactor' Projects I/II cc: See next page DISTRIBUTION Docket file p NRC & Local PDRs i

PDI-4 Reading S. Varga B. Boger S. Norris D. Jaffe OGC-Bethesda-E. Jordan 8706250416 870622 J. Partlow PDR ADOCK 05000213 y

PDR ACRS (10)

[GrayFile]

F. Akstulewicz 1

M. Boyle l

LAPDI-4 PD P

SN N D1 tsr JS 6/44/87-6 {7 Zfj7 6/21/

s

Mr. Edward J. Mroczka Haddam Neck Plant &

Connecticut Yankee Atomic Power Company Millstone Nuclear Power Station, Northeast Nuclear Energy Company Unit No. I g

1 CC:

Gerald Garfield, Esquire

.Kevin McCarthy, Director

-1 Day, Berry & Howard Radiation Control Unit Counselors at Law Department of Environmental-1 City Place Protection Hartford, Connecticut 06103-3499 State Office Building Hartford, Connecticut 06106 Wayne D. Romberg Vice President, Nuclear Operations Board of Selectmen Northeast Utilities Service Company-Town Hall 06103 Post Office Box 270 Haddam, Connecticut Hartford, Connecticut. 06141-0270 i

Superintendent State of Connecticut Haddam Neck Plant Office of Policy and Management RFD #1 i

ATTN:.Under Secretary Energy Post Office Box 127E

]

. Division East Hampton, Connecticut 06424

)

80 Washington Street.

Hartford, Connecticut 06106 Resident Inspector Haddam Neck Plant Richard M. Kacich, Manager c/o U.S. NRC Generation Facilities Licensing East Haddam Post Office Northeast Utilities Service Company East Haddam, Connecticut 06423 Post Office Box 270 Hartford, Cennecticut 06141-0270 Regional Administrator, Region I.

U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Northeast Nuclear Energy Company ATTN: Superintendent Millstone Nuclear Power Station P.O. Box.128 Waterford, Connecticut 06385 Resident Inspector l

c/o U.S. NRC Millstone Nuclear Power Station.

P.O. Cox 811 Niantic, Connecticut 06357 First Selectman.of the Town '

l of Waterford d

Hall of Records j

200 Boston Post Road

.I Waterford, Connecticut 06385 i

u d

Q Ct -

Mr. John F. Opeka Millstone Nuclear Power Station Northeast _ Nuclear Energy Company Unit No. ?

cc:

Gerald Garfield, Esq.

Mr.' Wayne D. Romberg Day, Berry 8.Howard Superintendent Counselors at Law Millstone Nuclear Power Station i

City Place P. O. Box 128 Hartford, Connecticut 06103-3499 Waterford, Connecticut 06385 1

Regional Administrator, Region I Mr. Edward J. Mroczka U.S. Nuclear Regulatory Commission Vice President, Nuclear Operations Office of Executive Director for Northeast Nuclear Energy Company

' Operations P. O. Box 270

~631' Park Avenue

. Hartford, Connecticut.06141-0270 Ving of Prussia, Pennsylvania 19406 Mr. Charles Brinkman, Manager Washington Nuclear Operations C-E Power Systems Combustion Engineering, Inc.

i 7910 Woodmont Avenue

^

Bethesda, Maryland _20814-Mr. Lawrence Bettencourt, First Selectman Town of Waterford Hall of Records - 200 Boston Post Road Waterford, Connecticut 06385 Northeast Utilities Service Company ATTN: Mr. Richard R. Laudenat, Manager Generation Facilities Licensing Post Office Box 270 Hartford, Connecticut 06141-0270 Kevin McCarthy, Director Radiation Control Unit Department of Environmental Protection State Office Building Hartford, Connecticut 06106 Mr. Theodore Rebelowski U.S. NRC P. O. Box 615 Waterford, Connecticut. 06385-0615 Office of Policy & Management ATTN: Under Secretary Energy Division 80 Washington Street-Hartford, Connecticut 06106

.