ML20212P837

From kanterella
Jump to navigation Jump to search
Response Team Activities Insp Repts 50-445/86-01 & 50-446/86-01 on 851101-860131.Violations Noted:Nonconforming Conditions Not Identified Per QA Program Requirements & Failure to Field Test Cable Reels
ML20212P837
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/26/1986
From: Barnes I, Ellershaw L, Hale C, Will Smith, Tapia J, Wagner P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20212P745 List:
References
50-445-86-01-02, 50-445-86-1-2, 50-446-86-01, 50-446-86-1, NUDOCS 8609030306
Download: ML20212P837 (104)


See also: IR 05000445/1986001

Text

.

_

.-

.

i

!

APPENDIX E

'

'

COMANCHE PEAK RESPONSE TEAM ACTIVITIES INSPECTION REPORT

=

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

,

.,

-

'

,x,,-

.

,.NRC'InspectionReporE:, 50-445/86-01

cps:

CPPR-126

50-446/86-01

CPPR-127

7

'

7

-

Dockets:

50-445

Category:

A2

.

50-446~"

<

u"

w

[.

Licensee: . Texas Utilities Electric Company

Skyway Tower

-

-

400 North Olive Street

. : Lock Box 81

'

Dallas, Texas 75201

<

Facility Name:

Comanche $ Peak Steam Electric Station (CPSES), Units 1 and 2

,

Inspection At:

Glen Rose, Texas

~

Inspection Conducted:

January 1 - 31, 1986

/

d

Inspectors:

1

LY E. Ellershaw, Reactor Inspector, Region IV

Date /

CPSES Group

'

(paragraphs 1, 5, 8.b, 8.d-8.e, 9.e-9.m)

GAkab

-

9/n s%

C. J. Hal y Rdactor Inspector, Region IV

Date

CPSES Group

(paragraphs 1, 3.a

4, 6, 8.b)

Y $<%

8/M/%

[ W. F. Smith, Resident Reactor Inspector (RRI)

Date

Region IV CPSES Group

'(paragraphs 1, 8.c)

g[0gg $

p

G

.

.

-

-- -

. - . .

_

,

,

_ - - - - - - - -

.

- - - - -


-

-

--


,

~ N

i

~

'

z

,

.

,,

,

.\\

-;- t

l

p

s

,

-/-

4

e .

.

.

.

.

, n'

-

,

<0

-

-

-2-

,

,

3

_

w

1

,,. , ,

,

.

-:

.

-

>

,

.

h.D. d ac A

6 /19/66

^'

P.C. Wagner,ReactorIngector,RegionIV

Date

CPSES Group

(paragraphs 1, 3.b, 8.a, 9.a-9.d)

6lLif S(o

v

J

I. Tapih, R6ac

Inspector,. Region IV

Date

ragraphs 1, 7, 8.d.(4))

l

Consultants:

EG&G - J. Dale (paragraphs 1, 5, 8.b(13), 8 e.(7))

A. Maughan (par *agroplis 1, 3.b(1) - 3.b(28), 8.a(2) -

8.a(3),9.b)

W. Richins (paragraphs 1, 8.d(2) - 8.d(3), 8.d(5), 8.e(2),

8.e(6), 9.f - 9.g)

R. Vanderbeek (paragraphs 1, 3.b(34) - 3.b(37), 8.a(6),

8.a(8), 8.e(1), 8.e(4), 9.a)

V. Wenczel (paragraphs 1, 6.a - 6.g)

-

Parameter - J. Birmingham (paragraphs 1, 8.b(1) - 8.b(11))

J. Gibson (paragraphs 1, 3.b(5), 3.b(29) - 3.b(34),

3.b(38) - 3.b(39), 8.a(1), 8.a(4)'- 8.a(5), 9.c - 9.d)

K. Graham (paragraphs 1, 8.b(14), 9.k - 9.1)

D. Jew (paragraphs 1, 8.b(12), 8.d(1), 8.e(3), 8.e(5), 9.e,

-

9.h - 9.j)

q

Teledyne - J. Malo.nson (paragraphs 1, 6.h - 6.j)

f

Approved:

ASec-r+>

P/26/N

'I. Barnes, Chief, Region IV CPSES Group

Date

!

Inspection Sammary

Inspection Condected:

January 1-31, 1986 (Report 50-445/86-01; 50-446/86-01)

Areas Inspected:

Ncaroutine, unannounced inspection of applicant actions on

previous inspection f'. ridings, inspection process control, applicant processing

of ERC inspection findings, assessment of allegations, pipe support

modifications, and Comanche Peak Response Team (CPRT) issue

specific action

plans (ISAPs).

A sunimary of NRR and IE audit / inspection activities is provided

in paragraph 2'of this appendix.

,

.

___

_

_ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - . _ _ _ _

__ ._.___ _

-3-

Results:

Within the six areas inspected, two violations (nonconforming

conditions not identified in accordance with QA program requirements,

paragraphs 4 and 5; failure to perform field testing of cable reels,

paragraph 9.a) and two deviations (failure to comply with approved instructions

in performance of inspections, and inadequate engineering review during

preparation of an inspection checklist, paragraph 9.j.) were identified.

e

.c<

S

s -

(

4

-4-

DETAILS

,

1.

Persons Contacted

J. Adams, ERC Supervisor, Safety Significance Evaluation Group

S. R. Ali, TV3Co QA Staff Engineer, TUGCo Nuclear Engineering (TNE)

J. Arros, TERA Civil / Structural Issue Coordinator

W. Baker, Brown & Root (B&R) Project Welding Engineer

G. Benfer, Site QA Manager, Bahnson Services Co.

G. Bennetsen, B&R Quality Engineer (QE)

L. Bast, TUGCo Corrective Actions Supervisor

T. Birdwell, B&R Paper Flow Group

T. Blixt, BLR QE

D. Boydston, ERC Issue Coordinator

  • C. T. Brandt, TUGCo QE Supervisor (Ebasco)

C. I. Browne, Project Manager, R. L. Cloud & Associates

  • R. E. Camp, Assistant Project General Manager, Unit 1 (Impell Corp.)

J. D. Christenson, ERC Deputy QA/QC Review Team Leader

A. Contieu, TUGCo Training Coordinator- Non ASME

S. L. Crawford, ERC Issue Coordinator

M. Curland, ERC Special Evaluation Team (SET)

R. Curtis, TUGCo Senior Tech., Operations QA

  • D. E. Deviney, TUGCo Operations QA Supervisor

M. Evans, TUGCo Operations Machine Shop Foreman

J. Finneran, TUGCo Lead Pipe Support Engineer

J. R. Galzer, ERC Issue Coordinator

  • P. E. Halstead, TUGCo Site QC Manager
  • J.

L. Hansel, ERC QA/QC Review Team Leader

R. Haskovec, TUGCo Licensing

~

J. Hayworth, B&R ASME Inspector Training Coordinator

D. Hicks, TUGCo QC Supervisor

J. R. Honekamp, TRT Issues Manager, TERA ,

P,. Hooton, TUGCo Project Civil Engineer

D. J. Hudson, ERC Certification Administrator

A. Lancaster, TUGCo QA Surveillance Supervisor

P. Leyendecker, TUGCo QC Surveillance Supervisor

J. B. Leutwyler, B&R Electrical QC Supervisor

J. Mallanda, CPRT Electrical Review Team Leader

J. Maxwell, TUGCo Operations QC Supervisor

_

R. Melton, TERA Documentation Coordinator

  • J. T. Merritt, TUGCo Assistant Project General Manager

C. K. Mcehlman, TUGCo Project Mechanical Engine'er

M. Obert, ERC Issue Coordinator

C. Osborn, B&R Permanent Plant Records Vault (PPRV) Supervisor

G. W. Parry, QA Surveillance Supervisor

B. Parr, Authorized Nuclear Inservice Inspector, Hartford Steam Boiler

A. A. Patterson, ERC Reinspection Engineering Supervisor

G. R. Purdy, B&R QA Manager

G. W. Ross, ERC Onsite QA Representative

r

.

-5-

-

D. Sampson, B&R Receiving Inspection Supervisor

J. C. Smith, TUGCo Operations QA

C. Spinks, ERC Inspection Supervisor

D. Snow, B&R QA/QC Coordinator

P. Stevens,-TNE Electrical Engineer

J. F. Streeter, TUGCo Assistant to Executive Vice President

A. 3mithy, B&R Interim Records Vault Supervisor

J. Sutton, ERC SET

K. Thomton, B&R Warehousing Supervisor

-

'P. Turi, TERA Issue Coordinator

T. G. Tyler, TUGCo CPRT Program Director

W. I. Vogelsang, TUGCo Coordinator, Electrical and Instrumentation and

Controls

J. Wehlein, EBASCO Section XI Surveillances"

C. H. Welch, TUGCo QC Services Supervisor

  • J. R. Wells, TUGCo Director, QA

.J. E. Young, ERC Issue Coordinator

  • Denotes those persons who attended the exit interview.

The NRC inspectors also contacted other CPRT and applicant employees

during this inspection period.

2.

NRR and IE Audit / Inspection Activities

a.

NRR:

ANCO cable tray testing was observed at Culver City,

California, on January 8-9, 1986.

A site technical review was

performed on January 16, 1986, with respect to allegations in the

mechanical and structural areas.

A site audit was performed on

January 17, 1986, of activities being performed in the review of

heating, ventilation, and air conditioning (HVAC) supports.

An audit

was performed on January 21, 1986, at R. L. Cloud Associates,

Berkeley, California, with respect to the random calculation overview

approach on EBASCO and Impell activities in the cable tray and

conduit support effort.

Impell was audited at Concord, California,

on January 22, 1986, with respect to activities in the safeguards

building cable tray and conduit support effort.

An audit was

performed on January 27, 1986, at Stone and Webster, New York City,

New York, with respect to status of piping analysis special technical

issues,

b.

IE:

A site inspection was performed on January 16-17, 1986, relative

to TERA implementation of design adequacy procedure DAP-21 and for

the purpose of planning IE inspection of the process.

The report for the January-17, 1986, site audit of HVAC supports review

activities will be included in a future Region IV inspection report;

i.e.,

NRC Inspection Report 50-445/86-03; 50-446/86-02.

Copies of reports for

the other activities will be placed in the Public Document Room upon

completion.

-6-

3.

Applicant Actions on Previous Inspection Findings

,

a.

QA/QC:

>

(Closed) Deviation (445/8511-0-01):

Side bars were not being used to

identify all changes to ERC procedures and instructions.

The NRC inspector verified that Procedure CPP-001 was revised as -

committed.

Records indicate that training relative to the revised

procedure was conducted October 24, 1985, with appropriate lead

personnel in attendance.

The NRC inspector selected four recently

revised procedures for review to verify the_ effectiveness of the

preventive measures.

No noncompliance with the revised procedure was

identified.

This item is closed.

b.

Electrical:

,

(1) (0 pen) Open Item (445/8511-0-06): .Further review of this open

item pertaining to a loose grounding strap bolt showed that

Deviation Report (DR) I-E-CATY-004-DR01 and Nonconformance

Report (NCR) E85-101318SX were written for the deficiency.

This

item will remain open pending disposition of the NCR.

(2) (0 pen) Open Item (445/8511-0-07):

Further review of this open

item pertaining to a tray T140CDJ17 which had two 1-inch

openings in it's solid bottom showed that DR I-E-CATY-004-DR02

and NCR E85-101318SX were written for the deficiency.

This tray

is only 2 feet 9 inches above T13GCCM08.

This item will remain

open pending disposition of the NCR.

(3) (Closed) Open Item (445/8511-0-08):

Further review of this open

item pertaining to Drawing El-712-11, Revision 7, which showed

the tray elevation as 819 feet while the actual elevation is

817 feet, indicated that the drawing was for reference of

approximate location only.

Actual installation is performed per

Drawing El-712-01 which shows the elevation at 817 feet.

This

item is closed.

(4) (0 pen) Open Item (445/8511-0-09):

This item was incorrectly

associated as being part of cable tray package 047.

DR I-E-CATY-024-DR01 and NCRs E85-100844SX and E85-100831 were

written for the deficiency pertaining to sharp edges in

tray T130RCJ28 and jacket damage to a seven conductor 600 vult

cable.

This item will remain open pending disposition of the

NCRs.

(5) (0 pen) Open Item (445/8511-0-11):

This item pertained to a

loose bolt on a splice plate.

DR I-E-CATY-036-DR01 and

NCR E85-100988X were written for this deficiency.

This item

will remain open pending disposition of the NCR.

. . - . ._

, , . ,

. -

-.

-

.

-7-

(6) (Closed) Open Item (445/8511-0-12):

This item pertained to a

welded splice plate which had two of eight required bolts

missing.

Design Change Authorization (DCA) No. 4178,

Revision 29, dated July 7, 1985, required the two bolts be

removed when the splice plate was welded to the cable tray.

This item was incorrectly associated with cable tray

package 047.

This item is closed.

(7) (Closed) Open Item (445/8511-0-13):

This item pertained to a

pipe (FD-1-880-21A) clearance less than the required 6 inches

from cable trays.

Further review determined that the pipe is a

floor drain pipe and that only a 1-inch clearance need be

maintained instead of the 6-inch clearance from cable trays

required for safety-related pipes.

This pipe meets this

separation criteria.

This item is closed.

(8) (0 pen) Open Item (445/8511-0-14): This item pertained to the

following four findings:

(a) torn fire blanket material on

conduit C14B11217 - NCR E85-1013405 has been written for this

damage; (b) damaged fire blanket material on conduits C15W11119,

C15W16160 and C15W11989 - NCRs E86-100003S, E86-100004S, and

E86-100005S have been written; (c) the fire blanket material on

conduits C15W11119 and C15W11989 was touching f~ree air cables -

NCRs E86-100004S and E86-1000055 have been written; (d) damaged

2

fire blanket material on conduits C14G19934 and C14G19936 (this

material is located at tray sections T13GCCM92 and T13GCCM79 in

the Lower Cable Spreading Room). TUGCo has written

NCRs E86-100006S and E86-100007S.

These items will remain open

pending disposition of the NCRs.

(9) (0 pen) Open Item (445/8511-0-16):

This iten, pertained to a

'

conduit to tray transition separation distance of only

6 1/2 inches.

DR I-E-CDUT-066-DR01 and NCR E85-100363SX have-

been written for this deficiency. This item will remain open

pending disposition of the NCR.

'

(10) (0 pen) Open Item (445/8511-0-17): _This item pertained to a

separation deficiency where a conduit was only 1 inch from

cable tray T14KCCL23.

DR I-E-CDUT-064-DR02 and NCR E85-101622SX

were written for this deficiency.

This item'will remain open

pending disposition of the NCR.

(11) (0 pen) Open Item (445/8511-0-18):

This item pertained to fire

blanket material on conduit C13016037, which had a separation

of less than 1 inch to cable trays T13KCCT22 and T13KCCV18.

OR I-E-CDUT-064-DR02 and NCR E85-101622SX were written for this

deficiency.

This item will remain open pending disposition of

the NCR.

!

. . _ , . , _ . _ _ - . - _ _

.- _,

___

_,_ _

_ _ , _ _ .

_

_

_

-

-8-

'(12) (Closed) Open Item (445/8511-0-19):

This item pertains to a

termination panel, CP1-ECPRCR-15, which had no fire seal in the

end of a conduit in the control room, DR I-E-CDUT-064-DR01 was

written for this deficiency but was invalidated by ERC because

fire stop/ seal material was found to be installed in the other

end of the conduit in the Lower Cable Soreading Room.

This item

is closed.

(13) (Closed) Open Item (445/8511-0-20T:

This item pertained to

cables apparently lacking 2 inches of slack when coming out of

the conduit stubs (which are thermal-lagged) at Motor Control

Center (MCC) MCC 1EB4-1.

ERC memo QA/QC-RT-466 dated

September 5, 1985, has provided the ERC inspectors with a method

of determining the slack for thermal-lagged cables.

Thermal

lagging of free air cables is controlled by

Procedure CP-CPM-10.3.

Based on this information, this item is

closed.

(14) (0 pen) Open Item (445/8511-0-25):

This item pertained to a wall

sleeve, TWS-020, not being shown on cable routing schedule,

2323-El-1700.

DR I-E-CABL-045-DR02 and NCR E85-101209SX were

written for this deficiency.

This item will remain open pending

disposition of the NCR.

(15) (0 pen) Open Item (445/8511-0-26):

This item pertained to a

cable lacking the required 2 inches of slack at the conduit to

cable tray (C13011615 to T130CCQ22) transition.

DR I-E-CABL-045-DR01 and NCR E85-101138SX were written for this

deficiency.

This item will rer.1ain open pending disposition of

the NCR.

(16) (0 pen) Open Item (445/8511-0-27):

This item pertained to a

cable lacking 2 inches of slack at the C13003316.to-T130CCQ45

transition.

DR I-E-CABL-045-DR01 and NCR E85-101138SX were

~

written for this deficiency.

This item will remain open pending

disposition of the NCR.

.

,

(17) (Closed) Open Item (445/8511-0-29):

This item' pertained to wire

,

'

terminations not being properly identified on

Drawing 2323-El-0035, Sheet 38.

Supplemental instructions in

ERC Quality Instruction (QI) QI-014 were written to verify the

termination points by checking the position of'the _ limit switch

contacts before and during operation.

Position of the switch is

checked by measuring continuity.

This item is closed.

(18) (Closed) Open Item (445/8511-0-30):

This item pertained to wire

terminations not being properly identified on

Drawing 2323-El-0035, Sheet 37.

Supplemental instructions in

.

i

1

-9-

QI-014 were written to' verify the termination points by checking

the position of limit switch contacts before and during

operation.

Position of the switch is checked by measuring

i

continuity.

This item is closed.

(19) (0 pen) Open Item (445/8513-0-23): This item pertained to the

following three findings:

(a) a three piece fitting that was

not hand-tight.

DR I-E-CDUT-027-DR02 and NCR E85-101344SX have

been written for this deficiency; (b) less than 1 inch

separation between conduit ESB6-5, tray T13KECH, and

conduit C14013763.

DR I-E-CDUT-027-DR03 and NCR E85-101344SX

have been written for this deficiency; (c) a conduit size which

was 1 inch when it should have been 3/4 inch.

Electrical

Erection Specification 2323-ES-100, Revision 2, dated

October 15, 1980, Section 4.8.2 states for lighting, "All

metallic conduits shall be rigid galvanized steel and 3/4-inch

minimum unless otherwise noted on the drawings."

In the same

specification, Section 4.4.2 states, in part, ". . . In order to

facilitate construction conduit of the rext larger

size . . . may be substituted'for reasons such as the smaller

sized conduit is not in stock." Based on this information,

finding (c) is closed. . Findings (a) and (b), above, will remain

open pending the disposition of the NCRs.

(20) (0 pen) Open Item (445/8513-0-26):

This item. pertained to the

following two findings:

(a) an outlet box with a 3-inch stub

.that was not sealed as required; and (b) an outlet box which had

two cover retaining screws that were stripped.

NCR E85-101439SX

has been written for these deficiencies.

This item will remain

open pending disposition of the NCR.

~

'

(21) (0 pen) Open Item (445/8513-0-30):

This item pertained.to

electrical conductor seal assemblies (ECSAs) which were longer

than shown by the drawings and the supplemental instructions.

DR I-E-EEIN-052-DR01 and NCR E85-101288SX were written for this

deficiency.

This item will remain open pending disposition of

the NCR.

'

(22) (0 pen) Open Item (445/8513-0-31):

This item pertained to the

following two findings:

(a) ECSA-1-HV-5561 was longer than

shown by the drawings and the supplemental instructions.

DR I-E-EEIN-039-DR01 and NCR E85-101259SX were written for this

deficiency; and (b) ECSA-1-HV-5561 associated had a bend radius

under the required minimum of 5 inches.

DR I-E-EEIN-039-DR02

and NRC E85-101259SX were written for this deficiency.

These

findings will remain open pending disposition of the NCRs.

(23) (0 pen) Open Item (445/8513-0-32):

This item pertained to the

following two findings:

(a) ECSA-1-HV-4725-3 had a fitting

that was not hand-tight.

DR I-E-EEIN-003-DR01 and

NCR E85-101268SX were written for this deficiency; and (b) three

>

T

---,.-.n-~

- - - - _ . .

. , . . . - ~

. , -

--- -

,.

.

-10-

ECSAs (1-HV-4725-1,

-2, and -3) were longer than shown by the

drawings and the supplemental instructions.

DR I-E-EEIN-003-DR02 and NCR E85-101268SX were written for thic

deficiency.

These findings will remain open pending. disposition

of the NCRs.

~

'

(24) (0 pen) Open Item (445/8513-0-33):

This item pertained to the -

following two findings:

(a) flexible conduits.C1388908-2 and -3

had bend radii under the allowed minimum of 5 inches.

e

,

DR I-E-EEIN-001-DR01 was writt en for this deficiency,'but was

invalidated by ERC because the flexible conduit run is not

considered part of the ECSA installation; and (b) two ECSA

assemblies were missing their identification tags.

._

DR I-E-EEIN-001-DR02 and NCR E85-10012895X were written for this

deficiency.

This item will remain open pending disposition of

the NCR.

(25) (0 pen) Open Item (445/8513-0-34):

This item pertained to the

L

following three findings:

(a) a three piece coupling on

l

ECSA-1-HV-4172-2 was not hand-tight.

DR I-E-EEIN-012-DR01 and

l

NCR E85-1012695X were written for this deficiency; (b) three

ECSAs (1-HV-4172-1, 2, and 3) were longer than shown by the

drawings and the supplemental instructions.

DR I-E-EEIN-012-DR02 and NCR E85-101269SX were written for this

deficiency; and (c) two ECSAs (1-HV-4172-2 and 3) had bend radii

under 5 inches.

DR I-E-EEIN-012-DR03 and NCR E85-101269SX were

written for this deficiency.

This item will remain open pending

disposition of the NCRs.

(26) (0 pen) Open Item (445/8513-0-35):

This item pertained to a

solenoid valve's flexible conduit which had a missing digit on

its identification tag.

DR I-E-EEIN-001-DR02 and

NCR E85-1012895X were written for this deficiency.

This item

will remain open pending disposition of the NCR.

(27) (0 pen) Open Item (445/8513-0-36): This item pertained to

conduits from junction box JB1C-2450 to ECSA-1-HV-4725-1 and 3

s

which had identification markings that were illegible.

NCR E85-101442SX has been written for this deficiency.

This

item will remain open pending disposition of the NCR.

(28) (0 pen) Open Item (445/8518-0-09):

This item pertained to

banding on fire blanket material for conduit C13G08248 which

was not installed within 2 inches from the end of the blanket.

DR I-E-CABL-026-DR03 and NCR E85-101155SX were written for this

deficiency.

This item will remain open pending disposition of

the NCR.

(29) (Closed) Open Item (445/8511-0-10):

This item was incorrectly

associated as being a finding of cable tray package 047.

The

-___ .

.

.

__ _

_

. - .

.

-_

_ __

_

. . .

,

,

I

.

?

-11-

.

4

finding, related to holes in the cable tray, has1 een resolved

b

b

tthrough the review of DCA No. 4178, Revisionc29,Idated July'24,

'

'

1985.

This item is closed.

(30).(0 pen) Open' Item (445/8514-0-08):- During October 1985, theLNRC

inspector performed-an independent inspection of, Unit No. 1

,

- cable tray T13GDCX60, Verification Package No.e I-E-CATY-167.

A

review of ERC inspection reports revealed agreement'.between

i

observations, and validated ERC DRLI-E-CATY-167-DR1.iqThe NRC c ~

inspector.also observed that cable tray T13G0CX50;had'. loose nuts

at the east splice plate connection.

This observation was

outside of the defined-inspection scope.' (;

i

,

,

,

This item will remain open pending theJNRC review of the I-

'

applicant's disposition.

~ ~ * '

l

'

"

, .

i

(31) (0 pen) Open Item (445/8514-0-10): .During October 1985, the NRC'

l

inspector performed an independent documentation review offthe

,

following six Unit 1 electrical conduits:

'

,

i

'

_

Verification

_

_

-

-

!

Package No.

Conduit No.

System

'

I

R-E-CDUT-027

ESB6-5

Lighting

R-E-CDUT-035

C12G03270

N/A

.

R-E-CDUT-044

ECB3-29

Lighting

R-E-CDUT-050

ECB1-16

Lighting

R-E-CDUT-065

C13G08606

N/A

R-E-CDUT-066-

C12G04985

N/A

Comparison of NRC findings to ERC finding is as follows:

(a) Verification Package Nos. R-E-CDUT-027, R-E-CDUT-044, and

j

R-E-CDUT-050 have been included in the new population for-

Lighting (LITG).

A repeat review will be performed in

i

accordance with QI-071.

(b) Review ~of Verification Packages R-E-CDUT-025, R-E-CDUT-065,

and R-E-CDUT-066 by the NRC inspector identified that

!

QI-009 does not list QI-QP-11.3-4, the inspection procedure

'

.in effect'at the time of the conduit inspection, against'

which inspector certifications are to be reviewed.

ERC has

identified this same condition, and has not been able to-

complete processing of the review results.

This item will

remain open pending NRC review of the applicant's

[

resolution of this finding.

L

(32) (Closed) Open Item (446/8511-0-12):

During October 1985, the

<

NRC inspector performed an independent inspection of cable

.

.

tray T23GECX18, ERC Verification Package No. I-E-CATY-241, Unit

i;

i

s

9 .-e9-

.- 9

,c.

,.--

in-

.

ww.-,y-i-


,---3

,---,rr-w.-,,,m.,,-,,-.--.--..,---,-i

,,my

-,.--.---,,,,----m-..~.vw-w-,--,wa--m-,,...--w----

-12-

No. 2.

The NRC inspector identified abandoned holes on both

sides of the tray near one of the splice plates.

The NRC inspector reviewed ERC inspection documentation for this

cable tray and verified that DR I-E-CATY-241-DR1 identified the

condition observed by the NRC inspector, and also documented

that the ERC inspector had identified a sharp edge where the

tray sections join together.

ERC has invalidated the DR based on the fact that the holes are

acceptable per DCA No. 4178, Revision 29, and that the tray

configuration is such that the sharp edge does not present a

cable hazard.

(33) (CloseJ) Unresolved Item (445/8514-U-17):

Accomplishment of

conduit separation inspections.

During independent conduit

inspections and documentation reviews performed by the NRC

inspector during October 1985, it was observed that TUGCo

inspection procedures did not contain provisions for inspection

of electrical separation.

The NRC inspector was informed that

inspection for electrical separation was performed in

conjunction'with room / area turn-over per QI-QP-11.3-29, instead

of at the time of the' installation inspection.

During January 1986, the NRC inspector reviewed building

turn-over files in the Permanent Plant Records Vault (PPRV) for

16 rooms / areas.

These records represented inspections for

various elevations in the Reactor Containment, Safeguards,

Diesel Generator, Control, and Auxiliary buildings of Unit

No . 1.

With the exception of the Cable Spreading Room

(No. 133), all of the packages reviewed contained Inspection

Reports and supporting documentation, indicating: inspection for

electrical separation in accordance with QI-QP-11.3-29.

Documentation for the cable sprea' ding room was-located'in the

Unit No. 1 Paper Flow Group (PFG) files.

With the exception of

the cable spreading room, all of the Inspection Reports were

closed indicating completion and acceptance of any required

rework.

This review of documentation resolves the initial concern over

~

the lack of electrical separation attributes in conduit

installation inspection procedures.

The NRC inspector was informed that open inspection items

pertain, for the most part, to areas where separation barrier

material (SBM) is required, or to abandoned holes in the

siderails of cable trays.

No action is being taken with regard

to SBM problem areas due to a May 16, 1985, memorandum

prohibiting the installation of SBM, based on NCR E-85-1001805.

-13-

No action is being taken on the remainder of the separation

problem areas, including holes in the cable tray siderails,

pending receipt of further direction from TUGCo Nuclear

Engineering (TNE).

Through discussions with.the electrical QC inspection

supervisor, the NRC inspector was informed that the

approximately 300 to 500 separation problem areas were the

result of a reinspection initiated by QC in early 1985.

The

initial concern was the effectiveness of the cable tray as a

barrier with abandoned holes present in the siderail.

The

effort was terminated because of the amount of ongoing rework,

and a question as to the tignificance of the abandoned holes.

The electrical QC inspection supervisor informed the NRC

inspector that another room / area inspection by QC inspectors,

for electrical separation, would be required subsequent to

completion of rework activities.

Discussions with TNE indicated that a testing and evaluation

program has been initiated to justify the relaxation of

electrical separation requirements.

The NRC inspector was

informed that the results of the testing and evaluation program

should be available during April 1986.

The issue of inspection for electrical separation is an open

. item pending the NRC review of the applicant's

disposition / action pertaining to SBN installation, abandoned

holes in cable tray siderails, the engineering testing and

evaluation report, and the room / area separation inspection

program (445/8601-0-11).

-

(34) (0 pen) Open Item (445/8514-0-07):

Independent documentation

review of 10 verification packages comprising 22 cables.

Comparison of the results of NRC documentation reviews to the

results of the ERC reviews for the following,10 Unit.1

electrical cable verification packages ha's been. completed:

Verification

Package No.

System

Cable No.

R-E-CABL-004

Safety Injection (SI)

Ed123625Z,

'

R-E-CABL-011

Lighting

-

ESB2-13

R-E-CABL-026

Chilled Water

EG111199

R-E-CABL-028

Control Room HVAC

E0015951D

R-E-CABL-035

Instrument Air

EG112939

,

R-E-CABL-042

SI

EG123834

R-E-CABL-054

SI

E0100440

R-E-CABL-078

Diesel Generator'HVAC

EG113538

R-E-CABL-086

Chemical & Volume Control

E0121816Z

R-E-CAB L-089

SI

EG123639Z

>

.

.

-14-

Results of these comparisons are as follows:

R-E-CAB L-004:

A valid DR was issued by the ERC inspector

pertaining to an engineer failing to date his signoff of a

, cable pull card for identifying that the raceway was ready for

cable pulling.

NCR E-85-102052SX has been initiated for this

item.

R-E-CABL-011:

This package was moved to a new population for

lighting cable.

Rereview will be performed in-accordance with

QI-071.

R-E-CABL-026:

This package has been superceded by cable

package R-E-CABL-108 as a result of CPRT's determination that

an inadequate number of random digits were used in the initial

sample selections for the cable populations.

There were two DRs

identified by ERC during their review, which if validated, will

be submitted to TUGCo for processing into a NCR.

R-E-CABL-028:

This package has been superceded by cable

package R-E-CABL-109 for the same reason as R-E-CABL-026.

There was one OR identified by ERC during their review, which if

validated, will be submitted to TUGCo for processing into a NCR.

R-E-CABL-035:

This package has been superceded by cable

package R-E-CABL-110 for the same reason as R-E-CABL-026.

There were two DRs identified by ERC during their review, which

if validated, will be submitted to TUGCo for processing into

NCRs.

The above findings will remain open pending review of the final

disposition.

The comparison of the remaining verification

package resulted in no additional findings and these packages

are considered closed.

4

(35) (0 pen) Open Item (445/8514-0-04):

Further inspection of cable

routing deviating from the cable schedule (i.e., a cable was

routed through conduit C13G06325 instead of C13G06324) showed

that NCR E85-101756SX has been issued to address the finding.

This item will remain open pending disposition of the NCR.

(36) (0 pen) Open Item (445/8514-0-05):

Further inspection of this

open item, pertaining to a 2-inch slack requirement for. cables

and requirement to identify conduit sleeves, showed that two

NCRs were issued to address these concerns.

NCR E-85-101141SX

addressed the 2-inch slack requirement and NCR-E-85-101928SX

addressed the identification requirement.

This item will remain

open pending disposition of the NCRs.

. .

- - . -

. - . .

.-

- . - .

. . .

--

-.

-

E

-

-15-

(37) (Closed) Open Item (445/8514-0-06):

Further inspection of this

open item, pertaining to conduit size being 1 1/2 inch as

compared to the 2 inches referenced on the cable and conduit

schedule 2323-El-1700, showed that this item was addressed by

TUGCo letter TU0-3355.

No NCR was issued for this out-of-scope

item based on TUGCo's disposition per the above letter that

s

cable and conduit schedule 2323-El-1700 is not used to determine

conduit size but rather, the~ field physical

Drawing 2323-El-500-03, which specifies the conduit C13008544 is

to be 1 1/2 inches.

(38) (0 pen) Open Item (445/8513-0-24):

Further inspection of this

open item, pertaining to loose locknuts and bushing on

conduit CB3-24-29 and C83-29, showed that the two DRs were

validated and NCR E85-101342SX has been issued.

This item will

remain open pending disposition of the NCR.

(39) (0 pen) Open Item (445/8513-0-25):

Further inspection of this

open item, pertaining to loose couplings and conduit

separation, showed that the two DRs were validated and

NCR E85-101496SX has been issued to address the two DRs.

This

item will remain open pending disposition of the NCR.

4.

Inspection Process Control

The NRC inspector initiated an inspection of the Reliability Assessment

Program that will be completed in a subsequent report.

However, an

uncontrolled use of three part memos was found being used to document

potentially nonconforming conditions that were in areas outside the

process inspection control lots.

Further review of the use of these

three part memos resulted in the following findings:

(a) an informal log

was used to track these memos, but there was no assurance that all memos

were entered on the log; (b) several of the memos on the log could not be

located, thus disposition of the problems could not be assured; and

(c) with few exceptions, no NCRs were written to document / correct the

items on the memos.

These activities are in noncompliance with TUGCo

procedures including CP-QP-16.0 that requires immediate action leading to

an NCR when identifying a deficiency in characteristic, documentation, or

procedure which renders the quality of an item unacceptable or

indeterminate.

This failure to comply with procedures is identified as a

violation (445/8601-V-12; 446/8601-V-03).

5.

Applicant's Processing of ERC Inspection Findings

The NRC inspector conducted a review of the TUGCo QA/QC Coordinator's

files in order to assure that NCRs were being initiated as a result of

ERC issued and validated DRs, and to assess the processing of the NCRs.

The following procedures, applicable to the NCR program, were reviewed:

o

CPSES Station Administration Manual Procedure STA-405, " Control of

Nonconforming Materials," Revision 9, dated November 11, 1985

-16-

o

CPSES Station Administration Manual Procedure No. STA-406,

" Corrective Action," Revision 2, dated February 11, 1983

TUGCoProcedureCP-QP-16.0,"Nonconformance,"Rehision19, dated

~

o

October 16, 1985

o

TUGCo Procedure CP-QP-16.3, " Processing CPRT Deviation

Reports /0bservation Notices," Revision 1, dated August 28, 1985

o

TUGCo Procedure QI-QP-17.0-1, " Preparation and Distribution of Trend- .

Reports," Revision 1, dated January 10, 1986

o

B&R Procedure CP-QAP-16.1, " Control of Nonconforming Items,"'

Revision 25, dated August 17, 1985

m

g

o

B&R Procedure N61-1, " Program For Repair or Replacement of Mechanical

Components Accepted by the Owner," Revision 4, dated December 10,

1985, through Change Notice No. 1, dated January 2, 1986.

During this inspection effort, the NRC inspector identified' conditions

which were contrary to the requirements of the procedures.

Paragraph 3.2

in Procedure CP-QP-16.3 states, in part, ". . . All DRs will require the

'

generation of an NCR."

Review of the records revealed numerous instances

'

where the TUGCo QA/QC Coordinator had incorrectly invalidated DRs issued

by ERC, thus resulting in a failure to generate NCRs.

Further, the DR log

showed that Deficiency Notifications (DNs) were improperly used in lieu of

NCRs.

Rework or repairs were performed as a result of these DNs.

DNs, as

addressed in paragraph 8.0 of Procedure N61-1, are to be used for

documenting deficiencies identified during repair or replacement of

mechanical components previously accepted by TUGCo.

A nonconformance, as defined by Procedures CP-QP-16.0 and CP-QAP-16.1, is

a deficiency in characteristic, documentation, or procedure which renders

'

the quality of an item baacceptable or indeterminate.

Both procedures

required that nonconforming conditions be reported on NCRs.

,

Procedure CP-QP-16.3 addresses ERC's responsibility for generating

Observation Notices which are used for documenting out-of scope

observations, and their subsequent transmittal to the QA/QC Coordinator.

Further, paragraph 3.2 states, "The QA/QC Coordinator shall evaluate the

condition (s) identified on the Observation Notice to determine if a NCR

is to be issued." The NRC inspector observed over 100 Observation Notices

~

in which conditions were determined to be nonconforming, as evidenced by

subsequent rewor k or repair.

However, the QA/QC Coordinator had not

issued NCRs.

It was further noted that, in some cases, DNs had been

improperly initiated in order to effect the rework or repair.

Procedures CP-QP-16.0 and CP-QAP-16.1 require nonconforming items to be

identified by the use of signs, barriers, or hold tags.

However,

observation of numerous items identified on NCRs as being nonconformances,

revealed no evidence of signs, barriers, or hold tags.

4

-

-

- - - .

-

n

-

--

,

,.:-...-

- _ . -

- , , . - . .

-17-

Paragraph 3.5 in Procedure QI-QP-17.0-1 states, in part, "The Trend

Analysis report shall be issued monthly and contain Potentially Adverse

Trends . . . ." Paragraph 3.4.1.1 states that potentially adverse trends

are based on the relationship of the number of NCRs initiated in the

current reporting period to the preceding three month average.

The NRC inspector has identified that NCRs have not been initiated as

required.

As a result, the validity of potentially adverse trends

contained in the Trend Analysis Report is brought into question.

Failure to comply with the applicable requirements of the procedures is a

violation (445/8601-V-12; 446/8601-V-03).

6.

Assessment of Allegations

a.

AQ-145 (4-85-A-15) and AQ-153 (4-85-A-30):

It was alleged that the

Construction Startup/ Turnover Surveillance (CSTS) group:

(1) had

not trended their surveillance results from April 1983 to April 1985;

'

and (2) were being required to look at less, as a result of reduction

in staff from 10 to 4 people, without corresponding reduction in work

load (AQ-145).

It was also alleged that CSTS group management

created a difficult environment for their personnel to work in which

caused pressures that affected work output (AQ-153).

,

(1) AQ-145(1) - The program for trend analysis to identify

conditions adverse to quality was previously assessed by the

NRC.

This assessment was documented in NUREG-0797, Supplement

No. 11.

The substance of this current alleCation was considered

by the NRC in Appendix P of Supplement No. 11.

The NRC found

that deficiency reports, NCRs and CSTS reports, which identified

discrepant conditions were not trended periodically, as

prescribed by the FSAR for identification of adverse quality

trends.

The applicant responded to three NRC findings i Appen' dix C to

the CPRT Program Plan, ISAP No. VII.a.2.

This ISAP committed,

among other things, to (a) review.the trend analysis program

implemented on site versus FSAR commitments, and (b) to identify

any programmatic weaknesses which require correction with

^

respect to the work remaining on Unit 2 and the operations QA

program.

The NRC is currently inspecting the implementation of the

applicant's commitments.

(2) AQ 145(2) - The CSTS Oroup was found by the NRC inspector

through interview and reviewing organizational charts, to have

been comprised up to mid-1984 of two types of surveillance

technicians; i.e., construction and startup/ turnover (SU/TO).

The construction surveillance technicians were performing

hardware walkdown inspections to verify that hardware conformed

..

-

-

_

.- -

.

-

.- -.

.-

-18-

to drawings, procedures, and specifications governing work being

inspected.

SU/TO surveillance technicians monitored

preoperational testing activities for conformance to

procedure / programmatic requirements.

The CSTS group staff was

reduced from 10 to 4 people as identified during the summer of

1984.

The reduction in staffing resulted from completion of

specified Unit I room walkdowns in mid-1984 by the construction

technician section of the CSTS group. Accordingly, the group

was reduced (during the summer of 1984) consistent with handling

the remaining activities.

This reduction did not directly

affect the SU/TO surveillance technicians.

The procedure governing the surveillance program was reviewed.

Procedure CP-QP-19.6, Revisions 0 to 7,

" Surveillance of

Construction and Startup/ Turnover Activities," indicated that

the surveillance program for the construction, turnover, and

startup phases progressively evolved from a general program to a

more specific and structured program.

Between May 15, 1984, and August 9, 1984, three significant

revisions were made to CF-QP-19.6 as a result of experiences

learned through performed surveillances.

For example, room

walkdowns yielded numerous findings which were documented in

large surveillance reports.

Contained in the reports were minor

discrepancies, hardware nonconformances, and procedural

deviations.

Tracking and resolving these problems was found to

be an unwieldy process when compared to existing site mechanisms

such as NCRs for hardware nonconformances and deficient reports

for procedural / programmatic deviations.

NCRs and deficiency

reports were more suited to processing and resolving identified

problems than the surveillance reporting mechanism.' To address

the above condition, on July 31, 1984, an office memo (TUQ-2260)

was issued to more clearly identify what methods should be used

to identify and resolve findings resulting from surveillances.

Some of the subjects covered by the memo included correction of

minor items using the rework process, basis for documenting

.

discrepant items on an NCR, and a description of when to use the

!

CSTS deficiency reporting system.

These policies were included

l

in CP-QP-19.6, Revision 7, dated August 9, 1984.

Based on

!

review of procedures governing CSTS activities, there was no.

indication of a reduction of surveillance' requirements.

The-

revisions to CP-QP-19.6 and issuance of TUQ-2260 during the.tirr.e

period when the reduction in the group occurred could be viewed

l

as restricting the latitude and requirements for performing

surveillances.

i

With respect to adversely restricting surveillances ("look at

less"), the NRC inspector reviewed the log of performed

I

surveillances.

It appeared that the surveillances performed

after the reduction in personnel covered similar subjects to

those performed in the prior period.

A sample of Dallas

I

-19-

surveillance reports (DSRs), including DSRs identified by the

al. leger, was reviewed to determine if the scope, magnitude,

reporting requirements, and resolution to findings showed any

evidence of restriction of surveillance activities following the

reduction in personnel.

No changes were noted and DSRs appeared

to be resolved in a timely manner.

Dispositioning was with the

concurrence of the cognizant surveillance technician.

(3) AQ-153 - It was alleged that a difficult environment for their

personnel to work in was created by CSTS group management which

generated pressures that adversely affected work / output.

Since

the time frame and substance of the allegation appeared to be

similar to AQ-145(2), these allegations were assessed

simultaneously.

The information obtained from reviewing

procedures governing CSTS activities, published surveillance

reports and resolution to findings, organizational charts, and

office memos regarding CSTS activities is listed below.

From May to August 1984, three significant changes were made to

the procedure (CP-QP-19.6) directing CSTS activities.

An

office memo TUQ-2260 was written by the CSTS supervisor to

clarify policy regarding the identification and reporting of

surveillance findings.

The substance of the memo could be

interpreted as signifying that management was disenchanted with

the group's performance; however, no memos were found that were

written for disciplinary actions or personnel performance

problems.

The group was reduced in size from 10 to 4 due to

work realignment.

During 1984 and 1985, the lead position in

the group was changed three times and the supervisor's position

twice.

In September 1985, the CSTS surveillance program was

totally revised including the methods of reporting and resolving

findings.

The revision was to meet the changing role,of CSTS in

the site QC function.

Because of the numerous changes in policies, procedures, and

personnel described above, the alleger's expressed concern is

understandable.

The working environment appears to have been.

consistent with the nature of the changing work activities at

the site and did not appear to be systematic and intentionally

created by CSTS management to place pressure on the surveillance

technicians.

Based on review of the surveillance schedules and

published reports, it did not appear that the above described

onvironment abnormally affected work output.

In conclusion, the allegation AQ-145(1) that results from CSTS

reports and findings were not trended from April 1983 to

April 1985 was substantiated during an earlier TRT assessment.

The applicant has initiated corrective and preventative

measures, which the NRC is continuing to inspect.

In AQ-145(2),

it was identified that CSTS was reduced to a manpower level of

4; however, it was neither substantiated that the reduction

-20-

adversely affected surveillance performance, nor that the work

load was the same as before the reduction.

The concern (AQ-153)

that the CSTS management created a difficult working environment

which adversely affected work output was not substantiated.

b.

AQ-150 (4-85-A-30):

It was alleged that operations pl_ ant personnel

were unfamiliar with the operations QA orga'nization,' its site

personnel, and its function.

<'

,

s

Theinformationpresentedby'heallegerwasgeneralfinnAntureand

t

identified that operations personnel were. unaware ofis (1) the

quality organization's objectives, personnel, and functions, and-

.

(2) the mechanism to identify and report observed discrepancies and

concerns.

These concerns question the effectiveness'of employee

indoctrination and training regarding thi role ofiQA in thei

operations phase.

The approach to resolving this allegation.was to-

assess TUGCo's general employee training program relative to QA and

to interview a sample of employees to determine if they were

knowledgeable about the QA role at the site.

In reviewing the FSAR, it was found that Section 13.2 commits to

general station training.

Procedure TRA-101 is the implementing

station procedure for the general employee training (GET) program.

The objective of the procedure was to assure that all employees (and

-others) who have unescorted access to the protected area of the

station will receive training commensurate with their

responsibilities.

Among other things, one of the principal areas of

GET is the QA program and its role at the site. GET is given to new

hires with an annual refresher to assure that all individuals

maintain competency in the safe operation and maintenance of the

facility.

The GET program was implemented in February 1983.

The NRC inspector reviewed the GET indoctrination lesson plan and

notes given to TUGCo employees and other attendees.

The lesson plan

contained the following items:

(1) QA introduction, (2) definition

of selected QA terms, (3) discussion of legal requirements,

(4) organization structure, (5) hierarchy of documents, and

(6) problem identification and reporting.

QA indoctrination is

followed by an examination,'which has a minimum passing grade of 70%

for the following subjects:

o

Goal of the QA program (quality is the responsibility of

everyone)

o

Definitions of QA terms; e.g. , quality, QA, QC, hold point,

audit, safety related, deficiency, nonconformance, and quality

related

o

Relationship of 10 CFR Part 50, Appendix B, to the QA program at

CPSES and the NRC's responsiblity in monitoring the QA program

,

..

-21-

o

Stop work authority

o

Purpose of procedures, employee's responsibilities to use

procedures, and how to handle inadequate / incorrect procedures

o

Methods and individual (s) responsible for reporting deficiencies

and nonconformances and the employee option of talking to the

NRC

,

o

Purpose of hold tag, and how/who may remove' hold tags

~

,

o

Identification of selected examples of-deficiencies'and

nonconformances

,

,

,

For further reference, each student is given a.GET booklet which'

covers each of the above subjects in detail.

~

Training files were reviewed to verify implementation of. training

procedures.

It was observed that for each employee'and others, the

type of training received was entered into a computer data base ~and

backed up by a hard copy file.

The actual training session file

contained attendance records (with student signatures), examination

grades, and subject matter covered.

NRC, B&R, and other personnel

receiving GET training have files similar to'TUGCo employees.

The

only difference being that non-TUGCo employee training is based on a

need to know, rather than on a utility requirement.

1

~

To determine if site personnel were cognizant of the role of QA, its

organizational structure, its function, and methods used to report

nonconformances, as presented in GET, site operations personnel were

t

interviewed.

The sample included personnel from the administrative

function, engineering department, maintenance and operations

personnel, and QA/QC individuals.

It was observed that employees

were knowledgeable about the QA/QC goals and organization at the

site, what individuals should be contacted to identify and report

discrepant / nonconforming conditions, and the mechanism used to

document deficiencies /nonconformances.

In conclusion, the allegation that operations personnel were

unfamiliar with the operations QA organization, its site personnel,

and its function was not substantiated.

Since the GET program was

not implemented until February 1983, the alleged conditions could

have possibly existed to some degree in the past.

c.

AQ-144 (4-85-A-29) and AQ 152 (4-85-A-30)

It was alleged that TUGCo attempted to dictate what the authorized

nuclear inservice inspector (ANII) would review / inspect by bypassing

his prework review of maintenance action reques

(MAR) work packages

(AQ-152), one such MAR included an undersized barger weld (AQ-144).

_ . _ -

--

- - - - -

_ . - - - - - - . .

_ _ . - - _ - - _ _ .

.

.-.

-22-

These allegations concerned plant systems which have been completed

and accepted under the ASME Code Section III construction program and

have been turned over to TUGCo operations.

Any subsequent repair or

replacement activities are accomplished and controlled undar the

operations ASME Section XI QA program.

The impact of bypassing the

ANII's prework review (intended to establish required hold points for

repair activities only) questions the credibility of the applicant's

ASME Section XI repair and replacement program.

The ASME Code does

not require ANII prework review of replacement activities.

To determine if the ANII was bypassed in the prework review of MAR

work packages, all the "NIS-2 Owner's Reports for Repairs or

Replacements" were reviewed, consisting of approximately 150

packages.

For ASME Code repairs and replacements required in MAR

work packages, completion of the NIS-2 report form by the owner and

tha ANII certifies that all the applicable code requirements have

been meet and the required inspections have been performed.

The

NIS-2 report packages were obtained from the TUGCo operations vault

and reviewed for completeness and evidence of ANII prework review.

The packages were found to be complete.

In two of only four packages

involving weld size increases, the date of the ANII review was later

than the approval to start work date indicating possible bypassing of

the ANII's prework review.

In checking the ANII's daily inspection

log, it was found that these two packages had bypassed ANII prework

review.

When these packages initially were in the field, prior to

start of work, a QC inspector discovered the absence of required ANII

hold points and stopped work from continuing.

The packages were then

returned to the ANII for prework review and reissued to the field for

work.

An inspection report (No. 85-2) was issued by the ANII that

identified this bypassing as an implementation deficiency of

procedure MDA-303, Revision 0.

The applicant's~ response was to

reinstruct / retrain personnel involved in the review of repair and

replicement work packages to assure that ANII prework reviews were

provided for, when required.

Attached to this response was the

documentation attesting to completion of the training.

In discussing

this occurrence with the ANII, he stated that he was not aware of any

other instance of bypassing.

Further, the record' review by the ANII-

associated with the issuance of all NIS-2 reports would have

discovered any previous bypassing of the ANII.

In summary, although

two identified instances of bypassing were found to have occurred, no

other such occurances were found in a complete review of the relevant

MARS.

Moreover, the two instances were correctly identified by QC,

and corrective action to prevent reoccurrence was implemented.

For repair activities, the ASME Code requires the ANII to perform

prework documentation reviews (to establish desired hold points) and

perform inprocess inspections as necessary.

For replacement

activities, ANII prework review and inprocess inspection

participation is not a requirement.

The ANII is only required to

verify (by way of documentation review) that the applicable ASME Code

requirements have been met and required inspections performed.

Since

-23-

,

the alleger was not part of the operations personnel, he may have

perceived the lack of ANII participation during inprocess replacement

activities as bypassing the ANII review.

Although not required,

since June of 1985 the ANII has been involved in at least 30 percent

of Section XI replacement inprocess work activities by performing

prework reviews and establishing hold points and performing

inspections.

In conclusion, the general allegation that TUGCo attempted to dictate

what the ANII would review / inspect by bypassing his prework review of

Section XI repair and replacement work packages was not

substantiated.

ANII inprocess involvement for Section XI replacement

activities is not required by the ASME Code, thus bypassing the

ANII's prework review for replacement MARS would not have been a

requirement.

The ANII inprocess involvement for Section XI repair

MAR work packages is required by the ASME Code and is being

accomplished.

The instances where the ANII was bypassed on repair

MARS appears to have been an isolated occurrence that was identified

and corrected when it occured.

d.

AQ-149 (4-85-A-15):

It was alleged that operations QA surveillance

report findings were being suppressed or severely changed.

In assessing the allegation, the NRC inspector reviewed backup files

of quality surveillance reports from 1983 through 1985.

The purpose

of the review was to determine if the contents of draft findings were

changed or altered prior to final publication.

Copies of drafts were

found either in the official backup files or in the personal files of

individuals performing surveillance activities.

Comparison of-drafts

to final reports disclosed editorial (grammar and spelling) changes.

One draft contained redundant subjective comments which were not

included in the final report.

No suppression of findings or

alteration of content was observed.

Six of nine current and one former QA surveillance individuals were

interviewed.

None of the individuals interviewed believed that they

were pressured to suppress findings, and all indicated that they had

sufficient independence in writing surveillance findings.

As a

practice, changes to drafts were discussed between the surveillance

personnel and their supervision prior to changes being made.

One

individual acknowledged that at times his reports contained

subjective comments which he agreed to delete.

In conclusion, the allegation that surveillance findings were

suppressed or changed between initial drafts and final report

publication was not substantiated.

This conclusion is consistent

with similar assessments made by the NRC, in particular the NRC's

assessment of AQ-132 as presented in NUREG 0797, Supplement No. 11.

,

0

. . _ . _ _ _ . _ _ _

-24-

e.

AQ-155 (4-85-A-33):

It was alleged that maintenance procedures in

the operations area were not consistent with commitments to ANSI

standards and Regulatory Guides, and operations procedures had

similar problems.

In assessing the allegation, the NRC inspector reviewed TUGCo

procedures, policies, and FSAR commitments addressing the control of

operational phase procedures and instructions.

Documents reviewed included STA-201, Revision 12 " Preparation,

Responsibility and Content of Station Manuals"; STA-202, Revision 13,

" Preparation, Review, Approval and Revision of Station Procedures";

STA-209, Revision 4, " Preparation, Review, Approval, and Revision of

Station Instructions"; STA-401, Revision 10, " Station Operations

Review Committee"; QAI-008, Revision 0, " Review of Procedures,

Instructions, and Plans"; quality program policy as stated in the

Operations Administrative Control and Quality Assurance Plan (OAC&QAP),

Sections 13.1, 13.2, 13.3, and 13.4; and FSAR, Chapter 17.2.

These

documents were consistent with 10 CFR Part 50, Appendix B.

Section 17.2.5 of the FSAR requires that activities affecting the

quality of safety-related components be prescribed by and

accomplished in accordance with documented instructions and

procedures.

The implementing policy document establishing

instruction and procedures control for the operations phase is the

CPSES OAC&QAP.

The supervisor or superintendent that has cognizance over a specific

safety-related activity is responsible for the development and

approval of instructions / procedures prescribing the activity.

Administrative procedures and instructions are to be reviewed and

approved prior to performance of the activity.

The cognizant

supervisor is responsible for assuring that the activity is performed

in accordance with the procedures and instructions.

The development,

review, and use of instructions and procedures is to be monitored by

the operations QA supervisor as part of the station quality

surveillance program.

These commitments appear to be consistent with

the provisions of Regulatory Guide 1.33 and ANSI 18.7-1976/ANS-3.2.

Section 13 of the OAC&QAP delineates the requirements regarding the

content of various types of procedures and instructions.

These

requirements provide for the inclusion, as necessary, of items such

as purpose, references, prerequisites, precautions, limitations,

step-by-step instructions, acceptance criteria, and check-off lists.

Station manuals contain administrative procedures which describe

activities and reference implementing instructions.

As appropriate,

the procedures for an activity may themselves contain the necessary

instructions.

Implementing instructions may be contained in the

cognizant activity manual with associated administrative procedures,

-

-

- -

-25-

.

A

f

or may be in a separate station manual. Typically',' manuals cover

station administration, engineering, operations, maintenance, and

station refueling.

To verify implementation of the operations procedural control

program, a' sample of procedures / instruction governing and directing

maintenance, engineering, quality, and operations-activities was-

~

reviewed.

It was observed that the pro,cedures/ instructions were

,

prepared, reviewed, revised and distributed in accordance^with FSAR

commitments. All procedures / instructions which are safety-related

were reviewed by quality.

This review was' performed and documented

using the QA department procedure / instruction reviek sheet'-

(Attachment 1 to QAI-008).

Each procedure / instruction was; reviewed <

to determine if it adequately addressed the applicable' requirements

of the FSAR; associated specification (design and/or technical

>

specification, as applicable); Regulatory Guides; other site

procedures, instructions, and plans; nuclear industry standards

'

(i.e., ANSI N18.7-1976); OAC&QAP; and any other related documents;

i.e., NUREG, NRC Bulletin, Information Notice, and Circular.

To ascertain if the allegation was time dependent, the operations

quality surveillance reports which appraised procedural control for

operations and maintenance were reviewed.

Three such reports were

Quality Surveillance Reports QAR 85-001, QSR-003, and QSR-006.

These surveillances were conducted from October 14, 1984, to

January 24, 1985. Approximately 2000 hours0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> were spent providing

24-hour coverage by the operations QA staff during the performance of

these surveillances.

During the surveillance review of maintenance procedures, two

deficiency reports were written against several maintenance

surveillance test procedures for not complying with the OAC&QAP, ANSI

N18.7Property "ANSI code" (as page type) with input value "ANSI</br></br>N18.7" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., NUREG/CR-1369 and STA-702 requirements.

The NRC inspector

reviewed the deficiency reports and noted that resolutions were

timely and approved by the surveillance technician who initiated the

deficiency report.

No deficiency reports were written, however,

against operations procedures for not complying with the FSAR,

OAC&QAP, or NRC requirements.

Several deficiency reports were

written concerning procedural implementation and use.

The overall

summary from the surveillance reports was that the operations QA

program, including procedural control, was satisfactory.

The

identified deficiencies principally related to the station's

implementation of specific requirements.

Based on the NRC's assessment of the operation procedures / instruction

control programs, the allegation that maintenance and operations

procedures were not consistent with commitments to ANSI and

Reguistory Guides could not be substantiated.

However, from reviews

of past operations QA surveillance reports, minor deficiencies in

maintenance procedures not complying with ANSI and Regulatory Guides

requirennts have been identified, but none were identified against

- -

-

-

-

-

- - -

-

-

-

-

-

-

- -

- -

- -

-

- -

-26-

operations procedures.

It is possible that in the past there was

some substance to the allegation.

Currently, the

procedural / instruction control program appears consistent with

requirements.

f.

AQ-167 (4-85-A-18):

It was alleged that a B&R inspector performed

inspections of ASME activities for which he was qualified but not

certified, and subsequently his certification was predated by

. management.

A review of the B&R ASME procedures was i:onducted to determine if

procedurally it was permissable to (1) predate inspector

~

certifications or (2) perform inspections between qualification

testing and certification issuance, as alleged.

It was found that

neither of these two activities was permitted by procedure.

The

interval between qualification testing and certification issuance is

normally used by the certifying Level III to determine if the

candidate has met all certification prerequisites. '

^

A selected sample of B&R ASME inspector qualification and training

files (obtained from the permanent plant' records vault) were reviewed

for predating of certifications.

The certifications, including those

of the inspector alleged to have been improperly used, did not

disclose any predating or other irregularities (e.g. , white-outs or

undocumented changes to record content), which would appear to have

been falsification of records.

With respect to inspectors performing inspections between

qualification testing and certification issuance, a sample of

certification dates versus qualification testing dates were compared

with completed inspection records.

The time period selected was from

May 1982 to July 1984, the time frame of the allegation.

The

interval between testing and certification was found to vary from 1

to 67 days; the average being 8.4 days.

Inspection records (traveler

packages) were searched to identify all inspections performed by each

inspector in the sample, beginning with the time of qualification

testing to 6 or 8 months after certification.

The expansion of the

interval beyond certification issuance was to account for any time

lag that may have been associated with traveler package closecut.

In

every case, the NRC found inspectors were certified prior to the

performance of inspections.

In summary, the NRC did not find evidence of predating of B&R

inspector qualifications.

Certifications reviewed did not have any

apparent indications of falsification, neither were any instances

observed of inspectors performing inspections during the interval

between qualification testing and the issuance of certification.

Accordingly, this allegation was not substantiated.

-

-27-

g.

AQ-146 (4-85-A-15), AQ-151 (4-85-A-30), AQ-160 (4-85-A-31), and

AQ-164 (4-85-A-32):

It was alleged that plant operations management does not accept

deficiency report and surveillance findings identified by the

Construction Startup/ Turnover Surveillance (CSTS) group on operations

activities.

Examples identified were:

(1) a CSTS inspector found

inconsistent or ineffective implementation of procedures, but

operations did not provide feed back, thus CSTS had no knowledge of

any action taken (AQ-164); (2) operations had an uncooperative and

unresponsive attitude towards CSTS findings (AQ-146); and

(3) Surveillance Deficiency Report (SDR 84-12) involving operations

procedures, identified an adverse trend that did not appear to have

been acted upon by either operations or QA management (AQ-151 and

AQ-160).

The substance of the current allegations were considered by the NRC

in Appendix 0 of NUREG-0797, Supplement 11 during the assessment of

Allegation AQ-112.

Under most circumstances, allegation (s)

previously assessed by the NRC would be relied upon without further

assessment; however, because these issues were identified by several

different individuals, the NRC r'ected to reassess these specific

issues.

The roastessment also was to assure that the previous

assessment had addressed all relevant aspects of these issues.

The basis for AQ-146 and AQ-164 was what the CSTS group perceived as

a failure to follow procedures by the operations personnel.

Instances cited by the CSTS group were first reported to the

operations plant manager for action to prevent recurrence in TUGCo

Interoffice Memorandum (memo) No. DQA-84164, dated June 27, 1984.

By

July 6, 1984, the CSTS upgraded its findings and observations to an

SDR (84-012) which required a formal response within 7 calendar days.

The SDR's description of the reported deficiency was, " Review of Test

Deficiency Reports and observations during preoperational. tests has '

revealed an adverse trend in the area of operations and compliance to

sound operational principles, procedures and instructions.

Ref:

DQA 84164, SWA 20563, and attached TDR's (2822' 3075, and 3061)."

,

AQ-151 and AQ-160 deals with the processing and resolution of

SDR 84-012.

In a July 10, 1984, joint meeting with CSTS and operations personnel,

as documented in memo DQA-84182 to operations from the CSTS

supervisor, it was acknowledged that since " . . . the problem areas

identified in the above CSTS-SDRs (which included DQA-84164 and

SDR 84-012) had been identified by your staff and were being

investigated, no reply to this office is required." Nonetheless,

operations QA responded to the CSTS concerns in memo QIM-84116, dated

October 1, 1984.

Based on the information provided in QIM-84116, the NRC inspector

verified that the CSTS concerns expressed in DQA-84164 and SDR 84-012

- -

- .

-

-

.

-

.

-

-

-

- -

-

,

,

}

-gg.

.,

,had indeed been identified by operations QA personnel before being

-identified by the CSTS personnel.

QIM-84116 also provided the

' resolution of the CSTS concerns or the justification why no action

was required. The NRC inspector evaluated the disposition of the

CSTS concerns by operations QA and found them appropriate.

The allegation that' plant operations management did not accept

findings. identified by.the CSTS group could not be substantiated,

either in earlier or current NRC inspections.

Operations personnel

were found to respond to CSTS findings, observatior.s, and SDRs in a

cooperative and responsive manner.

Also, CSTS had knowledge of-

actions taken by operations with respect to'the. specific CSTS

findings in this allegation.

h.

AQ-158-(4-85-A-31):

It was alleged that there was no documentation

(records) for.surveillances in the construction areas for 1983

through mid-1984. Although surveillances or surveillance programs

are not an NRC regulatory requirement, TUGCo is committed to

surveillances by Section 17.1.1.1.1 of.the CPSES FSAR which states:

- The Quality Assurance Division is. responsible for the development,

"

implementation, and surveillance of the TUGCo Quality Assurance

program for design and construction.

This. responsibility extends

into all project activities including engineering, design,

procurement, and construction."

The NRC inspector interviewed _the QA and QC surveillance supervisors

and found that the allegation pertained to surveillance activity

performed by QA personnel who reported to the TUGCo. site QA

supervi sor.'

The surveillances were conducted in accordance with

TUGCo Procedure CP-QP-19.6, " Monitoring of Construction and

Installation Activities."' Revisions 2, 3, and 4 of the procedure

.

were applicable for the time frame'of the allegation.

For

clarification of the terminology,. monitoring versus surveillance,

although the procedure:is entitled monitoring, the activity is

commonly referred to as surveillance.

'

,

TUGCo Procedure CP-QP-19.6 stated that its purpose was 'to outline the -

method used to monitor quality related a6tivities to assurel ,

compliance to approved instructions, p'rocedures'and/or drawings

'

implementing the requirements of the B&R QA manual (QAM)l'and the

TUGCo CPSES QA plan. The procedure further states,," Construction ~<-

monitoring shall be performed by assigned personnel usini dstalled

checklists prepared from the B&R QAM and implementing procedures.

'

Assigned personnel shall verify complianca of the delineated

activities through observation of work activities, discussions with

'

cognizant personnel, and review of objective. evidence.

The results

,

I.

of the monitoring activities shall be documenteo on the checklist for'

l

subsequent review by the TUGCo Site QA. Supervisor'or his designee."

i

Additionally, the procedure addresses reporting and followup,'the "

frequency of monitoring, corrective action trends, and files.

i

,

-29-

The NRC inspector found that the non-ASME surveillance schedule for

1983 (Ref: office memorandum TUQ-1491 dated December 8, 1982) called

for 12 surveillances and designated the activity to be covered. The

NRC inspector's review of the surveillance record documentation found

that 19 surveillances were performed. However, only the scheduled

January surveillance was conducted in accordance with the schedule

for the activity specified.

Four of the other scheduled activities

were accomplished, but not in the month scheduled. The seven

surveillances conducted in February, April, July, August October,

November, and December were not those required by the schedule. The

departures from schedule were discussed with the QA supervisor who

explained that the schedule had been revised; however, he could not

produce a copy of the revision for the NRC inspector to review.

The NRC inspector reviewed the surveillance records for 1983 and

found that the checklists revealed that some of the surveillances

covered only a review of procedures. Since the stated purpose of

Procedure CP-QP-19.6 is to monitor construction and installation by

observations of work activities, discussions with cognizant personnel

and review of objective evidence, the NRC inspector found that those

surveillances consisting only of a procedure review did not comply

with the monitoring procedure. Some of the surveillance records

contained duplicate checklists which were marked to identify that one

was used for procedure review and the other used for verification of

implementation. Although the implementation checklist implied that

work activity was observed, and the lists were checked " SAT" or

"UNSAT", the construction / installation activity observed and the

objective evidence reviewed by those doing the surveillance were not

identified in the surveillance records.

In the review of the

surveillance records and discussions with the QA supervisor, the NRC

inspector found that the emphasis of the surveillance program appears

to have been on procedure reviews rather than observations of

construction / installation work activities and review of objective

evidence for those activities, which were the methods described in

the procedure.

During the NRC review of these surveillance records, several

anomalies were noted that included:

(1)checklistattributeswere

not checked, or were crossed out without explanation; (2) checklists

did not identify the person who completed the list; (3) some

checklists in the record file were not accompanied by the

surveillance report; and (4) there was no evidence that surveillance

reports were reviewed by the site QA supervisor. These conditions,

which are procedural noncompliances, reflect poor practice and are

indicative of ineffective implementation of the surveillance program.

The current surveillance program is conducted under the

responsibility of a surveillance supervisor and the structure of the

organization divides the surveillances into four separate well

defined tasks which cover: documentation, inspection, startup/ turnover

and construction.

New program procedures have been prepared

i

_

_ _

- . - - -

- _

_-.- -

.

.

_

,

-30-

,

a'nd issued and more controls imposed for performing, reporting.

- evaluation, and for trending the results of the surveillances.

In summary, this allegation has been substantiated in part, in that

surveillances were conducted but they were poorly documented.

In the

1983 timeframe, numerous departures from procedures were identified;

-

,

'

however, this problem appears to have been recognized by the

,

-

applicant in that the site surveillance program has since been

reorganized and restructured. The currsnt surveillance program,

which appears to be an improvement over the program in place in 1983,

is scheduled for NRC ir.spection during the next report period.

.

j

i

s

,

!

i.

AQ-154 (4-85-A-30):- It was alleged that a Section XI QA surveillance

'

>

supervisor incorrectly changed a procedure in order to disposition

1

-

,

deficiencies that were reported in a deficiency surveillance

report (DSR).

.

The NRC assessment of the allegation found that TUGCo QA surveillance

i

report DSR-85-013 dated February 28, 1985, reported a deficiency that

one work authorization per Section XI program (WASP) form did not

identify the applicable drawing number and that seven WASP forms,

'

although the _ drawing number was identified, did not indicate the

1

drawing revision. The omission of the drawing and/or revision number

!

!

was contrary to Section 3.2 of Procedure CP-XI-4.8, Revision 1,

" Preparation, Review, Control and Distribution of ASME Section XI TNE

)

De. sign Drawings."

Disposition of the cited deficiency was documented in TNE office

memo TSG-8762 dated April 1, 1985, to the QA surveillance supervisor.

The TNE disposition was to correct the deficient WASP forms by adding

the necessary drawing and revision numbers as well as a proposed

revision of Procedure CP-XI-4.8 eliminating the requirement for a

drawing revision number. The TNE proposed revision of

Procedure CP-XI-4.8 did not provide any justification for deletion of

the drawing revision numbers required on the WASP form other than to

prevent recurrence of the deficiency. The surveillance package also

contained documentation that the QA surveillance supervisor accepted

the THE disposition and reouested the formal revision to the

.

procedure. The NRC inspector found that the revised procedure

deleted the words " Revision Numbers" from Section 3.2.

1

,

The alleger had stated that the QA surveillance specialist that

4

perfomed the surveillance, and was responsible for closure of the

deficiency after the corrective action was addressed, disagreed with

,

'

the QA supervisor's acceptance of the corrective action because there

could be a later problem. The NRC inspector interviewed the QA

>

<

supervisor, but was unable to ascertain what the potential problem

!

was that concerned the surveillance specialist.

In further

discussion with the NRC inspector, the QA supervisor explained that

his basis for' revising the procedure in accordance with the TNE

disposition was justified by the fact that the work package that

!

'

..

a

v

-~--

,e

-- - - -

--,---,---..w

m, - , - - ,n,

w.en--

,~mu--,-,<

---m-

m,.n-n,-a

,,,, ,--

,-,n,,

.-,,.,----------------r---

e-,,r,, - - - - - - - --

--

_

_

. _ ___._ _

<

-31-

contains the WASP form also contains the actual drawings.

In

addition to the WASP form and applicable drawings, a package

inventory card is included in each work package that lists the

package contents, including drawing numbers and revisions, as

required by Procedure CP-CPM-7.1A, Revision 2, "Ducumentation Package

Preparation."

To verify the process described by the QA supervisor and the

implementation of Procedure CP-CPM-7.1A, the NRC inspector reviewed

the contents of 21 completed WASP work packages taken from the

interim records vault.

In every package, copies of the applicable

drawings were included, each package invertory card correctly listed

the contents of the package including drawing numbers and revisions,

and in all but three packages the WASP form included the drawing

revision number even though no longer required by Procedure CP-XI-4.8.

Therefore, the identification and control of these documents are

being maintained.

While the alleged actions did occur, the deletion of the revision

requirement on the WASP form from the procedure as corrective and

preventive actions does not appear to have been improper or

incorrect. The control of documents is still maintained through the

package inventory card in each package and the existence of the

drawing itself in each package.

J.

AQ-147 (4-85-A-30):

It was alleged that a TUSCo report to the NRC

may be misleading because it presented surveillance data concerning

welding supervisors' knowledge of procedural requirements which

occurred after the training had been conducted.

The NRC inspector reviewed TUGCo QA surveillance report DSR 85-004

dated January 18, 1985, which was referred to by the alleger, and

interviewed the QA surveillance supervisor, a QA technician in the

surveillance group, and the project welding engineer to obtain some

of the details necessary for this assessment.

The document review and interviews revealed that the surveillance was

performed as part of TUGCo's corrective action in response to

concerns which were raised as a result of an NRC site inspection tour

on January 10, 1985. This concern stated that it appeared that two

craft weiding supervisors lacked sufficient understanding of welding

procedure requirements, principally the control of weld filler

materials.

On January 11, 1985, a QA surveillance of craft supervisors was

initiated to determine the supervisors' knowledge of procedural

requirements. During the process of developing the methodology to

implement the surveillance, the QA supervisor instructed the QA

surveillance technician to develop a number of questions that would

be asked (verbally) of the supervisors. The questions were derived

from procedure CP-CPM-6.9B, " Weld Filler Material Control." The QA

L

__ _

__

-- --

-32-

surveillance group's evaluation of the accuracy of the craft

supervisor's answers to the questions would reveal the need for and

the extent of training for craft supervisors.

The surveillance was interrupted by management because a training

session had been scheduled for craft supervision on January 12, 1985,

making the surveillance unnecessary.

The NRC inspector verified

recorded evidence that procedure training and testing was conducted

as follows on January 12, 1985:

All craft supervisors - CP-CPM-6.98, " Weld Filler Material

Control"

Structural, Iron Workers and Millwright Supervisors - WES-29,

'" Welding Specification for Field Fabrication and Erection of

Structural Steel"

Fabrication Shop and Component Supports Supervisors -

CP-CPM-9.10 " Fabrication of ASME Related Component Supports"

Piping Supervisors - CP-CPM-6.9D, " Welding and Related

Processes."

On January 15, 1985 (after the training session), a surveillance was

conducted using the questionnaire developed on Jantary 11, to assess

the effectiveness of the January 12 training.

The surveillance

report stated that there were no QA concerns pertaining to the

supervisor's knowledge of the procedural aspects in the control of

weld filler material.

The NRC inspector compared the above actitns and their sequence with

the information contained in a January 15 1985, TUGCo letter to the

NRC.

The letter presented an accurate saquence of events and a brief

but correct description of actions taken.

One statement in the

letter could be viewed as misleading ("It appears that two. craft

welding supervisors lacked sufficient understanding of welding

procedure requirements."); however, this' statement refers to the

supervisors interviewed by the NRC during the site tour on

January 10.

This report goes on to clearly state that the training

of all supervisors was conducted on January 12, 1985, and that a

surveillance was being conducted to assess the effectiveness of the

training.

,

The inspection finds that the TUGCo report of actions regarding the

training of craft supervisors adequately and accurately responded to

the NRC's concern.

Accordingly, the allegation was not

substantiated.

L

.

-33-

7.

Pipe Support Modifications

Modifications to pipe supports resulting from design reviews by Stone &

Webster Engineering Corp. were addressed during this inspection.

Specific

attributes covered included control of design changes, work traveler

generation, and adequacy of modification implementation.

Pipe supports-

were evaluated to identify any probable potential for shifting or moving

into a position other than the position assumed in the piping stress

analysis.

Supports found to exhibit such probable potential behavior are

by procedure, either removed or modified to eliminate the probable

potential instability.

Definitions, examples, and corrective action for

identified supports are provided in Procedure CPPP-7, Revision 1,

Attachment 4-9, " Procedure for Identification and Correcting of Potential

Unstable Configurations." This procedure along with TUGC0 Nuclear

Engineering (TNE) Instructions TNE-AD-4-5, Revision 1, " Control of Unit 1

Pipe Support Drawings," and TNE-DC-21-1, Revision 1, " Preparation of Field

Design Changes for Pipe Support (s)," were reviewed by the NRC inspector.

The TNE instructions reviewed provide the programmatic control of design

changes for Units 1 and 2, respectively.

The NRC inspector verified that

all pipe support modifications are required to be reviewed by the

responsible pipe support engineer against the design information provided

in the pipe stress analysis to assure that the modifications do not affect

the original pipe stress analysis inputs.

This requirement is contained

in Project Procedure CPPP-9, Revision 1, " Pipe Stress / Support As-Built

Procedure."

The NRC inspector selected the following design change packages (DCPs) for

inspection of implementation of the reviewed programmatic requirements:

DCP NO.

SUPPORT NO.85-065

CT-1-039-008-C42R

85-122

CC-1-226-004-C53R

85-011

SI-1-102-007-041R-

85-047

CC-1-211-003-C53R

85-043

SW-1-129-736-A43R

85-038

FW-1-D17-707-C72K

85-048

CC-1-217-012-C53S85-107

CC-1-234-016-C53R

85-009

MS-1-SB-056-003-3

85-022

CC-1-204-003-C53R

The design calculations for DCPs85-011 and 85-047.were reviewed.~ The

work orders, travelers, inspection reports, material identification-log,

weld filler material log, and multiple weld data cards were reviewed for

items85-065 and 85-122. With the exception of DCPs85-011 and 85 047,

all'DCPs listed were inspected to verify that the supports subject to

engineering modifications were identified on the revisions to the pipe

support drawings.

,

'

_ _ . _

--

-

-34-

The following supports were addressed in Unit 2 for verification of

conformance to the design change control requirements:

a.

CT-2-053-402-C625

b.

CT-2-053-444-C62K

c.

FW-2-096-435-C62R

d.

CC-X-908-703-E23K

c.

CC-X-909-703-E23R

The design calculations for items b and c above were reviewed.

The

inspection reports, multiple weld data cards, and weld filler material log

for all items were reviewed.

Items d and e above were inspected as

installed to verify conformance to the engineering drawings and QC

inspection reports.

The results of the inspection performed by the NRC inspector indicated

correct implementation of the programmatic design control requirements and

conformance with applicable design criteria.

No NRC violations or deviations were identified.

8.

CPRT ISAPs (Excluding ISAP No. VII.c)

a.

Electrical

(1) Heat Shrinkable Cable Insulation Sleeves (ISAP No. I . a.1)

This ISAP arose from the NRC Technical Review Team (TRT)

identification that craft and inspection personnel lacked

familiarity with procedural requirements governing the

installation, inspection, and documentation of heat shrinkable

cable insulation sleeves.

To correct this situation and assess

plant status, the ISAP identified the following activities:

Activity

ISAP

NRC

Paragraph No.

Reference No.

Revise Construction Procedure EEI-8

4.1.1

01.a.01.01

EEI-8

Revise Inspection Procedure

4.1.1

01.a.01.02

QI-QP-11.3-28

Revise Inspection Forms

4.1.1

01.a.01.03

Train Craft Personnel

4.1.1

01.a.01.04

Train / Certify Inspection

4.1.1

01.a.01.05

Personnel

Identify Required Sleeve Locations

4.1.2.1

01.a.01.06

Establish Sampling Plan / Select

4.1.2.2

01.a.01.07

Review Inspection Reports (I.R.s)

4.1.2.2

01.a.01.09

Visual Hardware Inspection

4.1.2.2

01.a 01.10

Inspection 7 Cables /26 Equip.

4.1.3

01.a.01.11

Items

-

-35-

_

Review I.R.s for 7 Cables /26 Equip.

4.1.3

,'

01.a.01.12

Issue Non-Conformance Reports

4.1.4-

'01.a.01.08

Establish Root Causes/ Implications /

4.1.4

01.a.01.13

~ Safety

Identify Corrective Action

4.1.4.

01.a.01.14

,

The above identified activities have reportedly been completed

by CPRT.

However, the final results report has not yet"been

,

issued and assembly and review of-the working files have not yet

been completed.

,

Final NRC evaluation of the activities will ~be-initiated upon -

CPRT completion and review of.the working files for this. ISAP

and issue of the results report.

,

_

-

+

,

'

(2)

Inspection Reports on Butt Splices (ISAP No. I.a.2)

The applicant's response to the TRT inspections nd evaluation

of butt-splice installations is contained in ISAP Nos. I'.a.2 and

I.a.3.

The TRT's inspection findings evaluation and required

applicant actions are specified in NUREG-0797, Supplement.No. 7,

pages J-28 through J-31.

The scope of ISAP No.I.a.2 includes all butt-spliced Class IE

essantial and associated cables which are spliced with the AMP

preeinsulated butt-splice connectors.

This ISAP is divided into

three phases, with the objectives being to assure that the

splices are identified on drawings and are properly installed.

The program proposed by the applicant in response to the TRT

concerns requires the following activities to be performed:

IdAP

NRC

Activity

Paragraph No.

Reference No.

Phase I

Review Inspection Reports

4.1.1

01.a.02.01

on Butt Splices

Phase II

Drawings and Design Change

4.1.2

01.a.02.02

Reviews

Inspection of Cables for

4.1.2

01.a.02.03

As-Built Condition

Doc. Review of I.R.s for

4.1.2

01.a.02.04

Cables Inspected in

01.a.02.03

Revise Drawings to Match

4.1.2

01.a.02.05

As-Found Condition

L

-

-36-

Replacement of Rejected

4.1.2

01.a.02.06

Splices

Pullout Test and Radiograph

4.1.2

01.a 02.07

Replaced Splices

Inspection of Cabinets

4.1.2

'

01.a.02.08

'

Which Contain No Spliced

Cables

Inspection of Adjacent

4.1.2

01.a.02.09

Splices in Same Wire

Bundle

Phase III

Ident. of Spliced Cables

4.1.3

01.a.02.10

not Inspected in

01.a.02.03

Inspecticn of Cables

4.1.3

01.a.02.11

s

Identified in 01.a.02.10

NCRs Issued for Cables

4.1.3

01.a.02.12

Identified in 01.a.02.10

CPRT Overview of TUGC0 Insp.

4.1.3

01.a.02.13

Performed for 01.a.02.11

General

Root Cause and Corrective

4.1.4

01.a.02.14

Action

Training of Third Party

4.3

01.a.02.15

Inspectors

Inspectors Certified to

4.3

01.a.02.16

ANSI N45.2.6

Personnel Meet CPRT Quali-

4.3

01.a.02.17

fications and Objectivity

Requirements

The NRC inspectors have reviewed selected information from the

CPRT working files to assess the status of this ISAP.

The

results of the Phase II inspections were reported in previous

inspection reports, as have the results of those Phase III

inspections witnessed by the NRC inspectors.

Final NRC

inspector evaluation of the above activity items will be

addressed as the actions, and related files, are completed and

upon issue of the results report.

(3) Butt-Solice Qualification (ISAP No. I.a.3)

The objectives of this ISAP are to develop adequate procedures

to assure that continuity checks are performed on all circuits

in which splices are installed and that splices are staggered or

. -

.

-

...

-

-

-.

-

-

.--.

.

w

t

'

'

-37-

4

r

' separated.

A review of the qualifications of AMP pre-insulated

environmental seal splices will be made to assure'that it is-

"

. qualified for.its expected service.

The program proposed by the

applicant in response to the TRT concerns requires the.

following:

s

,.

'

ISAP

NRC-

Activity

Paragraph No.

Reference No.

Revise Procedure EEI-8

4.1.1

01.a.03.01

Revise Procedure

4.1.1

01.a.03.02

Q0-QP-11.3-28

Train Crafts to Revised

4.1.2

01~.a.03.03

Procedures

Train and Certify Inspectors

4.1.2

01'a.03.04

.

,

i-

to Revised Procedures

Repair of Adjacent-Splices

4.1.3

01.a.03.05

in Same Wire Bundle

Prepare Data Qualification

4.1.4

.01.a.03.06'

Package

,

Third Party Engineering.

4.1.4

01.a.03.07

Review of Data

"

Qualification Package

Replacement of Unqualified

4.1.4

01.1.03.08

.

Splices

_~

!~

Root Cause and Corrective

4.1.5

01.a.03.09

  • -

Action

'

,

'

NRC inspector review of the CPRT working files indicated that

.

revision evaluation is pending the, completion of'the required

'

actions, assembly and review of files, and issuance of the

i

results report.

!

.

,

'

l

(4) Agreement Between Drawings and Field Terminations (ISAP No. I'.a.4)

'

ThisISAParosefromaTRTinsp'e~ctionof'380 cables,*6Iofwhich

'

I

were not terminated in accordance with. current-drawings.

The.

.

l

-ISAP involves reinspection of essential class,'IE conductors

(-

which interface with the alternate shutdown panel and inc10 des

'

'

the following activities:

!

ISAP'

NRC-

Activity

Paragraph-No.-

. Reference-No.

i.

.

.

'

l

Establish Sampling Plan

4.1.1

01.a.04.01

.

Perform Physical

4.5.1-

01.a.04.02-

l

. Reinspection

Reconcile Differences

4.6

01.a.04.03

i

i

I

t

i

L.=

.

.

.

.

. .

.

. - .

-

.

.

- .

.

. .

. _ .

.

_

_

__ _ .__ . _

t

-38-

Determine Root Cause and

4.1.2

01.a.04.04

Corrective Action

^

ERC has reportedly completed _the reinspection activities

identified in this ISAP.

Final NRC evaluation is pending completion of the assembly and

review of the working files, and issuance of the results report.

(5) NCRs on Vendor Installed AMP Terminal Luos (ISAP No. I.a.5)

'endor installed AMP ring-torque terminal lugs in the Unit 1

V

6.9 KV switchgear cubicles were bent and/or twisted between the

ring-torque and barrel.

The NCRs which documented the.

conditions were determined by the TRT to be improperly

dispositioned,.in that the. full scope of the identified problems

were not addressed and the "use-as-is" dispositions were not

.

adequately justified.

In order to resolve the TRT concerns, the

-applicant was required to reevaluate and redisposition all NCRs

related to lugs.

,

The program proposed by the applicant, as set forth in

ISAP No. I.a.5, Revision 4, dated January 24, 1986, consists of

.the following activities:

ISAP

NRC-

Activity

Paragraph No.

Reference No.

Disposition of

4.1.1

1.a.05.01

Nonconformance

Vendor Analysis

4.1.2

1.a.05.02

Use of Results

4.1.3

1.a.05.~03

Related Activities

4.1.4

1.a'.05.04

'

The NRC inspector reviewed the CPRT working files"to evaluate

s

the status of these activities.

The results of this review are-

as follows:

(._

Disposition of Non-Conformance (NRC Reference-No.' 1.a.05.01)

,

..

The TUGCo Comanche Peak Project has redispositioned all of'the

original NCRs.on bent and twisted ring-torque terminals

'

.

(NCRs E-84-01066 through E-84-01081).

The redispositio'n,was in'

the form of two revisions to the applicable NCR;.the,first on

January 5, 1985, and the second on May 17, 19857 The'second

.-

revision addressed the use of twisted ring torque terminal ~-lugs

based on an AMP Engineering Evaluation ' Report 'which was attached .

~

to the NCR.

'

,

.

j

ReviewoftheNCRsbytheNRCinspector'confirmedihattheNCRs'

!

had undergone this redispositioning.

CPRT Electrical Review

team approval of the final disposition of'the NCRs had not,

1

however, been completed.

.

,, ,

~._,..y.

,

,_.,,,..-..,.,y-.-..

-

--

,_-,,,,.,-.,,..._,-.,,_~,_,-.,,,e.-

- . ,

,.m,

,,

,.c~

.

-39-

Vendor Analysis (NRC Reference No. 1.a.05.02)

As discussed above, the NRC inspector verified that an

engineering evaluation had been provided by the terminal lug

vendor, AMP.

The CPRT had not, however, as of the end of this

report period, formally accepted the completeness and adequacy

of this evaluation.

(6) Flexible Conduit to Fiexible Conduit Separation (ISAP No. I.b.1)

The separation between certain safety-related and non

safety-related flexible conduits inside control room panels was

not maintained in accordance with design requirements.

In order

to resolve NRC concerns, the applicant was required to correct

each violation of the separation criteria, or demonstrate the

acceptability of the conduit as a barrier.

The program proposed by the applicant to demonstrate the

acceptability of the conduit and its separation consists of the

following 10 activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Analysis of Circuits

4.1.1

1.b.01.01

Testing as a Short-Circuit

4.1.2

1.b.01.02

Current Barrier

~

'

Testing as an Overload Barrier 4.1.2

1.b.01.03

Test Procedures for the Above

4.1.2

1.b.01.04

Tests

Third Party Inspections

4.1'.3.2

1.b.01.05

.TUGC0 Inspections

4.1.3.2

1.b.01.06

Revision of Unit 2 Procedures

4.1. 4 -

1.b.01.07

Examinations of Other Panels

4.1.5

1.b. 01.03

'

Correction of Unit 1

- 4.1. 7

1.b.01.09

'

Deficiencies

3

.

.

,

Root Cause Determination

.4.1. 7

1.b.01.010

'

_.

Analysis of Circuits (NRC Reference No. 1.b.01.01).

.

The analyses to verify that the existin'g separation is. adequate

are being conducted by Gibbs and Hill.

Earlier analyses did not

contain sufficient detail to be considered acceptable'to the

CPRT.

The newer analyses will also include information from the

'

testing program to verify that the Sevicair conduit is an

adequate barrier.

_

_

.

.

-

. -

.

.-

--

-

..

.

.

-40-

,

Testing as a Short' Circuit Barrier, Testing as an Overload

Barrier, Test Procedures for the Above Tests (NRC Reference

,

'Nos. 1.D.01.02.-l.b.01.04)

-

The physical tests have been conducted as a two part program.

The first-test was designed to determine the adequacy of the

Servicair flexible conduit to provide a path-for a short circuit

'

'

current without damage to cables in adjacent or touching

conduits. 1This test was conducted-in.accordance with

Procedure I.b.1-001, "SERVICA.IR Short Circuit" Test."..Thie second

test was designed to determine the ability,.of the conduit'to act

as an effective barrier between, exposed. cables ^and adjacent or

,

touching conduit.

Procedure I.b.1-001, " Cable /SERVICAIR Heat;

Transfer Test," was written for this test.

The results.of these

-

tests are being evaluated.

-

.

ThirdPartyInspections(NRCReferenceNo.l'.b.01.05)

i

The third party QC inspectors have completed their'inspe'ctions

of the Unit 1 main control boards and two of the common ve'rtical

panels.

A draft tabulation of.these inspection results

'

indicates approximately 265 examples of improper conduit

L

separation or barrier installation.

These findings were

'

transmitted to the applicant for disposition.

Some of the

findings were, however, determined to be invalid by TUCGo

,

personnel, based on reinspections they performed using the

separation criteria being proposed rather than the original

Gibbs and Hill criteria.

l

The other reinspections, required by the applicant due to

revised separation attributes, have been completed, but the

reports have not been reviewed by the CPRT or NRC.

The

,

examination of the other panels for the presence of Servicair

.

conduit was initially completed, but the CPRT identified some

problems with the program which will necessitate some

reinspections.

.

The results of the analyses, test, and reinspections' are to be

-

!

factored into corrective actions.

For Unit 1, the problems

identified are being corrected through NCR dispositioning.

For-

Unit 2, the applicable drawing details were revised by a DCA and

,

the procedures were revised.

Th6 determination of a root cause

i -

and corrective action will be evaluated at the conclusion of the.

program.

,:

(7) Flexible Conduit to Cable Separation (ISAP No. I.b.2)

The separation between the Servicair flexible conduit and

certain safety-related and non safety-related cables inside

{

control room panels was not maintained in accordance with

i-

t

"

>

7

I

- . . . , -

- . .

. -

-

~ -

.

.

.-. -.

_._ . _ .-..-,..._.

. .

-

,-

-

-41-

original design requirements.

The program described in

ISAP I.b.1 incorporates all of the provisions necessary to

resolve this concern; therefore, ne additional requirements are

included in this ISAP.

(NRC Reference No. 1.b.02.01).

(8) Conduit to Cable Tray Separation (ISAP No. I.b.3)~

An analysis of the one-inch separation criteria between rigid

conduits and cable trays, contained in the Gibbs and Hill

electrical erection specifications,.had not been presented to

the NRC.

An analysis substantiating the acceptability of this

criteria is-required to be submitted to the NRC prior..to fuel

load.

As described in Section 4.1 of this ISAP, its objective is to.

substantiate the acceptability of the separation criteria.

Gibbs and Hill is to compile the criteria which,=after CPRT-

review, will be transmitted by the applicant to the NRC.

(NRC

Reference No. 1.b.03.01)

~

A CPRT review of the available information determined that

additional analyses were required.

These additional analyses

-

are being performed by Gibbs and Hill.

(9) Barrier Removal (ISAP Ho. I. b'.4)

The minimum separation of redundant class IE field wiring and

instrumentation was not maintained in accordance with design

requirements.

In order to resolve these TRT concerns, the

applicant was required to take corrective action to ensure that

the required minimum separation is maintained either by distance

'

or by an acceptable barrier.

The program proposed by the

,

applicant, as set forth in ISAP No. I.b.4, Revision 4, dated

January 24, 1986, consists of the following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Rework

4.1.1

1.b.04.01

Maintenance Procedures

4.1.2

1.b.04.02

Revision

Use of Results

4.1.3

1.b.04.03

The NRC inspector reviewed the CPRT working files to determine

the status of these activities.

Rework (NRC Reference No. 1.b.04.01)

NCR E-84-100524 was issued on October 9, 1984, to replace a

separation barrier between redundant electric train cables

within Unit 1 Control Room Panel CB-09.

The barrier was

-

,

. . , .

.-.

-.

-42-

replaced and the NCR was closed on October 19, 1984.

Physical

inspection of CB-09, by the NRC inspector, confirmed that the

barrier material had been' replaced.

Another NCR (E-84-100526) was issued on October 9, 1984, to

. retrain cable AG139390, located in CB-03, to meet the 1-inch

inspection criterion required by drawing 2323-31-1702-02, detail

61C. Work was completed and the NCR was closed October 19,

1984.

NRC inspection of control panel CB-03 confirmed that the field

cable had been retrained and a 1-inch minimum separation was

established.

No other NCRs had been issued.

Maintenance Procedures Revision (NRC Reference No. 1.b.04.02)

The-two procedures identified by the NRC inspector as being

associated with the ISAP activities are:

(1) I&C Maintenance-

Program Procedure No. INC-101, Revision 4, dated July 19, 1985;

and (2) Equipment Qualification Procedure No. MDA-107,

Revision 0, dated December 11, 1985. The first procedure was

revised to specify that maintenance of barriers and train

separation shall require explicit instructions via a

safety-related work order.

The second procedure was newly-

written to address equipment qualification and specifies the

control to be used for separation and fire barriers.

NRC inspector's review of these procedures found them to be

acceptable.

The Review Team Leader (RTL) had not, as.of the end

of this report period, documented the results of the review

team's evaluation of these procedures.

b.

QA/QC

(1) QC Inspection Qualifications (ISAP No.~ I.d.1)

,

,

This ISAP is a response to the -TRT identification of;a' lack of

supportive documentation in the training and certification files

regarding QC inspector qualifications.

Specific activities of

the action plan are delineated in the following t'able:

-

.

.

ISAP

NRC

Activity

Paragraph No.

Reference No.

TUGC0 Audit Group (TAG)

4.1.1.1

1.d.1.01

Review of Non-ASME Files

,

ERC Review of ASME Files

4.1.1.2

1.d.1.02

._

-43-

3

Special Evaluation Team

4.1.2

1.d.1.03

(SET) Evaluation of ASME

and Non ASME Inspector

Qualifications

Phase III Sample Selection

4.1.3

1.d.1.04

and Reinspection

Qualification of Personnel

4.3

1.d.1.05

Evaluation of Results

4.6.3 & 4.6.4

1.d.1.06

TAG (NRC Reference No. 1.d.1.01)

This activity was initially reported in NRC Inspection

Report 50-445/85-13; 50-446/85-09.

The NRC inspector reviewed

the checklist used in the TAG review of non-ASME inspectors and

ascertained that it included the guidelines in ANSI N.45.2.6

(1978); Regulatory Guide 1.58, Revision 1; and TUGCo site

inspection procedures.

The NRC verification that this activity

meets the requirements in paragraph 4.1.1 of this ISAP is

complete.

ERC ASME (NRC Reference No. 1.d.1.02)

This activity is complete except for review of non-ASME

certifications held by ASME inspectors (0 pen Item 445/8513-0-03).

NRC inspection of this activity was previously reported in NRC

Inspection Report 50-445/85-13; 50-446/85-09.

Open

Item 445/8513-0-04 from the same report was written concerning

the adequacy of GED test scores without the accompanying diploma.

These two items remain open.

The requirements derived from ERC review of certifying /

qualifying procedures for ASME inspections were formatted into

matrix form which was used during ERC review of ASME inspector

qualifications.

The matrix parallels the requirements of

ANSI N45.2.6 (1978) and Regulatory Guide 1.58, Revision 1.

The

ERC review was documented in an ERC memo to the I.d.1 file. As

previously reported, the NRC inspector insp.ected'10% of the ERC

review of ASME inspector files.

-

,

NRC inspection of this activity (paragraph 4.1.1.2) is complete

except for Open Items 445/8513-0-03 and 445/8513-0-04.

.

+

.

SET on ASME and Non-ASME (NRC Reference No. 1.d.1.03),

,

NRC inspection of this activity was initially 'eported in NRC

r

Inspection Report 50-445/85-13; 50-446/85-09.

The SET evaluated

ASME and non-ASME inspectors whose qualifications were

questioned by TAG or ERC evaluations.

The SET evaluation was

performed using the criteria in paragraph 4.1.2 and

Attachments 1 and 2 of this ISAP.

Results of the SET review

. _ ,

.

. . . -

-

.

.

.

.

.

.

- .

,

-44-

,

were documented on certification summary sheets.

The NRC

inspector reviewed 10% of.the complete certification summaries

by comparing the summary data to data in.each inspector's

qualification / certification file.

The NRC. inspector found that

the SET evaluations identified the inspectors whose

,

1

qualifications files did not meet requirements.

TUGCo will'be

contacted to ascertain if additional information is available.

NRC' inspection will continue as additional summary sheets are

completed.

$

_ Phase'III Sample Selection and Reinspection (NRC Reference

No. 1.d.1.04)

E

This activity was initially reported in NRC Inspection

Report 50-445/85-13; 50-446/85-09.

The NRC. inspector witnessed

10% of. Phase III reinspections to. verify that they were

+

conducted in accordance with'the requirements of the ISAP.

An

additional 5% of Phase III reinspections have been independently

verified by the NRC inspector. 'All reinspections were performed

j-

to the original inspection procedure by a Level'.II.TUGCo

inspector with a 100% overview by a-Level II ERC inspector.-

-

Deficiencies were documented on NCRs.

The reinspection samples were prepared by TUGCo.

NRC inspection

^

.

showed that these were the first 90 days of recreatable and

4

is

accessible inspections, with a minimum of 50 inspections.

If

'

50 inspections were not made in.the first 90 days, additional

sequential inspections were added'until 50 inspections or 100%

of the inspector's work was reinspected.

[

ERC personnel reviewed 20% of the inspections designated non-

!. .

recreatable by TUGCo to determine if the' inspections were

i

non-recreatble.

The NRC inspector. duplicated-25% of_the ERC

reviews and found that these inspect. ions _were.not recreatable

due to rework subsequent to the original,. inspection. -

a:

,

,.

.

, r ' -

.ERC reinspections were documented in a matrix approved by an ERC >

Level III inspector.

This matrix documentsithe. inspection

'

. attribute as accessible, recreatable, objective, subjective, and-

-

the acceptability of the attribute per.the' original' inspection ~

requirements.

The definitions of " inaccessible" and "not

recreatable were as given in Appendix B~ of the CPRT Program

Plan and further defined for Phase III of this ISAPiin ERC

l

QI-005.

NRC inspection of this activity will continue as

further Phase-III reinspections are performed.

-

l

Qualifications of Personnel (NRC Reference No'. 1.d.1.05)

The TAG personnel performing the independent assessment of

non-ASME inspectors in Phase I were verified to meet the

!

,

5

9

.

-

, . _ . - .

,

_,. -.

, . _ . . , _ _ _ _ , . _ . _ . _ . _ , _ . - . . . - . _ _ , _ - . - - - . . _ . . _

.

.

~

.

J

g

r.

- . ,

-45-

. "

,

requirements of DQI-QA-2.1, " Qualification of Audit. Personnel,"

during NRC inspection of the Dallas QA audit files.

The ERC personnel performing the review of-ASME inspectors, the

Issue Coordinator, and the RTL were found to meet the

requirements of the CPRT Program Plan by NRC review of their

resumes and objectivity questionnaires.

The same personnel

worked on ISAP Nos. I.d.2 and I.d.3 and met the qualification

requirements for those ISAPs.

-

Third party'and TUGCo inspectors were verified to meet the

requirements of ANSI N45.2.6 and Regulatory Guide 1.58 by review

of the certification files for all inspectors performing

reinspections in Phase III.

SET personnel were verified-to meet the specific requirements of-

ISAP Nos. I.d.1, I.d.2, and I.d.3 by review of their objectivity

questionnaires and resumes in ERC personnel files. 'All three

members met requirements.

'

NRC inspection of this item is complete. - If additional

-

personnel are to be utilized,- their qualifications will be

verified'per the CPRT Program Plan.

!

'

(2) Guidelines for Administration of QC Inspection Tests (ISAP No. I.d.2)

This ISAP is in response to the TRT identification of a lack of

guidelines and procedural requirements for testing and

certifying QC inspectors.

Specific activities of the ISAP are

delineated in the following table:

ISAP

NRC

. Activity

Paragraph No.

Reference No.

SET Review of Procedures and

4.1.1

1.d.2.01

I

and Recommended Changes

!

TUEC Evaluation of Recommen-

4.1.2

1.d.2.02

'

datiens and Revision of

Instructions

SET Evaluate Effectiveness of

4.1.3

1.d.2.03

Revisions

Qualifications of Personnel

4.3.

1.d.2.04

l

SET Review of Procedures (NRC Reference No. 1.d.2.01)

The SET is comprised of individuals independent'of the,CPSES

I

inspector / certification progra.a.

Their. qualifications and ^

objectivity were verified by NRC' review of their objectivity-

  • i

.

1

L

'

-

_

-46-

questionnaires and resumes from the ERC personnel files.

These

-

documents showed that the qualifications required by the ISAP

were met.

The SET review of training procedurer, was initially reported in

NRC Inspection Report 50-445/85-13; 50-446/85-09.

SET review of Procedures CP-QP-2.1, " Training of Inspection

Personnel," and QI-QP-2.1-23, " Training / Certification Records

Processing," is complete.

The results of the SET review have~

been inspected by the NRC to verify that the review criteria

considered FSAR commitments and the requirements of

paragraph 4.1.1 of this ISAP.

This activity was accomplished by

NRC inspection of-SET's review notes and SET recommendations

transmitted to TUGCo.

NRC inspection of this item is complete.

Evaluation of Recommendations and Revisions of Instructions (NRC

Reference No. 1.d.2.02)

,

The NRC inspector verified through review of available data and

interview of cognizant personnel that the TUGCo review of SET

recommendations has been completed.

Procedures and/or

instructions have been revised to incorporate the SET

reconmendations.

The RTL's agreement with tne adequacy of the

revised procedures has been documented for the initial

recommendations and procedure revisions.

If further SET

recommendations are made, they will be monitored by the NRC

inspector.

Evaluation of the Effectiveness of Procedure Revisions (NRC

Ea ference No. 1. d. 2. 03)-

The NRC inspector reviewed inspector qualification deficiencies

identified by the SET for certifications made since the

procedures for training / certification were revised to

incorporate SET recommendations.

TUGCo response resolved some

of the SET identified deficiencies, but in one case.NRC follow

up resulted in the identification of a violation (445/8518-V-03;

445/8515-V-02) regarding an incorrect discipline Level III

certifying an inspector and failure to record bases for

on-the-job training waivers.

SET monitoring of inspection certificat. ions and recertifications

is planned to continue to provide input for the evaluation of.

effectivity of training / certification procedure revis' ions.

This

monitoring occurs during the SET' Phase III reviews in

ISD No. I.d.1,

NRC inspection of_this activity ccntinues.

(3) Craft Personnel Training (ISAP No. I.d.3)

_.

'

This ISAP, which was originally part of ISAP No. I.d.2, is a

response to the TRT determination that craft perfonnel training

}

-47-

may have been inadequate and needed to be evaluated. Specific

activities of this ISAP are delineated in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Procedural Review

4.1.2.1

1.d.3.01

Interview Personnel

4.1.2.2

1.d.3.02

Observe Training and Field

4.1.2.3

1.d.3.03

Activities

Recommendations for Improvement

4.1.3

1.d.3.04

Evaluation of Changes

4.2.2.1

1.d.3.05

Qualification of Personnel

4.3

1.d.3.06

Root Cause Determined

4.6

1.d.3.07

from VII.c Results

There was no NRC inspection activity on th,is ISAP during this

report period.

(4) Material Traceability (ISAP No. VII.a.1)

This ISAP is a response to a TRT concern that control of

material traceability had been inadequate and needed to be

evaluated. The specific activities of this ISAP are delineated

in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Assure Ongoing VII.c Provides

4.1.2.1

7.a.1.01

Input

Evaluate Procedures For

4.1.2.2

7.a.1.02

Material Control

Evaluate Actions Relative to

4.1.2.3

7.a.1.03

1981 ASME Survey

Assure Actions On All

4.1.2.4

7.a.1.04

SER Findings

Assure VII.b.1 and VII.b.3

4.1.2.5

7.a.1.05

Results are Considered

Incorporate Input From VII.c

4.1.2.6

7.a.1.06

Assess Compliance with

4.1.2.7

7.a.1.07

Commitments

There was no NRC inspection activity on this ISAP during this

report period.

(5) Nonconformance and Corrective Action Systems (ISAP No. VII.a.2.)

This ISAP is a response to the TRT identification of

irregularities in the nonconformance and deficiency reporting

i

L

-48-

system.

Specific activities of the action plan are delineated

in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Identify Systems / Methods for

4.1.1.1

7.a.2.01

Recording Nonconformances

Review Samples of NCR Processing

4.1.1.2

7.a.2.02

Evaluate TRT & SSER Findings

4.1.1.3

7.a.2.03

on NCRs

Report Hardware Concerns and

4.1.1.4

7.a.2.04

Input to CA, etc.

Review CAR Procedures

4.1.2.1.

7.a.2.05

Sample CAR Implementation

4.1.2.2'

7.a.2.06

Review Trend Analysis Vs. FSAR

4.1.2.3

7.a.2.07

Evaluate TRT & SSER Findings

4.1.2.4

7.a.2.08

on CAR and Trending

Report Hardware Concerns and

4.l.2.5

7.a.2.09

'

Input to 55(e) Reporting

Evaluate Reporting Procedures

4.1.3.1

7.a.2.10

Review Implementation of 55(e)

4.1.3.2

.7.a.2.11

..

Reporting

Expand Review if Deficiencies

4.1.3.3

7.a.2.12

are Noted

TERA Technical Review of NCRs

4.2.3.1

E7.a.2.13

+

Identification of Site Methods for Recording Nonconformances-

(NRC Reference No. 7.a.2.01)

,

This activity is currently incomplete.

By a search of~

procedures, ERC identified the site methods used for recording

nonconformances.

The procedures searched were the current B&R

construction series (CP-QAM-XXX), current and historical TUGCo

quality series (CP-QP-XXX), and the current B&R quality series

(CP-QAP-XXX).

The NRC inspector reviewed the compiled notes and

data sheets resulting from the ERC review and compared them to

the identified procedures.

The results of the NRC review were

in agreement with the results of the ERC review, in that

proceduralized methods for recording nonconformances were

identified. The methods identified in the ERC search were,

NCRs, field deficiency reports, inspection reports (I.R.s),

receipt I.R.s, weld data cards for supports, and weld data cards

for piping.

Other methods may be identified during

implementation of this ISAP.

Review of NCR Processing (NRC Reference No. 7.a.2.02)

This activity is not complete.

Populations for five methods

identified for recording nonconformances have been defined by-

. - ,

-

_

_

.

.

~

.

-49-

ERC.

The five methods are NCRs, field deficiency reports,

I.R.s, weld data cards for supports, and weld data cards for

piping.

The NCRs for TUGCo and B&R have been divided into six groupings.

These groupings were primarily based on. chronology, but also

separated ASME related NCRs from non-ASME'related NCRs.

The NRC

inspector reviewed the data for division of the NCR population

and for subsequent generation of random samples.

This showed

the NCR groupings and sample selection to be in accordance with

the requirements of paragraph 4.1.1.2 of this ISAP.

This

resulted in samples of 60 NCRs taken from each of the six NCR

groups.

The NRC inspector reviewed the draft results of the ERC review

of the FSAR and TUGCo QA program.

The draft results were

utilized in the development of ERC's checklist for NCR review.

NRC inspection of the checklist found it incorporated QA program

requirements and the attributes listed in paragraph 4.1.1.2 of

this ISAP.

ERC's evaluations of the six NCR groups were inspected by the

NRC duplicating 10% from each of the six groups.

The NRC

inspection results found the ERC evaluation to be satisfactory.

NRC inspection of the remaining nonconformance populations used

to document nonconforming conditions is ongoing and will be

reported in subsequent reports.

Review of CAR Procedures (NRC Reference No. 7.a.2.05)

The NRC inspector inspected ERC's checklist prepared for

evaluation of TUGCo and B&R corrective action procedures.

This

inspection showed that the elements of paragraph 4.1.2.1 of this

ISAP were incorporated in the checklist.

The data sheets

resulting from the ERC evaluation were inspected to verify that

they addressed the elements of the checklist.

This inspection

found the checklist elements had been addressed and that the

data sheets accurately reflected the corrective action

procedures.

ERC's evaluation of the accumulated data will be

inspected when it is complete.

Implementation of Corrective Action System (NRC Reference

No. 7.a.2.06)

The ERC checklist to be used for review of CARS was inspected by

the NRC inspector.

This inspection found the criteria of

paragraph 4.1.221 of this ISAP and data gained from the

nonconformance system review were incorporated"in'the checklist.

.

y--

.w--

,--- - --

,,r-

9

y

-,

i-,

.

-50-

,.

The population of CARS to be evaluated has been identified by

ERC to be all closed TUGCo and B&R CARS. ERC's evaluation of

these CARS is ongoing.

NRC inspection of this activity will be

reported in a subsequent report.

(6) Document Control (ISAP No. VII.a.3.)

This ISAP is a response to TRT concerns over historical problems

in the area of document and record control.

Specific activities

of the ISAP are delineated in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Identify Other ISAPs

4.1.2.1

7.a.3.01

Verifying Document Control

Evaluate III.d. & VIfTc

4.1.2.2

7.a.3.02

'

Document Control Deficiencies

Determination of Corrective

4.1.2.3

7.a.3.03

Action

Procedure Evaluation

4.5

7.a.3.04

Action on Adverse

4.6

7.a.3.05

Trends / Deficiencies-

,

There was no NRC inspection activity on this ISAP during this

report period.

(7) Audit Program and Auditor Qualification (ISAP No. VII.a.4)

NRC concerns about the adequacy of the TUGCo QA audit program

and qualifications of the QA auditors were described in

NUREG 0797, Supplement No. 11.

ISAP No. VII.a.4 is intended to

evaluate the adequacy of the TUGCo QA auditors and audit

program. Specific activities are delineated in the following

table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Review All Procedures and

4.1.2.1

7.a.4.01

Program Revisions of Audit

Program

Effectiveness Evaluation Based on

4.1.2.2

7.a.4.02

Implementation Documents

..

._

__.

=

.-

-51-

Resolve Identified Program

4.1.2.3

7.a.4.03

Deficiencies

Evaluate Audition Qualifications

4.1.2.4

7.a.4.04

and Staffing

The results report for this ISAP has been submitted to the

Results Report Review Committee.

The NRC inspector has audited

files of the Dallas QA Audit Group and reviewed documentation in

the ISAP working file.

Implementation of the ISAP was verified

as follows:

Review of Current and Historical Procedures for the QA -

J

,

Audit Program (NRC Reference No. 7.a.4.01)

The issue coordinator for this.ISAP.has completed the review of

the CPSES PSAR/FSAR (Appendix 1A.(N) and 1A(B)),' Chapter 17.1;

TUGCo' Corporate Quality Assurance' Program manual, CPSES Pro' ject

Quality Assurance Plan (Design & Construction); and'Dallis

,

Quality Procedures / Instructions manual.

The review and ,

'

evaluation of these procedures and their revisi6ns~will be

-

.

documented in the results report.

The issue coordinator's

evaluation of the degree to which the written program, conforms

to commitment is based on this review'of. procedures.

For each of the above procedures', the NRC inspector reviewed the

ERC checklists and data sheets.

These are maintained in the

ISAP's working file. This review verified the completeness and

compliance of the issue coordinator's review to the ISAP

requirements.

Specifically, procedural implementation of

Amendment No. 2 of the PSAR and Amendment No. 52 of the FSAR

were verified.

Amendment No. 2 of the PSAR shows TUSI utilizing

the ANSI N45.2 series in the development of the QA program and

plan.

Amendment No. 52 of the FSAR endorses the guidance of

Regulatory Guide 1.144 for scheduling of external audits.

No

further NRC inspection is planned for this item.

(8) Periodic Review of QA Program (ISAP No. VII.a.5)

This ISAP is a response to findings by the TRT and RIV as

reported in NRC Inspection Report 445/8432; 446/8411 that TUGCo

management failed to periodically review the adequacy of their

QA program.

The specific activities of the ISAP are delineated

in the following table:

,

ISAP

NRC

,

Activity

Paragraph No.

Reference No.

Develop Criteria for Assessment

4.1.2.3

7.a.5.01

Evaluate Current Program

4.1.2.4

7.a.5.02

There was no NRC inspection activity on this ISAP during this

report period.

,

_

_ _ . _ _ _ _ - -

-

. - - - .

. -

.

-52-

'

(9) Housekeeping and System Cleanliness (ISAP No. VII.a.7.)

As a result of two issues identified by the TRT, this ISAP was

developed to assess the adequacy of the housekeeping and system

cleanliness programs at CPSES.

The specific activities of the

ISAP are listed in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Review Results of II.a, V.b & VI.a.

4.1.2.1

7.a.7,01

Review Procedures for Housekeeping

4.1.2.2

7.a.7.02

and Surveillance

Review of Flush and Swipe

4.1.2.3

7.a.7,03

Procedures

Review of Plant Areas

4.1.2.5

7.a.7.04

Review of Documentation on

4.1.2.5

7.a.7.05

Housekeeping

Analysis of All Data

4.1.2.6

7.a.7.06

Review Housekeeping and Surve' sance Procedures

(NRC Reference No. 7.a.7.02)

The NRC inspector reviewed ERC notes and data sheets resulting

from the ERC review of procedures controlling housekeeping,

plant and site surveillances, and system cleanliness.

This data

was compared against the controlling procedures; the

requirements of Criterion XIII of 10 CFR Part 50, Appendix B;

and FSAR requirements to verify the ERC evaluation of procedural

controls.

The ERC evaluation is not final; however, the ERC

data was found to properly reflect the procedural requirements.

Review of Flush Procedures (NRC Reference No. 7.a.7.03)

l

-

The NRC inspector reviewed the notes and data compiled from

'

ERC's revision of flush procedures.

The NRC inspector checked

this information against the applicable procedures and flush

plan documents reviewed including Westinghouse' Specifications

PS 292722 on cleanliness requirements for the NSSS, PS 597760 on

cleanliness maintenance, PS 84351 NL on chloride and fluoride

levels for stainless steel surfaces; Westinghouse startup

Procedure TBX/TCX-SU-1.2.1.10 on post hot functional cleaning of

the reactor coolant system; TUGCo flush plan FP-55-08 on reactor

l

l

-53-

coolant system (Unit 1); and startup Procedure CP-SAP-24 for

component cleanliness levels.

The ERC evaluation is not final,

but this NRC review found the ERC notes and data a're supported

by the procedures referenced.

Review of Plant Areas (NRC Reference No. 7.a.7.04)

Plant surveillances conducted by the site construction

surveillance group were overviewed by ERC. This activity was

initially reported in NRC Inspection Report 50-445/85-14;

50-446/85-11.

NRC inspection is ongoing for ERC reviews of

plant survey documentation.

Qualifications of Personnel

The NRC inspector verified the qualificatians of ERC personnel

performing analyses on evaluations for the ISAP.

The individual

resumes and objectivity questionnaires were reviewed and

evaluated as meeting the requirements of the CPRT Program Plan.

Certified inspectors were not required in the performance of the

ISAP.

Unless additional personnel are utilized, no further NRC

inspection activity is planned in this area.

(10) Fuel Pool Liner Documentation (ISAP No. VII.a.8.)

This ISAP is a response to the TRT identification of

irregularities in fuel pool travelers.

NUREG'0797,

Supplement Nos. 10 and 11, provided additional information on

the adequacy of fuel pool liner welds.

Specific activities of

the ISAP are delineated in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Identify Inspection & Test

4.1.2.1

7.a.8.01

Requirements From Documentation

Review

Select Sample From All Liner Welds

4.1.2.2

=7.a.8.02

Verify Required and Proper

~ 4.1.2.3

7.a 8.03

Inspection of Sample

j

Identify Inspection and Test Requirements from Document

Reviews (NRC Reference No. 7.a.8.01)

-_

This activity is not complete.

The results of NRC inspection.of

this activity will be documented in a subsequent report.-

s

,

N.

+

-

1.

-54-

Identify Fuel Pool Liner Weld Population and Select a Sample

of Fuel Pool Liner Welds (NRC Reference No. 7.a.08.02)

A list of all spent fuel pool, transfer canal, and cask loading

pit travelers used during erection of the fuel liner and

associated components has been compiled.

Composition of this

list has been verified by the NRC inspector reviewing the list

itself, checking the-traveler files, and interviewing the ERC

personnel responsible for its compilation.

This review showed

that the weld travelers for each of the above parts of the fuel

pool liner were included.

This compilation resulted in a fuel

pool liner population of 2,610 weld travelers.

Each has been

assigned a unique sequential number. A sample of this

population has been selected using the guidance given in

Appendix D of the CPRT Program Plan.

This has been verified

through review of the population list, the random number list,

and the correlation matrix.

For this ISAP, a random list of 300

weld travelers was generated, of which 60 were used.

Verify Required and Proper Inspection of Sample (NRC Reference

No. 7.a.8.03)

The ERC data sheets for each of the 60 weld traveler samples

have been reviewed by the NRC inspector.

Eight of the data

sheets were selected for comparison to the weld packages and

other verification sources against the standards and criteria

defined in paragraph 4.5 of this ISAP.

Specifically, the data

sheets were checked to verify proper recording of weld number,

weld process, welder I.D. and qualification, and inspector 1.0.

and certification. Welder's qualifications were checked by

review of the welder's personnel file.

Inspector's

certifications were checked by review of the inspector's

personnel file.

For the eight selected packages, the NRC

inspector checked a total of 19 welder qualifications and 19

inspector certifications.

The results of the NRC review were in

agreement with those of the ERC review.

The issue coordinator has written DRs for deficiencies in some

of the weld traveler packages, including some where the required

inspections appear not to have been performed.

.

Qualification of Personnel

.

Qualification of personnel for this ISAP was verified for'

objectivity and training.

These were.found to be acceptable by

review of the ERC personnel file and an ERC reply to deviation

445/8511-0-02.

No inspectors requiring certification are

planned to be used for this ISAP.

No further NRC inspection is

planned for this item.

-55-

(11) Onsite Fabrication (ISAP No. VII.b.1.)

This ISAP resulted from several TRT findings of fabrication shop

inadequacies which are identified in NUREG-0797, Suppler, ant

No. 11 and USNRC letter dated January 8, 1985. Specific

activities of this ISAP are delineated in the following table:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Review and Evaluate Procefures

4.1.2.1

7.b.1.01

for Onsite Fabrication

Identify and Select Sample from

4.1.2.2 &

7.b.1.02

ASME and non-ASME Fabrications

4.1.2.3

Review Fabrication Packages

4.1.2.4

7.b.1.03

Hardward Reinspection of

4.1.2.4

7.b.1.04

Fabrication Package Discrepancies

Review Storage and Surveillance

4.1.2.5

7.b.1.05

Procedures and Records for

Adequacy

Review VII.a.1 Deviations for

4.1.2.6

7.b.1.06

Reinspection

Analyze Data for Fabrication

4.1.2.7

7.b.1.07

Compliance

Provide Input to ISAP VII.a.1.

4.1.2.8

7.b.1.08

Notify TUGCo of Hardware Deviations

4.1.2.9

7.b.1.09

Report Programmatic Implications

4.1.2.10

7.b.1.10

and Issues to Other ISAPs

There was no NRC inspection activity on this ISAP during this

report period.

(12) Valve Disassembly (ISAP No. VII.b.2)

The TRT found that installation of certain butt-welded valves in

>

three systems required removal of the valve bonnets and

internals prior to welding to protect temperature-sensitive

i,

parts. The three systems involved were the spent fuel cooling

and cleaning system, the boron recycle system, and the chemical

and volume control system. This installation process was poorly

ccntrolled in that disassembled parts were piled in uncontrolled

-56-

areas, resulting in lost, damaged, or interchanged parts.

This

practice created the potential for interchanging valve bonnets

and internal parts having different pressure and temperature

ratings.

The program proposed by the applicant, as set forth in ISAP

No. VII.b.2, devision 1, dated January 24, 1986,. consists of the

,

following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Identify Population of Valves

4.1.1

07.b.02._01

Which Have Been Disassembled

Develop List of Valves in the

4.'1.1

07.b.02.02

._

Three Systems Identified by the

TRT

.

Review Construction and QC

4.1.2

07.b.02.03'

Procedures to Determine if They

Provide Adequate Controls of

Materials During Disassembly /

Reassembly

Perform an Analysis to Determine

4.1.3

07.b.02.04.

Safety Consequences of Improperly

Assembled Valves

Reinspection of a Sample of the

4.1.4

07.b.02.05

Valves Listed in ISAP Paragraph

No. 4.1.11

Inspection Procedure for Re-

4.1.5

07.b.02.06

inspection of Valves, Identified

in ISAP Paragraph No. 4.1.1,

will be Predicated on Review of

-

Vendor Drawings, Procedures and

Documentation Packages

Preparation of Results Report

07.b.02.07

As of this reporting period, NRC inspection activities for the

items referenced above are as follows:

Identify Population of Valves Which Have Been Disassembled (NRC

Reference No. 07.b.02.01)

Valves which must be disassembled after installation have been

identified by the CPRT.

The identification of these valves has

.

.

-.

. - - - ,

-57-

been reviewed by the NRC inspector.

Refer to NRC Inspection

Report 50-445/85-13; 50-446/85-09.

This activity is complete.

No NRC violations or deviations were identified.

Develop List of Valves in the Three Systems Identified

by the TRT (NRC Reference No. 07.b.02.02)

From the list developed in 07.b.02.01 above, a list of valves in

the spent-fuel cooling and cleaning, boron recycle, and the

chemical and volume control systems that. require disassembly was

developed.

Subsequent NRC review confirmed this list.

Refer'to

NRC Inspection Report 50-445/85-13; 50-446/85-09. This activity

is complete.

.

No NRC violations or deviations were identified.

Reinspection of a Sample of the Valves Listed in ISAP

Paragraph No. 4.1.1 (NRC Reference No. 07.b.02.05)

Two samples of valves consisting of a random sample and an

engineered sample were reinspected by the CPRT.

The two sample'

sizes and selection were in accordance with ERC Procedure

CPP-006.

These two combined samples consist of 101 reinspection

packages.

The NRC inspector verified this. activity by

witnessing eight of the reinspections and performing seven

independent inspections.

Refer to NRC Inspection Reports

50-445/85-11, 50-446/85-06; 50-445/85-13, 50-446/85-09; and

50-445/85-14, 50-446/85-11.

This activity is complete.

No NRC violations or deviations were identified.

Inspection Procedure Predicated on Review of Vendor Drawings,

Procedures, and Documentation Packages in Order to Perform

Reinspections (NRC Reference No. 07.b.02.06)

Prior to the re#iisktctions being pe~rformed, the packages had to

be assembled h c*t r to define reinspection activities. When

the NRC iraps 29r

tnessed or performed inspection activities,

the inspection p.s"4ge was also reviewed for adequacy and

completion.

Refer to NRC Inspection Reports discussed in

07.b.02.05 above. This activity is complete.

No NRC violations or deviations were identified.

No NRC inspection has been performed, to date, in the other

defined activities.

i

i

_.m

. - . .

.

_ , .

. - . , ~ _ ,

,

. - . .

-.r

_

--

-

-

- .

I

4

58-

-

!

(13)PipeSupportInspections(ISAPNo.VII.b.3)

The TRT conducted a series of inspections encompassing as built

safety-related pipe support installations. These inspections

were of completed systems or components that had been previously

inspected and accepted by applicant QC as meeting the respective

construction and installation requirements. Of the 42 pipe

supports inspected, 37 were randomly selected and 5 originated

from an alleger's list.

Forty-six deficiencies ~were identified

-in the supports inspected. There were six specific deficient

items identified by the TRT that required further evaluation.

The TRT concern is that the items may have a high rate of

.

occurrence throughout plant safety-related systems.

The program proposed by the applicant as set forth in ISAP

No. VII.b.3, Revision 1, dated January 24, 1986, consists of the

-

following activities:

ISAP

NRC

Activity

Paragraph No. Reference No.

Verify TRT Identified Dis-

4.1.1

07.b.03.01

crepancies

Develop Reinspection Checklists 4.1.1.1

07.b.03.02

for TRT Identified Discrepancies

Prepare Reinspection Packages

4.1.1.2

07.b 03.03

4

Perform Reinspection of Hardware

4.1.1.3

07.b.03.04

Conipare Inspection Results and

4.1.1.4

07.b.03.05

,

l'

Identify Differences

Reinspect Random Sample in

4.1.2

07.b.03.06

i

Accordance with ISAP VII.c.

Identify VII.c. Pipe Support

4.1.2.1

07.b.03.07

Populations Representative of

the TRT Samples

,

Include all Attributes and

4.1.2.2

07.b.03.08

L

Instructions Required to Verify

l

TRT Identified Discrepancies in

!

the VII.c Inspection Checklists

Review VII.c. Inspection Results

4.1.2.3

07.b.03.09

,

l

for Pipe Supports and Identify

l

Valid Discrepancies

!

J:

i

,

---

. . - - . . - . . .

,

.

,

-- - _ - _

-.--,~--,.-z---~,-..

. . - ,

,,

= - ,

-

,...,,_er,..,

-

-59-

Evaluate Valid Discrepancies for

4.1.3.1

07.b.03.10

Safety Significance in Accordance

with Appendix E of the CPRT

Program Plan

Perform Trend Analysis for all

4.1.3.2

07.b.03.11

Valid Deviations

This Action Plan is to be Conducted

4.1.4

07.b.03.12

in Accordance with Existing

Procedures and Inspectors Are to

be Qualified to Applicable

Procedures and ANSI N45.2.6.

Additional Procedures to be

4.1.4.4

07.b.03.13

Developed as Required.

Determine Root Cause, Generic

4.1.4.5

07.b.03.14

Implications and Programmatic

Concerns for any Construction

Deficiencies and Adverse Trends

As of this reporting period NRC inspection activities are as

follows:

Develop Reinspection Checklists for TRT Identified Discrepancies

(NRC Reference No. 07.b.03.01)

QIs and their reinspection checklists were developed for the

reinspection of TRT identified discrepancies; i.e., QI-059 and

-061 for the TRT 42 pipe supports, and QI-037 and -038 for the

TRT Room 77N pipe supports. This activity is complete.

Prepare Reinspection Packages (NRC Reference No. 07.b.03.03)

The TRT inspection results were utilized in the selection and

preparation of inspection packages in the TRT Room 77N and TRT

42 pipe supports. This activity is complete.

Include All Attributes and Instructions Required to Verify TRT

Identified Discre)ancies in the VII.c. Checklists (NRC

Reference No. 07.).03.08)

All valid attributes relative to the ISAP No. VII.b.3

discrepancies were identified and utilized in the development of

the ISAP VII.c pipe support inspections. The procedures and

checklists are contained in QI-027, QI-028, QI-29, and QI-030.

This activity is complete.

The NRC inspector has performed the following inspections as of

the end of this reporting period:

l

t

-60-

(a) Room 77N Pipe Supports

The NRC inspector has reviewed ERC QI-037, Revision 0.

To

date, seven reinspections have been witnessed, of which the

following two occurred during this report period:

Verification

Package No.

Support No.

  • System

Unit No.

1-S-PS7N-097

CS-1-158-036-542R

CS

1

1-S-PS7N-080

-CS-1-074-042-542R

CS

1

  • CS - Chemical and Volume Control System

No NRC violations or deviations were identified.

(b) TRT Issues - 42 Pipe Supports

The NRC inspector has reviewed ERC QI-058, Revision 0.

To

date, three reinspections have been witnessed, none of

l

which occurred during this report period. Six independent

inspections have been conducted, with the following one

being performed during this report period:

Verification

Package No.

Support No.

  • System

Unit No.

_

I-S-PS42-021

CT-1-005-004-S22K

CT

1

The following conditions were identified by the NRC

inspector during this independent inspection. The NRC

inspector observed a broken lockwire on the snubber adapter

assembly. This lockwire was identified as an out-of-scope

observation per the ERC inspector's notes in the inspection

package. Paragraph 6 on page 34 of the Attachment 6.17 to

QI-058 states, "In those cases where attachment bolts

,

,

!-

between forward bracket assembly and snubber assembly are

I

safety wired by the verdor, QCI shall verify the following

conditions exist:

1

Bolts are tight.

2

Lockwire is not damaged.

3

Lockwire is crimped.

Prior to installation, if any (,f the above conditions are

unsatisfactory, the bolts shall be retorqued and the new

lockwire shall be installed."

i

l

l

l

t

-61-

Attribute 5.3.1 of the inspection checklist required the

ERC inspector to verify that all threaded fasteners, except

SA-193 and SA-325 bolting materials and Hilti bolts were

provided with locking devices. This attribute was accepted

by the ERC inspector, despite the recorded observation of a

broken lockwire. Acceptance of this attribute is a

deviation (445/8601-D-13).

(14) Hilti Anchor Bolt Installation (ISAP No. VII.b.4)

The TRT inspected Hilti anchor bolt installation on pipe

supports and electrical raceway supports to the requirements of

QI-QP-11.2-1, and identified the following types of deficiencies

during its inspection:

(a) Minimum effective embedment criteria were not met for

certain installed Hilti Kwick bolts.

(b) Anchor bolt torque was not verified.

(c) Hilti bolts were not marked in accordance with procedure

requirements.

(d) Hilti bolt lengths were not verifiable.

(e) Base plate bolt holes violated minimum edge distance.

(f) Hilti bolt skewed more than the allowable 6*.

The program proposed by the applicant, as set forth in ISAP

No. VII.B.4, Revision 1, dated January 24, 1986, consists of the

following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

'

Review Specifications / Procedures

4.1.1

07.b.04.01

and Identify Safety-Significant

!

Attributes

l

'

Review Action Plan VII.c to Assure

4.1.2

07.b.04.02

Inclusion of Safety-Significant

Attributes

Review Specifications, Procedures,

4.1.3

07.b.04.03

QC Inspections, and Training

Procedures and Records to

Determine Comonality

Obtain results from Action

4.1.4

07.b.04.04

Plan VII.c Inspections

l

l

-

-

.

-.

_ _

.

. - -

- - -

-

-

.

.. . _ - -

-

i

-62-

Assure That Sample Size, Chosen

4.1.5

07.b.04.05

from Action Plan VII.c, is

Adequate

Perform Reinspections in Accordance

4.1.6

07.b.04.06

With Action Plan Vii.c

Torque Verification Program

4.1.7

07.b.04.07

Determine Programmatic Implications

4.1.8

07.b.04.08

As of this reporting period, NRC inspections for the activities

referenced above are as follows:

Obtain Results From Action Plan VII.c Inspections (NRC Reference

No. 07.b.04.04)

Reinspection / verification and documentation reviews for populations

contained in ISAP VII.c are currently in process. Results of NRC

inspection activities are contained in NRC Inspection Reports

50-445/85-13, 50-446/85-09; 50-445/85-14, 50-446/85-11; 50-445/85-16,

50-446/85-13; and 50-445/85-18, 50-446/85-15.

There was no NRC inspection activity or other activities in this ISAP

during this report period.

c.

Test Programs (ISAP No. III Series)

There was no followup inspection activity in the Test Programs ISAPs

during this inspection period.

Since most of the inspections in this

area have been completed, it is anticipated that followup inspections

for the Test Programs actions will resume upon issuance of the next

revision of ISAP No. III, which is currently targeted for March 1,

1986.

The current status of followup inspections on Test Programs ISAPs is as

follows:

III.a.1

Hot Functional Testing Data Packages:

Complete with seven

inspection findings and one possible enforcement action.

See NRC Inspection Reports 445/85-11, 85-13, and 85-16.

III.a.2

JTG Approval of Test Data:

Complete. See NRC Inspection

Report 445/85-16.

III.a.3. Technical Specifications for Deferred Tests:

Complete.

See NRC Inspection Report 445/85-16.

III.a.4

Traceability of Test Equipment:

Started, but not yet

documented in an inspection report.

.

,,

_ , . - ,

- , - , - - - -

- - - , , ,

-

,,

,

..

.

d

-63-

,

III.b

Conduct of the CILRT: Not started.

III.c

Prerequisite Testing: Not started.

III.d

Preoperational Testing: Completed ISAP III.d.4.1.1.1

through 4.1.2.6 with seven inspection findings including

two deviations. See NRC Inspection Reports 445/85-16 and

445/85-18.

~

None of the final results reports, as approved by the Senior Review

Team (SRT), have been reviewed. Completions listed above are subject to

reinspection upon issuance of a revised ISAP.

d.

' Civil / Structural

(1) Electrical Conduit Supports (ISAP No. I.c)

The TRT examined the nonsafety-related conduit support

installation in selected seismic Category I areas of the plant.

The support installation for nonsafety-related conduits less

than or equal to 2. inches was inconsistent with seismic

requirements and no evidence could be found that substantiated

the adequacy of the installation for nonsafety-related conduit

of any size. According to Regulatory Guide 1.29 and FSAR

Section 3.7B.2.8, the Seismic Category II and non-seismic items

should be designed in such a way that their failure would not

adversely affect the function of safety-related components or

cause injury to plant personnel.

The program proposed by the applicant, as set forth in ISAP

No. I.c, Revision 3, dated January 24, 1986, consists of the

following activities:

(a) Demonstrate That All Nonsafety-Related Conduits and

Supports Satisfy Regulatory and FSAR Provisions:

ISAP

NRC

Activity

Paragraph No. Reference No.

Evaluate Interaction of Train C

4.1.1

01.c.01.00

,

!

Conduit Greater Than 2 Inches in

Diameter in Seismic Cat. I

Buildings with Safety-Related

Conduits

!

!

i

i

_ _ _ .

__

._ _

_

.

.

.

_ _

__

_

.

.

.

.

-64-

.

(b) Verify Nonsafety-Related Conduit Less Than or Equal To 2

Inches in Diameter Satisfy Applicable Design Requirements

ISAP

NRC

Activity

Paragraph No.

Reference No.

Selection of the Random and

4.1.2.1

01.c.02.00

Engineered Samples of Train C

Conduit with Diameter Less Than

or Equal to 2 Inches

Field Verification of the Samples

4.1.2.2

01.c.03.00

of the Train C Conduit 2 Inches

-

or Less in Diameter Per Procedure

CP-EI-4.0-64

Seismic Analysis and Acceptance

4.1.2.3

01.c.04.00

Criteria of Two Samples

Damage Analysis Where Sample Runs

4.1.2.4

01.c.05.00

are Considered for Interaction

with Safety-Related Targets

Population Acceptance Criteria

4.1.2.5

01.c.06.00

Where Interactions are Evaluated

and Accepted / Rejected

Issuance of Results Report

01.C.07.00

As of this reporting period, inspection activities for the items

referenced above are as follows:

Evaluate Interaction of Train C Conduit Greater Than 2

Inches in Diameter in Seismic Cat. I Building With Safety-

Related Conduit (NRC Reference No. 01.c.01.00)

The CPSES Damage Study Program evaluated all Train C conduit

greater than 2 inches in diameter in seismic Cat I areas. The

CPRT evaluation of the adequacy of this program will be

contained in ISAP II.d. Therefore a separate evaluation of this

conduit is not required in ISAP No. I.c.

Selection of the Random and Engineered Samples of Train C

Conduit With Diameters Less Than or Equal to 2 Inches

(NRC Reference No. 01.c.02.00)

The CPRT has identified 126 conduit runs in the random sample

and 131 conduit runs in the engineered sample. The NRC

inspector has reviewed the procedures for selection of the two

samples to assure compliance with the CPRT program plan.

.

.-

-

. - .

. _ _ _ _ _ ___.

-65-

Verification of the two samples has also been completed.

Refer

to NRC Inspection Reports 50-445/85-13, 50-446/85-09;

50-445/85-14, 50-446-85-11.

There was no NRC inspection activity on this ISAP during this

report period.

(2) Reinforcing Steel in the Reactor Cavity (ISAP No. II.a)

This ISAP addresses the documented occurrence of the omission of

some reinforcing steel from a reactor cavity concrete placement

in Unit 1.

The primary objective is to assess the design

adequacy of the as-built condition. The program proposed by the

applicant as set forth in ISAP No. II.a. Revision 3, dated

January 24, 1986, consists of the following activities:

ISAP

NRC

Activity

Paragraph No. Reference No.

Analysis of As-Built Reactor Cavity

4.1

02.a.01.00

Wall

Review Circumstances Leading to

4.1

02.a.02.00

Provision for and Deletion of

Subject Rebar

Review Rebar Omissions Documented in

4.1

02.a.03.00

Project NCRs

Review Sample of Pour Cards for use

4.1

02.a.04.00

of Current Design Documents

Review Engineering Field Interface

4.1

02.a.05.00

of Major Embedments

Review Design Change Procedures and

4.1

02.a.06.00

Their Effectiveness Regarding

Implementation

Review of Results for Generic

4.1

02.a.07.00

Applications

The CPRT has informed the NRC inspector that the actions

committed to by ISAP No.-II.a are essentially complete; however,

an additional commitment has been added. The actual existence

of reinforcement steel will be physically verified in a sample

of locations. The scope and other details of this added

commitment is currently being addressed by CPRT.

.

- - .

_

_ _ _ _ _

.

.

5

-66-

Analysis of As-Built Reactor Cavity Wall (NRC Reference

4

No. 02.a.01.00)

An analysis of the as-built condition of the Unit I reactor

cavity by Gibbs & Hill was previously reviewed by the NRC

inspector (see NRC Report 50-445/85-11;50-446/85-06).

There was no NRC inspection activity on this ISAP during this

report period.

(3) Maintenance of Air Gap Between Concrete Structures (ISAP No. II.c)

"

This ISAP addresses the seismic gap required by the FSAR for

separation of seismic category I buildings to prevent

interaction during a seismic event. The program proposed by the

applicant as set forth in ISAP No. IIc, Revision 3 dated

January 24, 1986, consists of the following activities:

,

ISAP

NRC

Activity

Paragraph No. Reference No.

Reinspect and Assess As-Built

4.1

02.c.01.00

Condition

,

Removal of Debris or Rotofoam

4.1

02.c.02.00

Analyze Final As-Built Condition

4.1

02.c.03.00

Documentation of Final As-Built

4.1

02.c.04.00

Condition

Revision of Engineering Calculations

4.1

02.c.05.00

l

to Reflect Final As-Built Condition

Review Procedures for Gap Maintenance

4.1

02.c.06.00

!

Determine Generic Implications

4.1

02.c.07.00

Assess Sequence of Events Leading to

4.1

02.c.08.00

Existing Condition

.

Evaluate Need to Update the FSAR

4.1

02.c.09.00

Reinspect and Assess As-Built Condition (NRC Reference

.

No. 02.c.01.00)

1

Inspection of the as-built condition of the double-walled *

building sep6iration gaps is complete.

Debris was located and

l

identified using visual examination, long probes, and remote

i

video cameras. Drawings were prepared showing the location,

,

,

- - _

. .. -

_.

.--

- - - . .

. - .

-

.-

--

-

.

_ . .

_

._

_

_

_

__ ..

h

-67-

l

-

identification, and a conservative estimate of the extent of the

debris. Video tapes are also available.

Inspection activities

and results were witnessed and reviewed by Southwest Research

Institute (SWRI), a third-party organization.

Inspection of the single-walled * building separation gaps is

also complete. Debris was located using visual examination and

probes. Remote video cameras were generally not used for

single-walled gap inspection.

Inspection activities and results

were witnessed and reviewed by SWRI.

'

The NRC inspector has independently reinspected a portion of the

double-walled gap between the Fuel and Auxiliary Building (A-F

wall) at elevation 810 foot and has also witnessed and reviewed

inspection of both single and double-walled gaps. This

inspection included review of video taping techniques and

results as well as drawings showing the location of debris.

Removal of Debris or Rotofoam (NRC Reference No. 02.c.02.00)

i

ProtoPower has the general contract for gap cleaning. Most work

to date on double-walled gaps has been concentrated along the

,

j

LA-AF wall between the Fuel and Auxiliary Buildings.

Gap cleaning for this double-walled gap is generally complete

down to elevation 810'6".

Below that level, existing rotofoam

may be left in place if the Gibbs & Hill calculation indicates

that rotofoam is allowed. The rotofoam will be drilled at

intervals below elevation 810'6" to show that no concrete is in

,

~

the gap. Some concrete does exist in the gap above this

3

elevation. This concrete will be removed by EverFab under

subcontract to ProtoPower using diamond impregnated cable.

Double-walled gaps will be completely reinspected using the same

techniques employed for the initial inspection.

,

Cleaning and repairing of single-walled gaps is nearly complete.

Debris has been removed and gaps have been widened to conform

with the Gibbs & Hill analysis.

i

i

The NRC inspector has witnessed the cleaning and repairing of

both single and double-walled gaps on numerous occasions. This

'

includes witnessing the use of various tools for debris removal

and review of the overall' progress.

Analyze Final As-Built Condition (NRC Reference No. 02.c.03.00)

Gibbs & Hill has completed analysis of minimum gap requirements

for single and double-walled gaps including the reactor building

internal to external structure gaps. TERA is reviewing this

analysis for adequacy.

1

l

i

_

_

. . .

. .

. . .

. .

- .

.

. ..

.

.

..

..

.

-68-

Review Procedures for Gap Maintenance (NRC Reference No. 02.c.06.00)

Initially, TUGCo Instruction QI-QP-11.0-3, Revision 6, dated

,

April 22, 1985, entitled, " Concrete or Mortar Placement

Inspection," was used for building gap inspection and

maintenance.

Revision 7 dated October 8, 1985, was issued to

include reactor building (Units 1 and 2) internal structure to

external structure.

Revision 8 of this instruction is scheduled

to be issued by early February 1986 and will extend inspection

down to the base mat.

Previous revisions specify a lowest

applicable elevation for each identified building separation

gap, generally 790 or 810 foot elevation.

The NRC inspector has reviewed these procedures.

No NRC inspections have occurred of other ISAP No. II.c

activities.

No NRC violations or deviations have been identified to date.

  • Double and single-walled gaps are defined in ISAP No. II.c as:

Double-walled building separation gaps are separation gaps

between two buildings which have a solid wall (except for

openings from one building to the other) on each building face

for full height of a specific separation gap. Single-walled

building separation gaps are separation gaps between two

buildings in which one building has a solid wall (except for

openings) for full height of a specific gap and the opposite

building provides gap walls only by slab, beam, column, or wall

ends.

(4) Seismic Design of Control Room Ceiling Elements (ISAP No. II.d.)

The primary objective of this ISAP is to assure th'at all

elements of the control room ceiling satisfy, the seismic

interaction provisions of Regulatory Guide 1.29 and FSAR

Section 3.78.2.8.

The control room ceiling has been redesigned

and is currently being replaced.

The program proposed by the applicant, as set forth in ISAP

No. II.d., Revision 3, dated January 24, 1986, consists of.the

following activities:

ISAP

NRC

Activity

Paragraph No.,

Reference No.

Design of New Control Room

4.1.1.1

02.d.01.00

Ceiling Structure and Components

to he Reviewed

L

i

i

-69-

Installation of New Control Room

4.1.1.1

02.d.02.00

Ceiling Structure and Components

Review of Process for Evaluating

4.1.1.2

02.d.03.00

'

Potential Seismic Interaction

Damage Study Verification for

4.1.3.2

02.d.04.00

Architectural Features

Review Procedures and Methods

4.1.3.3

02.d.05.00

for Damage Study

Review Criteria and Acceptability

4.1.3.4

02.d.06.00

of Category II Interaction-

Review Criteria for Evaluation

4.1.3.6

02.d.07.00

of Consequences for Interactions

Review Implementation of

4.1.3.7

02.d.08.00

Damage Study

Comparative Damage Assessment

4.1.3.8

02.d.09.00

in Selected Rooms

As of this reporting period, inspection activities for the items

referenced above are as follows:

Design of New Control Room Ceiling Structure and Components

to be Reviewed (NRC Reference No. 02.d.01.00)

Gibbs & Hill, Inc. has completed the seismic design of the new

ceiling structure.

Design requirements are. delineated in

Gibbs & Hill Design Procedure 09.3, " Control Ro'om Ceiling,"

Revision 1.

The NRC inspector reviewed-this procedure and found

it in accordance with NRC Regulatory Guide 1.29, Revision 3,

" Seismic Design Classification"; FSAR Section 3.78.2.8,

" Interaction of Non-category I Structures with Seismic

Category I Structures"; FSAR Section 3.78.3.5, "Use of

Equivalent Static Load Method of Analysis"; and FSAR

Section 3.8.4, "Other Seismic Category I Structures." Results

,

of the third party review of design calculations performed by.

TERA were reviewed during this inspection. ' Answers'and

i

clarifications to questions generated by TERA were. reviewed.

The NRC inspector also reviewed portions of the following Gibbs

l

& Hill calculations:

i

'

Calculation No. SAB-271C, Set 1, " Control Room Ceiling-Secondary

Frame Support (Louvered Panel Supports)"

Calculation No. SAB-171C, Set 2, " Control Room Ceiling

(Stage I-Main Frame Support)"

.

.

-70-

Calculation No. SAB-171C, Set 3, " Control Room

Ceiling-Reevaluation of Concrete Floor at Elevation-854-4"

Calculation No. SAB-171C, Set-4, " Control Room Ceiling (Main

Frame Support)"

Calculation No. DAB-20, Set-1 and Set-2, " Dynamic Analysis of

Control Room Ceiling"

-

Installation of New Control Room Ceiling Structure and

Components (NRC Reference No. 02.d.02.00)

B&R has removed the original ceiling and commenced the

installation of the new ceiling.

The main' structural steel

frame has been installed.

Verification of_the' adequacy of-the

-

installed main structural steel framing was addressed during

this inspection by measuring the as-built Hilti bolt locations' ,

for ceiling support base plates on beams 68,.71,177'and 79.

The

design and installation of the inspected Hilti bolts was found

to be correct and in accordance with the requirements of Gibbs &

Hill Specification 2323-SS-30, Revision 2, " Structural

Embedment" and Brown & Root Procedure 35-1195-CEI-20,

" Installation of Hilti Drilled-In Bolts."

.

,

Quality control inspection and documentation of the Hilti bolt

installation conformed to the requirements'of TUGCo

Procedure CP-QP-11.2, Revision 9, " Inspection of Concrete Anchor

Bolt Installation."

Review of Process For Evaluating Seismic Interaction

(NRC Reference No. 02.d.03.00)

The process for evaluating potential seismic interactions among

components above the new control room ceiling has been reviewed

by the third party.

However, the cognizant engineer and the

results of his evaluation were not available onsite during this

inspection period.

NRC inspections were not performed on other activities

identified above during this report period.

No NRC violations or deviations were identified.

(5) Rebar in the Fuel Handling Building (ISAP No. II.e)

This ISAP addresses the alleged instance of unauthorized cutting

of rebar in the Fuel Handling Building.

The program proposed by

the applicant as set forth in ISAP No. II.e, Revision 3, dated

January 24, 1986, consists of the following activities:

t

-71-

ISAP

NRC

Activity

Paragraph No.

Reference No.

Analysis of As-Built Condition

4.1

02.e.01.00

Assuming Cut Rebar

Review Controls Governing Rebar

4.1

02.e.02.00

Cutting

Review of All Cases Where Rebar

4.1

02.e.03.00

Cutting was Requested

Assess Work of Construction Crew

4.1

02.e.04.00

Review Pipe Supports with Shear Lugs

4.1

02.e.05.00

Installed by Core Drilling

The CPRT has informed the NRC inspector that the actions

committed to by ISAP No. II.e are essentially complete.

Additional rebar cutting requests have been identified delaying

the issuance of the final results report.

.

Analysis of As-Built Condition Assuming Cut Rebar-

(NRC Reference No. 02.e.01.00)

An analysis of the effects of cutting two layers of rebar

associated with the installation of the trolley process aisle

rails in the Fuel Handling Building was completed by Gibbs &

Hill and reviewed by TERA.

Ultrasonic testing was carried out

by SWRI.

These activities were previously reviewed by the NRC

inspector (see NRC Report 50-445/85-11,50-44U85-06).

No NRC inspections have occurred in other ISAP No. II.e

activities,

e.

Mechanical

(1) Inspection for Certain Types of Skewed Welds in_

NF Supports (ISAP No. V.a)

B&R procedures for welds in pipe supports designed to

Subsection NF in Section III of the ASME Code contained no

fillet weld inspection criteria for certain types of skewed

welds.

This lack of inspection criteria and lack of

verification of proper inspection procedures is a violation of

ASME Code for NF supports committed to by TUEC in FSAR

Section 5.2.1 and Criterion X7 in Appendix B of 10 CFR 50.

The program proposed by the applicant, as set forth in

Revision 2 of the ISAP, to demonstrate the adequacy of the

corrective actions consists of the following activities:

.___.

_.

-72-

ISAP

NRC

Activity

Paragraph No.

Reference No.

Chronology of Inspection Methods

4.1.1

05.a.01.00

o Develop Chronology of

05.a.01.01

Inspection Methods

o Chronology to Identify

05.a.01.02

Methods, Inspection Documents

Required, Revisions to

Procedures not Superseded by

'

Subsequent Inspection

Inspection Procedures

4.1.2

05.a.02.00

o Review Procedure QI-QAP-

05.a.02.01

11.1-26, -11.1-28 and CP-QAP-

12.1 to Determine if

Inspection Method was Adequate

to Address Unique Aspects of

-

Skewed Weld Dimensional

Configurations.

o Third party to Assess

05.a.02.02

Adequacy.

o Revise Procedures Where

05.a.02.03

Applicable.

o Third party to Evaluate the

05.a.02.04

Physical Significance of any

Procedural Changes

Select Random Sample for Inspection

4.1.3.

05.a.03.00

o Develop Sampling Plan in

Accordance With Appendix I

05.a.03.01

o Perform Sampling Evaluation

-

05.a.03.02

to Determine if Procedural

Ambiguities Resulted in

Undersized Welds

o Perform Analysis to Determine

05.a.03.03

if Welds Meet ASME Code

Allowable Stress Levels for

Those Found not to Meet Design

Requirements

o Determine Whether Sample is

05.a.03.04

to be Expanded

,

o Determine Need for Additional

05.a.03.05-

Inspection

Reinspection by Third Party

4.1.4

05.a.04.00

o Inspection Criteria Will be

05.a.04.01

Based on Revised Procedures

Resulting From NRC Reference

No. 05.a.02.00

- - - -

-

-

-

-73-

Use of Results

4.1.5

05.a.05.00

o Assess Root Cause and

05.a.05.01

Generic Implications

o Identify any Physical

05.a.05.02

Modifications and Procedural

Changes Required

o Identify Corrective Actions

05.a.05.03

Required

-Third-Party Will Oversee and

4.1.6

05.a.06.00

Verify the Review Program

As of this reporting period, inspection activities are as follows:

Review Procedure-QI-QAP-11.1-26, -11.1-28, and CP-QAP-12.1 to

Determine if Inspection Method was Adequate to Address Unique

Aspects of Skewed Wold Dimensional Configuration (NRC Reference

No. 05.a.02.01)

These procedures were reviewed and were found to originally not

adequately address type 2 skewed welds.

Refer to NRC Inspection

Report 50-445/85-13; 50-446/85-09.

This activity is complete.

Third Party to Assess Adequacy (NRC Reference No. 05.a.02.02)

Third party assessment of adequacy concluded that revisions

would be required.

Refer to NRC Inspection Report 50-445/85-13;

50-446/85-09.

This activity is complete.

Revise Procedures Where Applicable (NRC Reference No. 05.a.02.03)

It was verified that the procedures were revised to properly

address type 2 skewed welds, including their inspection and

subsequent documentation.

Refer to NRC Inspection Report

50-445/85-13, 50-446/85-09.

This activity is complete.

Reinspection By Third Party (NRC Reference No. 05.a.04.00)

The reinspection of the random sample of 60 NF supports

containing 99 type 2 skewed welds is complete.

Refer to NRC

Inspection Report 50-445/85-13, 50-446/85-09.

NRC witnessed and

independent inspections are complete and are referenced in NRC

Inspection Reports 50-445/85-13, 50-446/85-09; and 50-445/85-14,

50-446/85-11.

This activity is complete.

Inspection Criteria Will be Based on Revised Procedures Resulting

From NRC Reference 05.a.02.00 Activity (NRC Reference 05.a.04.01)

The reinspection effort was performed in accordance within the

revised procedures which resulted from the actions taken in

activity 05.a.02.00.

The NRC inspector verified compliance with

i

_

i

-74-

the inspection procedure requirements.

Refer to NRC Inspection

' Report 50-445/85-11; 50-446/85-06.

This activity is complete.

NRC inspections have not currently been performed in the other

activities.

Open Item 445/8511-0-04 was identified with respect to the

dispositioning of 12 undersize skewed welds documented on NCRs.

With the exception of the previously documented violation

(445/8514-V-03), no other NRC violations or deviations have been

identified.

(2) Improper Shortening of Anchor Bolts in Steam Generator

Upper Lateral Supports (ISAP No. V.b)

The objective of this ISAP is to ensure that the anchor bolts in

the steam generator upper lateral supports meet design

requirements.

Other installations dependent on bolt thread

engagement will be sampled and reinspected.

The program

proposed by the applicant as set forth in ISAP No. V.b,

Revision 2, dated January 24, 1986, consists of the following

activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Rework of Unit 1 for Acceptable

4.1.1

05.b.01.00

Thread Engagement

Inspection of Unit 2 for Acceptable

4.1.1

05.b.02.00

Thread Engagement

Examine Bolts, Blind Threaded Holes,

4.1.2

05 b.03.00

and Assembly Dimensional Tolerances

Determine Potential Generic

4.1.3

05.b.04.00

Applicability Through Sample

Reinspection of Two Separate

Populations

..

Inspection of Richmond Inserts'on

4.1.3.1

05.b.04.01

ASME Pipe Supports

,

Inspection of Blind Hole Bolted

4.1.3.2

05.b'.04.02

Connections

-

Identify Root Cause and Generic

4.1.6

05.b.05.00

Implications

-

-.

.

-

F

-75-

Rework of Unit 1 for Acceptable Thread Engagement (NRC

Reference No. 05.b.01.00)

.

Inspection of the thread engagement of anchor bolts in the steam

generator upper lateral supports for Unit 1 is complete.

Further work is waiting the completion of analysis of the upper

lateral supports by Gibbs & Hill (addressed separately under

DSAP 71). . The NRC inspector independently inspected thread

engagement on bolt 1E15 on steam generator No. I and found it to

be acceptable.

Inspection of Richmond Inserts on ASME Pipe Supports

TNRC Reference No. 05.b.04.01)

This population consists of approximately 1800 safety

_

significant pipe supports with Richmond' inserts.' A~ total of 60

pipe supports will be selected'and all Richmond inserts

'

associated with these supports will be reinspected. ' The initial .

review of the population by TERA' revealed error's? Currently,

TUGCo is re-evaluating the population _for accuracy and

completeness.

~

'

Inspection of Blind Hole Bolted Connections (NRC Reference

No. 05.b.04.02)

This population consists of blind hole bolted connections where

thread engagement is an important design attribute.

This

population has been prepared and is currently being reviewed by

TERA.

No NRC inspections have occurred of other ISAP No. V.b

activities.

No NRC violations or deviations have been identified to date.

(3) Design Consideration for Piping Systems Between Seismic

Category I and Non-Seismic Category I Buildings (ISAP No. V.c)

The TRT discovered that piping systems, such as Main Steam,

Auxiliary Steam and Feedwater, are routed from the Electrical

Control Building (seismic Category I) to the Turbine Building

(non-seismic Category I) without any isolation.

To be

acceptable, each seismic Category I piping system should be

isolated fro:n any non-seismic Category I piping system by-

separation, barrier or constraint.

If isolation is not feasible, then the effect on the seismic

Category I piping of the failure in the non seismic Category I

piping must be considered (CPSES FSAR 3.78.3-13.1).

-76-

The objective of this action plan is to assure that piping

systems routed from seismic Category I to non-seismic Category I

buildings meet the FSAR criteria.

This objective.has been

assigned to the Project Piping and Supports Program (PPSP) with

a third party overview by the Design Adequacy Program (DAP).

The program proposed by the applicant, as set forth in

ISAP No. V.c, Revision 2, dated January 24, 1986, consists of

the following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Identification of all Unit 1,

4.1.1

05.c.01.00

2,'nd Common Piping With

a

Seismic /non-Seismic Interface

Review and Discuss Events and

4.1.2

05.c.02.00

Reasons for Auxiliary Steam .

Pipe Situation

Recommendations to PPSP and DAP

4.1. 3 -

05.c.03.00

are to Address Potential

Implications Which Should be

Considered During Implementation

of PPSP/DAP.

Prepare and Issue Results Report

4.1.4

05.c.04.00

As of this reporting period, inspection activities for the items

referenced above are as follows:

Identification of All Unit 1, 2, and Common Piping With

Seismic /Non-Seismic Interface (NRC Reference No. 05.c.01.00)

The CPRT has generated lists identifying all Unit 1, 2, and

common piping with a seismic /non-seismic interface.

The NRC

inspector has reviewed these lists to verify validity and to

assure no pipe lines have been omitted. This activity is

documented in NRC Report 50-445/85-13, 50-446/85-09; and is

considered complete.

There was no NRC inspection activity on this ISAP during this

report period.

(4) Plug Welds (ISAP No. V.d)

The TRT confirmed the existence of uncontrolled repairs to

misdrilled holes in seismic Category I pipe supports, cable tray

supports, and base plates in Units 1 and 2.

-77-

- The program proposed by the applicant, as set forth in

Revision 2 of the ISAP, to demonstrate the adequacy of the

corrective actions consists of the following activities:

ISAP

. NRC

Activity

Paragraph No.

Reference No.

Select two Random Samples

4.1.1.1

05.d.01.00

of ASME Pipe Supports and

Base Plates

Reinspection of ASME Pipe Supports

4.1.1.1

05.d.02.00

and Base Plates

Document, Investigate, and

4.1.1.1

05.d.02.01

Disposition Detected Deficiencies

o Utilize Mockups to Verify

05.d.02.02

and Refine Detection

Techniques

o Select Field Inspectors Based

05.d.02.03

on Performance of Detecting

Mockup Plug Welds

Identify Plug Welds in ASME Pipe

4.1.1.2

05.d.03.00

Supports and Base Plates

o Make Comparison to Prior

05.d.03.01

Inspection to Determine if

Welds Were Authorized and

Documented

Expand Sample Size if one or More

4.1.1.4

05.d.04.00

Unauthorized or Undocumented Welds

are Found in ASME Pipe Supports

or Base Plates

For Detected, Unauthorized or

4.1.1.5

05.d.05.00

Undocumented Plug Welds Found

in ASME Pipe Supports or Base

Plates Determined not to Affect

-

1

'

Quality, Additional Inspection

'

may Be Performed Based on Observed

,

Trends in the Inspection Results'

,

,

Unauthorized and Undocumented

4.1.1.6 *

05.d.06.00

Plug Welds to ASME Pipe Supports

and Base Plates Will be Identified

by NCRs and Modified if Required

QC Inspection and Documentation

4.1.1. 7

05.d.07.00

Procedures to be Reviewed and

Changes Recommended if Required

,

D

-78-

Third-Party to Provide Overviews

4.1.1.8

05.d.08.00

of Reinspection Effort

Cable Tray Support Plug Welds

4.1.2

05.d.09.00

o Sample Inspect Cable Tray

05.d.09.01

Supports the Same as Pipe

Supports and Plates.

o Determine Frequency and

05.d.09.02

Location of Plug Welds.

o Determine Effects of Plug

05.d.09.03

Welds on Quality of Supports.

Authorized Cable Tray Support

4.1.3

05.d.10.00

Plug Welds

o Third party to Review Design

05.d.10.01

Change Authorizations (DCAs)

for Cable Tray Supports

o Third party to Determine

05.d.10.02

Whether Sufficient Basis

Existed for DCAs.

Documentation of QC Weld

4.1.4

05.d.11.00

Inspections

o Third party to Review

05.d.11.01

Historical Programmatic

Requirements and

Implementation Procedures

for QC Documentation.

o Third party Review to Assess

05.d.11.02

Compliance With QA Program,

Licensing Commitments of FSAR,

and Perform an Evaluation on

any Lessons Learned for Future

Program Modification.

Root Cause and Applicability

4.1.5

05.d.12.00

o Determine Root Cause

05.d.12.01

o Determine Generic Implications

05.d.12.02

Procedures

4.2.1

05.d.13.00

o Develop Inspection Procedure (s)

05.d.13.01

for Cable Tray Supports, Pipe

Supports and Base Plates.

o Train and qualify inspectors

OS.d.13.02

L

f

k

4

-

-

-79-

Existing QC Procedure Criteria

4.2.2

05.d.14.00

for Visual Inspection Will be

Used.

Issuance of Results Report

05.d.15.00

As of this reporting period, inspection activities are as follows:

Select Two Random Samples of ASME Pipe Supports and Base

Plates (NRC Reference No. 05.d.01.00)

NRC inspection identified that the two selected random samples

<

were not exclusively ASME Code,Section III supports and base

plates.

As a result, a deviation was identified and documented

in NRC Inspection Report 50-445/85-13, 50-446/85-09.

Subsequent

to this, additional samples were selected and inspected. This

activity is complete.

Reinspection of ASME Pipe Supports and Base Plates (NRC

Reference No. 05.d.02.00)

The ERC reinspection effort has been completed and is documented

.in NRC Inspection Report 50-445/85-16, 50-446/85-13.

This

activity is complete.

Document, Investigate, and Disposition Detected Deficiencies

(NRC Reference No. 05.d.02.01)

,

!

During the NRC's independent and witnessed inspections, there

were no unauthorized plug welds found.

During a review of ERC

documentation, no evidence of unauthorized plug welds were found

and no deficiencies detected.

This information is referenced in

,

NRC Inspection Reports 50-445/85-11, 50-446/85-06; 50-445/85-13,

50-446/85-09; 50-445/85-14, 50-446/85-11; and 50-445/85-16,

50-446/85-13.

This activity is complete.

4

Utilize Mockups to Verify and Refine' Detection Techniques

s

(NRC Reference No. 05.d.02.02)

~

At the beginning of this reinspection effort, mockups of plug

welds in various types of plate _and structural members were

~,

constructed and utilized to train field inspectors. In~ addition

to mockup training, the inspectors were required to observe

documented field plug welding.

Completion of this activity is

pending the NRC inspector's review of training records ^and

inspector certification.

!

-

.

.

- -

-

-

-

_

..

-80-

Select Field Inspections Based on Performance of Detecting

Mockup Plug Welds (NRC Reference No. 05.d.02.03)

Selection of field inspectors was based on their performance in

detecting a minimum of 75% of plug welds in the mockups.

This

4

activity will be verified by the NRC inspector's review of the

activity listed above.

Identify Plug Welds in ASME Pipe Support and Base Plates

'

>

(NRC Reference No. 05.d.03.00)

Four olug welds were identified in two ASME pipe support base

plate >.

Refer to NRC Inspection Report 50-445/85-13;

50-446/85-09.

Planned NRC inspection of this activity is

complete.

Make Comparison to Prior Inspection Records to Determine

!

if Welds Were Authorized and Documented (NRC Reference

i

No. 05.d.03.01)

A review of prior inspection records was conducted with respect

to the four plug welds that were identified, and it was verified

that these welds were authorized and documented.

Refer to NRC

Inspection Report 50-445/85-13; 50-446/85-09.

Planned NRC

inspection of this activity is complete.

'

Expand Sample Size if one or More Unauthorized or

Undocumented Plug Welds are Found in ASME Pipe Supports

I

or Base Plates (NRC Reference No. 05.d.04.00)

There were no unauthorized or undocumented plug welds found in

.

ASME pipe supports or base plates; therefore, the sample size

was not increased.

Refer to NRC Inspection Report 50-445/85-16,

50-446/85-13.

The NRC inspector considers this activity closed.

For Detected Unauthorized or Undocumented Plug Welds Found

in ASME Pipe Supports or Base Plates Determined not to

Affect Quality, Additional Inspection may be Based on

Observed Trends in the Inspection Results (NRC Reference

No. 05.d.05.00)

There were no unauthorized or undocumented plug welds

identified; therefore, no observable trends were establisted,

thus precluding the need for additional inspections.

Refer to

NRC Inspection Report 50-445/85-16; 50-446/85-13.

The NRC

inspector considers this activity closed.

3

i

}

4

- - - ,

v

.n-

,e-,

-,

e,

rm. - - - - , ---- ---, - - . ,-- ~ - <

n----

-+s-,

--~n--,-----

-.--,,------.-c,

- - - - - - - -

-wn-

n -

-81-

Unauthorized and Undocurnented Plug Welds to ASME Pipe Supports

-

and Base Plates Will be Identified by NCRs and Modified if

Required (NRC Reference No. 05.d.06.00)

No unauthorized and undocumented plug welds to ASME pipe

supports and base plates were identified, thus precluding the

need for NCRs and modifications.

Refer to NRC Inspection Report

50-445/85-16; 50-446/85-13.

The NRC inspector considers this

activity closed.

Cable Tray Support Plug Welds (NRC Reference No. 05.d.09.00)

.

The status of NRC inspection activities is listed below.

Sample Inspect Cable Tray Supports the Same as Pipe

Supports and Plates (NRC Reference No. 05.d.09.01)

To date, all planned NRC inspections have'been completed.

Results_of previous NRC inspections are documented in NRC

'

--

Reports 50-445/85-14, 50-446/85-11; 50-445/85-13, 50-446/85-09;

and 50-445/85-11, 50-446/85-06.

Determine Frequency and Location of Plug Welds (NRC Reference

No. 05.d.09.02)

To date, all planned NRC inspections have been completed.

Results of previous NRC inspections are documented in NRC

Reports 50-445/85-14, 50-446/85-11; 50-445/85-13, 50-446/85-09;

and 50-445/85-11, 50-446/85-06.

Procedures (NRC Refe.ence No. 05.d.13.00)

The status of NRC inspection activities is listed below.

After

the completion of inspections by ERC, the NRC inspector will

perform an assessment of ISAP No. V.d commitment implementation.

Develop Inspection Procedure (s) for Cable Tray Supports,

Pipe Supports, and Base Plates (NRC Reference No. 05.d.13.01)

ERC QI-007 was developed to provide instruction for the

identification and inspection of plug welds in cable tray

supports, pipe supports, and base plates.

Train and Qualify Inspectors (NRC Reference No. 05.d.13.02)

All of the inspectors used for this effort successfully

demonstrated their ability to identify plug welds in the mockup

supports prior to the initiation of the reinspection effort.

The remaining outstanding activities will be inspected during

subsequent reporting periods.

-82-

(5)

Installation of Main Steam Pipes (ISAP No. V.e)

The TRT investigated an allegation that a Unit 1 main steam line

had been installed incorrectly and had been forced into proper

alignment after flushing operations by use of the main polar

crane and come-alongs.

It was also claimed that pipe supports

.

had been modified to maintain the line in its forced position

and vibrations following detachment of the flushing line could

have damaged the main steam line.

Based on its investigation,

the TRT determined that the alleged incident pertained to

restoration of the Unit 1, Loop 1 main steam line to its

initial, correct installation position.

The program proposed by the applicant, as set forth in ISAP

No. V.e. , Revision 2, dated January 24, 1986, consists of

performing a special engineering investigation of the steam line

adjustment, and a generic study of possible damage in other

piping, including the Unit 1, Loop 4 main steam (MS) line.

These two items consist of the following activities:

a)

Engineering Investigation of Steam Line Adjustment

ISAP

NRC

Activity

Paragraph No. Reference No.

Review Procedures for MS Pipe

4.2

05.e.01.00

Erection and Support Placement

Interview Personnel Involved With

4.2

05.e.02.00

Line Adjustment

Evaluate Engineering Significance

4.2

05.e.03.00

of Procedures and Practices

Perform Analytical Evaluation of

4.2

05.e.04.00

Stresses and Support Load Changes

.

Establish Engineering Significance of

4.2

05.e.05.00

Stresses and Support Load Changes

From Previous Step

,

l

Review Existing UT Examinations

4.2

05.e.06.00

and Hydrostatic Tests

Determine the Need for Reinspection

4.2

05.e.07.00

of Portions of MS Line

!

.

,

.

-83-

b)

' Generic Study of Possible Damage to Other Piping

ISAP

NRC

Activity

Paragraph No.

Reference No,

Review Procedures and

4.2

05.e.08.00

Specifications for Pipe

Erection and Support

Placement

Review NCRs and Pipe Deviation

4.2

05.e.09.00

Request Forms (PORFs) nith

Circumstances Similar to

Steam Line

Interview Installation Personnel

4.2

05.e.10.00

~

to Determine 0*her Piping With

Circumstances Similar to Steam

Line

Review all Other Sources of

4.2

05.e.11.00

Residual Stresses to Piping

Systems

Evaluate Engineering Significance

4.2

05.e.12.00

of Other Residual Stresses

Perform Engineering Evaluations

4.2

05.e.13.00

on Other Lines if Required

i

Where Required, Modif" Gibbs &

4.2

05.e.14.00

Hill Specifications and

Procedures to Avoid Similar

Occurrences

.

As of this reporting periou, inspection activities for the items

referenced above are as follows:

,

Review Procedures for MS Pipe Frection and SLpport Placement

-

(NRC Reference No. 05.e.01.00)

i

Prior to evaluating the MS line ir.ta11ation problem, the

applicable procedures were revieved by R. L. Cloud and ,

Associates (RLCA).

These procedures are contained in the

appendix of the RLCA report.

The NPC. inspector, while reviewing

the RLCA report, has documented the relevar.cy and adegaacy of

those procedures in NRC Inspection Report 50-445/85-11;

50-446/85-06.

,

This activity is now complete.

No NRC violations or deviations were identified.

-r-

Evaluate Engineering Significance of Procedures and Practices

(NRC Reference No. 05.e.03.00)

Evaluate and cite practices, and incorporate the results of the

-review into activity 05.e.04.00.

The NRC inspector's review of

this activity was performed in conjunction with activity

05.e.01.00 and 05.e.04.00 and is documented in NRC Inspection

Report 50-445/85-11; 50-446/85-06.

This activity is .aow complete.

No NRC violations or deviations were identified.

Perform Analytical Evaluation of Stress and Support Load

Changes (NRC Roference No. 05.e.04.00)

The RLCA report documents a comprehensive static analysis of the

Unit 1, Loop 1 MS line lift.

The different loading conditions

included deadweight, lifting condition, disconnect of the

,

temporary line condition, and flushing condition.

These loading

conditions were used in conjunction with various temporary

supporting schemes.

The various analysis parameters were

evaluated and included in the stress analysis, such that the

results represent conservative, worst case, or bounding

i

conditions consistent with the sequence of events.

'

During the NRC inspector's review of the RLCA stress report, an

unresolved item (445/8514-U-13) was identified in October 1985.

The unresolved item was concerned with the following:

1)

While the use of a "come-along" for horizontal adjustment

is mentioned in Section 1.3, " Additional Background," it is

not addressed in the analytical portion of the report.

2)

The 18-inch bypass line is modelled in as a schedule 60

pipe, but drawing FSM-00165 specifies a schedule 40 pipe.

Documentation was not available to substantiate that a

schedule 60 pipe was used.

Even though the schedule 60

piping is conservative as far as stress is' concerned, it

will have some impact on other conclusions made in the

report such as n rtical displacements.

3)

Figure 'i-12 in the analysis does not represent computer

output No. RLCA P142-1-551-018, in that the node numbers do

not correspond.

4)

The NRC TRT identified that sagging occurred during

flushing operations.

RLCA states that sagging occurred

before flushing.

The date of the flushing should be

established.

-85-

Documentation has been produced by the CPRT which:

1)

Shows that 18-inch schedule 60 pipe was purchased for use

on the by pass line (item 2) above)

2)

Narrows down the actual date of flushing of this system to

the beginning of March 1982.

This date.is two months after

the documented polar crane lift date of. Loop 1 (Item 4

above).

The other two portions of the unresolved item (Items 1 and 3))

involve changing or adding statements in Revision 1 cf the RLCA

'

report.

With the exception of following up on the unresolved item, NRC

~

~

inspection of this activity is complete.

,

Additional information is documented in NRC Inspection

a

Report 50-445/85-14; 50-446/85-11.

'

'4

-

,

J

No NRC violations or deviations were identified.

Establish Engineering Significance of Stresses and Support ~

Load Changes From Previous Step (NRC Reference No. 05.e.05.00)

The stresses in the MS Unit 1, Loop 1 piping, which was analyzed

in the previous activity, are documented and compared to the

applicable ASME Section III allowables in the RLCA report.

The

stresses are extracted from the appropriate ANSYS computer

output after including the proper stress intensification factor

for elbows and welds.

The maximum stress condition occurred

during a deadweight analysis with temporary supports, and this

stress was 60% of the appropriate ASME Section III allowable

stress.

Support loads were not affected since support hardware

was not attached to the piping at the time of polar crane lift.

NRC inspection of this activity is now complete.

Additional

information is documented in NRC Inspection Report 50-445/85-14;

50-446/85-11.

No NRC violations or deviations were identified.

Review Existing UT Examinations and Hydrostatic Tests for

the Affected Piping on Unit 1, Loop 1 (NRC Reference

No. 05.e.06.00)

The CPRT has reviewed the inspection data for all associated

shop, field, and pre-service inspection welds.

Their review of

hydrostatic test records for Loop 1 showed the hydrostatic test

.-

f

-86-

package to be complete and the results satisfactory.

Subsequent

NRC inspection showed documentation to be complete and

acceptable.

Refer to NRC Inspection Report 50-445/85-18;

50-446/85-15.

No NRC violations or deviations were identified.

Determine the Need for Reinspection of Portions of the Line

That may Have Been Highly Stressed (NRC Reference No. 05.e.07.00)

While the analysis showed no regions of the line to De more than

60% stressed when compared to the appropriate ASME Section III

allowable, CFRT elected to reinspect two regions of the Loop 1

line.

One reinspection was at the field weld (FW-7) in the

region of highest. stress, and the other was at the field weld

(FW-14) connecting the line to the containment penetration.

Radiographic examinations (RTs) were performed to ASME

Section III requirements and compared to the' original, inspection

reports.

The new RTs had satisfactory results.

Two ultrasonic

tests (UTs) were performed and compared to the: original baseline

pre-service inspection performed by Westinghouse Electric.

Corporation.

Both reinspections indicated the' welds are'of

acceptable quality and that the pipe sustained no damage as a.

result of the alignment correction.

,

.

9

Subsequent NRC inspection of the RTs and'UTs verified the CPRT

findings and also verified that the reinspections were performed-

in accordance with approved site _ procedures by NDE personnel

certified to at least Level II requirements of SNT-TC-1A. 'This

information is documented in NRC Inspection Report 50-445/85-18;

50-446/85-15.

No NRC violations or deviations were identified. This activity

is complete.

Review NCRs'and JDRFs With Circumstances Similar to the Steam

Line (NRC RefeTeIwe No. 05.e.09.00)

The CPRT identified 12 NCRs on safety-related piping where

o

fit-up was a problem.and temporary supports may have sagged,

settled, or failed,-or cold springing may have been stated or

implied. :llowever, further review of the 12 NCRs revealed that

the fit-up problem was not related to the above causes or had

cold springing of the line into final alignment occurred.

The NRC inspector's review of these NCRs verified the CPRT

findings.

Review of the PORFs by the CPRT showed that the PDRF was only

used to document acceptance of tolerance deviations, with

_

_

___

-87-

respect to gradients, centerlines, sleeve centerlines, and

clearances.

None of these four categories affect the fit-up of

the piping; therefore, they would not identify circumstances

similar to the main steam line installation. This information

was documented in NRC Inspection Report No. 50-445/85-13;

50-446/85-09.

No NRC violations or deviations were identified.

Specific Additional Samples of Piping Fit-up Will be Chosen

and Specific Engineering Evaluations Performed (NRC Reference

No. 05.e.13.00)

An analytical evaluation of a polar crane lift for Unit 1,

Loop 4 main steam line was performed.

The maximum stress

condition occurred during a deadweight analysis and this stress

was 36% of the appropriate ASME Section III allowable stress.

Reinspection of the line in two locations similar to activity

05.e.07.00 above also occurred with satisfactory results.

NRC inspection of these actions confirmed the CPRT findings.

This activity is complete.

No NRC violations or deviations were identified.

No NRC inspection has been performed in other activities to

cate.

(6) Gap Between Reactor Pressure Vessel Reflective Insulation

and the Biological Shield Wall (ISAP No. VI.a)

This ISAP addresses the adequacy of the testing and analysis

performed to confirm that sufficient air flow is provided in the

annulus between the reactor pressure vessel reflective

insulation and the biological shield wall.

The program proposed

by the applicant as set forth in ISAP No. V1.a Revision 2,

dated January 25, 1986, consists of the following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Verify Cooling Requirements fo'r

4.1.1

06.a.01.00

'

Units 1 and 2 are met

,

,

,

Review Procedures, Programs, etc.

4.1.2

06.a.02.00

'

"

for Effect of Non-Safety Items

on Safety Items

,

t

c

. . - .

- - - , , ,

._,n

- -

_.

.

-88-

Modify Procedures and Programs

4.1.2

06.a.03.00

if Inadequate

Verify Implementation of Programs

4.1.3

06.a.04.00

and Procedures for NonSafety-

Related Items

Program for Identifying Critical

4.1.5

06.a.05.00

Spaces

Inspection of Critical Spaces and

4.1.6

06.a.06.00

QC Inspection Program

Review of Current and Past

4.1.7

06.a.07.00

Housekeeping Methods

No NRC inspection activity has occurred on this ISAP to date.

(7) Polar Crane Shimming (ISAP No. VI.b)

Investigation of the polar crane rail support system by the TRT

identified girders with gaps under the bottom flange that

reduced the bearing surface to less than required, three

rail-to-rail. ground wires broken, two shims partially worked out

from under the rail, two broken Cadwelds, and. conditions

indicating there may still be circumferential movement.

The program proposed by the applicant within Revision 2 dated

January 24, 1986, of the ISAP to demonstrate the adequacy of the

corrective actions consists cf the following activities:

ISAP

NRC

Activity

Paragraph No.

Reference No.

Polar Crane Rail Girders

4.1.2

06.b.01.00

o Inspection of Seat-to-

06.b.01.01

Bracket Connections.

o Third party Review of

06.b.01.02

Findings Assess Safety

Significance Design

Requirements net.

o Third party Review of

-06.b.01.03

Inspection and any Corrective

Action.

e a

Polar Crane Rail Movement

4.1.3

06.b.02.00

o Develop Measurement Program,

06.b.02.01'

'

Execute, and Evaluate.

'

o Determine Cause of Rail

06.b.02.021

'

Movement, Assess Safety

-

t

%

, - - -

, . - - -

-_

-

, .

.

.

. - - .

.

. - .

-

..

-

- - -

..- -

-89-

.

Significance and Recommend

Modifications.

o Gibbs & Hill to Analyze

06.b.02.03

and Design and any Required

Modifications

o~ Third party Review of. Design

06.b.02.04

Rail and Rail Support System

4.1.5.

06.b.03.00

o Inspect Rail and Rail Support

06.b.03.01

System to Identify any Safety

Significant Deviations.

o Prescribe Corrective Action

06.b.03.02

on any Found Deficiencies.

o Third party Verification of

06.b.03.03

-Inspection and Review of

Corrective Action.

Maintenance and Surveillance Programs

4.1.4

06.b.04.00

o Review Existing Maintenance

06.b.04.01

and Surveillance Programs.

o Third party to Recommend any

106.b.04.02

"

Required Changes.

Historical Records

' 4.1.1

06.b.05.00

-o. Review-History'of Crane

u06.b.05.01

<

Support System Construction

and Performance.

o Identify and Categorize Design

06.b.05.02

Requirements in Terms of

Performance or Structural

Function.

As of the reporting period, no NRC inspection activity has

occurred on this ISAP.

-

.,

_

,

}

- 9.

CPRT ISAP'No. VII.c

~

a.

Electrical Cable

.

<

Status of CPRT Activity

,

- ERC has completed 81 reinspections and-79, documentation reviews'of..

'

sampled electrical cable as of Janua,ry 31, 1986.

The decrease in the

.

above totals, from those previously reported, was due to the, removal

of some completed samples for evaluation in a new; lighting population

-

and from errors detected in the sample selection. process'es: ~.

,

.-

s. ,

'

Status of NRC Inspection Activity

'[^ "~

,

.

~'

The NRC inspectors have, as of January .31,1986,' witnessed 21'ERC .

'

reinspections, conducted 6 independent inspections and' performed

<

d

$

e

m---

r.

,e

g

y

--

--

.gr-

+ r ,

-

n.----A--.,..

.v.

, - ,

- - ,

- ~ , .

m

.-,,

-m,s--

-

-e-

'

.

,

-90-

10 documentation reviews of sampled electrical cables.

These totals

remain unchanged from those previously reported.

The requirements for construction testing and startup testing related

to electrical equipment were reviewed by the NRC inspector.

These

requirements are contained in paragraph 6.15 of Gibbs & Hill

Electrical Erection Specification 2323-ES-100, Revision 2, dated

October 15, 1980.

Paragraph 6.15.1(t) of the specification requires

the contractor to perform tests on all cable reels'in accordance with

the manufacturer's recommendations.

The-NRC inspector,was not'able

to locate any documentation which would confirm that these required

tests were performed.

The failure to perform the required tests on cable reels _is an

apparent violation of Criterion V of Appendix B to 10 CFR Part 50

(445/8601-V-14; 446/8601-V-04).

'

'

.

b.

Cable Trays

Status of CPRT Activity

.

- ,

,

,

+.

ERC has completed 91 reinspections~and 84. documentation reviews of

sampled cable. trays as of January 31, 1986.

Status of NRC Inspection Activity

The NRC inspectors have witnessed 11 ERC reinspections, conduc'ted 6

independent inspections, and performed 7. documentation reviews as of

January 31, 1986.

Review of the NRC files and records disclosed that Verification

Package No. I-E-CATY-024 had been incorrectly identified as

I-E-CATY-047 in NRC Inspection Report 50-445/85-11; 50-446/85-06.

The status of the identified open items (50-445/8511-0-09, -10 and

-12) from the inspection of this cable tray is addressed in

paragraph 2 of this Appendix.

The results of the following three independent reinspections of

Unit 1 cable trays, which were conducted by NRC inspectors during

November 1985, were compared to the ERC inspection results during

this report period:

Verification Package No.

Cable Tray No.

Location

I-E-CATY-141

T140AF004

Aux. Bldg.

Hallway

I-E-CATY-174

T12GRBM27

Reactor Bldg.

I-E-CATY-247

T13GCCM62

Cable Spread

Room

No NRC violations or deviations were identified.

-91-

.

c.

Electrical Conduit

Status of CPRT Activity

ERC has completed 72 reinspections and 72 documentation reviews of

sampled electrical conduit as of January 31, 1986.

The decrease in

the above, from previously reported totals, was due to the removal of

some of the sampled conduits from the population because of problems

discovered in the original sample selection process and for

reinspection activities necessitated by redefined inspection

criteria.

,

Status of NRC Inspection Activity

The NRC inspectors have witnessed 14 ERC reinspections, conducted 5

'

independent inspections and performed 15 documentation reviews of

sampled electrical conduit.

Review of the NRC files and records disclosed that three inspections

of Unit 1 electrical conduits had been conducted (one in October and.

two in November 1985) but had not been reported pending comparison of.

inspection findings to the results of the ERC inspections.

The

comparison of results has been completed for two of'the following

conduits:

..

Verification Package No.

Conduit No.

Location

I-E-CDUT-110

C12G06346

Control Bldg.

I-E-CDUT-111

C02012621

Safeguards Bldg'.

I-E-CDUT-113

C13G04051

Room 100

Verification Package No. I-E-CDUT-111 has been reissued to the ERC.

inspectors for another reinspection.

This is an open item pending

NRC inspector review of the ERC reinspection findings

(445/8601-0-15).

-

No NRC violations or deviations were identified.

d.

Electrical Equipment Installation

Status of CPRT Activity

ERC has completed 78 reinspections and 21 documentation reviews of

sampled electrical equipment installations as of January 31, 1986.

Status of NRC Inspection Activity

The NRC~ inspectors have witnessed 11 ERC reinspections, conducted 3

1

independent inspections and performed 10 documentation reviews of

sampled electrical equipment installations as of January 31, 1986.

,

..

,

,.

-

-

-92-

The NRC inspector performed an independent inspection of Verification

Package No. I-E-EEIN-015 for ECSA-1-8802A during November 1985 and

compared inspection results to the ERC inspection results during this

report period.

The seal assembly is for valve MOV-8802A which is a

-

safety injection accumulator outlet valve inside the Unit 1 Reactor

Building.

No NRC violations or deviations were identified.

e.

Piping System Bolted Joints / Materials

Status of CPRT Activity

ERC has completed 71 reinspections of piping system bolted

joints / materials out of the total random and engineered sample size

of 73.

In the December reporting period, it was reported that ERC

had completed 73 reinspections.

The reason for the variance in

completed reinspections is because two packages were removed from_the

sample as a result of it being discovered that construction work had

been performed on these flanges subsequent to the initial

reinspection, thus invalidating the reinspections.

Eight valid DRs

have been generated as a result of the above reinspections.

ERC has completed 68 document reviews of these packages with 9 valid

DRs being issued to date.

These are the same numbers that were

reported in the December reporting period.

Status of NRC Inspection Period

To date, the NRC inspector has witnessed eight reinspections,

performed five independent inspections and performed two document-

reviews.

No NCR inspection activity occurred during this reporting

period.

f.

Concrete Placement

Status of CPRT Activity

Reinspection of concrete placement packages is approximately 88%

~

complete with 97 verification packages in:the combined'first and

second samples.

Forty-one valid deviations have been identified

relating primarily to unfilled holes, voids, and debris in the

concrete surface.

Documentation reviews have not'yet been started.

Status of NRC Inspection Activity

,~

The NRC inspector has reviewed ERC QI-043, Revision 1, and witnessed

,

i

15 reinspections representing approximately 15% of the combined first

i

and second samples.

The NRC inspector has also independently

l

inspected six concrete placements. The following ERC reinspection

was witnessed during this report period:

l

1

!

,

y

- -~, .

. .

---

-

.

-93-

Verification

Concrete

' Package No.

Placement No.

Building

Unit No.

I-S-CONC-087

IRCN-CPC-101-5805-026 Reactor

1

Verification Package No. I-S-CONC-087 involved the reinspection of

the exterior wall of the Unit 1 Reactor Building between the 955' 6"

and 961' 6" elevation, approximately 150 feet above grade level.

The

corresponding interior wall is inaccessible due to the steel

containment liner.

Attribute 2A, size, was verified using the

results of a B&R survey requested by ERC. Attribute 3A, surface

inspection, was verified using an ERC procedure specified in a

Supplemental Inspection Instruction written for this package.

High

power binoculars were used to identify areas of cencern (potential

voids, etc.) in the concrete surface. Two areas with potential voids

were inspected using one-man staging at the elevation of the exterior

wall.

No voids or other deviations were identified.

Comparison of

potential voids, cracks, and other surface defects identified using

the binoculars with the results of actual hands-on inspection in two

areas using the one man staging confirms that the procedure in the

Supplemental Inspection Instruction was adequate. The NRC inspector

witnessed apprcximately 75% of this reinspection.

No NRC violations or deviations were identified.

g.

Small Bore Pipe Supports

Status of CPRT Activity

Reinspection of small bore pipe supports is 100% complete with 76

supports reinspected.

Eighty-five deviations have been issued with

60 valid. deviations identified to date.

These deviations relate

primarily to Hilti bolt embedment, bolt hole spacing and edge

distance in base plates, and pipe clearances.

Documentation review

is also 100% complete with 23 valid deviations identified.

A total

of 31 valid deviations identified during documentation reviews were

listed by ERC in December 1985.

Subsequently, eight deviations

previously identified as valid have been invalidated when additional

documentation was located.

To date, 47 of 33 valid deviations

(combined reinspection and documentation review) have been'e' valuated

by ERC and found to not be safety significant.

Status of NRC Inspection Activity

.

The NRC inspector has reviewed ERC QI-019,? Revision'2, and QI-020,

Revision 0, and witnessed seven reinspections representing

'

approximately 9% of the combined first and second samples.

The NRC

inspector has also independently inspected eight small bore pipe.

supports including the following three s'upports during this report

period:

'

'

,

e

-

> - - - -

+--,--e,-

-rws

}

y

-+

,

e

v

-

-

.%

-

-

_

_. .

-

.

.

..

..

e

-94-

,

Verification

Pipe

Package No.

Support No.

  • System

Unit No.

I-S-SBPS-044

CC-1-RB-003-006-3

CC

1

I-S-SBPS-012

MS-1-RB-010A-013-2

MS

'l

I-S-SBPS-037

CH-X-FB-003-021-3

CH

Common

  • CC - Component Cooling Water System, CH - Ventilated Chilled Water

4

System, MS - Main Steam System

Verification Package No. I-S-SBPS-037 involved the reinspection of a-

portion of a gang type box frame supporting four small bore pipes'.

The support. selected for this reinspection attaches.to the structure

of support No. CH-X-FB-005-022-3 and has pipe attachment-drawing

No. CP-AA-999 Revision 4.

This-drawing shows pipe clearances only,

with all structural portions shown in phantom.

The other three pipes

in the gang support are assigned separate pipe support numbers in a

similar manner.

Thus the gang support as a whole is assigned a tota 1

1

of five support numbers, one for the. structural framework and four

_

involving pipe clearances only. All attributes on the checklist for

.

Verification Package No. I-S-SBPS-037 with the exception of (1)

identification, (2) location and. orientation, and (3D) clearances had

"NA"-(not applicaole) entered by the ERC engineer.

No material

(structural steel, anchor bolts, U-bolts, snubbers, etc.) or welding

was involved in the reinspection so that few attributes on the

checklist were applicable.

The NRC inspector examined .the 76 ERC verification packages for small

bore pipe supports and identified the following 21 packages in which

insignificant reinspections were performed:

2

--

clearance only, no material

2

clearances and shim only, no structural members

--

.

2

U-bolts only, no structural members

--

1

--

Shear lugs only, no structural members

14

--

Pipe support attachments consisting.of one to three

minor box members, no structural framework.'

_

,

'

Paragraph NF-1110 of Subsection NF'in Section III of the 1974 Edition "

of the ASME Code, entitled " Aspects of Construction Covered by .These

Rule,," defines supports by stating in part.

.

"(b) Nuclear power plant component supports for.which rules'are

specified in this Subsection are those metal supports which

'

are designed to transmit loads from the pressure retaining

barrier of the component to the load carrying building

structure, whether concrete or structural steel . . . ."

i

. , . - .

_ . _ _ _

. , - _ _ , - . _ _ . , . _ _ _ _ _

_,

. , _

-95-

The above packages are only partial supports by this definition.

Paragraph 4.1 of the CPRT Action Plan for 7.c states, in part, "The

results of the sampling for each population will be evaluated and

utilized to provide significant input into the overall evaluation of

construction adequacy." Verification packages with few attributes

reinspected and addressed on the checklist may not provirie this

significant input. The homogeneity and validity of tha small bore

,

pipe support population is questioned.

This matter is considered

-

unresolved. (445/8601-U-16, 446/8601-U-05).

No NRC violations or deviations were identified.

'

h.

Pipe Whip Restraints

Status of CPRT Activity

ERC has completed 56 reinspections of pipe khip restraints out of the

planned combined random and engineered sample size of- 111.

The

sample size was increased from the December reported sample size of

110 as a result of ERC's identification that, in order to meet the

engineered sample criteria, the sample size must be-increased by 1;

Seventy valid DRs have been identified and issued.

-

,

._

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed five'ERC reinspections and

performed two independent inspections.

There was no NRC inspection

activity performed during this report period.

i

Instrument Pipe / Tube Supports

.

Status of CPRT Activity

ERC has completed 85 reinspections of instrument pipe / tube supports

out of the combined random and engineered sample size of 111.

The

combined sample size was, increased from a previous figure of 102.

After further evaluation of the engineered sample size, it was

determined that nine adaitional packages were required to meet the

sample criteria.

Two-hundred and seventy valid DRs have been

identified and issued by ERC.

4

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed four reinspections and

performed a total of five independent inspections.

There was no NRC

inspection activity during this ' report period.

-

-_

._

-.

. _.

- _-

-_

-.

-

-96-

j.

Large Bore Piping Configuration

Status of CPRT Activity-

.

ERC has completed 81 reinspections of large bore piping

configurations out of the planned random and engineered sample size

of 82.

Fifty-one valid DRs have been identified and issued.

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed seven ERC reinspections and

performed three independent inspections.

The following independent

inspections occurred during this inspection period:

Verification

Package No.

Drawing No.

Unit No.

System *

I-M-LBC0-038 ~BRP-CS-1-SB-029

1

'CS

"

I-M-LBCO-103

BRP-RC-1-RB-022

1

-

-RC

I-M-LBC0-144

BRP-CC-1-RB-046

1

CC~

,'-

-

CC - Component Cooling Water System

'

,

While performing the independent inspection on. Verification Package

No. I-M-LBCO-038, the following conditions were identified:

(1) A 0.75-inch clearance existed between spool piece.No~.22Q2 on

Drawing BRP-CS-1-SB-060 at a point 12 inches above sleeve No. 3

on the inspected line, yet attribute 1.f in the ERC inspection-

checklist was checked off as being acceptable.

Paragraph

5.2.6.2 in QI-025 requires a minimum 1-inch clearance.

Acceptance of the below minimum clearance is a deviation

(445/8601-0-17).

(2) Attribute 1.e. in the IRC inspection checklist had N/A inserted

by the QA/QC engineer, thus was not inspected.

This attribute

addresses assuring that branch connections are in accordance

with the piping isometric drawing.

The NRC inspector identified

,

the e<istence of a branch connection which should have been

inspected.

The failure to identify the applicability of this attribute is a

deviation (445/8601-D-18).

(3) During the independent inspection performed on Verification

Package No. 1-M-LBC0-144, the following conditions were

identified:

<

~ , -

- --

-

,. _

i

-97-

(a) Paragraph 5.1 in Revision i to QI-025 provides for a i

2-inch tolerance with respect to location of piping and

piping system components.

Field survey measurements taken

by B&R on December 6, 1985, as requested by ERC, show the

distance from the end of the containment penetration at

field weld No. 18-A to the working point of the 76 bend,

to be 10 feet 5 7/16 inches.

However, isometric drawing

No. BRP-CC-1-RB-046 shows this distance as 10 feet

8 1/8 inches, which is 11/16 inch in excess of the i 2-inch

,

tolerance.

This attribute (1.d) on the inspection

checklist was accepted by the ERC inspector.

Acceptance of this measurement is a deviation

(445/8601-D-19).

I

(b) Paragraph 5.2.6.3 in Revision 1 to QI-025 require that all

lines with operating temperatures less than 200 F be

installed, such that an air gap exists between the pipe or

pipe insulation, and other objects.

Attribute 1.f. " Piping

Clearances" in the inspection checklist was signed off by

,

the ERC inspector as being acceptable.

However, the NRC

inspector observed a portion of a support in contact with

the inspected line's pipe insulation at approximately

14 feet south of the 76 bend.

This is a deviation (445/8601-0-20).

k.

Mechanical Equipment Installation

Status of CPRT Activity

Reinspection of 46 mechanical equipment installation items from the

combined random and engineered sample of 190 has been completed.

A

total of 35 deviations have been identified, 28 of which have been

reviewed with 21 determined to be valid.

Status of NRC Inspection Activity

The NRC inspector reviewed QI-059 and performed the following

independent inspection'of a motor-driven auxiliary feedwater pump:

Verification

Equipment

Package No.

Tag No.

System *

Unit No.

I-M-MEIN-009

CPI-AFAPMD-01

,AF

1

- '

,

No NRC violations or deviations were identified.

,

, - , -

,

.

.-

- - - - . - - - ,

-. ,

. , , ,

,

-

.. . .- ,

-

,

-98-

During this inspection, the NRC inspector observed what appeared to

,

be an unacceptable weldment on an adjacent AF system valve, Tag

No. I-FV-2456.

A seismic arrester bracket had been welded over the

raised cast identification letters of the actuator barrel assembly,

resulting in a weld which exhibited incomplete fusion and overall

poor workmanship.

This finding is an unresolved item pending further

NRC review (445/8601-U-21).

1.

Inspection of Non-Pressure Boundary Welds For A

Supplementary Evaluation of Visual Welding Inspection Techniques

Status of CPRT Activity

To date, 23 randomly selected samples of weld joints obtained from

ISAP Nos. 7.b.3, ISAP 7.b.5, and ISAP 7.c have been inspected before

removal of coatings.

The following 12 samples were inspected during

this report period:

Verification

Equipment

Package No.

Tag No.

System * Unit No.

I-S-NPBW-014

FW-1-019-902-C57W

FW

1

I-S-NPBW-050

FW-1-018-901-C57W

FW

1

I-S-NPBW-046

FW-1-102-901-C57W

FW

1

I-S-NPBW-049

FW-1-015-901-557W

FW

1

I-S-NP3W-010

MS-1-001-902-C77W

MS

1

I-S-NPBW-017

MS-1-001-908-C67W

MS

1

I-S-NPBW-004

FW-1-017-908-C77W

FW

1

I-S-NPBW-067

SG-1-852-1J-1AF

Structure

1

I-S-NPBW-055

CB-790-2N-100

Structure

1

I-S-NPBW-005

-1-FI-4695

NI

1

I-S-NPBW-016

1-LS-4795

NI

1

I-S-NPBW-052

1-FT-156

NI

1

NI - Nuclear Instrumentation

The following seven weld joints were inspected after

removal of coatings in January:

Verification

Equipment

Package No.

Tag No.

System *

Unit No.

I-S-NPBW-007

D0-1-DG-009A-0043

D0

1

I-S-NPBW-053

CS-1-241-010-A42R

CS

1

I-S-NPBW-048

CS-1-058-701-A42R

CS

1

I-S-NPBW-021

VA-X-005-702-A73R

VA

, Common

I-S-NPBW-030

SI-1-104-001-C42S

SI

1

I-S-NPBW-075

SW-1-007-700-J03S

SW

1

I-S-NPBW-059

MS-1-RB-010A-013-2

MS

1

.

,-

,

,

e

n

..

---

g-

,

n---

.--- --

,

_

_

h

-99-

  • D0 - Diesel Oil; CS'- Chemical and Volume Control System; VA -

Heating, Ventilation, Air Conditioning; SI - Safety-Injection System;

'SW - Service Water System; and MS - Main steam System

A comparison of weld joint inspection results for the coated and

uncoated condition revealed no discrepant conditions.

Status of NRC Inspection Activity

The NRC inspector has witnessed 100% of inspections performed on weld

joints in the coated and uncoated condition.

No NRC violations or deviations were identified.

10.

Exit Interview

An exit interview was conducted February 6, 1986, with the applicant

representatives identified in paragraph 1 of this appendix.

During this

interview, the NRC inspectors summarized the scope and findings of the

inspectbol.

The applicant acknowledged the findings.

.

b

8

i

e

6

I-

.

k

s%-

e

..