Discusses 920505 Conference Call Re Agreement That NRR Should Assign TAC Number to Collect Hours Expended by Millstone Assessment Panel.Tac Number Established as M83309
ML20203G160
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 05/20/1992
From: Jaffe D
Office of Nuclear Reactor Regulation
To: Blough R, Stolz J, Wiggins J
NRC
Shared Package
ML20203G108 List:
References
FOIA-97-469 TAC-M83309, NUDOCS 9803020217
Download: ML20203G160 (1)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - - _ _ - _

/ p2 asioq'o.,

UNITED STATES

'n NUCLEAR REGULATORY COMMISSION h

WASHINGTON. D. C. 20635

)

May 20, 1992 MEMORANDUM FOR:

J. Wiggins R. Blough J. Stolz C. Anderson J. Joyner L. Doerflein W. Raymond R. Barkley T. Meek FROM:

D. H. Jaffe, Senior Project Manager Project Directorate I-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

SUBJECT:

MILLSTONE ASSESSMENT PANEL In our conference call of May 5,1992, we agreed that NRR should assign a TAC number to collect the hours expended by the Millstone Assessment Panel.

That TAC number has now been established 3

1 s(rp 1

koject Manager D. H.

Sen Project Directorate I-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation 9803020217 980226 9"

0 HE

-469 PDR

~

//"

UNITED ST ATEs j

NUCLEAR REGULATORY COMMISSION

[

g' '

n

.f etGION I

)

e, f

475 ALLENDALE ROAD

/

KING OF PRUSslA, PENNSYLVANIA 19406 1415 MAY 2 71992 MEMORANDUM FOR:

James T. Wiggins, Deputy Director, Division of Reactor Projects FROM:

Thomas T. Martin, Regional Administrator

SUBJECT:

MILLSTONE ASSESSMENT PANEL CHARTER As a result of the observed decline in performance at the Millstone Station, a series of NU self assessment Task Forces were conducted in the Summer and Fall 1991. Subsequently, the recommendations from these efforts were integrated and further analyzed. The licensee currently intends to docket a comprehensive Performance Enhancement Program (PEP) in June 1992 to address identified deficiencies. A large agency effort will be required to follow licensee actions resulting from the implementation of the PEP.

The principal purpose of the Millstone Assessment Panel (MAP) is to assist Region I and NRR in the coordination of NRC resources for performance monitoring, inspection planning, and assessment of the Millstone Station. You have been designated Chairman and John Stolz has been designated Vice Chairman of the panel, i

The MAP responsibilities are:

1.

Review the PEP and assure it addresses problems / weaknesses identified by NRC program activities.

2.

Maintain an ongoing overview of licensee performance during the period of significant PEP implementation activities.

3.

Conduct periodic meetings with NU to discuss progress towards satisfactory completion of the Performance Enhancement Program (PEP) and addressing NRC concerns. These meetings shall be open for public observation.

4.

Provide oversight of the NRC's PEP followup activities. Review NRC inspection and assessment plans and findings and facility performance; identify areas where NRC inspection and/or technical review are warranted.

5.

Provide recommendations at the performance and trends review (MR) meetings regarding additional followup inspections based on facility performance.

6.

Periodically, provide relevant MAP assessment of licensee performance trends to NRC 7

management,

(&

aymd p rej w1 nd% b EDo llw,

ouus ',a Mk? rwau

- og / ef GL9.r. ?

Q5 wwn

,; 2.x.c,na a 6

s.

Memorandum for Jim Wiggins 2

)

/

7.

Membership:

Deputy Director, DRP - Chairman Director, Projects Directorate I Vice Chairman Chief, Projects Branch 4, DRP Chief. Engineering Branch, DRS (Division Representative)

Chief, Facilities Radiation Protection Section, DRSS (Division Representative)

Chief, Reactor Projects Section 4A, DRP Millstone Project Maager, NRR Millstone Senior Resident Inspector l= '

Thomas T. Martin Regional Administrator cc:

T. Murley, NRR T. Martin, RA W. .assell, NRR 7' Kane, DRA C. Varga, NRR J. Richardson, NRR A. Thadani, NRR R. Lobel, OEDO G. Zech, NRR L. Plisco, NRR J. Roe, NRR MAP Members l

.