|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000219/19980121999-03-0404 March 1999 Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items IR 05000219/19980091998-11-25025 November 1998 Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000219/19980081998-10-20020 October 1998 Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19980051998-08-26026 August 1998 Insp Rept 50-219/98-05 on 980614-0726.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support IR 05000219/19980071998-07-0202 July 1998 Insp Rept 50-219/98-07 on 980615-19.No Violations Noted. Major Areas Inspected:Status of Plant motor-operated Valve Program to Determine Acceptability for Closure of NRC Review Under GL 89-10 ML20217F6641998-04-22022 April 1998 Insp Rept 50-219/98-80 on 980223-0313 & 0330-0402.Violations Noted.Major Areas Inspected:Engineering ML20216H1911998-04-15015 April 1998 Insp Rept 50-219/98-04 on 980226-0318.Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000219/19970081997-12-0404 December 1997 Insp Rept 50-219/97-08 on 971020-24.No Violations Noted. Major Areas Inspected:Onsite Emergency Plan IR 05000219/19970041997-07-29029 July 1997 Insp Rept 50-219/97-04 on 970526-0706.Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000219/19970051997-07-17017 July 1997 Insp Rept 50-219/97-05 on 970407-11.No Violations Noted. Major Areas Inspected:Engineering ML20141G9431997-07-0303 July 1997 Insp Rept 50-219/97-03 on 970414-0525.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000219/19970021997-05-19019 May 1997 Insp Rept 50-219/97-02 on 970224-0413.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20137E9491997-03-21021 March 1997 Insp Rept 50-219/97-01 on 970113-0223.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19960101996-09-27027 September 1996 Insp Rept 50-219/96-10 on 960923-27.No Violations Noted. Major Areas Inspected:Radiological Source Term Assessment, Results of Exposure Reduction Initiatives & Evidence of Station ALARA Program IR 05000219/19960111996-01-0202 January 1996 Insp Rept 50-219/96-11 on 961021-1201.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19930811993-12-22022 December 1993 Insp Rept 50-219/93-81 on 930927-1015.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance & Mgt & Corrective Actions IR 05000219/19930261993-11-18018 November 1993 Insp Rept 50-219/93-26 on 931101-05.No Violations Noted. Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Access Control of Personnel & Packages & Vehicles IR 05000219/19930241993-11-18018 November 1993 Insp Rept 50-219/93-24 on 930921-1101.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support,Including Security & Emergency Preparedness & Safety Assessment/Quality Verification ML20058A3791993-11-12012 November 1993 Insp Rept 50-219/93-23 on 931018-20.Onsite Response to Exercise Scenario Was Good.Major Areas inspected:full- Participation Ingestion Pathway Emergency Preparedness Exercise IR 05000219/19930251993-11-0909 November 1993 Insp Rept 50-219/93-25 on 931018-22.No Violations Noted. Major Areas Inspected:Design Mods & Engineering Support ML20059F6251993-10-28028 October 1993 Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation Event IR 05000219/19930181993-10-28028 October 1993 Insp Rept 50-219/93-18 on 930823-1020.No Violations Noted. Major Areas Inspected:Alara,Rirs,Qa Audits,Air & Swipe Sample Counting Facilities & Radiological Controls Organization Professional Staffing IR 05000219/19930201993-10-19019 October 1993 Insp Rept 50-219/93-20 on 930816-930917.No Violations Noted. Major Areas Inspected:Radioactive Liquid & Gaseous Effluent Control Programs Including Mgt Controls & QA Audits IR 05000219/19930211993-10-15015 October 1993 Insp Rept 50-219/93-21 on 930810-0920.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality Verification IR 05000219/19930111993-09-10010 September 1993 Insp Rept 50-219/93-11 on 930629-0809.No Violations Noted. Major Areas Inspected:Day Shift & Back Shift Hours of Station Activities IR 05000219/19930191993-09-0909 September 1993 Insp Rept 50-219/93-19 on 930816-20.Violations Noted.Major Areas Inspected:Radiological Environ Monitoring Program & Meteorological Monitoring Program IR 05000219/19930141993-09-0202 September 1993 EP Insp Rept 50-219/93-14 on 930802-05.Concerns Noted. Major Areas Inspected:Epip,Equipment,Instrumentation & Supplies IR 05000219/19930161993-08-27027 August 1993 Insp Rept 50-219/93-16 on 930726-30.Major Areas Inspected: Erosion/Corrosion Insp Program,Per GL 89-08.Program & Program Implementation Generally Good.Staff Responsible for Program Development & Implementation Qualified IR 05000219/19930121993-08-26026 August 1993 Insp Rept 50-219/93-12 on 930706-09.No Violations Noted. Major Areas Inspected:Licensee Progress in Incorporating EQ Component Info Into GMS2 Computer Database IR 05000219/19920221993-03-19019 March 1993 Mobile NDE Lab Insp 50-219/92-22 on 921207-11 & 930111-15. No Violations Noted.Major Areas Inspected:Cs,Css,Sdc,Ms & FW Sys IR 05000219/19920251993-02-10010 February 1993 Insp Rept 50-219/92-25 on 921215-930118.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Maint & Surveillance,Engneering & Technical Support, Emergency Preparedness & Security IR 05000219/19930011993-01-29029 January 1993 Insp Rept 50-219/93-01 on 930104-08.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Postings & Other in Plant Radiological Controls,Work in Progress, Housekeeping & Self Reading Dosimeter Use IR 05000219/19920231992-12-24024 December 1992 Insp Rept 50-219/92-23 on 921103-1214.No Violations Noted. Major Areas Inspected:Plant Operations,Security & Safety Assessment/Quality Verification IR 05000219/19910041991-03-0101 March 1991 Partially Withheld Insp Rept 50-219/91-04 on 910204-07.No Violations Noted.Major Areas Inspected:Protected Area Physical Barriers,Isolation Zones & Lighting,Protected Area Access Control of Personnel & Security Training IR 05000219/19900191990-11-16016 November 1990 Insp Rept 50-219/90-19 on 900923-1020.Violations Noted. Areas Inspected:Radiological Protection,Surveillance & Maintenance,Emergency Preparedness,Security,Engineering & Technical Support & Safety Assessment/Quality Verification IR 05000219/19900201990-11-0202 November 1990 Insp Rept 50-219/90-20 on 901022-26.No Violations Noted. Major Areas Inspected:Internal Exposure Control & Review of Procedures for Drywell Occupancy During Fuel Movement IR 05000219/19900161990-10-18018 October 1990 Insp Rept 50-219/90-16 on 900823-0922.Violations Noted.Major Areas Inspected:Observation of Plant Activities,Review of Operational Events,Operation of Turbine Bldg Ventilation Sys & Walkdown of Emergency Diesel Fuel Oil Transfer Sys ML20058F3241990-10-0202 October 1990 Insp Rept 50-219/90-17 on 900918-21.No Violations Noted. Major Areas Inspected:Transportation & Solid Radwaste Programs IR 05000219/19900151990-09-20020 September 1990 Partially Withheld Safeguards Insp Rept 50-219/90-15 on 900820-24 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Support,Security Program Plans,Audits,Protected & Vital Areas Physical Barriers,Power Supply & Testing IR 05000219/19900111990-08-15015 August 1990 Insp Rept 50-219/90-11 on 900610-0711.Noncited Violation Noted.Major Areas Inspected:Observation & Review of Plant Operations,Review of Radiological Controls & Routine Observations of Maint Activities & Surveillance Tests ML20056A6191990-07-19019 July 1990 Insp Rept 50-219/90-09 on 900422-0609.Violations Noted. Major Areas Inspected:Observation & Review of Routine Plant Activities & Operational Events,Site Radiological Controls & Events & Observations of Corrective Maint Activities IR 05000219/19890291990-02-16016 February 1990 Insp Rept 50-219/89-29 on 891203-900106.Major Areas Inspected:Observation & Review of Plant Operational Events, Condenser Vacuum Transient,Unusual Events Due to Low Intake Water Level & Simultaneous Movement of Two Control Rods IR 05000219/19890181989-09-13013 September 1989 Insp Rept 50-219/89-18 on 890724-28.No Violations Noted. Major Areas Inspected:Review of Licensee Actions on Previous NRC Concerns,Atws Rule Implementation,Procurement Control & non-licensed Operators Training IR 05000219/19890201989-09-0707 September 1989 Insp Rept 50-219/89-20 on 890829-30.No Exercise Weaknesses Noted.Major Areas Inspected:Licensee Emergency Preparedness Exercise Conducted on 890829-30 ML20246J6261989-08-18018 August 1989 Insp Rept 50-219/89-16 on 890702-29.Violations Noted.Major Areas Inspected:Plant Operational Events,Control of High Radiation Areas,Evaluation of Plant Operation W/High Canal Water Temps & Security Response to Vital Area Door Problem IR 05000219/19890191989-08-15015 August 1989 Insp Rept 50-219/89-19 on 890802-04.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys & Transportation Programs,Including Mgt Controls,Audits,Qa & Implementation of Subj Programs IR 05000219/19890151989-08-0909 August 1989 Insp Rept 50-219/89-15 on 890627-30.No Violations Noted. Major Areas Inspected:Organization & Qualifications of Radiological Controls Personnel in Site Organization IR 05000219/19890141989-08-0303 August 1989 Insp Rept 50-219/89-14 on 890604-0701.No Violations Noted. Major Areas Inspected:Core Spray Booster Pump Trips,Under Voltage Relay Failure,Monthly Surveillance Observations, Emergency Svc Water Pump Operability & Oyster Creek Drawing IR 05000219/19890111989-07-25025 July 1989 Insp Rept 50-219/89-11 on 890606-08.Major Areas Inspected: Emergency Preparedness Insp of full-participation Exercise of Licensee Emergency Plan Conducted on 890607.Exercise Did Not Meet Requirements for Annual Test of Emergency Plan IR 05000219/19890121989-07-21021 July 1989 Insp Rept 50-219/89-12 on 890430-0603.Violations Noted.Major Areas Inspected:Plant Operational Events Including Three Reactor Startups & Licensee Corrective Actions Re Reactor Coolant Pressure Boundary Hangers Being Pinned 1999-03-04
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000219/19980121999-03-0404 March 1999 Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items IR 05000219/19980091998-11-25025 November 1998 Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000219/19980081998-10-20020 October 1998 Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19980051998-08-26026 August 1998 Insp Rept 50-219/98-05 on 980614-0726.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support IR 05000219/19980071998-07-0202 July 1998 Insp Rept 50-219/98-07 on 980615-19.No Violations Noted. Major Areas Inspected:Status of Plant motor-operated Valve Program to Determine Acceptability for Closure of NRC Review Under GL 89-10 ML20217F6641998-04-22022 April 1998 Insp Rept 50-219/98-80 on 980223-0313 & 0330-0402.Violations Noted.Major Areas Inspected:Engineering ML20216H1911998-04-15015 April 1998 Insp Rept 50-219/98-04 on 980226-0318.Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000219/19970081997-12-0404 December 1997 Insp Rept 50-219/97-08 on 971020-24.No Violations Noted. Major Areas Inspected:Onsite Emergency Plan IR 05000219/19970041997-07-29029 July 1997 Insp Rept 50-219/97-04 on 970526-0706.Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000219/19970051997-07-17017 July 1997 Insp Rept 50-219/97-05 on 970407-11.No Violations Noted. Major Areas Inspected:Engineering ML20141G9431997-07-0303 July 1997 Insp Rept 50-219/97-03 on 970414-0525.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000219/19970021997-05-19019 May 1997 Insp Rept 50-219/97-02 on 970224-0413.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20137E9491997-03-21021 March 1997 Insp Rept 50-219/97-01 on 970113-0223.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19960101996-09-27027 September 1996 Insp Rept 50-219/96-10 on 960923-27.No Violations Noted. Major Areas Inspected:Radiological Source Term Assessment, Results of Exposure Reduction Initiatives & Evidence of Station ALARA Program IR 05000219/19960111996-01-0202 January 1996 Insp Rept 50-219/96-11 on 961021-1201.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19930811993-12-22022 December 1993 Insp Rept 50-219/93-81 on 930927-1015.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance & Mgt & Corrective Actions IR 05000219/19930261993-11-18018 November 1993 Insp Rept 50-219/93-26 on 931101-05.No Violations Noted. Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Access Control of Personnel & Packages & Vehicles IR 05000219/19930241993-11-18018 November 1993 Insp Rept 50-219/93-24 on 930921-1101.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support,Including Security & Emergency Preparedness & Safety Assessment/Quality Verification ML20058A3791993-11-12012 November 1993 Insp Rept 50-219/93-23 on 931018-20.Onsite Response to Exercise Scenario Was Good.Major Areas inspected:full- Participation Ingestion Pathway Emergency Preparedness Exercise IR 05000219/19930251993-11-0909 November 1993 Insp Rept 50-219/93-25 on 931018-22.No Violations Noted. Major Areas Inspected:Design Mods & Engineering Support ML20059F6251993-10-28028 October 1993 Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation Event IR 05000219/19930181993-10-28028 October 1993 Insp Rept 50-219/93-18 on 930823-1020.No Violations Noted. Major Areas Inspected:Alara,Rirs,Qa Audits,Air & Swipe Sample Counting Facilities & Radiological Controls Organization Professional Staffing IR 05000219/19930201993-10-19019 October 1993 Insp Rept 50-219/93-20 on 930816-930917.No Violations Noted. Major Areas Inspected:Radioactive Liquid & Gaseous Effluent Control Programs Including Mgt Controls & QA Audits IR 05000219/19930211993-10-15015 October 1993 Insp Rept 50-219/93-21 on 930810-0920.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality Verification IR 05000219/19930111993-09-10010 September 1993 Insp Rept 50-219/93-11 on 930629-0809.No Violations Noted. Major Areas Inspected:Day Shift & Back Shift Hours of Station Activities IR 05000219/19930191993-09-0909 September 1993 Insp Rept 50-219/93-19 on 930816-20.Violations Noted.Major Areas Inspected:Radiological Environ Monitoring Program & Meteorological Monitoring Program IR 05000219/19930141993-09-0202 September 1993 EP Insp Rept 50-219/93-14 on 930802-05.Concerns Noted. Major Areas Inspected:Epip,Equipment,Instrumentation & Supplies IR 05000219/19930161993-08-27027 August 1993 Insp Rept 50-219/93-16 on 930726-30.Major Areas Inspected: Erosion/Corrosion Insp Program,Per GL 89-08.Program & Program Implementation Generally Good.Staff Responsible for Program Development & Implementation Qualified IR 05000219/19930121993-08-26026 August 1993 Insp Rept 50-219/93-12 on 930706-09.No Violations Noted. Major Areas Inspected:Licensee Progress in Incorporating EQ Component Info Into GMS2 Computer Database IR 05000219/19920221993-03-19019 March 1993 Mobile NDE Lab Insp 50-219/92-22 on 921207-11 & 930111-15. No Violations Noted.Major Areas Inspected:Cs,Css,Sdc,Ms & FW Sys IR 05000219/19920251993-02-10010 February 1993 Insp Rept 50-219/92-25 on 921215-930118.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Maint & Surveillance,Engneering & Technical Support, Emergency Preparedness & Security IR 05000219/19930011993-01-29029 January 1993 Insp Rept 50-219/93-01 on 930104-08.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Postings & Other in Plant Radiological Controls,Work in Progress, Housekeeping & Self Reading Dosimeter Use IR 05000219/19920231992-12-24024 December 1992 Insp Rept 50-219/92-23 on 921103-1214.No Violations Noted. Major Areas Inspected:Plant Operations,Security & Safety Assessment/Quality Verification IR 05000219/19910041991-03-0101 March 1991 Partially Withheld Insp Rept 50-219/91-04 on 910204-07.No Violations Noted.Major Areas Inspected:Protected Area Physical Barriers,Isolation Zones & Lighting,Protected Area Access Control of Personnel & Security Training IR 05000219/19900191990-11-16016 November 1990 Insp Rept 50-219/90-19 on 900923-1020.Violations Noted. Areas Inspected:Radiological Protection,Surveillance & Maintenance,Emergency Preparedness,Security,Engineering & Technical Support & Safety Assessment/Quality Verification IR 05000219/19900201990-11-0202 November 1990 Insp Rept 50-219/90-20 on 901022-26.No Violations Noted. Major Areas Inspected:Internal Exposure Control & Review of Procedures for Drywell Occupancy During Fuel Movement IR 05000219/19900161990-10-18018 October 1990 Insp Rept 50-219/90-16 on 900823-0922.Violations Noted.Major Areas Inspected:Observation of Plant Activities,Review of Operational Events,Operation of Turbine Bldg Ventilation Sys & Walkdown of Emergency Diesel Fuel Oil Transfer Sys ML20058F3241990-10-0202 October 1990 Insp Rept 50-219/90-17 on 900918-21.No Violations Noted. Major Areas Inspected:Transportation & Solid Radwaste Programs IR 05000219/19900151990-09-20020 September 1990 Partially Withheld Safeguards Insp Rept 50-219/90-15 on 900820-24 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Support,Security Program Plans,Audits,Protected & Vital Areas Physical Barriers,Power Supply & Testing IR 05000219/19900111990-08-15015 August 1990 Insp Rept 50-219/90-11 on 900610-0711.Noncited Violation Noted.Major Areas Inspected:Observation & Review of Plant Operations,Review of Radiological Controls & Routine Observations of Maint Activities & Surveillance Tests ML20056A6191990-07-19019 July 1990 Insp Rept 50-219/90-09 on 900422-0609.Violations Noted. Major Areas Inspected:Observation & Review of Routine Plant Activities & Operational Events,Site Radiological Controls & Events & Observations of Corrective Maint Activities IR 05000219/19890291990-02-16016 February 1990 Insp Rept 50-219/89-29 on 891203-900106.Major Areas Inspected:Observation & Review of Plant Operational Events, Condenser Vacuum Transient,Unusual Events Due to Low Intake Water Level & Simultaneous Movement of Two Control Rods IR 05000219/19890181989-09-13013 September 1989 Insp Rept 50-219/89-18 on 890724-28.No Violations Noted. Major Areas Inspected:Review of Licensee Actions on Previous NRC Concerns,Atws Rule Implementation,Procurement Control & non-licensed Operators Training IR 05000219/19890201989-09-0707 September 1989 Insp Rept 50-219/89-20 on 890829-30.No Exercise Weaknesses Noted.Major Areas Inspected:Licensee Emergency Preparedness Exercise Conducted on 890829-30 ML20246J6261989-08-18018 August 1989 Insp Rept 50-219/89-16 on 890702-29.Violations Noted.Major Areas Inspected:Plant Operational Events,Control of High Radiation Areas,Evaluation of Plant Operation W/High Canal Water Temps & Security Response to Vital Area Door Problem IR 05000219/19890191989-08-15015 August 1989 Insp Rept 50-219/89-19 on 890802-04.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys & Transportation Programs,Including Mgt Controls,Audits,Qa & Implementation of Subj Programs IR 05000219/19890151989-08-0909 August 1989 Insp Rept 50-219/89-15 on 890627-30.No Violations Noted. Major Areas Inspected:Organization & Qualifications of Radiological Controls Personnel in Site Organization IR 05000219/19890141989-08-0303 August 1989 Insp Rept 50-219/89-14 on 890604-0701.No Violations Noted. Major Areas Inspected:Core Spray Booster Pump Trips,Under Voltage Relay Failure,Monthly Surveillance Observations, Emergency Svc Water Pump Operability & Oyster Creek Drawing IR 05000219/19890111989-07-25025 July 1989 Insp Rept 50-219/89-11 on 890606-08.Major Areas Inspected: Emergency Preparedness Insp of full-participation Exercise of Licensee Emergency Plan Conducted on 890607.Exercise Did Not Meet Requirements for Annual Test of Emergency Plan IR 05000219/19890121989-07-21021 July 1989 Insp Rept 50-219/89-12 on 890430-0603.Violations Noted.Major Areas Inspected:Plant Operational Events Including Three Reactor Startups & Licensee Corrective Actions Re Reactor Coolant Pressure Boundary Hangers Being Pinned 1999-03-04
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000219/19980121999-03-0404 March 1999 Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items IR 05000219/19980091998-11-25025 November 1998 Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000219/19980081998-10-20020 October 1998 Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19980051998-08-26026 August 1998 Insp Rept 50-219/98-05 on 980614-0726.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support IR 05000219/19980071998-07-0202 July 1998 Insp Rept 50-219/98-07 on 980615-19.No Violations Noted. Major Areas Inspected:Status of Plant motor-operated Valve Program to Determine Acceptability for Closure of NRC Review Under GL 89-10 ML20217F6641998-04-22022 April 1998 Insp Rept 50-219/98-80 on 980223-0313 & 0330-0402.Violations Noted.Major Areas Inspected:Engineering ML20216H1911998-04-15015 April 1998 Insp Rept 50-219/98-04 on 980226-0318.Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000219/19970081997-12-0404 December 1997 Insp Rept 50-219/97-08 on 971020-24.No Violations Noted. Major Areas Inspected:Onsite Emergency Plan IR 05000219/19970041997-07-29029 July 1997 Insp Rept 50-219/97-04 on 970526-0706.Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000219/19970051997-07-17017 July 1997 Insp Rept 50-219/97-05 on 970407-11.No Violations Noted. Major Areas Inspected:Engineering ML20141G9431997-07-0303 July 1997 Insp Rept 50-219/97-03 on 970414-0525.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000219/19970021997-05-19019 May 1997 Insp Rept 50-219/97-02 on 970224-0413.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20137E9491997-03-21021 March 1997 Insp Rept 50-219/97-01 on 970113-0223.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19960101996-09-27027 September 1996 Insp Rept 50-219/96-10 on 960923-27.No Violations Noted. Major Areas Inspected:Radiological Source Term Assessment, Results of Exposure Reduction Initiatives & Evidence of Station ALARA Program IR 05000219/19960111996-01-0202 January 1996 Insp Rept 50-219/96-11 on 961021-1201.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19930811993-12-22022 December 1993 Insp Rept 50-219/93-81 on 930927-1015.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance & Mgt & Corrective Actions IR 05000219/19930261993-11-18018 November 1993 Insp Rept 50-219/93-26 on 931101-05.No Violations Noted. Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Access Control of Personnel & Packages & Vehicles IR 05000219/19930241993-11-18018 November 1993 Insp Rept 50-219/93-24 on 930921-1101.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support,Including Security & Emergency Preparedness & Safety Assessment/Quality Verification ML20058A3791993-11-12012 November 1993 Insp Rept 50-219/93-23 on 931018-20.Onsite Response to Exercise Scenario Was Good.Major Areas inspected:full- Participation Ingestion Pathway Emergency Preparedness Exercise IR 05000219/19930251993-11-0909 November 1993 Insp Rept 50-219/93-25 on 931018-22.No Violations Noted. Major Areas Inspected:Design Mods & Engineering Support ML20059F6251993-10-28028 October 1993 Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation Event IR 05000219/19930181993-10-28028 October 1993 Insp Rept 50-219/93-18 on 930823-1020.No Violations Noted. Major Areas Inspected:Alara,Rirs,Qa Audits,Air & Swipe Sample Counting Facilities & Radiological Controls Organization Professional Staffing IR 05000219/19930201993-10-19019 October 1993 Insp Rept 50-219/93-20 on 930816-930917.No Violations Noted. Major Areas Inspected:Radioactive Liquid & Gaseous Effluent Control Programs Including Mgt Controls & QA Audits IR 05000219/19930211993-10-15015 October 1993 Insp Rept 50-219/93-21 on 930810-0920.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality Verification IR 05000219/19930111993-09-10010 September 1993 Insp Rept 50-219/93-11 on 930629-0809.No Violations Noted. Major Areas Inspected:Day Shift & Back Shift Hours of Station Activities IR 05000219/19930191993-09-0909 September 1993 Insp Rept 50-219/93-19 on 930816-20.Violations Noted.Major Areas Inspected:Radiological Environ Monitoring Program & Meteorological Monitoring Program IR 05000219/19930141993-09-0202 September 1993 EP Insp Rept 50-219/93-14 on 930802-05.Concerns Noted. Major Areas Inspected:Epip,Equipment,Instrumentation & Supplies IR 05000219/19930161993-08-27027 August 1993 Insp Rept 50-219/93-16 on 930726-30.Major Areas Inspected: Erosion/Corrosion Insp Program,Per GL 89-08.Program & Program Implementation Generally Good.Staff Responsible for Program Development & Implementation Qualified IR 05000219/19930121993-08-26026 August 1993 Insp Rept 50-219/93-12 on 930706-09.No Violations Noted. Major Areas Inspected:Licensee Progress in Incorporating EQ Component Info Into GMS2 Computer Database IR 05000219/19920221993-03-19019 March 1993 Mobile NDE Lab Insp 50-219/92-22 on 921207-11 & 930111-15. No Violations Noted.Major Areas Inspected:Cs,Css,Sdc,Ms & FW Sys IR 05000219/19920251993-02-10010 February 1993 Insp Rept 50-219/92-25 on 921215-930118.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Control, Maint & Surveillance,Engneering & Technical Support, Emergency Preparedness & Security IR 05000219/19930011993-01-29029 January 1993 Insp Rept 50-219/93-01 on 930104-08.No Radiological Safety Concerns or Violations Noted.Major Areas Inspected:Postings & Other in Plant Radiological Controls,Work in Progress, Housekeeping & Self Reading Dosimeter Use IR 05000219/19920231992-12-24024 December 1992 Insp Rept 50-219/92-23 on 921103-1214.No Violations Noted. Major Areas Inspected:Plant Operations,Security & Safety Assessment/Quality Verification IR 05000219/19910041991-03-0101 March 1991 Partially Withheld Insp Rept 50-219/91-04 on 910204-07.No Violations Noted.Major Areas Inspected:Protected Area Physical Barriers,Isolation Zones & Lighting,Protected Area Access Control of Personnel & Security Training IR 05000219/19900191990-11-16016 November 1990 Insp Rept 50-219/90-19 on 900923-1020.Violations Noted. Areas Inspected:Radiological Protection,Surveillance & Maintenance,Emergency Preparedness,Security,Engineering & Technical Support & Safety Assessment/Quality Verification IR 05000219/19900201990-11-0202 November 1990 Insp Rept 50-219/90-20 on 901022-26.No Violations Noted. Major Areas Inspected:Internal Exposure Control & Review of Procedures for Drywell Occupancy During Fuel Movement IR 05000219/19900161990-10-18018 October 1990 Insp Rept 50-219/90-16 on 900823-0922.Violations Noted.Major Areas Inspected:Observation of Plant Activities,Review of Operational Events,Operation of Turbine Bldg Ventilation Sys & Walkdown of Emergency Diesel Fuel Oil Transfer Sys ML20058F3241990-10-0202 October 1990 Insp Rept 50-219/90-17 on 900918-21.No Violations Noted. Major Areas Inspected:Transportation & Solid Radwaste Programs IR 05000219/19900151990-09-20020 September 1990 Partially Withheld Safeguards Insp Rept 50-219/90-15 on 900820-24 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Support,Security Program Plans,Audits,Protected & Vital Areas Physical Barriers,Power Supply & Testing IR 05000219/19900111990-08-15015 August 1990 Insp Rept 50-219/90-11 on 900610-0711.Noncited Violation Noted.Major Areas Inspected:Observation & Review of Plant Operations,Review of Radiological Controls & Routine Observations of Maint Activities & Surveillance Tests ML20056A6191990-07-19019 July 1990 Insp Rept 50-219/90-09 on 900422-0609.Violations Noted. Major Areas Inspected:Observation & Review of Routine Plant Activities & Operational Events,Site Radiological Controls & Events & Observations of Corrective Maint Activities IR 05000219/19890291990-02-16016 February 1990 Insp Rept 50-219/89-29 on 891203-900106.Major Areas Inspected:Observation & Review of Plant Operational Events, Condenser Vacuum Transient,Unusual Events Due to Low Intake Water Level & Simultaneous Movement of Two Control Rods IR 05000219/19890181989-09-13013 September 1989 Insp Rept 50-219/89-18 on 890724-28.No Violations Noted. Major Areas Inspected:Review of Licensee Actions on Previous NRC Concerns,Atws Rule Implementation,Procurement Control & non-licensed Operators Training IR 05000219/19890201989-09-0707 September 1989 Insp Rept 50-219/89-20 on 890829-30.No Exercise Weaknesses Noted.Major Areas Inspected:Licensee Emergency Preparedness Exercise Conducted on 890829-30 ML20246J6261989-08-18018 August 1989 Insp Rept 50-219/89-16 on 890702-29.Violations Noted.Major Areas Inspected:Plant Operational Events,Control of High Radiation Areas,Evaluation of Plant Operation W/High Canal Water Temps & Security Response to Vital Area Door Problem IR 05000219/19890191989-08-15015 August 1989 Insp Rept 50-219/89-19 on 890802-04.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys & Transportation Programs,Including Mgt Controls,Audits,Qa & Implementation of Subj Programs IR 05000219/19890151989-08-0909 August 1989 Insp Rept 50-219/89-15 on 890627-30.No Violations Noted. Major Areas Inspected:Organization & Qualifications of Radiological Controls Personnel in Site Organization IR 05000219/19890141989-08-0303 August 1989 Insp Rept 50-219/89-14 on 890604-0701.No Violations Noted. Major Areas Inspected:Core Spray Booster Pump Trips,Under Voltage Relay Failure,Monthly Surveillance Observations, Emergency Svc Water Pump Operability & Oyster Creek Drawing IR 05000219/19890111989-07-25025 July 1989 Insp Rept 50-219/89-11 on 890606-08.Major Areas Inspected: Emergency Preparedness Insp of full-participation Exercise of Licensee Emergency Plan Conducted on 890607.Exercise Did Not Meet Requirements for Annual Test of Emergency Plan IR 05000219/19890121989-07-21021 July 1989 Insp Rept 50-219/89-12 on 890430-0603.Violations Noted.Major Areas Inspected:Plant Operational Events Including Three Reactor Startups & Licensee Corrective Actions Re Reactor Coolant Pressure Boundary Hangers Being Pinned 1999-03-04
[Table view] Category:UTILITY
MONTHYEARIR 05000219/19900201990-11-0202 November 1990 Insp Rept 50-219/90-20 on 901022-26.No Violations Noted. Major Areas Inspected:Internal Exposure Control & Review of Procedures for Drywell Occupancy During Fuel Movement IR 05000219/19900161990-10-18018 October 1990 Insp Rept 50-219/90-16 on 900823-0922.Violations Noted.Major Areas Inspected:Observation of Plant Activities,Review of Operational Events,Operation of Turbine Bldg Ventilation Sys & Walkdown of Emergency Diesel Fuel Oil Transfer Sys IR 05000219/19900111990-08-15015 August 1990 Insp Rept 50-219/90-11 on 900610-0711.Noncited Violation Noted.Major Areas Inspected:Observation & Review of Plant Operations,Review of Radiological Controls & Routine Observations of Maint Activities & Surveillance Tests ML20056A6191990-07-19019 July 1990 Insp Rept 50-219/90-09 on 900422-0609.Violations Noted. Major Areas Inspected:Observation & Review of Routine Plant Activities & Operational Events,Site Radiological Controls & Events & Observations of Corrective Maint Activities IR 05000219/19890291990-02-16016 February 1990 Insp Rept 50-219/89-29 on 891203-900106.Major Areas Inspected:Observation & Review of Plant Operational Events, Condenser Vacuum Transient,Unusual Events Due to Low Intake Water Level & Simultaneous Movement of Two Control Rods IR 05000219/19890181989-09-13013 September 1989 Insp Rept 50-219/89-18 on 890724-28.No Violations Noted. Major Areas Inspected:Review of Licensee Actions on Previous NRC Concerns,Atws Rule Implementation,Procurement Control & non-licensed Operators Training IR 05000219/19890201989-09-0707 September 1989 Insp Rept 50-219/89-20 on 890829-30.No Exercise Weaknesses Noted.Major Areas Inspected:Licensee Emergency Preparedness Exercise Conducted on 890829-30 ML20246J6261989-08-18018 August 1989 Insp Rept 50-219/89-16 on 890702-29.Violations Noted.Major Areas Inspected:Plant Operational Events,Control of High Radiation Areas,Evaluation of Plant Operation W/High Canal Water Temps & Security Response to Vital Area Door Problem IR 05000219/19890191989-08-15015 August 1989 Insp Rept 50-219/89-19 on 890802-04.No Violations or Deviations Noted.Major Areas Inspected:Solid Radwaste Sys & Transportation Programs,Including Mgt Controls,Audits,Qa & Implementation of Subj Programs IR 05000219/19890151989-08-0909 August 1989 Insp Rept 50-219/89-15 on 890627-30.No Violations Noted. Major Areas Inspected:Organization & Qualifications of Radiological Controls Personnel in Site Organization IR 05000219/19890141989-08-0303 August 1989 Insp Rept 50-219/89-14 on 890604-0701.No Violations Noted. Major Areas Inspected:Core Spray Booster Pump Trips,Under Voltage Relay Failure,Monthly Surveillance Observations, Emergency Svc Water Pump Operability & Oyster Creek Drawing IR 05000219/19890111989-07-25025 July 1989 Insp Rept 50-219/89-11 on 890606-08.Major Areas Inspected: Emergency Preparedness Insp of full-participation Exercise of Licensee Emergency Plan Conducted on 890607.Exercise Did Not Meet Requirements for Annual Test of Emergency Plan IR 05000219/19890131989-06-15015 June 1989 Insp Rept 50-219/89-13 on 890522-26.No Violations Noted. Major Areas Inspected:Licensee Liquid & Gaseous Radioactive Effluent Control Programs & Radiological Environ Monitoring Program IR 05000219/19890101989-05-24024 May 1989 Insp Rept 50-219/89-10 on 890402-29.No Violations Noted. Major Areas Inspected:Action of Plant Deficiencies Discovered During Startup,Instrument Air Sys Problems, Surveillance Testing & Control Rod Scram Timing Testing IR 05000219/19890071989-05-17017 May 1989 Insp Rept 50-219/89-07 on 890226-0401.No Violations Noted. Major Areas Inspected:Activities in Progress at Completion of Outage,In Preparation for Startup & Plant Startup Activities IR 05000219/19890061989-05-10010 May 1989 Insp Repts 50-219/89-06 on 890217-24.Violations Noted.Major Areas Inspected:Review of Preliminary Safety Concern Process Including Concerns Involving Standby Gas Treatment Sys, Automatic Depressurization Sys & Containment Spray Sys IR 05000219/19890081989-04-28028 April 1989 Insp Rept 50-219/89-08 on 890313-17.No Violations Noted. Major Areas Inspected:Implementation of Relief & Safety Valve Position Indication Sections of NUREG-0737 & Procedures Re Handling of Emergency Diesel Generator Fuel IR 05000219/19890041989-04-14014 April 1989 Insp Rept 50-219/89-04 on 890115-0225.Violations Noted.Major Areas Inspected:Activities in Progress,Including Air Accumulator Testing,Environ Qualification,Reactor Pressure Vessel Testing,Operations & Physical Security IR 05000219/19882031989-03-13013 March 1989 SSOMI Rept 50-219/88-203 on 881128-1216.Major Areas Inspected:Adequacy of Licensee Mgt & Control of Mods Performed During Major Plant Outage & to Identify Strengths & Weaknesses in Licensee Mod Programs ML20236A5571989-03-0303 March 1989 Safety Insp Rept 50-219/89-03 on 890117-20.No Violations, Deviations or Unresolved Items Noted.Major Areas Inspected: Licensee Emergency Preparedness Program ML20245H9681989-02-21021 February 1989 Insp Rept 50-219/88-38 on 881204-890114.No Violations Noted. Unresolved Items Observed.Major Areas Inspected:Maint & Surveillance Activities,Radiation Control & Physical Security,Including Security Events Re Unauthorized Entry ML20235H2681989-02-0303 February 1989 Insp Rept 50-219/89-02 on 890117-20.Violations Noted.Major Areas Inspected:Licensee Activity Re Info Notice 86-053 (Raychem Splices) IR 05000219/19880311988-11-29029 November 1988 Insp Rept 50-219/88-31 on 881003-07,20 & 1031-1104. Violations Noted.Major Areas Inspected:Status of Outstanding Items,Radiological Controls Re 12R Refueling Outage & Review of Circumstances Concerning Radioactive Spill Incident IR 05000219/19880321988-11-28028 November 1988 Insp Rept 50-219/88-32 on 881017-21.Violation Noted.Major Areas Inspected:Mgt Support,Security Program Plans,Audits, Protected & Vital Area Physical Barriers,Access Control, Detection & Assessment Aids,Testing & Maint & Power Supply IR 05000219/19880281988-11-15015 November 1988 Insp Rept 50-219/88-28 on 880911-1004 & 1014-29.Apparent Violation Noted.Major Areas Inspected:Activities in Progress,Including Plant Operations,Radiation Control, Physical Security,Maint & Forced Shutdown Activities ML20206D0131988-11-0101 November 1988 Environ Qualification Enforcement Conference Rept 50-219/85-39 on 881020.Major Areas Discussed:Significance of Concerns Re Environ Qualification of PVC Tape Splices & Limit Switches Associated W/Msivs.Related Info Encl ML20205P6101988-10-31031 October 1988 Insp Rept 50-219/88-30 on 880929.Notice of Violation Withdrawn.Major Areas Inspected:Emergency Preparedness Activities Re Licensee Response to Notice of Violation & Inspector Followup Items IR 05000219/19880801988-10-28028 October 1988 Augmented Insp Team Rept 50-219/88-80 on 881005-13.Major Areas Inspected:Circumstances Surrounding Steaming Phenomenon on Both Isolation Condensers in Late Aug & Sept 1988 & Electrical Fault on Diesel Generator 2 on 881002 IR 05000219/19880291988-10-22022 October 1988 Insp Rept 50-219/88-29 on 880914-15.App R Violation Re High & Low Pressure Interface During Design Basis Fire Which Could Cause Loss of Reactor Coolant Noted.Major Areas Inspected:Interviews W/Personnel & Inspector Observations ML20205J7301988-10-11011 October 1988 Insp Rept 50-219/88-26 on 880909 & 0912-15.No Violations Noted.Major Areas Inspected:Licensee Inservice Insp Program to Ascertain That Program Complies W/Applicable ASME Code & Regulatory Requirements & Response to Generic Ltr 88-01 ML20207N2331988-10-0404 October 1988 Insp Rept 50-219/88-25 on 880829-0902.No Violations Noted. Major Areas Inspected:Licensee Actions in Response to NRC Bulletins 79-02 & 79-14,Deficiencies Noted in Some Pipe Support & Pipe Support Base Plates IR 05000219/19880231988-09-27027 September 1988 Insp Rept 50-219/88-23 on 880731-0910.Violation Noted. Major Areas Inspected:Plant Operations & Startup,Radiation Control,Physical Security,Maint & Forced Shutdown Work Activities & Isolation Condenser Sys Operability IR 05000219/19880241988-09-0909 September 1988 Insp Rept 50-219/88-24 on 880715 & 18-0812.No Violation Noted.Unresolved Item Identified.Major Areas Inspected: Failure of MSIV NS03A Stem,Including Sequence of Events, Maint & Surveillance Test History & Stem Matl ML20151Y3081988-08-15015 August 1988 Insp Rept 50-219/88-15 on 880523-0726.Violations Noted. Major Areas Inspected:Licensee Action in Response to Mark I Containment Mod Requirements of NUREG-0661,review of Design Analyses & Plant Unigue Analysis Rept IR 05000219/19880221988-08-12012 August 1988 Insp Rept 50-219/88-22 on 880718-22.No Violations Noted. Major Areas Inspected:Gaseous & Liquid Radioactive Effluent Control Programs,Licensee Action on Previous Insp Findings, Effluents,Instrumentation,Audits & Air Cleaning Sys IR 05000219/19880171988-07-26026 July 1988 Insp Rept 50-219/88-17 on 880613-17.No Violations Noted. Major Areas Inspected:Previously Identified Findings,Spds & Planned Mods to Institute Corrective Measures to Satisfy ATWS IR 05000219/19880181988-07-11011 July 1988 Mgt Meeting Rept 50-219/88-18 on 880609.Major Areas Discussed:Status of Licensee Action/Plans & Schedules for Work Per IE Bulletins 79-02 & 79-14 IR 05000219/19880121988-07-0808 July 1988 Insp Rept 50-219/88-12 on 880425-29.No Violations Noted. Major Areas Inspected:Review of Licensee Program Implementation of 10CFR21 Regulation & Review of Station Procurement Program IR 05000219/19880051988-06-30030 June 1988 Insp Rept 50-219/88-05 on 880511-12.No Violations Noted. Major Areas Inspected:Emergency Exercise Conducted on 880511-12 IR 05000219/19880141988-06-27027 June 1988 Insp Rept 50-219/88-14 on 880516-20.Violation Noted.Major Areas Inspected:Selected Areas of Fire Protection & Electric Power Sys,Including Reviews of Administrative Control, Surveillance & Fire Brigade Procedures IR 05000219/19880131988-06-14014 June 1988 Insp Rept 50-219/88-13 on 880424-0521.One Violation Noted. Major Areas Inspected:Plant Operations,Physical Security, Radiation Control,Housekeeping,Fire Protection & Emergency Preparedness & Annual Emergency Exercise Participation IR 05000219/19880091988-05-26026 May 1988 Insp Rept 50-219/88-09 on 880320-0423.No Violations Noted. Major Areas Inspected:Plant Operations,Radiation Control, Physical Security,Surveillance,Maint & Environ Qualification Files for Reactor Vessel Pressure Switches IR 05000219/19880111988-05-11011 May 1988 Safety Insp Rept 50-219/88-11 on 880411-15.Violations Noted. Major Areas Inspected:Status of Items Identified During 1987 Integrated Performance Assessment Team Insp & Status of Measures to Control Drywell Access IR 05000219/19880041988-05-0606 May 1988 Insp Rept 50-219/88-04 on 880207-0319.Violations Noted.Major Areas Inspected:Activities in Progress,Including Plant Operation,Physical Security,Radiation Control,Housekeeping, Fire Protection & Emergency Preparedness ML20153D8181988-04-29029 April 1988 Insp Rept 50-219/88-06 on 880222-26.Violation Noted.Major Areas Inspected:Emergency Implementing Procedures & Plans, Emergency Facilities,Equipment,Instrumentation & Supplies & Application of IE Info Notices 83-28 & 84-80 IR 05000219/19880081988-04-29029 April 1988 Mgt Meeting Rept 50-219/88-08 on 880308.Major Areas Discussed:Licensee Activities Re NRC Bulletins 79-02 & 79-14.Licensee Presentation Encl IR 05000219/19870421988-03-14014 March 1988 Insp Rept 50-219/87-42 on 871220-880206.No Violations Noted. Major Areas Inspected:Activities in Progress,Including Operations,Radiation Control,Physical Security,Surveillance & Maint IR 05000219/19880021988-02-29029 February 1988 Insp Rept 50-219/88-02 on 880125-29.Violations Noted.Major Areas Inspected:Safety Implications of Freezing Conditions Identified in Reactor Bldg on 880106 & Effectivness of Licensee Corrective Measures IR 05000219/19880011988-02-19019 February 1988 Insp Rept 50-219/88-01 on 880104-08.No Violations or Deviations Noted.Major Areas Inspected:Licensee Actions on Previously Identified NRC Concerns,Util Offsite Review Committee & Organization & Administration & QA Audits IR 05000219/19870401988-01-21021 January 1988 Physical Security Insp Rept 50-219/87-40 on 871106.No Violations Noted.Major Areas Inspected:Three Allegations Re Deficiencies in Security Program.Allegations Were Not Substantiated 1990-08-15
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARPNO-I-99-043, on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power1999-09-16016 September 1999 PNO-I-99-043:on 990916,Hurricane Floyd Was Approaching Ccnpp,Sgs,Hcgs & Ocnpp.Hurricane Was Centered at Latitude 36.0 North & Longitude 76.6 West & Moving north-northeast at Approx 25 Mph.Plants Remain at Power IR 05000219/19980121999-03-0404 March 1999 Insp Rept 50-219/98-12 During Periods 981214-18,990106-07 & 20-22.No Violations Identified.Major Areas Inspected: Review of Licensee self-assessment of Plant Environ Qualification Program & Corrective Actions for Open Items IR 05000219/19980091998-11-25025 November 1998 Insp Rept 50-219/98-09 on 980914-1025.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20196C6071998-11-25025 November 1998 Notice of Violation from Insp on 980914-1025.Violation Noted:On 981014,security Force Vehicle Escort Left Non licensee-designated Vehicle Unattended in Protected Area & Failed to Ensure That Vehicle Ignition Locked & Key Removed IR 05000219/19980081998-10-20020 October 1998 Insp Rept 50-219/98-08 on 980727-0913.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19980051998-08-26026 August 1998 Insp Rept 50-219/98-05 on 980614-0726.No Violations Noted. Major Areas Inspected:Plant Operations,Maint,Engineering & Plant Support IR 05000219/19980991998-07-17017 July 1998 SALP Rept 50-219/98-99 for 961201-980613 IR 05000219/19980071998-07-0202 July 1998 Insp Rept 50-219/98-07 on 980615-19.No Violations Noted. Major Areas Inspected:Status of Plant motor-operated Valve Program to Determine Acceptability for Closure of NRC Review Under GL 89-10 ML20249B3661998-06-15015 June 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Prior to 980304, Licensee Failed to Establish Adequate Design Control Measures to Verify Adequacy of Design Voltage ML20237E4491998-06-10010 June 1998 EN-98-047:on 980615,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on Severity Level III Problem Involving Inoperability of Three of Five Automatic Depressurization Valves ML20217F6641998-04-22022 April 1998 Insp Rept 50-219/98-80 on 980223-0313 & 0330-0402.Violations Noted.Major Areas Inspected:Engineering ML20217F6491998-04-22022 April 1998 Notice of Violation from Insp on 980223-0313 & 0330-0402. Violations Noted:On 980226,seismic Deficiency W/Containment Spray Heat Exchanger,That Had Been Identified in Late 1996 by Licensee,Had Not Been Adequately Corrected ML20216H1911998-04-15015 April 1998 Insp Rept 50-219/98-04 on 980226-0318.Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support ML20216H1701998-04-15015 April 1998 Notice of Violation from Insp on 980226-0318.Violations Noted:Since Initial Plant Operation,Operators Implemented Procedure 307,isolation Condenser Sys,Permitting Fill & Make Up to Isolation Condensers During Normal Plant Operations ML20216J0181998-04-14014 April 1998 Notice of Violation from Insp on 971229-980208.Violation Noted:Written SE Was Not Performed to Provide Bases for Determination That Change in Facility as Described in SAR Did Not Involve USQ IR 05000219/19970081997-12-0404 December 1997 Insp Rept 50-219/97-08 on 971020-24.No Violations Noted. Major Areas Inspected:Onsite Emergency Plan ML20199G7881997-11-17017 November 1997 Notice of Violation from Insp on 970707-970824.Violation Noted:In Oct 1993,vendor Specification for Emergency Svc Water Pump Bowl Assemblies Was Changed from Cast Iron to Stainless Steel PNO-I-97-045, on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR1997-08-0404 August 1997 PNO-I-97-045:on 970801,electricians Restoring One Set of Main Generator Exciter Brushes,Following Routine Surveillance,When One of Brushes Sparked Excessively & Disintegrated.Electricians Exited Area & Notified CR IR 05000219/19970041997-07-29029 July 1997 Insp Rept 50-219/97-04 on 970526-0706.Violations Noted. Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support IR 05000219/19970051997-07-17017 July 1997 Insp Rept 50-219/97-05 on 970407-11.No Violations Noted. Major Areas Inspected:Engineering ML20141G9431997-07-0303 July 1997 Insp Rept 50-219/97-03 on 970414-0525.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20141G9401997-07-0303 July 1997 Notice of Violation from Insp on 970414-0525.Violation Noted:On 970423,CROs Placed a & B Loops of Shutdown Cooling Sys in Svc W/O Placing Suction Pressure Interlocks in Svc for a & B Pumps by Opening Ps Isolation Valves IR 05000219/19970021997-05-19019 May 1997 Insp Rept 50-219/97-02 on 970224-0413.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20141J5221997-05-19019 May 1997 Notice of Violation from Insp on 970224-0413.Violation Noted:Permanent Change,Dec 95,made to Facility,As Described in SAR Involving Removal of Isolation Condenser Radiation Monitors W/O Considering All Relevant Portions of SAR PNO-I-97-024, on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem1997-04-23023 April 1997 PNO-I-97-024:on 970422,Oyster Creek Nuclear Generating Station Commenced Controlled Shutdown of Unit Due to Equipment Problems.Unit Expected to Be Shut Down for Six Days for Correction of Diaphram Problem PNO-I-97-022, on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention1997-04-10010 April 1997 PNO-I-97-022:on 970410,GPU,Inc Announced,Addition to Continued Operation of Oyster Creek & Also Exploring Options of Sale.Util Will Begin Next Wk to Develop Plans to Support Sale of Plant,Decommissioning & Personnel Retention ML20137E9411997-03-21021 March 1997 Notice of Violation from Insp on 970113-0223.Violation Noted:Procedure 108.7, Lockout/Tagout Procedure, Rev 4, Did Not Include Appropriate Quantitative or Qualitative Acceptance Criteria ML20137E9491997-03-21021 March 1997 Insp Rept 50-219/97-01 on 970113-0223.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19960991997-01-0909 January 1997 SALP Rept 50-219/96-99 for Oyster Creek Nuclear Generating Station for 950625-961130 ML20133D6781997-01-0202 January 1997 Notice of Violation from Insp on 961021-1201.Violation Noted:Written Safety Evaluation Was Not Performed to Provide Bases for Determination That Change to Station Procedure 336.3 Did Not Involve Unreviewed Safety Question PNO-I-96-078, on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event1996-10-29029 October 1996 PNO-I-96-078:on 961025,licensee Manually Scrammed Reactor Due to Turbine Runback,Resulted from Problem in Stator Cooling Sys.Resident Will Continue to Follow Event IR 05000219/19960101996-09-27027 September 1996 Insp Rept 50-219/96-10 on 960923-27.No Violations Noted. Major Areas Inspected:Radiological Source Term Assessment, Results of Exposure Reduction Initiatives & Evidence of Station ALARA Program IR 05000219/19960111996-01-0202 January 1996 Insp Rept 50-219/96-11 on 961021-1201.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000219/19920991994-01-26026 January 1994 SALP Rept 50-219/92-99 for Period 920719-931211 ML20059B6331993-12-23023 December 1993 Notice of Violation from Insp on 930927-1015.Violation Noted:All NRC Violations & Ten Licensee Event Repts Issued in 1992 & 1993 Did Not Receive Required Independent Safety Reviews IR 05000219/19930811993-12-22022 December 1993 Insp Rept 50-219/93-81 on 930927-1015.Violations Noted.Major Areas Inspected:Engineering,Maint,Surveillance & Mgt & Corrective Actions IR 05000219/19930261993-11-18018 November 1993 Insp Rept 50-219/93-26 on 931101-05.No Violations Noted. Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Access Control of Personnel & Packages & Vehicles IR 05000219/19930241993-11-18018 November 1993 Insp Rept 50-219/93-24 on 930921-1101.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support,Including Security & Emergency Preparedness & Safety Assessment/Quality Verification ML20058A3791993-11-12012 November 1993 Insp Rept 50-219/93-23 on 931018-20.Onsite Response to Exercise Scenario Was Good.Major Areas inspected:full- Participation Ingestion Pathway Emergency Preparedness Exercise ML20059M3211993-11-0909 November 1993 EN-93-081A:on 930812,notice of Proposed Imposition of Civil Penalty in Amount of $75,000 Issued to Licensee.Action Based on Five Radiological Controls Violations IR 05000219/19930251993-11-0909 November 1993 Insp Rept 50-219/93-25 on 931018-22.No Violations Noted. Major Areas Inspected:Design Mods & Engineering Support ML20059F6251993-10-28028 October 1993 Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation Event IR 05000219/19930181993-10-28028 October 1993 Insp Rept 50-219/93-18 on 930823-1020.No Violations Noted. Major Areas Inspected:Alara,Rirs,Qa Audits,Air & Swipe Sample Counting Facilities & Radiological Controls Organization Professional Staffing IR 05000219/19930201993-10-19019 October 1993 Insp Rept 50-219/93-20 on 930816-930917.No Violations Noted. Major Areas Inspected:Radioactive Liquid & Gaseous Effluent Control Programs Including Mgt Controls & QA Audits IR 05000219/19930211993-10-15015 October 1993 Insp Rept 50-219/93-21 on 930810-0920.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality Verification ML20059A2201993-10-15015 October 1993 Notice of Violation from Insp on 920719-0825.Violation Noted:Licensee Determined That Records Required to Be Maintained by Commission Regulations or License Conditions Not Complete & Accurate in All Matl Respects IR 05000219/19930171993-09-14014 September 1993 Exam Rept 50-219/93-17OL on 930810-12.Exam Results:All 16 Licensed Operators Passed All Portions of Exam That Was Administered & All Three Crews Performed Satisfactorily in Simulator ML20149D5021993-09-13013 September 1993 Notice of Violation from Insp on 930629-0809.Violation Noted:On 930709,NRC Identified Condition Adverse to Quality That Had Existed Since 920709 IR 05000219/19930111993-09-10010 September 1993 Insp Rept 50-219/93-11 on 930629-0809.No Violations Noted. Major Areas Inspected:Day Shift & Back Shift Hours of Station Activities ML20149D7051993-09-10010 September 1993 Notice of Violation from Insp on 930816-20.Violation Noted: as of 930820,appropriate Measures Were Not Established to Assure Adequate Quality Was Suitably Included in Documents for Procurement of Svcs 1999-09-16
[Table view] |
See also: IR 05000219/1986009
Text
{{#Wiki_filter:__ _ _ _
.
U.S. NUCLEAR REGULATORY COMMISSION
REGICN I
Report No. 50-219/86-09
Docket No. 50-219
License No. DPR-16
Licensee: GPU Nuclear Corporation
i
Oyster Creek Nuclear Generating Station
l P. O. Box 388
l Forked River, NJ 08731
i
Facility Name: Oyster Creek Nuclear Generating Station
Inspection At: GPU-Parsippany, New Jersey and Oyster Creek Plant
Inspection Conducted: May 5-9, 1986
Inspectors: I N N Jc; P6 _
A,7. ~Varela, Lead Reactor Engineer ' da'te
NRC Contract Personnel: M. E. Nitzel, EG&G Idaho, Inc.
V. B. Call, EG&G Idaho, Inc. -
Approved by: 1., '
l
J. gT, 'W ggins[[Cfief, Materials and date
Process Sectun", EB, DRS
Inspection Summary: Inspection on May 5-9, 1986 (Report No. 50-219/86-09).
Areas Inspected: Special announced inspection by a region-based inspector and
two contractor personnel at the GPU, Parsippany, New Jersey engineering office
and at the Oyster Creek Plant. The inspection encompassed review of licensee
responses and subsequent as-built inspection, analysis and modifications of
, masonry walls in response to IE Bulletin 80-11, Masonry Wall Design. This
inspection included a walkdown of existing walls affected by safety related
equipment, a review of design analyses and a review of werk packages on wall
modifications necessary to preclude jeopardy to safety related equipment.
Results: Two violations and 1 deviation were identified.
g7150006860630
0 ADOCK 05000219
,
PDR
.
DETAILS
1. Persons Contacted
!
GPU Nuclear Corporation
i) *R. Armstrong, Engineer E&D
*D. K. Croneberger, Director-Engineering and Design
*T. H. Chang, Senior Engineer
*P. E. Czaya, Licensing Engineer
P. B. Fiedler, Vice President
; *L. Gariblan, Engineering & Design
;
D. Grace, Engineering Projects - Director
i *L. R. Hillman, Senior Project Engineer
3 R. E. Hudoy, QA Auditor
*L. W. Harding, Manager, Q&E
i M. Laggart, Manager, BWR Licensing
*R. S. Markowski, Manager, QA Prog. Dev./ Audit i
! *G. J. Mencinsky, QA Engineer
*A. P. Rochino, Manager, Engineering Mechanics
*R. F. Wilson, Technical Functions Vice President
c
Impell Corporation (contractor or A/E)
S. D. Costello, Supervising Engineer
E. Fishman, Lead Senior Engineer
2. Inspection Purpose and Scope
The purpose of this inspection was to review with cognizant and respon-
sible licensee representatives at the corporate office and the plant, the
completeness of the licensee's responses to NRC/IE Bulletin 80-11, Masonry
Wall Design. The scope of the inspection included a review of engineering
design and quality assurance documentation relating to inspection, test-
ing, analysis and modifications satisfying requirements and licensee
commitments with respect to the Bulletin. A walkdown inspection of the
plant verified repairs and/or modifications relating to the Bulletin.
3. Review Criteria
The Bulletin was used to define actions expected of the utility. In
'
addition, Temporary Instruction (TI) 2515/37 was used to further define
inspection requirements. Applicable sections of the Code of Federal
Regulations (10 CFR 50) were used to provide f,rther guidance,
i
!
l
4
b
--
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ __________._...____ _._ _ _ ____ _ _. _ __.____ _ _ _ _ _____.___ _ _ _ __ _
___._ . . _ _ . _ . __ __ __ _ _ ___ _ _. _. .. ._.
,
!
-
! !
,
*
, 3
'
i
: 4. Review of Licensee Responses
I
'
The inspection team reviewed the licensee's Bulletin responses prior to '
! the inspection. This activity consisted of comparing the pertinent
] information presented in the submittals to the Bulletin requirements and
, licensee commitments to verify, to the extent possible, that all Bulletin
i requirements were met. The responses reviewed included reports addressing
'
the reevaluation methodology, acceptance criteria, wall configurations and
functions, structural adequacy, proposed modification plans, and modifi-
i cation schedules. Table 1 lists those documents reviewed prior to the
inspection.
.
Any items of noncompliance or those requiring further discussion were
-
I noted as items to be addressed while at the corporate office or plant ,
i site. Questions relating to the response were forwarded to the licensee '
i in advance of this inspection as preliminary agenda for discussion.
1
i The inspection team reviewed additional material provided by the licensee
l during the inspection. This material consisted of documentation of
j masonry wall identification used in recent utility walkdowns and proce-
: dures and specifications for repair, wall modifications, and configuration
j control. Reevaluation calculations for sample masonry walls and wall
modification calculations, both of which were performed by the licensee's
j consultants (Impell Corp.) were also reviewed. The review of these docu- i
,
ments consisted of comparing pertinent information to Bulletin require- '
j ments to verify compliance, and a review of the assumptions, boundary
j conditions, physical properties, and other analysis parameters to the t
conditions existing in the plant to assure that appropriate results had
- been obtained in the reanalysis effort. The pertinent c'ocuments described "
; above for IEB 80-11 are listed in Tables 2 and 3.
1
4.1 Findings:
l Two violations, one deviation, and two unresolved items resulted
from the reviews described above. Further details regarding the
,
i
i findings are given below.
~
4.1.1 Control of Vendor Services
J
i The licensee engaged Computech Engineering Services, Inc., to
! develop acceptance criteria applicable to masonry walls at
Oyster Creek and to assist in responding to questions posed by '
lf
j
the NRC staff. These engineering activities formed an integral
part of the licensee's reevaluation program since, in its ulti- i
l
mate use, the criteria document would directly affect safety-
related systems and/or components by defining acceptance limits
! on structural adequacy. Thus, these activities are subject to
,
l the requirements of 10 CFR 50, Appendix 8. Computech prepared
the 180 day Bulletin response to the NRC for GPU for the crt-
l teria for the reevalution of Masonry Walls at Oyster Creek.
1
l. .
-- . _ . _ - - - . - . - - . _ - . _ - . . - _ . - - _ _ - . . _ - -___
j .
'
4
l
; They also prepared for GPU the additional information, requested
i by the NRC June 8,1983, concerning masonry wall design at
i Oyster Creek. However, the licensee produced no evidence
, indicating Quality Assurance oversight of Computech to assure its
! control of quality for the engineering services provided to GPU.
l The licensee provided documentation demonstrating quality assur-
i ance (QA) oversight of all vendors or consultants involved in.
l Bulletin activities except Computech. This lack of QA oversight
j of Computech was determined to be an apparent violation of
1
Criteria VII (Control of Purchased Material and Services) of 10
i CFR 50, Appendix B (50-219/86-09-01).
4.1.2 Control of Records
I
j The licensee stated that approximately 200 masonry walls exist
throughout the plant; 45 walls were addressed by Bulletin
responses. A review process, possibly including the review of
existing drawings and an in plant walkdown was required to
, arrive at this reduced number of walls. The activity of deter- ,
- mining which walls supported safety-related equipment or had the '
potential for impacting safety-related equipment if they failed
, during a seismic event directly affected the safety status of
! the subject equipment. Therefore, this activity would also be
j governed by the requirements of 10 CFR 50, Appendix B. The -
; licensee was asked to provide documentation resulting from the !'
{ masonry wall survey so that verification of the reduced number
. could be performed. The licensee was also asked to provide
! documentation demonstrating that this original activity was
i performed using controlled procedures and/or instructions. The
i licensee was not able to provide this information. Due to the '
lack of documentation the inspectors were not able to verify
'
l
1 that Action Item 1 of IEB 80-11 was performed correctly and was
j controlled.
j Failure to maintain adequate records of the activities described
j above is an apparent violation of 10 CFR 50, Appendix B,
i
Criteria XVII (50-219/86-09-02).
4.1.3 Use of Type M Mortar
i Action Item 3 of Bulletin IEB 80-11 states that " Existing test
data or conservative assumptions may be used to justify the
reevaluation criteria...." Contrary to this, the licensee
i relied upon mortar properties found in the construction spect-
! fication as input to wall reevaluations. Thase strength values
j were for high strength type M mortar. No apparent attempt was
j made to verify, by testing or by documentation other than the
- specification, that type M mortar was actually used throughout
j the construction of all safety-related masonry walls. The
I
4
)
l
!
i-._.---- _ - - . - - , . , . _ - , - - - _ - - . _ . - - - - - . -
.- _ ._._ _ . _ _ . . _ _
_ _ __ _ _ _ _ . _ _ -__ _ _ _
i
'
) 5
!
.
.
inspectors also noted that lower mortar strength properties were
} not assumed to demonstrate structural adequacy by reanalysis.
.
The inspectors concluded that the licensee had deviated from the
l actions it had committed to regarding Bulletin Action Item 3
*
without adequate justification. An assumption was made regard-
) ing mortar strength where records were not found to substantiate
that high strength type M mortar was used in the initial masonry
-
wall construction. This item is a deviation from commitments
made in response to IE Bulletin 80-11. (50-219/86-09-03).
j Unresolved Items:
i
i
During the inspection the licensee stated that a complete
; resurvey of all 200 masonry walls is planned to reestablish
l the baseline data (physical dimensions, boundary conditions,
! attached equipment, etc.) which will be used for any future
'
plant modifications which might affect safety-related masonry
'
walls. This new data will also be used as input to indicate 4
which masonry walls are categorized as safety-related and to '
, provide documentation, and verification of the original survey.
The inspectors requested a schedule for the completion of the i
'
resurvey effort and a copy of the procedure (s) or instructions
i which will be used to control the resurvey effort. This area
{ will remain unresolved pending review of the above and of the
j results of the resurvey effort (50-219/86-09-04).
I
- During the inspection the licensee stated that a plan was being
- developed to control future modifications to safety-related
i masonry walls. This procedure is intended to prevent the
! alteration of any masonry wall that could invalidate the struc-
! turai analysis or, as an alternative, provide proper notifi-
!
cation so an engineering evaluation can be completed. It was
; noted that a final approved version of this procedure was not
available for review. The licensee also stated that periodic
! surveillance of the subject masonry walls would be performed to
j ensure that the physical conditions assumed during the reanal- ,
j ysis effort remain valid. This iterr is unresolved pending
i
implementation of these procedures and review by the NRC !
(219/86-09-05).
^
; 5. Verification Walkdown Inspection i
A physical inspection of certain masonry walls subject to Bulletin action I
!' was conducted. The walls included in this sample were chosen by the
inspection team. The purpose of this walkdown was to verify samples of
,
;
inspections and/or modifications required by the Bulletin. The walls
j shown in Table 4 were examined. The modification status of these walls
is shown in Table 5.
i ,
I
l -
i
!
!
4
_- _ __._ . . _ _ _ _ _ _ _ _ _ _
'
.
,
'
.
'
j 6
-
!
i
5.1 Findings:
! One unresolved item resulted from the plant walkdown. Further ,
a details regarding this item are given below. ~
!
i During the walkdown-inspection it was noted that wall 22 had incurred
! a through-wall crack. It was also noted that wall 23 had incurred
j
'
a similar crack; however, due to the location of equipment it could
not be verified if this crack extended through the wall. Several
other, less extensive cracks were noted to exist in these two walls.
., The licensee was requested to provide the following information
! regarding these walls:
I
! 1. An analysis of the probable cause of these cracks,
!
2. Documentation of the repair efforts for these cracks or a
]
3 demonstration of the structural adequacy of the walls including
j the effects of the cracked block and mortar.
<
l This area is considered unresolved pending NRC review of the licen-
!
see's actions (50-219/86-09-06).
!
; 6. Review of Licensee Administrative Controls and Quality Assurance
1
l In determining the adequacy of administrative controls in assuring quality
i
work, the inspector requested records of GPU quality assurance documen-
, tation relating to activities affected by IE Bulletin 80-11. Although no
] quality assurance documentation of audits of the initial engineering
surveys of all as-built walls and their effect on safety related equipment
was produced, there was evidence of QA/QC involvement in Bulletin-related
,
activities. These audit records were reviewed and discussed with cogni-
'
zant personnel,
i
1 Masonry wall modification packages were also sampled for QA/QC interface
:
' activities. Wall numbers 21, 22 and 23, modified during 1984, were adequa-
tely signed-off by quality control personnel. Documentation of quality
I assurance in plant modifications, as required by procedure number 124,
I
was observed to have adequately satisfied system walkdown documentation
! requirements prior to turnover for operation.
) Documentation reviewed included: '
-
Design / Modification Control audit May 4, 1984 of GPU Tech Function
; Division (follow-up/ corrective actions for NRC construction
assessment inspection April 1984)
!
i
l
1
:
I
4
!
.
'
7 l
1
-
Audit Report No. 0-0C-86-01 of Burns & Roe, Inc. February 12-14,
1986/ B&R Quality Assurance Program
-
Audit Report No. 0-0C-85-05 of Stone & Webster Engineering Corp.
July 22-24,1985/SWEC QAP-Engineering Services
-
Audit Report No. 0-COM-84-04 of Impell Corp. , February 22-24 and
March 14-15, 1984/ Masonry Wall design / Implementation of QAP
-
Audit Report No. 0-COM-03 of SWEC, February 13-14, 1984/QAP relatir.g
to design of plant modifications
-
Various vendor computer software and services, audit of QAP versus
10 CFR Appendix B 1983
Additionally the inspector verified pertinent documents such as the
following:
Notification, dated April 26, 1985, to all AEs, to document in
writing that modifications they design for GPU facilities must be
reviewed to determine what relationship (if any) these modifications
have with respect to the masonry walls at each facility. Guidelines
are attached to this notification for submittal by each AE for evalu-
ation by GPUN's project engineer prior to performing specific modi-
fication.
Findings:
No violations were identified.
7. Summary
Based on the information examined during this inspection and the field
walkdowns which resulted in violations and deviations, IEB 80-11 remains
open pendirg licensee responses, corrective actions and completion of the
reverification survey identified in Paragraph 4.
8. Definition of Unresolved Items
Unresolved items are matters about which more information is required in
order to ascertain whether they are acceotable, violations, or deviations
relative to the bulletin requirements. Unresolved items identified during
this inspection are discussed in paragraphs 4 and 5 above.
9. Exit Meeting
The inspection team conducted an exit meeting attended by licensee repre-
sentatives (denoted in paragraph 1). The NRC inspector summarized the
inspection findings and the licensee acknowledged these comments. At no
time during the inspection was written material other than the preliminary
agenda described in paragraph 4 provided to licensee personnel.
_ - .. - - _ _
- - - . _ _ __ . -
.
4
* *
l Table 1 - DOCUMENTATION REVIEVED PRIOR TO INSPECTION
Document Description
!
----
Gr ; Nuclear (GPUN) letter to NRC dated 7-7-80 containing
; 60 day response to IE8 80-11
;
----
GPUN letter to NRC dated 9-19-80 containing revisions to
.
60 day response
'
----
GPUN letter to NRC dated 11-14-80 containing 180 day
; response
----
GPUN letter to NRC transmitting reevaluation results
1
----
GPUN letter to NRC dated 4-15-83 requesting deferment of IEB
80-11 modifications .
----
NRC letter to GPUN dated 6-8-83 requesting additional informa-
tion regarding IFB 80-11 submittals ,
----
GPUN letter to NRC dated 7-15-83 transmitting proposed schedule
for additional responses to IEB 80-11
----
GPUN letter to NRC dated 8-11-83 containing additional responses
----
GPUN letter to NRC dated 11-2-83 containing additional responses
to IEB 80-11
----
GPUN letter to NRC dated 3-14-84 containing consequence analysis
of masonry wall failures
----
NRC letter to GPUN dated 3-27-84 transmitting formal concurrence
'
with delays for masonry wall nodifications scheduled for outage
10R
----
GPUN letter to NRC dated 5-11-84 trasmitting revisions to
masonry wall failure consequence analysis report
----
GPUN letter to NRC dated 7-26-84 transmitting revision 0 to
Topical Report TR-019 regarding masonry wall reanalyses
;
----
NRC letter to GPUN dated 9-18-84 transmitting conc m rerice with
GPUN request to delay modifications to wall 21 to the cycle 11
refueling outage
----
GPUN letter to NRC dated 3-21-85 containing a status report on
IEB 80-11 activities at Oyster Creek
,
!
!
i
**
-- ---e , -----r - ~ - - - - - --- -' + - - - -- ' - "-- ~ T
.
Table 1 1
----
GPUN letter to NRC dated 6-14-85 transmitting revisions to
topical report TR-019
----
GPUN letter to NRC dated July 26, 1985 requesting delays is
scheduled modifications to masonry walls.
----
GPUN letter to NRC dated 8-14-85 transmitting final eval::ation
of masonry walls (revision 1 to TR-019)
----
NRC summary (dated 10-29-85) by J. Donohew of a meeting held at
Oyster Creek on 9-18-85. Attachment I contains proposed masonry
wall modifications for cycle 11R outage.
----
NRC letter to GPUN dated 12-23-85 transmitting the NRC (NRR)
safety evaluation of the licensee responses for IEB 80-11
d
.
_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ -
l
*
Table 2 - DOCUMENTATION REVIEWED DURING INSPECTION
Document Description
----
GPUN internal memo regarding information to be collected in
block wall surveys (not original survey procedure)
----
GPUN wall survey forms (not original survey data) for walls
25, 26, and 27
0370-108-1641 Impell Corp. design review report regarding masonry wall
reanalysis -checklist for completeness
0370-108-PI-002 Impell project instruction for phase II of the masonry wall
modification program
----
Supplier evaluation report - a detailed QA audit performed for
license agreement for the ANSYS computer program
SP-1302-23-001 GPUN specification for repair of cracks in masonry walls at
Oyster Creek Nuclear Generating Station (OCNGS)
OCIS 402240-003 GPUN installation specification for control room paneling
(part of modification to wall 2)
509-80-1 GPUN modification proposal for the removal of masonry walls
1.8. 509.01-2 GPUN installation specification for boundary supports of
masonry walls
,
_ - _ _ _ - _ _ _ _ _ -
.
Table 3 - Calculation Packages Reviewed
Calc. No. Wall Elev. (ft.) Field Inspection
C-1302-150
5320-005 5,6,7 46'-6" No
37-108-022 8 46'-6" No
37-108-002 31,32,33,45 23'-6" Yes
37-108-021 31,32,33,45* 23'-6" Yes
* Includes redesigned pipe support.
_ ___
.
Table 4 - MASONRY WALLS FIELD VERIFIED
Wall Elevation (ft.) Location
9 46'-6" Computer Room
17,18,53* 35' Battery Room
21 23'-6" 480V Switchgear Room
22 23'-6" 480V Switchgear Room
23 23'-6" 480V Switchgear Room
24 3'-6" Turbine Bldg.
25 35' Cable Spreading Room
26 35' Cable Spreading Room
27 35' Cabie Sprecding Room
43 51' Reactor Bldg.
29,30 -19'-6" Reactor Bidg.
31,32,33,45 23'-6" Reactor Bldg.
* Walls shown in groups were analyzed in one combined model.
l
:
I
l
_ __ _ _. ... . _. _ . . . _ _ _ .
4
1
! .
*
Table 5 - MODIFICATION STATUS OF MASONRY WALLS FIELD VERIFIED
,
Wall Drawing Number Status
l
1 9 Preemptive 2 Complete
i
17,18,532 0370-108-005,6,73 To Be Completed
21 3E-153-38-003 Completed
22 3E-153-38-005 Completed
23 3E-153-38-006 Completed
24 0370-108-001,3 To Be Completed
25 N/A" No Mod. Required
26 N/A No Mod. Required
'
.
27 N/A No Mod. Required
; 43 0370-108-009,10 To Be Completed
- 29,30 0370-108-002 To Be Completed
31,32,33,45 0370-108-008 To Be Completed
.
Note:
1
2
1
-
Preemptive modifications were made to some walls. This consisted
, of removing portions of walls to remove the potential for impact
following failure during a seismic event.
'
2 -
Walls shown in groups were analyzed in one combined model.
!
3 -
All drawing numbers beginning with 0370 indicate Impell Corp. drawings.
4 -
N/A = Not Applicable.
4
l
4
.
.
,
*
.
?l
. i
! .
>
*
.
i
i
!
. , . , - - , - , , - - , . . . - , . - - - . - . _ - . . - . . - - . . - . _ _ , - , . . , - . -
. . , . . . - _ - _ - . , .
-
_ , - - . . , .
}}