ML20198H510

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-346/97-201 on 970505-09,0519-23 & 0609-20.No Violations Noted
ML20198H510
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/04/1997
From: Richards S
NRC (Affiliation Not Assigned)
To: Jeffery Wood
CENTERIOR ENERGY
References
50-346-97-201, NUDOCS 9709180176
Download: ML20198H510 (5)


See also: IR 05000346/1997201

Text

,e

png

/

[

UNITED STATES

!kf.

I.

I

E

NUCLEAR REGULATORY COMMISSION

ill p E

WASHINGTON, D.C. 205%-0001

gg v gj

  • ..,+

September 4, 1997

Mr. John K. Wood

Vice-President - Nuclear, Davis-Besse

Centerior Service Company

c/o Toledo Edison Company

Davis-Besse Nuclear Power Station

5501 North State Route 2

Oak Harbor, Ohio 43449-9760

SUBJECT: DAVIS-BESSE DESIGN INSPECTION

(NRC INSPECTION REPORT N0. 50-346/97-201)

Dear Mr. Wood:

A design inspection at Davis-Besse was performed by the Special Inspection

Branch of the Office of Nuclear Reactor Regulation (NRR) during the period

April 14, 1997 through June 20, 1997, including on-site inspections during

May 5-9, May 19-23, and June 9-20, 1997.

The team selected for inspection the

high pressure injection (HPI) system and the low pressure injection (LPI)

functions of the decay heat removal system (DHRS).

The purpose of the

inspection was to evaluate the capability of the systems to perform safety

functions required by their design bases, the adherence to the design and

licensing bases, and the consistency of the as-built configuration with the

updated safety analysis report (USAR).

The results of this inspection are presented in the enclosed report.

The

inspection team noted that the mechanical, electrical, and instrumentation and

control designs of the HPI and LPI systems were adequate to provide the

required emergency core cooling flow to mitigate design basis accidents, and

concluded that the systems were capable of performing their safety functions.

The team identified some weaknesses in the design process and installation of

,

the systems.

For example: reverse flow testing of check valves DH81 and DH82

on the two LPI pump suction linas from the borated water storage tank (BWST)

and seat leakage testing of stop check valves HP31 and HP32 on the HPI pump

recirculation lines were not done; and although your staff had identified the

deterioration of the BWST level transmitter support hardware in 1994, no

action was taken to remove, examine, and replace the hardware until the

inspection team expressed its concern on the condition of the supports.

The

team referred to NRR staff for evaluation the issue of the acceptability of

the use of normally open safety-related valves as safety class interface

between the HPI system and local pressure gages that were not seismically

[

qualified.

{o

,

[

hk hh%

hy

97o9180176 970904

$

PDR

ADOCK 05000346

y

G

PDR

ll.li. I.ll1.1!Ill.ll!I.llll ll

.

. .

u

-

,

.

Mr. John K. Wood

-2-

Other issues-identified by the team included USAR discrepancies, weaknesses in

periodic testing of battery chargers, lack of testing of inverters, not

including certain electrical components in-the environmental qualification

program, and not revising an installation detail drawing after modifying the

actuators for DHR cooler outlet and bypass valves.

You have initiated measures to address the-team's concerns.

In order for the

NRC to coordinate follow-up inspections, please provide within 60 days of this

letter a schedule for completion of your corrective actions for the open items

listed in Appendix A of the enclosed report.

Any enforcement action resulting from this inspection will be handled by the

NRC Region III office via separate correspondence.

As with all NRC inspections, we expect that you will evaluate the

applicability of the results of this inspection and the specific findings to

other systems and components.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure

will be placed in the NRC Public Document Room.

Should you have any questions

concerning the attached inspection report, please contact the project manager,

Mr. - A.G. Hansen at (301) 415-1390, or the inspection team leader, Mr. S.K.

Malur at (301) 415-2963.

Sincerely,

/k

< y i\\- Q 2 4

)

Stuart A. Richards, Chief

Special Inspection Branch

Division of Inspection and Support Programs

Office of Nuclear Reactor Regulation

Docket No.:

50-346

Enclosure : NRC Inspection Report No.: 50-346/97-201

cc:

see next page

- _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _

Hr. John K. Wood

-2-

Other issues identified by the team included USAR discrepancies, weaknesses in

periodic testing of battery chargers, lack of testing of inverters, not-

including certain electrical components in the environmental qualification

program, and not revising an installation detail drawing after modifying the

actuators for DHR cooler outlet and bypass valves.

You have initiated measures to address the team's concerns.

In order for the

NRC to coordinate follow-up inspections, please provide within 60 days of this

letter a schedule for com)letion of your corrective actions for the open items

listed in Appendix A of tie enclosed report.

Any enforcement action resulting from this inspection will be handled by the

NRC Region 111 office via separate correspondence.

As with all NRC inspections, we expect that you will evaluate the

ap)licability of the results of this inspection and the specific findings to

ot1er systems and components.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure

will be placed in the NRC Public Document Room.

Should you have any questions

concerning the attached inspection report, please contact the project manager,

Mr. A.G. Hansen at (301) 415-1390, or the inspection team leader, Mr. S.K.

Malur at (301) 415-2963.

Sincerely,

ORIGINAL SIGNED BY

Stuart A. Richards, Chief

Special Inspection Branch

Division of Inspection and Support Programs

Office of Nuclear Reactor Regulation

Docket No.:

50-346

Enclosure :

NRC Inspection Report No.: 50-346/97-201

cc:

see next page

DOCUMENT NAME: G:\\DBESSE.RPT

To eceive a copy of this document. Indicate in the boa: *C* = copy without enclosures *E" = Copy with enclosures "N' = No copy

0FFICE

PSIBcDISP

l

PSIBiDISR s k PDIll-3

J

PSIB: DISP lE

l

NAME

SKRa%1r /

DPNorkind M

GHMarcus Q & _

SARichards

._

DATE

/\\\\ hvF M41

C(

' *- O 1

't/3/97~'

SV9/$6

t

4

,.

capability of the make-up system.

Information on the HPI flow and the time at

which the flow is required to be initiated to mitigate the consequences of the

accident was not available.

The licensee has initiated efforts to obtain this

information from B&W.

(Inspection Follow-up Item 50-346/97-201-01)

B&W calculation 32-1171604-00 includui the HPI flow as a penalty in the

calculation cf the core reflood rate because inclusion of the HPl flow

increases the pressure in the reactor vessel, and therefore, increases the

reflood time.

Section 1.2.1 of the HPI system description SD-038 stated that

for a large break LOCA, the minimum HPI flow shown in Table 1.2-1 of SD-038

was required, but did not discuss the conservatism in the B&W evaluation due

to consideration of HPl flow.

The licensee stated that system description 40-

038 would be revised to properly characterize the conservatism in considering

full HPI flow,

b. HPI System In.iection Flow Rate and Pumo Surveillance Testina

The team reviewed the licensee's calculations for HPl system hydraulic

resistance, piping isometric drawings, and pump surveillance test procedures

and acceptance criteria, to evaluate HPl system capability to provide the

limiting flow specified in Table 1 2-1 of system description S0-038.

Calculations 36.017, "HPI Flow vs. Reactor Coolant System Pressure," Revision

03, and C-NSA-52.01-001, "HPI Flow Rate As a function of RCS Pressure,"

Revision 01, determine the HPl injection flow rates.

The pressure drops in

3

l

'

- - -

'

.

-

.

'

l

l

~

.

both the pump suction and discharge lines for standard flows of 100, 200, and

500 gpm, the lump head for these flows from the original test performance

curves, and t1e RCS pressure at the HPl nozzle, were determined in these

calculatibns. The RCS pressure versus HPl flow rate had also been measured by

test, and the test results were provided in calculation C-NSA-52.01-003, "HPI

Pump Acceptance Criteria," Revision 03.

The team compared the data in these

documents and noted that the calculated values were conservative with respect

to the actual measured values.

The data for developing HPI flow rate versus

RCS pressure curve was provided in Calculation C-NSA-52.01-004, "HPI System

Resistance Curves," Revision 0.

Calculation C-NSA-52.01-007, "HPI System

Curve with Instrument Error," provided the best-estimate HPI flow curve with a

7% flow reduction to account for degradation of the pump and a further flow

reduction of 1.5% to account for instrument error.

This best ostimate HPI

flow curve enveloped the minimum flow required by the B&W analysis _ to mitigate

an accident.

Calculation C-NSA-52.01-003, "HPI Acceptance Criteria," developed acceptance

criteria for the surveillance test for the HPI pumps.

Because of system

limitations for periodic surveillance testing at full-HPI flow, the test is-

conducted at about 400-gpm.

The HPl pump performance test performed during

plant startup showed that the pump delivered a total flow of 820 gpm or 410

gpm per injection leg at an RCS pressure of 400 psig.

The results from tests

DB-SP-03218. "HPI Pump 1 Quarterly Pump and Valve Test," dated March 17, 1997

and DB-SP-03219 "HP1 Pump 2 Quarterly Test," dated April 25, 1997, show that

the pump will deliver about 380 gpm at a pump discharge pressure of 1500 psig.

The original pump test curves showed that the pumps delivered a flow of 380

gpm at a pump pressure of about 3500 ft. or about 1515 psig.

The latest pump

tests showed minimal degradation of the aump performance since its

installation.

The teaN concluded that t1e TS 4.5.2 requirement of HPI flow of

375 gpm in each injection leg at 400 psig at the core flood nozzle was

satisfied taking into consideration the system hydraulic resistance.

The team concluded that the HPI system had been designed to provide the flow

required for accident mitigation, assuming a 7% degradation in pump flow

capacity, and that the surveillance tests verify the system capability,

c.

HPI Pumo Net Positive Suction Hejd

The team reviewed calculatioin 36.010. "LPI, HPI, CS NPSHA from BWST,"

Revision 0, and 36.031, "HPI Pump NPSHA at a Possible 1020 gpm Flow,"

Revision 0, along with piping isometric drawings M-233A, " Emergency Core

Cooling Systems - Borated Water Supply," Revision 15, and M-233B, " Emergency

Core Cooling Systems - Pump Suction Piping," Revision 19, to verify the

available net positive suction head (NPSH ) for the HPI pumps when taking

suctionfromtheBWSTatpumprunoutcondltion.

The team's review, however,

indicated that on the basis of the pump performance characteristics and the

pressure drop in the discharge line, pump runout will not occur.

Consideration of the-pump runout in the evaluation was conservative.

With conservative assumptions regarding low water level and temperature in the

BWST, the NPSH at pump runout conditions of 900 gpm and 1020 gpm were

cal ~ulatedas%9.5feetandabout44feetrespectively.

The required net

c

4

--

-

_=

=

=

_

_ _ - , . - - - , - - - - - - - - - -

-

-__

<

.

.

I

..

positive suction head (NPSH,) at a pump flowrate of 1020 gpm was about 35

feet.

Therefore, there was adequate margin in the NPSH

As stated above,

becauseofhighhydraulicresistanceinthedischargepi. ping, the HPl pumps

are not expected to reach runout conditions.

The team reviewed calculation C-NSA-52.01-ll, "HPl NPSH on CTMT Emergency Sump

Recirculation," Revision 0, to determine the NPSH for the HPl pump operating

inthepiggy-backmodetakingsuctionfromtheLPlpumpdischarge.

The

calculated total hydraulic losses were based on actual test measurements and

calculated values.

The calculation estimated the NPSH, at about 200 feet

which was much greater than the NPSH,,

The team concluded that sufficient NPSH margin was available for the HPI pumps

when taking suction from either the BWST or the containment emergency sump in

the piggy-back mode,

d.

System Boundaries and Safety Class Interfaces

The team verified that appropriate system boundaries and safety c;4ss

interfaces were considered and incorporated into the design for the interfaces

between the HP! system and RCS, make-up and purification system, and DHR

system.

Locally mounted pressure gages PI 1519 and 1520 were installed in the high

pressure injection (HPI) system with one normally open manual isolation valve

in each sensing line from the system piping.

Each isolation valve was an ASME

Code, Section 111, Class 2 valve and was the boundary between the Class 2

system piping and the non safety-related sensing line and pressure gage.

The

pressure gage was not seismically qualified and its pressure boundary could

fail in a seismic event.

However, the sensing line was designed to seismic

class I requirements, and the line and the pressure gage were provided with

seismic class I supports.

Because the pressure gage was not seismically

qualified, the team questioned the acceptability of a normally open valve as

boundary between ASME Class 2 piping and the prassure gage although the gage

was seismically supported.

This issue has been referred to NRR staff for

further evaluation.

(Inspection follow-up Item 50-346/97-201-02)

e.

Pipina Desian Pressure and Temperature

The team reviewed the HPI system piping and instrumentation diagram (P&lD)

H-033. Revision 25, system description SD-038, Revision 02, piping class

specification M-200,' Revision 05, and piping isometric drawings to verify the

piping design pressure and temperature classification for the suction,

discharge, minimum recirculation, and test lines.

The team determined that

the pressure and temperature classifications were acceptable except for the

following:

Piping isometric drawing H-233D, "HP Injection System - Auxiliary

Building," Revision 22, provided a table of operating pressure and

temperatures for various lines that were not consistent with the Piping

Design Table, in specification M-200.

The licensee stated that the

operating temperature and pressure shown on drawing M-2330 were not used

5

.

-,

.

.

in the piping design, and initiated DCN M-233D-12 to delete this

information from the drawing.

Specification M-200 listed the maximum working pressure for lines CCB-19

and CCB-12 as 2500 psig and 1650 psig respectively.

These two lines are

connected and have no isolation devices between them, and therefo,*e, the

pressure in both lines should be identical.

However, the team noted

that piping stress calculation No.54 for line CCB-12 used the correct

value of 2500 psig as the service pressure in the line.

The licensee

issued a saecification change notice SCN) M-200-05-15 to correct the

error in t,1e maximum operating pressur(e for line CCB-12 in specification

M-200.

Specification M-200 listed the maximum design pressure for piping CCB-2

between the HPl pump discharge check valves and the motor-operated

containment isol'. tion valves as 2600 psig, whereas the pressure for

piping downstieam of the containment isolation valves was listed as 2500

psig which is the RCS pressure.

Specification M-200 did not

explanation for the difference in the design pressure values. provide any

The

piping stress analysis used a pressure of 2600 psig which is the ASME

Code allowable pressure for the pipe.

The licensee issued SCN M-200-05-

16 to clarify in specification M-200 the basis-for the higher pressure

rating in the portion of line CCB-2 upstream of the containment

isolation valve.

The maximum service pressure and temperature rating for line CC6-2 from

HPl pump 1-1 discharge to the pump discharge check valve HP22, and from

HP22 to motor-operated isolation valve HP 2C And 2D was listed in Spec.

M-200 as 1650 psig at 260'F.

The same values are also applicable for

the HPl pump 2 discharge line.

The maximum service pressure in these

lines should be 1850 psig which was the maximum expected pressure when

the HPI system was operating in the piggy-back mode.

The stress

analysis for this portion of CCB-2 line was performed at a pressure of

1650 psig and a temperature of 260'F.

The stress analysis was,

therefore, performed using a lower pressure than the expected value.

This discrepancy was identified by the licensee during the inspection

>

and was documented in potential condition adverse quality report (PCAQR)

P -0825 for reevaluation of this portion of the CCB-2 line to address

the increased service pressure in the pum) discharge line.

lne team

determined that the pressure rating for t.1e valves, fittings, and piping

for this portion of the pipe enveloped the pressure of 1850 psig, and

the small pressure increase from 1650 to 1850 psig should not

significantly impact the pipe hangers and supports.

f.

Environmental Oualification of Eouloment in ECCS Rooms 105. 113. and 115

The team reviewed USAR Table 3.6-11, procedure NG-EN-00306, " Environmental

Qualification Program," Revision 02, calculation C-NSA-000.02-005, " Main

Feedwater 1.ine Breaks and Cracks in the Auxiliary Building," Revision 01, and

selected electrical schematic drawings for electrical equipment in ECCS rooms

105,113, and 115 to verify the environmental qualification (EQ) of the

electrical components.

6

.

.

.

The environment in the ECCS rooms becomes harsh due to high temperature in the

event of a niain feedwater line break (MfWLB), auxiliary steam line break or a

break in the steam generator blowdown line in the auxiliary building.

Except

for the MFWLB accident for which the HPl system is required to operate to

bring the reat. tor to safe shutdown conditions, the ECCS systems are not

required to operate.

In the event of a LOCA, the radiation levels in the ECCS

rooms increase.

The team's review of electrical components in the ECCS rooms that are powered

from the Class lE bus indicated that some safety-related electrical

components, such as sump pump motors, sump level switches LS-4621, LS-4623,

LS-4625, associated hand switches, and electrical boxes were not listed in the

EQ Master List.

These components are required to operate under harsh

environ:nental conditions.

Failure of these components could jeopardize Class

lE circuit integrity and operation of associated safety-related equipment.

The licensee provided a list justifying exemption of some of these components

from the EQ program.

This list was not an EQ Exempt List that was described

in procedure NG-EN-00306, ' Environmental Qualification Program," Revision 2.

The licensee agreed that sump pumps and associated level instruments and local

control stations should have been included in the EQ program in accordance

with procedure NG-EN-00306.

The licensee issued PCAQR 97-0796 to address the environmental qualification

of these components in the ECCS rooms and additional required documentation,

and concluded that there was no operability concern because identical local

control stations and level instrumentation components have been qualified for

harsh environments and the materials commonly used for sump pump motor

windings had been demonstrated to be qualified for calculated radiation levels

in the ECCS rcoms.

(Inspection Follow-up item 50-346/97-201-03)

g.

Calculations

The licensee provided a total of 19 mechanical system calculations for the HPl

system, which accounted for all the mechanical calculations performed by the

original architect-engineer and the licensee. Of these calculations, the team

identified only eight that appeared to support the current design basis.

If

the calculations that support the design basis are not explicitly identified

as such and the other calculations are not archived, superseded, or identified

as historical information, the team was concerned that data from the

calculations that are not part of the design basis could inadvertently be used

for future design changes or as input to operational decisions.

The licensee stated that as a part of the design basis validation program, the

existing calculations will be reviewed for adequacy and it will be ensured

that they reflect the current plant design,

b.

System Modifications

The team selected modification 96-006, " Installation of High Point Vent in HPI

Pump 2A Discharge Line" for review.

The design of the system was such that a

section of the HP1 pump discharge line could be drained following maintenance

or testing of the system and the small trapped air volume in that segment

7

_____

_

__

.

i

t

could only be flushed out after a pump start.

The modification installed a

vent to ensure proper refilling of the discharge piping. The ter.m concluded

that the design of the modification, safety analysis, t .d closeout of the

modification was adequately performed.

El.2.2.3

Conclusions

The team concluded that the HPI system design was adequate to provide the

required flows assumed in the B&W analysis for SBLOCA and MSLB/MFWLB

considering a M reduction in the pump flow capacity.

The system provided

sufficient NPSH for the HPI pumps when taking suction from either the BWST or

the containment emergency sump.

Except for the locally mounted pressure gages

at the suction of the HPl pumps, the system incorporated appropriate

boundaries and class breaks with interfacing systems.

This issue has been

referred to the NRR staff for evaluation.

The team noted several

discrepancies in piping specification M-200 regarding piping design pressure

and temperature classification.

The team noted that exclusion of some

electrical equipment in the ECCS rooms was a weakness in the EQ program.

The

team was concerned that lack of proper identification of design bases

calculations could result in the use of information from calculations that

have been superseded and do not support the system design.

El.2.3

Electrical Design Review

El.2.3.1

Scope of Review

for the electrical design review, the team focused on the essential power

supplies to the HPI and DHR systems.

The areas examined, such as emergency

diesel generators, 4,160-volt AC buses. 480-volt unit substations and motor

control centers (MCCs) -125-volt DC system, and the 120-volt vital AC system,

were common to both systems.

Therefore, a separate discussion of the

inspection of electrical aspects of the DHR system is not included in the

report.

The team reviewed USAR Section 8.0, TS 3/4.8 " Electrical Power," system

descriptions, Design Criteria Manual (DCM) Section Ill.D " Electrical,"

electrical calculations and drawings, specifications and procedures for

electrical requirements and mnstruction, one modification work order (MWO)

package, PCAQRs, and other miscellaneous electrical documents.

The team assessed portions of the following that are applicable to the HPI and

DHR systems: essential power systems including switchgears, transformers,

motors, raceway, panels, cables, terminations; regulatory and standard

compliance; channel separation; voltage drops and available voltages; controls

and interlocks; alarms and indications; protective device setpoints; field

installations; modifications; labeling and identification; fire stops; drawing

and record changes; and seismic and environmental considerations.

8

i

_ _ _

__

- - - - . _ _ - - -

- _ _ _ _ _ _ _ _ _ _

______

.

.

.

El.2.3.2

Findings

The team reviewed the emergency diesel generator (EDG) system description,

capacity calculations, elementary diagrams, protective relay setpoints, and

electrical equiament.

The calculations showed that EDG loading was properly

estimated and t1e EDGs had adequate capacity margin.

This was ver fled by the

records from the SFAS integrated time response test performed in % y 1996.

The electrical loads including the ECCS loads were sequenced onto the EDG

within the required time, and the dr.op in output voltage and frequency and

their recovery were acceptable.

The team reviewed the system description, drawings, protective relay setpoints

and coordination calculations, and other aspects-of the 4160-volt AC system

with emphasis on undervoltage protection schemes.

The calculations indicated

that the undervoltage setpoints were adequate for proper operation of the

electrical loads and for shedding loads in the event of a loss of off-site

power.

The team reviewed the system descriptions for i,he 480-volt unit substations

and motor control centers, art,tection settings and coordination, cable

ampacities and derating met 1ods, calculations for voltage drops, and valve

operations under reduced voltage. The team reviewed selected HPl and LPI

elementary diagrams and SFAS actions and equipment interlocks.

The team had

no concerns regarding the 480-volt system.

Except for the testing of battery chargers and invertars discussed in the

following paragraphs, the team had no other concerns regarding the 125-volt DC

and the 120-volt vital AC systems,

a.

Battery Charaers

3

The electrical distribution system functional inspection (EDSFI) finding

346/92007-06 stated that the battery charger surveillance requirements were

different from the charger design commitment described in USAR Section

8.3.2.1.3.

The USAR stated that each " charger is capable of supplying all

steady-state DC loads required under any conditions of operation while

recharging the battery to a fully charged condition over a period of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

from a discharged condition of 105 volts per battery." TS 4.8.2.3.2.c.4

requires a verification at least once per 18 months that the " battery charger

will supply at least 475 amperes at a minimum of 130 volts for at least 8

hours."

The licensee revised procedure DB-ME-03002, " Station Battery Service and

Performance Discharge Test" to include Enclosure 7: " Battery Charger Current

Readings During Recharge Following Test Discharge." The revised procedure did

not require that the load box that was used to discharge the battery be used

again to simulate a worst-case steady-state load on the battery and battery

charger while the battery was being recharged.

The licensee provided

Enclosure 7 test result readings for the four batteries for the team's review.

The team noted that the initial reading was close to 600 amperes which was the

current-limited full rating of the charger.

The charging current dropped to

less than 475 amperes within 45 to 60 minutes and dtcreased to near zero

9

._

_.

.,_.-_mm..

~

-

.

_ _ _ _ _ -

- -_

,

l

within 1-1/2 to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and remained at near zero for the rest of the 12-hour

charging cycle,

it was apparent that without using the load box to simulate a

steady-state load, the procedure did not verify the USAR commitment.

The team

also noted that the two backup chargers DBCIPN and OBC 2PN were not normally

used for recharging and they were not tested. (Inspection Follow-up Item 50-

346/97-201-04)

b.

Testina of Inverters and Associated Components

The team reviewed the inspection and testing of the power supplies for the 120

VAC essential instrumentation distribution panels Yl, YlA, Y2, Y2A, Y3, and

Y4.

Four channels of essential instrumentation are fed by these panels and

supply vital 120 VAC to systems, such as reactor protection, safety features

actuation, radiation monitoring, auxiliary shutdown, and others as shown on

drawing E-7.

The channel 1 esseniial instrumentation distribution panels Y1 and YlA are

normally supplied by inverter YVI, which converts 125 VOC to 120 VAC.

This

inverter is rated at 10 kVA a.d operates at about 60% of full load, supplying

loads that do not significantly t.hange during postulated abnormal events.

The

inverter YVI is normally energized with 125 VDC from regulated rectifier YRF1

which, in turn, is supplied from the 480-volt essential MCC E12A.

If the 480-

volt feed is de-energized during a transient, such as a loss of off-site

power, the inverter is transferred without interruption to a 125-VDC supply

from the Channel I battery.

When the 480-volt feed is restored the inverter

will transfer back to the regulated rectifier supply.

Should the inverter

itself fail, a static transfer switch within the inverter will switch the 120-

VAC panels' from the inverter to a 480-to-120-VAC constant voltage transformer

(CVT) XYl.

The CVT powers the buses until the inverter is restored.

An

additional function of the CVT is to provide fault-clearing power during

problems in the 120-VAC circuits.

Channels 2, 3, and 4 have a sin.ilar

configuration.

The regulated rectifiers, inverters, and constant voltage transformers are not

mentioned in the technical specifications.

Therefore, there was no commitment

to perform surveillance tests on these Class IE equipment, and no periodic

surveillance tests are performed to demonstrate the load carrying capabilities

of the regulated rectifier, inverter, static transfer switch, or CVT or to

demonstrate the operability of special functions.

The existing preventive

maintenance procedures for cleaning and visual inspection, the continuous

monitoring of CVT availability during normal operation, and the continuous

supply of normal loads by the regulated rectifier and inverter, do not

demonstrate the specified capabilities or the available margins under abnormal

conditions of the 120 volt AC system.

(Inspection Follow-up Item 50-346/97-

201-05)

c.

Electrical Installation Procedures

The team reviewed maintenance procedure DB-ME-09512. " Installation Procedure

for Raceways Carrying Electrical Cables," to evaluate implementation of

raceway criteria.

All safety-related cables at Davis-Besse are routed in

Class IE conduits.

Procedure DB-ME-09512 provided few specific requirements

10

___

_ _i

_

9

.

.

.

and guidance for the installation of conduits.

The team had numerous comments

on this procedure relating to safety-related aspects, such as material

requirements, seals and fittings, codes and standards, conduit supports,

installation practices, and acceptance criteria.

The team also reviewed

electrical specification 7749-E-14. " Electrical Construction and

Installation," several sheets of drawings E-302A and E-1037P dealing with

electrical standards and details and grounding details, and maintenance

procedure DB-MM-01001 " Installation Procedure for Essential Electrical Hangers

and Supports." The team did not find specific installation requirements or

guidance in these documents.

The licensee issued PCR 97-1596 to revise

procedure DB-ME-09512 to resolve the team's comments.

The team reviewed maintenance procedure DB-ME-09500, " Installation and

Termination of Electrical Cables," because the licensee stated that the

instructions for wiring within panels were covered by this procedure.

This

procedure did not include installation requirements, such as physical

separation and color coding stated in USAR subsection 8.3.1.2.25, and

separation of low level signal wiring from power or control wiring stated in

panel specifications.

It appeared that no other criteria document or

procedure addressed such requirements.

El.2.3.3 Conclusions

The team concluded that the essential power supplies for the HPI and LPI

systems were capable of performing their safety functions required by their

design bases, adhere to the licensing bases, and are consistent with the

commitments in the USAR.

Calculations for protective relay setpoints,

coordination, voltage drops

EDG loading, battery loading, and others were

conservative in approach, used appropriate methodology, produced reasonable

results, and were consistent with the_ design bases.

Design bases documents

-

cover the performance requirements, design requirements, developmental and

code references, component descriptions, technical _ specifications, and limits.

Some weaknesses in raceway installation and panel wiring procedures were

identi fied.-

The functional and performance requirements appeared to be consistent with the

USAR, technical specifications, system descriptions, and calculations and

analyses.

The battery charger capability testing did not fully comply with

the intent of the commitment in the USAR as identified in an EDSFI finding.

The team also questioned the lack of testing of some features of inverters and

associated components.

E1.2.4

Instrumentation and Control Design Review

El.2.4.1 Scope of Review

The scope of the instrumentation and control design assessment consisted of a

review of HPI system documents, such as sections 6 and 7 of the USAR,

technical specifications, system description, P&lDs, loop diagrams,

operational schematics / control logic diagrams, four setpoint calculations and

loop uncertainty analysis, six instrument data packages, maintenance,

surveillance, and operating procedures, and one modification package.

11

_.

.

.

El.2.4.2 Findings

'

The system design documents reviewed by the team adequately supported the

design bases, except for the items discussed in the following paragraphs,

Reactnr Coolant low Pressure (SFAS level 2) Actuation Setooint

a.

The reactor coolant pressure instrument loop provides low reactor coolant

pressure input for the SFAS Actuation Level 2 permissive for HPl operation.

The team noted inconsistencies in the' reactor coolant low pressure setpoint on

the various documents that were reviewed.

Technical Specification Table 3.3-4

specifies a trip setpoint of 1620.75 psig and an allowable value of 1615.25

psig.

This was based on the low pressure trip value of 1585 psia considered

in the B&W SBLOCA analysis (calculation 32-1159744-0, dated June 16,1986)

with an addition of 2.03% for instrument error.

A subsequent reanalysis (B&W

calculation 32-11178648-00, Revision 1) Justified a value of 1515 psia, but

this value was not considered in the technical specifications.

Instrument

data package 64B-IShtCO2A3, Revision 4, showed a calibrated setpoint of 1661

psig which was considered by the team to be conservative.

The team also

reviewed calculation C-lCE-48.01-002, Revision 2, which established a loop

uncertainty of 12 psig and a setpoint of 1660 psig.

Although conservative,

this value did not match the results of the B&W analysis and the instrument

data package.

The licensee, however, stated that this calculation, now in its

6th revision, was intended to support a future amendment to the technical

specifications that will establish new allowable values, a new trip setpoint,

and instrument loop uncertainty.

The licensee acknowledged the above

inconsistencies and indicated that this issue will be addressed as part of a

'

future technical specification update and design basis validation program.

b.

HP1 Pumo Flow Test Calculation

Calculation C-NSA-52.01-003, "HP1 Pump Acceptance Criteria," Revision 3,

established the acceptance criteria for the HPl pump quarterly flow test.

The

team reviewed this calculation and noted that the assumed 1.5% accuracy for

the flow indicator for obtaining test data was not consistent with the 2%

calibration tolerance specified in the instrument data package.

The licensee

initiated PCAQR 97-0577 to revise the instrument calibration tolerance to 1.5%

to be consistent with the calculation.

This error did not invalidate previous

test result because the calibration record for the flow indicator that was

used in the test was verified to have an as-left instrument tolerance of

0.75%, which enveloped the required instrument accuracy.

El.2.4.3 Conclusions

The team concluded that the instrumentation and control design for the HPl

system was adequate.

All instrumentation setroints that were reviewed had

adequate margin and the technical specification limits were met and the errors

that were noted by the team were minor.

The team noted an inconsistency in

the RCS low pressure setpoint value in the technical specification, loop

uncertainty calculation, and instrument data sheet.

However, the actual

setpoint was conservative and acceptable.

12

..

..

.

.

..

_

.. . . .

.

--

--

,

,

.

El.2.5 System Interfaces

El.2.5.1

ECCS Room Coolers

The team reviewed 50-0280, " System Description for Auxiliary Building

Radioactive Area HVAC System," Revision 2,50-018 " System Description for

Service Water System," Revision 2, and calculations for the ECCS room cooler

capacity to determine whether ECCS room coolers had the capability to maintain

the maximum design room temperature.

The HPI system description SD-038 stated that the normal temperature in the

ECCS rooms was 95'F and the maximum allowable temperature was 125'F.

This

maximum temperature limitation was imposed by the ECCS pump motor bearing and

lubricant.

Calculation C-NSA-032.02-003, " Maximum Allowable Service Water Temperature

with inoperable ECCS Room Coolers," Revision 3, supported the post-LOCA design

room temperature of 125'F for the ECCS rooms.

The team also reviawed

calculation 25.13. "ECCS Pump Room Heat Load / Fan-Coil Unit capacity vs.

Service Water Temperature," Revision 1, and calculation 25.14. "ECCS Pump Room

Heat Load / Fan-Coil Unit Capacity vs. Service Water Temperature for Rm Max.

Design Temp. - 122*F (50'C)," Revision 0, and estimated equivalent heat loads

for an ECCS room temperature of 125'F.

The heat loads used in calculation C-

NSA-032.02-003 were consistent with the team's estimates.

The team concluded

that with the technical specification limit of 85'F for the maximum allowable

service water bay temperature, the combined capacity of both room coolers in

each ECCS room was adequate to limit the maximum room temperature in the ECCS

room to 125'F under post-LOCA conditions.

SD-028C stated that the normally closed (NC) motor-operated valve SW 5425 at

the outlet of the room coolers opened automatically on increasing room

temperature. Modification 95-006 implemented a design change that left the

valve permanently open and power to the motor o)erator was removed.

The

system P&lD showed that the power to the valve ,1ad been removed.

The team

noted that, in accordance with )lant modification procedure NG-EN-00301,

Section 6.4, Action item 8, a c1ange notice should have been issued to update

the system description as part of the closecut of modification 95-006.

The

team noted that Table 2.4-1 in 90-028C showed the rating of cooler E42-1 as

100 Btuh, whereas the correct rating was 180,000 Btuh.

The licensee issued

SDCN-0280-02-005 to correct these errors.

El.2.6 HPI System Walkdown

El.2.6.1

Scope

The team inspected the installed mechanical, electrical, and instrumentation

and control equipment for the HPI system to evaluate their consistency with

drawings, design specifications, and regulatory requirements.

During the

walkdown the team interviewed plant system engineers, and operation-and

maintenance personnel.

The team walkdown covered the HPI pump rooms, control

room, auxiliary shutdown panel, BWST area, cable spreading room, switchgear

rooms, battery rooms, and electrical distribution panels,

13

_ _ _ _ _

,

.

.

For the electrical walkdown, the team chose three HPI and three LPI cables.

These included two instrument cables, two control cables, one 480-volt power

supply cable to a valve motor operator, and one 4,160-volt pump motor power

supply cable.

Some of the aspects examined included cable sizin

radii, control board and enclosure wiring, separation, raceway, g and bend

seismic

supports, identifications, fire stops and wraps, drawings and records,

environmental considerations, material control, and installation procedures.

El.2.6.2 Findings

a.

Motor Operator Installation for Valve DH63

The team observed that the motor operator installation for isolation valve DH

63 was nonstandard.

This valve was originally designed for manual operation

during the piggy-back mode of HPl operation. A aodification was performed to

add a motor operator to permit remote operation of the valve.

Because of

space limitations, the motor was mounted away from the valve with a connecting

shaft to the valve stem.

The licensee did not perform an analysis to verify

acceptability of the loading on the piping due to the nonstandard mounting of

the motor.

During the inspection, the licensee performed a preliminary piping

and pipe support analysis that showed that the stresses were much below the

allowable value.

The licensee will update the appropriate piping stress

analysis to incorporate the preliminary analysis,

b.

Droundwater leakane

in pump room 115, the team noted that a tygon tube was attached to a vertical

structural support, and was discharging water to a floor drain.

The licensee

explained that groundwater was getting into conduit runs and drains through

holes in the conduits into an area above the non-essential electrical

distribution switchboard MCC F-21.

The tygon tubing drain observed by the

team was a portion of the leak collection system installed to preclude water

intrusion into switchgear and other important plant equipment.

The licensee

explained that the station was maintaining a leak collection log for tracking

leakages and the drainage arrangement was temporary.

Groundwater leakage into

buildings was a larger concern that the licensee was evaluating for potential

corrective actions,

c.

Electrical Construction

The team's comments on electrical installation procedures are discussed in

El.2.3.2.c of this report.

,

The licensee resolved the team's questions during the walkdown on the use of

threadless conduit couplings and conduit unions, the criteria for spacing of

conduit supports, and the radiation resistance and fire loading of PVC

covering on flexible conduits.

d.

HP1 Pump tube Oil Pressure Switch

During the walkdown of ECCS pump room 115, the team noted that the HPl pump

P58-2 lube oil pressure switch PDS-4961 had a material deficiency tag (MTD

14

.

. .

.

.

- -_

1

~

,

,

.

C469, dated May 2, 1995) attached to it, with a caution statement not to bump

the pressure switch.

The function of the pressure switch was to initiate

operation of the backup DC lube oil pump in case of failure of the safety-

related AC lube oil pump.

Plant personnel were cautioned not to bump-the

switch to preclude its failure or inadvertent actuation.

The team noted that

PCAQR 95-0237 was issued on March 20, 1995, identifying a calibration

stability problem with the pressure switch, but the PCAQR stated that I&C

maintenance was unable to determine the exact cause.

The licensee concluded

that there were no onerability concerns because the pressure switch failure

would cause the DC lube oil pump to start, and would not affect operation of

the AC lube oil pump.

The licensee stated that the pressure switch would be

replaced in July 1997, with a suitable narrow-range type that was inherently

more accurate and stable.

Recommended changes to the post-calibration

installation techniques would be incorporated in the PM procedure.

The team was concerned that the corrective actions to replace the pressure

switch had not been timely.

The pressure switch for the redundant train (PDS-

4957) had experienced a similar failure in 1994, and was replaced with the

original model w th the same range and setpoint.

The team discussed the

inappropriatenen of the use of a pressure switch with a range of 0-70 psid

for an applimion that required a setpoint of 8 psid with a deadband of 4.2

psid.

The licensee indicated that the feasibility of making the pressure

switches in both trains identical would be evaluated.

e.

Taaaina of Instruments and Associated Valves

The team noted that several instruments, isolation valves, and manifold valves

in the HPl and LPI systems did not have identification tags.

The team also

noted that some devices had more than one tag with different identification

numbers and some tags were attached at the incorrect locations.

Tagging

procedure DB-DP-00023,-Revision 02, applies only to new tr.gs, and existing-

tags not conforming to the requirements of the procedure are considered

acceptable until replacement is necessary,

Based on discussions with plant

personnel, it appeared that the existing instrument and valve tagging

condition had not hindered plant operations or maintenance.

Without a

consistent tagging system, the plant has to rely on operators' familiarity

with the plant's physical configuration.

The licensee acknowledged that this

problem was previously identified, and a program was being initiated to

address the tagging issue on a generic basis.

This program will cover

definition of requirements, standardization, procedure update, and

implementation schedule.

El.2.7

Updated Safety Analysis Report

The licensee had initiated an USAR program in August 1996 to review and update

the USAR,

Concerns resolution request (CRR) forms were prepared for the

identified questions or open concerns in the USAR related to the HPI and DHR

systems.

The team reviewed the CRR forms that had been resolved and approved

by the station review group, and concluded that the USAR issues had been

appropriately resolved.

15

_ _ .

-

,

,

.

.

The team identified the following additional discrepancies in the USAR:

USAR Section 6.3.1.4 stated that " permissive signal is provided to allow

the manual opening of the sump valves" whereas Section 6.3.5 stated that

"No actions are required by the operator in large pipe LOCA..."

These

two statements are contradictory.

The SFAS set point of 1600 psig for low RCS pressure and the high

pressure injection setpoint in USAR Table 15.4.2-1 did not correspond to

either the analyzed design bases set point of 1570 psig or the technical

specification set point of 21620.75 psig.

The licensee had submitted

license amendment request (LAR) 96-C014 dated April 18, 1997, to the NRC

to revise the technical specifications.

The USAR will be revised after

the approval of the LAR.

USAR Table 7.5-1 indicated that HPl and LPI flow readouts in the main

control room are types A(analog), D(digital), and F(computer).

The

actual instalied readouts are types A and F only.

The licensee issued

UCN 97-066 to revise the USAR.

USAR Section 15.4.4.2.3.2 provided a sequence of events and elapsed time

to justify an assumption of a 35-second delay in injection of water to

the RCS.

The team considered the assumption to be conservative,

however, the timing of sequence of events listed in the USAR did not

correspond to the SFAS integrated time response test, the time delay

analysis provided in B&W analysis 32-1171604, or the licensee's

calculation C-EE-004.01-049. The USAR also considered the time delay

for starting the HPl pumps, although the opening of the motor-operated

injection valves was a more critical contributor to the time delay.

The above discrepancies had not been corrected and the USAR updated to assure

that the information included in the USAR contained the latest material as

required by 10 CFR 50.71(e).

(Unresolved item 50-346/97-201-06)

El.3 Decay Heat Removal System

El.3.1

System Description and Safety functions

The decay heat removal (DHR) system performs both normal operation and

accident mitigation functions.

In its normal operation mode, the system

removes decay heat from the reactor core and sensible heat from the RCS.

The

system also providet auxiliary spray to the pressurizer, maintains the reactor

coolant temperature during refueling, and provides a means for filling and

draining the refueling canal,

in its accident mitigation or LPI mode, the

system injects borated water into the reactor vessel and provides long-term

reactor core cooling after a LOCA.

The decay heat removal system includes the BWST, the containment emergency

sump, the BWST recirculation pump and heat exchanger, the refueling canal

drain pump, the decay heat dropline valve pit, the decay heat removal pumps,

the decay heat removal coolers, and the piping and valves associated with

these components.

Two redundant DHR pumps are arranged in parallel and are

16

_ - - - _

_ -

,

.

.

designed for continuous operation during the period required (nr removal of

decay heat.

Each DHR train has one decay heat removal cooler to remove deuy

o

heat from the RCS during a cooldown.

Operating both coolers provides the

design capability to reduce the reactor coolant temperature from 280'F to

140*F in approximately 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />.

The BWST contains an available borated water volume between 482,778 and

550,000 gallons with a minimum of 2600 ppm boron in solution and is used for

emergency core cooling and filling the refueling canal during refueling.

The

BWST supplies borated water for emergency cooling to the containment spray

system, the LPI function of the DHR system, and the HPl system.

it also

supplies makeup water to the spent fuel pool cooling system and can serve as a

source for the makeup pumps.

The LPI functions of the DHR system are initiated automatically by an SFAS

signal', and the LPI pumps take suction from the BWST and inject borated water

into the reactor vessel.

The DHR pumps are referred to in this report as LPI

pumps where the emergency core cooling functions of the pumps are discussed.

After a low-low level of 95 inches in the BWST is reached, the LH pump

suction is manually transferred to the containment emergency sump to provide

long-term cooling of the reactor.

In this mode the DHR system removes heat

from the containment by cooling the containment sump water in the DHR coolers

before pumping the water back to the reactor vessel.

During the piggy-back operation of the HPl system, the LPI pumps provide

containment water to the suction of the HPI pumps after the cross-connect

,

i

valves between the two systems are manually opened by the operator.

The spent fuel pool cooling system is not designed to meet seismic Class I

'

criteria. When manually interconnected with the spent fuel pool, the DHR

,

system provides safety-grade cooling and a larger capacity for heat removal

from the spent fuel pool.

El.3.2

Mechanical _ Design Review

El.3.2.1.

Scope of Review

for the mechanical design review of the LPI functions of the DHR system, the

team evaluated the capability or the_ system to provide emergency core cooling

during the injection and recirculation phases of post-accident ECCS operation.

The team reviewed system description SD-042, Revision 2 for th' SHR system,

USAR sections 6.3 and 15.4, drawings, calculations, and operating and

surveillance testing procedures. The team also performed system walkdowns and

discussed _the system design and-installation with licensee-engineering and

operating personnel.

El.3.2.2 Findings

a.

LPI In.iection Flow Rate and LPI Pumo Surveillance Testina

The design basis for LPI injection flow rates as a function of the pressure at

the reactor vessel core flood nozzle is given in Table 1.2-1 of the decay heat

17

.

-

.

.

1

l

.

removal system description SD-042, Revision 2.

The team verified that the

system was designed so that each of the two trains provide the minimum LPI

tiow rate and the flow rate was consistent with data in B&W document 51-

1158934-01, " Functional Requirements for the DH/LPI System," dated August 27,

1985.

Technical specification 4.5.2 has a requirement for verifying the LPI pump

flow rate in each injection leg of 2650 gpm at 100 psig pressure at the core

flood nozzle on the reactor vessel.

T11s requirement was presented in a B&W

1etter dated January 11, 1978.

Interp.11ation of the data in Table 1.2-1 of

SD-042, showed that the LPI flow rate at 100 psig was about 2486 gpm.

Survel11ance test procedures DB-SP-03130 and DB-SP-03137 specified an

accepttnce criteria for the LPI pump tothi developed head between 337.3 feet

and 369.8 feet for flow rates between 2940 and 3060 gpm.

The surveillance

requirement was, therefore, higher than the design basis injection flow rate

at 100 psig in the reactor vessel and was accsptable.

Calculation C-NSA-049.02-010. " Review of Test Data from DB-SP-10065 for Valve

DH14A," Revision 0, showed that the LPI train with the lowest flow could

deliver considerably more than 2650 gpm at 100 psig in the reactor vessel.

This calculation also showed that the surveillance requirement could still be

met with a 10% degradation in the performance characteristics of the pump with

the appropriate reduction in system resistance.

Therefore, the team concluded

that the quarterly inservice testing of the LPI pumps in accordance with ASME

Code Section XI with an acceptance criteria accounting for a 10% degradation

in the pump performance characteristics was acceptable.

The licensee issued system description change notice (SDCN) SDCN-042-02-005 to

clarify the discussion of the LPI system flow requirements,

b.

Net Positive Suction Head (NPSH) Calculation

USAR Section 6.3.2.14. " Net Positive Suction Head Requirement," included a

table listing the NPSH

either the BWST or from, and NPSH, for the LPI pumps drawing suction from

the emergency sump in the containment.

The NPSH for

the LPI pumps when taking suction from the BWST was more than four times,the

NPSH,, and the team reviewed the NPSH calculation 36.010, "LPl.HPl.CS NPSHA

from B'..'ST," Revision 0, to verify the adequacy of the NPSH for the LPI pumps.

Calculation C-NSA-049.01-004, " Vortex Formation with ECCS Pump Suction from

the BWST," Revision 0, assumed conservatively high flowrate from the BWST and

mini"xm BWST level accounting for instrument errors, and concluded that at the

minie m switchover level in the BWST, potential air ingestion into LPI pump

suction of 2% by volume was the maximum to be expected.

In accordance with

Appendix A of Regulatory Guide 1.82, a 2% air ingestion into the suction flow

will cause the pump NPSH to increase by a factor of two.

Because there was

adequate margin in the NESH , the team concluded that there were no NPSH

concerns during the operati,on of the LPI pumps while taking suction from the

BWST.

The licensee had performed calculations C-NSA-049.02-004, " Maximum Pump Flow

for DH Pump 1-1 Under Accident Conditions," Revision 1, C-NSA-049.02 -005,

" Maximum Pump Flow for DH Pump 1-2 Under Accident Conditions." Revision 1, and

18

_ . . . . _ . . . _ . . . . .

_ . _ _

_

.

.

C-NSA-049.02-009, " Mechanical Str j Position for Valve DH14B," Revision 0, to

determine the position of the r .hanical stops for the replacement valves

DHl4A and DH148 located at th

utlet of DHR coolers to limit the system flow

rate and prevent pump run F

in addition, flow testing was done with pump

suction from the BWST to :c. trm the required system flows with the new valve

stops.

This testing revealec + hat the actual system flow resistance was about

25% less than the calculated s lue. A new system flow calculation C-NSA-

049.02-010. " Review of Test Data from DB-SP-10065 for Valve DH14A." Revision

0, was performed using the reduced system flow resistance.

However, no new

NPSH, calculation was performed with suction from the containment emergency

sump and utilizing the revised system flow resistance.

The licensee issued

PCAQR 97-0478 to document and resolve this issue.

Calculation C-NSA-49.02-19, " Modification to Bechtel Calculation 36.35,"

Revision 0, was issued on May 17, 1997, to correct discrepancies in

calculation 36.35, such as use of original pump curves instead of pump curves

consistent with the modified pump impellers, and incorrect pressure drop

through the flow measuring orifice.

The new calculation concluded that

adequate-NPSH margin (2.59 feet for train 1 and 5.01 feet for train 2)

existed for e,ach LPI pump at flow rates limited by the new stop positions in

valves DH14A and DH148.

However, the team noted that the calculation used the

pump inlet flange elevation which was about 2 feet higher than the pump

centerline elevation and a water temperature of 120"F instead of the higher

estimated post-accident temperature of the containment emergen:y sump water.

As a result, the team determined that the calculated NPSH, was underestimated

by about 3.5 feet and was conservative.

The licensee issued RFA 97-0203 to

revise calculation C-NSA-49.02-19 to account for the pump centerline

elevation.

In addition, the team noted that the calculation did not address the scenario

in which one LPI pump supplied both injection lines with the crosstie valves

open.

In this configuration, emergency procedure DB-0P-02000 required the

operator to limit the total injection flow in both lines to 4000 gpm, which

results in a total pump flow of 4100 gpm including pump recirculation flow of

100 gpm.

The actual- flow would be higher if the flow instrument errors were

considered, and NPSH under this condition would be higher.

In view of the

conservatisminthehPSHcalculationdescribedaboveandtheexistingmargins,

the team did not have additional concerns regarding LPI pump NPSH.

c.

ECCS leakaae Testina

During the inspection, the licensee initiated PCAQR 97-0529, and identified

that reverse flow testing of check valves DH81 and DH82 on the two LPI pump

suction lines from the BWST, and the leakage rate through stop check valves

HP31 and HP32 on the HPI pump recirculation lines, were not being tested.

Leakage of post-accident containment sump water through check valves DH81 and

DH82 in conjunction with either leakage through the BWST isolation valves DH7A

or DH7B or failure of the isolation valves to close could result in increased

off-site dose.

19

-

. . . -

- _ _ _ _ - - - - - - - - - -

.

.

e

No analyses had been performed to demonstrate that a conservatively high

l

containment pressure under post-accident conditions was not sufficient to

overcome the static head of water in the BWST, thus eliminating the need to

reverse flow test these valves.

The inservice testing (IST) program

documentation for DHRS valves stated that the reverse flow testing of check

valves DH81 and DH82 was not required because isolation valves DH7A and DH7B

would be closed.

The potential leakage through isolation valves DH7A and DH7B

or their failure to close was not considered.

The licensee successfully

tested valve DH82 during the inspection and scheduled the testing of DH81 at a

later date.

The IST program documentation for DHRS valves was revised to

include reverse flow testing of these check valves.

Leakage of containment sump water through stop check valves HP31 and HP32 on

the HPI pump recirculation lines during the piggy-back mode of operation could

result in increased off-site dose because the recirculation lines discharge

into the BWST.

The licensee was evaluating the testing requirements for these

two valves as part of the resolution of PCAQR 97-0529.

The design basis for

valves DH81, DH82, rip 31, and HP32 was apparently not correctly translated into

procedures and instructions as required by 10 CFR 50, Appendix B, Criterion

111. " Design Control," and Toledo Edison Nuclear Quality Assurance Manual,

Section 3.4.6.1. (Unresolved item 50-346/97-201-07)

TS 6.8.4 required that a program be established to reduce leakage from the

ECCS and that integrated leakage irnm each system be tested at refueling

-

intervals or less.

USAR Table 15.4.6.5-2 shows the offsite dose due to an

assumed total post-accident ECCS leakate of 5890 ml/hr.

Procedures DB-SP-

03136, DB-SP-03137, DB-SP-0 3218, and DB-SP-03219 verify external leakage from

components, such as pumps and valves.

Results of the recent tests showed

negligible external leakage from the ICCS.

Because the leakage tests were

performed at a temperature lower than the expected temperatures under post-

accident conditions, the team considered that this test could not verify that

the post-accident leakage from the system would be less than the assumed

value.

The licensee is currently evaluating the issue of testing of internal

and external leakage from the ECCS. (Inspection Follow-up Item 50-346/97-201-

08)

d.

Eressure Interlock Setooint for Valves DHil and DHil

Valves DHil and DH12 are nonna11y closed motor operated valves in the DH drop

line that isolate the RCS from the DHR system.

These valves form the pressure

boundary between the two systems (the design pressure rating of the RCS is

2500 psig whereas the design pressure rating of the DHR system is 300 psig).

The pressure interlock in the valve control is designed to prevent these

valves from being opened when the RCS pressure is above the design pressure of

the DHR system.

The interlock would also cause automatic closure of DHil and

DH12 as the RCS pressure increases past the pressure setpoint.

In addition,

other procedural controls are in place to ensure that these valves are not

moved to their incorrect positions during various plant operating modes,

in TS 4.5.2.d and TS Table 3.3-4, the setpoint for the DHil and DH12 pressure

interlock is stated as <438 psig.

The licensee stated that the setpoint was

in error and that PCAQR 97-0238 was initiated on February 25, 1997, to

20

- _--

,

,

e

disposition this issue.

Nuclear engineering memo 08E-97-00164 and calculation

C-ICE-048.01-002, "SFAS Reactor Coolant Pressure Actuation Setpoints,"

determined a new TS allowable value of <328 psig.

Licensing Amendment Request (LAR) 96-0014 will implement the change to the

appropriate technical specification by replacing the original setpoint of <438

psig with the new allowable value of <328 psig.

The team verified that the

actual setpoints for these valves were 306 psig for DHil and 265 psig for

i

DH12, which were both below the new allowable value,

in response to the

team's question, the licensee stated that the actual valve setpoints had

remained approximately the same since 1977, and therefore, the team concluded

that there was no conchrn of potential overpressurization of the DHR system.

e.

Procedure RA- Q 02820

-

Procedure RA-EP-02820, " Earthquake," governs the operation of the station

after a seismic event.

The team noted that this procedure did not mention the

availability of or refer to other procedures for back-up cooling of the spent

-

fuel pool.

The DHR system is designed as a seismic class I system and

provides a back-up cooling capability.

The licensee initiated arocedure

change request (PCR) 97-1404 to revise the procedure to direct t1e operators

to consider aligning a DHR system train to cool spent fuel in the event the

normal spent fuel pool cooling system was not operable.

.

In addition, the licensee initiated PCR 97-1435 to revise procedure DB-0P-

06012 to provide additional guidance to operators regarding the degradation of

the LPI function of the DHR system if the DHR system is aligned to perform

spent fuel cooling functions during Modes 1, 2, and 3.

El.3.2.12 Conclusions

The team concluded that the LPI system was designed and tested to provide the

required flow rates assumed in the accident analyses.

The system provided

sufficient NPSH for the LPI pumps when taking suction from either the BWST or

the containment emergency sump.

The team noted that reverse flow testing of

check valves DH81 and DH82 and leak testing of valves HP31 and HP32 had not

been performed and this was a weakness in the IST program.

At the time of the

inspection, the licensee had taken actions to test these valves.

.

El.3.3 Electrical Design Review

,

The discussion in Sec'

. El.2.3 of this report covers the electrical design

review of the LPI functions of the DHR system.

j

El.3.4

Instrumentation and Control Design Review

El.3.4.1

Scope of Review

,

The scope of the instrumentation and control design assessment consisted of a

review of LPI system design and associated documents.

The team reviewed the

instrumentation and control portions of sections 6 and 7 of the USAR,

technical specifications, system descriptions, P&lDs, loop diagrams,

i

21

. - - . . -

- - . -

. - - - - - -.

- - - -.

- .

.- - -

e

.

.

.

operational schematics / control logic diagrams, four setpoint calculations and

loop uncertainty analyses, and ten instrument data packages.

The team also

reviewed the associated surveillance, normal and emergency operating

procedures, and two modification packages.

El.3.4.2 Findings

The system design documents reviewed by the team adequately supported the

design bases, except for the items discussed in the following paragraphs.

'

a.

BWST low-low level Setooint

The BWST level instrument loop provides input for the low-low BWST level (SFAS

Actuation Level 5) permissive to initiate recirculation flow from the

cont:inment vessel emergency sump.

The team noted several inconsistencies in

the BWST Low-Low level trip setpoint value shown in the various documents.

TS

Table 3.3-4 specified a Low-Low level trip setpoint of 89.5 to 100.5 inches,

"with an allowable value of 88.3 to 101.7 inches," measured from the bnttom of

the tank.

USAR Section 6.3.1.4 states that at a BWST level of approximately 8

feet a permissive signal is provided to allow manual opening of sump valves.

Operational Schematic 0S-004, Sheet 1, Revision 20, and Instrument Data

Package 49A-ISL1525A, Revision 1, specify a calibrated setpoint of 95" from

the suction pipe or 99" from the tank bottom.

Calculation C-ICE-48.01-004,

"SFAS BWST Low Level Setpoint," Revision 2, established a loop accuracy value

of 19.5" with a setpoint of 96".

Document RFA 94-0509 dated January 17, 1995, calculated the minimum acceptable

BWST level at which the SFAS Level 5 permissive bistable will trip.

The team

noted the following discrepancies in this document: the zero level reference

point was at the bottom of the tank, while the setpoint calculation assumed a

reference point 4" higher resulting in a conservative calculated setpoint; the

licensee could not retrieve the basis for the instrument string inaccuracy and

bistable tolerance values of 113.5" and 15.5" respectively that were used to

establish consistency with the technical specification trip setpoint; and

although the document performed the function of a calculation or analysis, it

did not comply with the format and review requirements for calculations.

To verify consistency of the setpoint calculation methodology, the team

reviewed a subsequent revision to the instrument string data package and

Revision 3 of the setpoint calculation.

On the basis of review of these

documents, the team determined that the BWST low-low level setpoint of 95" had

adequate margin to account for instrument error, valve stroke time, and

operator delay, and to ensure that enough water from the BWST had been

transferred to the containment to provide the minimum NPSH for the LPI and

containmentspraypumpstakingsuctionfromthecontainmentemergencysump.

The team verified that the permissives and interlocks for the valves on the

suction lines from the BWST and containment emergency sump were acceptable.

-

22

l

_ _J

-

- _ _ _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _

.

.

To resolve the team's concerns, the licensee indicated that document RFA 94-

0509 would be reissued as a calculation and would include verification of

assumptions and references.

Also an evaluation of interfacing documents and

other affected calculations would be performed.

(Inspection follow-up Item

50-346/97-201-09)

The team also reviewed the BWST level instrument setpoints for high and low

level alarms and determined that they were acceptable,

b.

Hiah Containment Pressure (SFAS level 3) Actuation Setooint

The containment pressure instrument loop provides input for the high

containment pressure (SFAS Actuation Level 3) permissive to initiate LPI

operation.

In the reviewed documents the team noted inconsistencies in the

containment high pressure trip setpoint.

TS Table 3.3-4 provided a trip

setpoint of 18.4 psia, with an allowable value of 18.52 psia.

Justification

for these technical specification values were provided in Rechtel letter BT-

11388, "TM1 Action Plan, Section ll.E.4.2, Containment isolation

Dependability," dated January 7, 1981.

Instrument Data Package 59A-ISP2000,

Revision 5, showed the actual calibrated setpoint as 17.4 psia, providing a

margin of 1 psia.

The licensee was unable to provide supporting documentation

for this margin but considered 1 psia as a reasonable value to account for

instrument loop inaccuracies, in addition to a built-in margin of 1 psia in

the technical specifications as evaluated in the Bechtel letter.

The team was

concerned that no loop uncertainty calculation had been performed to document

that the combined instrument inaccuracies would not exceed the setpoint

margin.

The team noted that calculation C-ICE-48.01-001, "SFAS Containment Pressure

Actuation," Revision 0, established a loop accuracy value of 1.5 psia (which

exceeded the 1 psia margin discussed above) and a setpoint of 18.625 psia.

However, the licensee stated that this calculation was intended to support a

future licensing amendment that would implement a new setpoint and revised

technical specification values.

The licensee acknowledged the weakness in the I&C calculation and indicated

that this issue will be addressed as part of a planned DBD reconstitution

program at DB.

(Inspection Follow-up Item 50-346/97-201-10),

c.

RG 1.97 Indication for BWST level

Emergency procedure DB-0P-02000 required monitoring of BWST level indicators

L1-1525A, B C, and D, on the main control room vertical panel C5716 to permit

manual switchover of the DH pump suction from the BWST to the containment

emergency sump.

The team noted that these indicators were powered from a

Class lE bus and seismically mounted, but they were classified as non safety-

related.

The indicators are classified as a Type A Category 1 variable

requiring full Class lE qualification in accordance with RG 1.97 because they

provide primary information to permit control room operators to take manual

control actions,

23

i

l

,

.

,

!

The team also noted that there were four other BWST level indicators (LI-

'

1525Al, Bl

Cl, and 01) located on the safety-related SFAS cabinets in the

main control room. The team considered it appropriate for the operators to

monitor the safety-related BWST level instruments during post-accident

conditions.

The licensee initiated PCR 97-1397 to revise the procedure DB-OP-

02000 to include monitoring of the safety-related level indicators in the SFAS

cabinets when performing the DH pump suction switchover operations.

d.

Document Discrepancies

The team identified the following document discrepancies:

Drawing 05-004, Sheet 1, did not show the correct ccior coding and

instrument symbols for FYlDH2A and FYlDH28.

The licensee issued DCN 05-

004-0054 to correct the drawing.

Drawing E-30-23 showed an incorrect model number for containment

pressure transmitter PT-2001.

DCN E-30-23-35 was issued to delete this

information from the drawing, because it was provided in M-7201.

Section 1.2.1.3 of system description 50-042 stated that a safety-

related alarm shall be provided if the dropline valves were open and

power was not removed.

The annunciator system is non-safety related.

The licensee issued SDCN 42-02-004 to correct the system description.

Section 1.1.1.1 of system description 50-042, stated that valves DHil

and DHl2 were associated with pressure switch PSH-RC284.

However, only

valve DHil was interlocked-with the pressure switch. The licensee

issued SDCN 42-02-005 to correct this discrepancy.

El.3.4.3 Conclusions

The team concluded that the instrumentation and control design for the LPI

'

system was adequate.

All=setpoints that were revie,4ed had adequate margins

and technical specification limits were met.

However, some inconsistencies

were observed between the technical specifications, loop uncertainty

calculations, and data sheets.

The basis for the current setpoint for BWST

low-low level documented in RFA 94-0509 was not appropriately verified and

approved, although the current setpoint was acceptable.

The licensee

initiated corrective actions for the discrepancies identified by the team.

El.3.5 LPI System Walkdown

El.3.5.1

Scope

The team inspected the installed mechanical, electrical, and instrumentation

and control equipment for the LPI system to evaluate their consistency with

drawings, de.ign specifications, and regulatory requirements.

During the

walkdown the team interviewed plant system engineers, and operations and

,

maintenance personnel.

The team walkdown covered the HPI pump rooms, DH

24

..

..

. . . . .

-

____ _ _ _ - _ _

,

.

cooler room, control room, auxiliary shutdown panel, BWST area, cable

spreading room, switchgear rooms, battery rooms, and electrical distribution

panels.

The results of the electrical walkdown are discussen ti' Section El.2.6 of this

report.

El.3.5.2 Findings

a.

Control of Temoorary Shieldina

During the plant walkdown, the team noted a temporary shielding installation

on a pipe near valve DH134 in decay heat cooler room 113.

The line was

currently not in use and had apparently become a potential crud tra).

This

shielding had temporary shielding request tag No. 94-0003, dated Fearuary 3,

1994, attached to it.

This installation had been in place for overthree

years.

Request for assistance (RFA) 94-0042 that was issued to evaluate this

temporary shielding installation was approved for temporary use on,y by Design

a

Engineering / Civil on January 26, 1994.

The team inquired whether this

installation had been periodically reviewed and approved by engineering and

whether the attachment of shielding to the piping was analyzed from the poisit

of view of seismic II/I concerns.

The licensee stated that the shielding had

not been reviewed since its initial installation and that its attachment to

the piping had not been seismically analyzed.

The licensee reviewed the original calculation done in response to RFA 94-

0042,-and concluded that the RFA was still applicable for use on a temporary

basis, and the attachment of the shielding to the piping considering the

seismic loads was acceptable.

Installation of temporary shielding was controlled by procedure DB-HP-01802,

" Control- of Temporary- Shielding." This procedure was currently in the process

of.being enhanced and will address the concerns raised by the inspection team

regarding periodic review of installed tempora /y shielding packages to ensure

installation requirements continue to be met, and-inclusion of complete

descriptions of the installation and fastening methods in the shielding

request documents to ensure seismic considerations were fully understood by

all parties involved in the preparation, review, and approval of these

requests,

b.

BWST Level Transmitters

The team reviewed the instrument installation details and instrument data

packages and performed verification walkdowns of the BWST level transmitters.

The transmitters were properly spanned, compensated, and were calibrated to

account for boron concentration and differences in elevations.

During the walkdown of the four BWST level transmitters in tho valve pit and

the shed next to the BWST, the inspection team noted that the transmitter

mounting brackets, nuts, and bolts for transmitters LT-1525B and LT-1525C.were

'

severely rusted while the mounting hardware for LT-1525A and LT-15250 showed

A

25

.,

_ _ _ _ _ _ . _ . _ _ _ _ _ . _ _ - - . _ . _ . _

_

_

._ .

_ _ _ _ _ _ _ _ _ _ _ .

.

.

.

.

signs of corrosion to some degree.

The team was concerned that structural

integrity of two of four transmitter supports could be degraded.

The licensee initiated work requests WR-97-1286 and WR-97-1247 to repair

transmitters LT-1525B and LT-15250.

The team noted that PCAQR 94-0840 dated

September 28, 1994, had previously identified corrosion of LT-15258 and

LT1525-0 based on a seismic qualification walkdown of the components in the

BWST pit, and the licensee had concluded that the condition of the transmitter

supports was acceptable.

The licensee conducted another inspection on January

13, 1997, and concluded that the supports were still capable of meeting

operability requirements.

However, the team noted that the PCAQR and

corresponding evaluations only' addressed the transmitters in the BWST pit and

did not include the two transmitters in the shed, one of which (LT-1525C) had

been severely corroded.

The licensee also issued work requests WR-97-1546 and WR-97-1550 to repair

supports for transmitters LT-1525A and LT-1525D.

The team expressed its

concern about the delays in initiation of corrective actions and the licensee

stated that the focus was on rectifying water leakage in the pit which took a

I

long time to accomplish ~and had delay 3d implementation of any corrective

action and closecut of the PCAQR.

During the implementation of the work.

request, the licensee will examine the removed hardware to verify that the

corrosion was not severe enough to have had the potential for failure of the

supports,

in this instance, the licensee's measures to assure that conditions

adverse to quality are promptly corrected as required in 10 CFR 50, Appendix

B, Criterion XVI, " Corrective Action," were not adequate. (Unresolved item 50-

346/97-201-11).

The team noted that some piping insulation and protective metal covers had

been removed from the HPI pump recirculation and test return lines to the BWST

and were left on the catwalk near DH-7A & B valve operators.

The licensee

stated that this material was wet at the time of inspection of the BWST valve

pit.

The piping insulation should have been reinstalled in accordance with

the niaintenance work package in response to corrective actions for PCAQR 94-

0840, but did not get included in tne process.

The licensee reinstalled the

required piping in w1ation after the team questioned the acceptability of the

uninsulated sections of the piping.

The licensee stated that during the

period without insulation, the piping heat tracing and use of space heaters in

the area prevented potential freezing problems,

c.

Modification of Valves DH13A/B and DH14A/B

Modification 87-1168 was implemented to replace the single-acting type

actuators on DH cooler discharge valves DH13A/B and bypass valves DH14A/B with

double-acting type actuators.

P&lD M-033A and drawing 05-004 Sh.1 show the

double-acting type actuators that agree with the as-installed condition, but

instrument installation detail drawing Q-084 and the vendor drawing series M-

329 still showed the old configuration with single-acting valve actuators.

The team noted that these drawings were not listM as affected documents in

the modification package,

it was noted that marked-up PalD, isometric

drawings and bills of materials were used to install the modification,

26

,

"

-

.

-4

However, no installation detail drawing or a revision to drawing Q-084 was

included in the modification package.

The installation was consistent with

the information provided in the modification package and was acceptable.

Section 6.6.2.f of plant m,dification procedure NG-EN-00301, states that the

Planner shall verify that applicable documents, such as change notices,

reflect the as-built configuration and had been correctly updated as part of

the post implementation / closeout process.

The licensee acknowledged that in

the modification closecut process drawing Q-084 was omitted in error, and

initiated DCN Q-084-1 to update the drawing.

The licensee stated that vendor drawings for the actuators and associated

control tubing are classified as " fabrication" status, and are not required to

be updated.

X1

Exit Meeting

After completing the on-site inspection, the team conducted an exit meeting

with the licensee on June 20, 1997.

During the meeting the team presented the

results of the inspection. A list of persons who attended the exit meeting is

contained in Appendix B.

.

27

- _ _ ___ _ _ _ _ _ _ _ ___ _ _ _ __ _

.

,

APPENDIX A

OPEN ITEMS

This renort categorizes the inspection findings as unresolved items and

j

inspection follow-up items in accordance with the NRC Inspection Manual,

i

Manual Chapter 0610. An unresolved item (URI) is a matter about which more

information is required to determine whether the isste in question is an

acceptable item, a deviation, a nonconformance, or a violation.

The NRC

Region 111 office will issue any enforcement action resulting from their

review of the identified unresolved items. An inspection follow-up item (IFI)

is a matter that requires further inspection because of a potential problem,

because specific licensee or NRC action is pending, or because additional

information is needed that was not available at the time of the inspection.

Item Number

Findino

I_i_tig

lyAt

i

50-346/97-201-01

Ill

HPl flow Requirements for SG Tube Rupture Accident

(Section El.2.2.2.a.)

50-346/97-201-02

IFI

Safety Class Interface at Pressure Gage Isolation

Valves (Section El.2.2.2.d.)

50-346/97 201-03

IFI

Environmental Qualification of Equipnent in ECCS Rooms

(Section El.2.2.2.f.)

50-346/97-201-04 IFI

Battery Charger Surveillance Testing (Section

El.2.3.2.a.)

50-346/97-201-05 IFI

Testing of Inverter and Associated Components (Section

El.2.3.2.b.)

50-346/97-201-06 URI

USAR Discrepancies (El.2.7)

50-346/97-201-07 URI

Reverse Flow Testing of LPI Pump Check Valves and HPI

Pump Recirculation Stop-Check Valves (Section

El.3.2.2.c.)

50-346/97-201-08 IFI

ECC5 teakage Testing (El.3.2.2.c.)

50-346/97-201-09 IFl

BWST Low-Low Level Setpoint Calculations (El.3.4.2.a.)

50-346/97-201-10 IFl

High Containment Pressure Actuation Setpoint

(El.3.4.2.b.)

50-346/97-201-11 URI

Corrective Action for BWST Level Transmitter Support

Corrosion-(E1.3.5.2.b.)

A-1

    1. ,-.

.

,

APPENDIX B

l

EXIT-MEETING ATTENDEES

[LAE

ORGANIZATION

Toledo Edison

J. Stetz

Senior V.P., Nuclear

J. Wood

V. P., Davis-Besse

J. Lash

Plant Manager

T. Myers

Director, Nuc.-Support Services

R. Donnellon

Director, Engineering and Services

F. Swanger

Manager, D-B Engineering

J. Freels

Manager, Reg. Affairs

J. Rogers

Manager, Plant Engineering

H. Stevens

Manager, Nuclear Safety & Inspections

D. Lockwood

Supervisor, Compliance

C. Kraemer

Engineer, Compliance

A. Stallard

Sr. Ops. Advisor

J. Hartigan

Sr. Staff Engineer, DBE

K. Prasad

Sr. Staff Engineer, DBE

J. Marley

Sr. Engineer, Plant Engineering

A. Wise

Sr. Engineer, Plant Engineering

R. Hovland

Sr. Engineer, Plant Engineering

G. LeBlanc

Sr. Engineer, DBE

P. Jacobsen

Sr. Engineer, DBE

lE

M. Ring

Chief, Engineering Branch, Region III

D. Norkin

Chief, Special Inspection Section, NRR

M. Miller-

-Reactor Engineer, Region Ill

S. Stasek -

Sr. Resident Inspector

S. Malur

Team Leader, NRR

A. Bizzara

Contractor, S&L

M. Sanwarwalla

Contractor, S&L

R. Jason

-Contractor, S&L

K. Steele

Contractor, S&L

L. Rogers

Contractor, S&L

B-1

i

I

._..

.

,

4

APPENDIX C

LIST OI ACRONYMS

AB

Auxiliary Building

AC

Alternating Current

A0V

Air-0perated Valve

ASME

American Society of Mechanical Engineers

AT0G

Abnormal Transient Operating Guidelines

AUX S/D

Auxiliary Shutdown

AUX

Auxiliary

AUX S/D PNL.

Auxiliary Shutdown Panel

B&W

Babcock & Wilcox

BS

Building Spray

BTU

British Thermal Unit

BWST

Borated Water Storage Tank

CF

Core Flood

CFR

Code of Federal Regulations

CFT

Core Flood Tank

CTHT

Containment

CV

Control Valve

CVT

Constant Voltzge Transformer

DB

Davis-Besse

DBA

Design Base Accident

DBD

Design Basis Documentation

DBMMS

Davis-Besse Maintenance Management System

DBNPS

Davis-Besse Nuclear Power Station

DC

Direct Current

DCN

Drawing Change Notice

DCR

Document Change Request

DH

Decay Heat

DHR

Decay Heat Removal

DHRS

Decay Heat Removal System

DP

Differential Pressure

EcCS

Emergency Core Cooling System

EDG

Emergency Diesel Generator

EDSFI

Electrical Distribution System Functional Inspection

E0P

Emergency Operating Procedure

EQ

Environmental Qualification

ESF

Engineered Safety Features

ESFAS

Engineered Safety Features Actuation System

F

Fahrenheit

FCN

Field Change Notice

FCR

Facility Change Request

FCV

Flow Control Valve

ft., FT

Feet or Foot

FW

Feed Water

gal., GAL

Gallons

gpm., GPM

Gallons Per Minute

C-1

)

-

_ _ _ _ .

______

.

i

HELB

High Energy Line Break

HP

High Pressure

HPI

High Pressure Injection

HS

Hand Switch

HVAC

Heating, Ventilating, and Air Conditioning

HZ, Hz

Hertz

I&C

Instruments and Control

IFI

Inspection Follow-up Item

ILRT

Integrated Leak Rate Test

IN

Information Notice

ISI

In Service Inspection

IST

In Service Testing

kVA

Kilovolt-Ampere

LAR

License Amendment Request

LCO

Limiting Condition for Operation

LER

Licensee Event Report

LOCA

Loss-of-Coolant Accident

LOOP

Loss-of-Offsite Power

LF

Low Pressure

LPI

Low Pressure Injection

M/HELB

Moderate /High Energy Line Break

M&TE

Measuring and Test Equipment

MCB

Main Control Board

MCC

Motor Control Center

MF

Main Feedwater

MOV

Motor Operated Valve

MS

Main Steam

MU&P

Make-Up and Purification

MWO

Maintenance Work Order

NC

Normally Closed

NG

Nuclear Group Procedure

NNI

Non-Nuclear Instrumentation

NNS

Non-Nuclear Safety

NO-

Normally Open

NPSH

Net Positive Suction Head

NRC

Nuclear Regulatory Commission

NSR

Nuclear Safety Related

NSSS

Nuclear Steam Supply System

OTSG

Once Through Steam Generator

P&ID

Piping & Instrumentation Diagram

PAM

Post Accident Monitoring

PB.

Piggy-Back

PCAQ

Potential Condition Adverse to Quality

PCAQR

Potential Condition Adverse to Quality Report

PI

Pressure Indicator

PIC

Pressure Indicator Controller

PM

Preventive Maintenance

PMT

Post Maintenance Testing

PMW0.

Preventive Maintenance Work Order

PORV

Power Operated Relief Valve

PRA

Probabilistic Risk Assessment

psi, PSI

Pounds per Square inch

C-2

_

.

.

..

.

.

_-. -

I

o t ,, e

.

i

.t

psia, PSIA

Pounds per Square Inch Absolute

psid,_PSID

Pounds per Square Inch Differential

psig, PSIG

Pounds per Square Inch Gauge

PT

Pressure Transmitter

PVC

Polyvinyl Chloride

QA

Quality Assurance

RB

Reactor-Building

RC

Reactor Coolant

RCP

Reactor Coolant Pump

RCS

Reactor Coolant System

REV

Revision

RFA

Request for Assistance

RG

Regulatory Guide

.

RPS

Reactor Protection System

RV

Reactor Vessel

S&L

Sargent & Lundy

S\\D

Shutdown

SA

Safety Actuation

SCFM

Standard Cubic Feet per Hour

SCN

Specification Change Notice

SDCN

System Description Change Notice

SE

Safety Evaluation

SEC

Seconds

SER

Safety Evaluation Report

SF

Spent Fuel

SFAS

Safety Features Actuation System

SFPP

Spent Fuel Pool Pump

SG

Steam Generator

S0V, SV

Solenoid Operated Valve

SPDS

Safety Features Display System

SPEC

Specification

SSFI

Safety System Functional Inspection

SW

Service Water

TCV

Temperature Control Valve

TDH

Total Developed Head

TE

Toledo Edison

.

TM

Temporary Modification

TMM

Temporary Mechanical Modification

TR

Temperature Recorder

TS, Tech. Spec.

Technical Specifications

TT

Temperature Transmitter

UPS

Uninterruptible Power Supply

URI-

Unresolved Item

USAR

Updated Safety Analysis Report

V DC, VDC

Volts DC

V AC, VAC

Volts AC

W

Watts

C-3

j