May 20, 1987 Docket No. 50-410 NEW RANDUM FOR:
T. Murley*
J. Partlow P. Capra J. Sniezek*
F. Congel W. Butler F. Miraglia*
H. Miller V. Nerses R. Starostecki* S. Black
- J. Stolz S. Varga*
B. Boger*
E. Adensam D. Crutchfield* G. Lainas*
L. Rubenstein L. Shao*
F. Schroeder B. J. Youngblood C. Rossi*
G. Holahan A. Thadani J. Pichardson W. Lanning THRU:
Robert A. Capra, Acting Director Project Directorate I-l Division of Reactor Projects, I/II DISTRIBUTION FROM:
Joseph D. Neighbors, Proj' t Manager
'Dockst file
Project Directorate I-1 PDI-l Rdg.
Division of Peactor Projects, I/l!
jq.
SUBJECT:
DAILY HIGHLIGHT Nine Mile Point Nuclear Station, Unit 2 It is expected that Nine Mile Point 2 will be brought critical late today or early en May 21, 1987.
The low power license was issued on October 31, 1986 but because of leakage problems with the brll-type MSIVs the licensee replaced them with wye-pattern olobe valves. License amendments related to the MSIVs 7
were issued by NRR and construction deficiencies identified in the license were resolved by Pegion I.
These actions cleared the way for initial criticality.
Joseph D. Neighbors, Project Manager Project Directorate I-1 Division of Reactor Pro.iects, I/II