Staff Requirements Memo Re 860225 Briefing in Washington,Dc Concerning Incident Investigation Team Rept on 851226 Loss of Power in Integrated Control Sys.Schedules for Followup Plan & Assessment Re Lack of Plant Mods Requested
ML20154M151
Person / Time
Site: Rancho Seco
Issue date: 03/06/1986
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
REF-10CFR9.7 M860225, TAC-60462, NUDOCS 8603130336
Download: ML20154M151 (2)


Text

IN RESPONSE, PLEASE c#' '** UNITED STATES REFER TO: M860225 i !

g NUCLEAR REGULATORY COMMISSION W ASHINGTON, D.C. 20655 M

j

% . , , , . *# March 6, 1986 OFFICE OF THE SECR ETARY s

MEMORANDUM FOR: Victor Stello, Jr.

Acting Executive Directo 3 or Operations FROM: Samuel J. Chilk, Secretar 7 K

SUBJECT:

STAFF REQUIREMENTS - BRI E@kNGBY'1NCIDENT INVESTIGATION TEAM ON STATUS OF RANCHO SECO, TUESDAY, FEBRUARY 25, 1986, COMMISSIONERS' CONFERENCE ROOM, D.C. OFFICE (OPEN TO PUBLIC ATTENDANCE)

The Commission

  • met to be briefed by staff on the loss of DC power in the integrated control system (ICS) event which occurred at the Rancho Seco Nuclear Power Plant on December 26, 1985.

Chairman Palladino requested information on whether or not the Rancho Seco plant has a reactor water level indicator.

(NRR) (SECY Suspenre: 3/14/86)

Chairman Palladino also requested the staff to respond on why the emergency feedwater initiation and control (EFIC) system has not been installed at Rancho Seco. Commissioner Bernthal requested information on the significance of the EFIC system in '

terms of overall plant safety.

(NPR) (SECY Suspense: 3/14/86)

Chairman Palladino requested the staff to provide the following:

1. schedule for follow-up plan;
2. schedule for staff recommendations on corrective action:
3. schedule for staf f assessment as to why plant modifications which should have been done were not done;
4. status of confirmatory orders or letters requiring the plant to remain shut down until NRC is satisfied that corrective actions are completed; and
  • Commissioner Roberts was not present.

l 8603130336 860306 PDR 10CFR PT9.7 PDR

~o

5. information on whether the licensee is planning a submittal for the Commission and, if so, when.

(NRR) (SECY Suspense: 3/14/86)

Chairman Palladino indicated that a follow-on meeting with staff and, possibly, a meeting with the Sacramento Municipal Utility District (SMUD) would be scheduled following receipt of staff's follow-up plan.

ec: Chairman Palladino

, Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Zech Commission Staff Offices PDR - Advance DCS - 016 Phillips 1

- -