GH OPERATING DATA REPORT DOCKET NO. 50-301 E8 3
- 8 E8 n
(14 OPERATING STATUS h8 U
l.
UNIT NAME POINT BEACil NUCLEAR PLANT - UNIT 2 NOTES 2.
REPORTING PERIOD. April-1998 be 3.
LICENSED TiiERMAL POWER (MWT): 1,518.5 4.
NAMFPLATING RATING (GROSS MWE): 523.8
' 5.
DESIGN ELECTRICAL RATING (NET MWE): 497.0 6.
MAXIMUM DEPENDABG CAPACITY (GROSS MWE): 509.0 7.
MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 8.
IF CllANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 TilROUGil 7) SINCE LAST REPORT, GIVE REASONS:
l NA 9.
POWER LEVEL TO WilICII RESTRICTED, IF ANY (NET MWE): NA
- 10. REASONS FOR RESTRICTIONS,(IF ANY):
NA' TilIS MONTil YEAR TO DATE CUMULATIVE
- 11. IlOURS IN REPORTING PERIOD 719.0 2,879.0 225,696.0
- 12. NUMBER OFllOURS REACTOR WAS CRITICAL 719.0 1,422.9 189,307.9
- 13. REACTOR RESERVE S11UTDOWN IlOURS 0.0 0.0 233.9
- 14. IlOURS GENERATOR ONLINE 719.0 1,377.0 186,673.8
- 15. UNIT RESERVE SilUTDOWN llOURS 0.0 0.0 302.2
'6. GROSS TIIERMAL ENERGY GENERATED (MWII) 1,090,411.0 2,042,258.0 268,218,206.0
- 17. GROSS ELECTRICAL ENERGY GENERATED 375,850.0 700,760.0 91,180,310.0
- 18. NET ELECTRICAL ENERGY GENERATED (MWil) 359,770.0 661,545.5 86,882,306.5
- 19. UNIT SERVICE FACTOR 100.0 %
47.8 %
82.7 %
l
- 20. UNIT AVAILABILITY FACTOR 100.0 %
47.8 %
82.8 %
l
- 21. UNIT CAPACITY FACTOR (USING MDC UET) 103.2 %
47A%
78.9 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 100.7 %
46.2 %
77.5 %
- 23. UNIT FORCED OUTAGE RATE 0.0%
52.2 %
2.4 %
- 24. S11UTDOWNS SCIIEDULED OVER NEXT 6 MONTilS (TYPE, DATE, AND DURATION OF EACll):
}
Refueling 9/19/98 60 days
- 25. IF SilUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEI'TEMBER 22,1977 t