ML20151N909

From kanterella
Jump to navigation Jump to search
Response Team Activities Insp Repts 50-445/85-13 & 50-446/85-09 on 850901.Violations & Deviation Noted:Erroneous Conduit Observation,Incomplete &/Or Incorrect Documents & Incorrect Population Development
ML20151N909
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/23/1985
From: Barnes I, Ellershaw L, Hale C, Andrea Johnson, Will Smith, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20151N849 List:
References
50-445-85-13, 50-446-85-09, 50-446-85-9, NUDOCS 8601030202
Download: ML20151N909 (45)


See also: IR 05000445/1985013

Text

,

-

,

g

. f."

,

f

4

+. ge

,

-

,

APPENDIX E

'

.

.

,

. COMANCHE PEAK RESPONSE; TEAM ACTIVITIES INSPECTION RE, PORT.

.

.x

- 1

,'

O. S. NUCLEAR REGULATORY COMMISSION-

'

'

~ ,

'

.-

_

REGION IV

'

'

'

'

'

<

,

.

,

"Ep f (,

-

~

.f

NRCJInspection Reports:

50-445/85-13

Permit: CPPR-126:

'

,

-

50-446/85-09

CPPR-127

>

__

Dockets': ~50-445.

Category:

A2

,

_

50-446'

o-

-

Applicanti Texas Utilities, Electric Company (TUEC)

,

.

' Skyway Tower

. .

400 North Olive-Street

Lock Box 81'

Dallas, Texas

75201'

,

Facility Name:

Comanche Peak Steam Electric Station (CPSES), Units 1 and 2

.

-Inspection At:

Glen Rose, Texas

' Inspection Condu ed: September 1-30, 1985

Inspectors:

1

if a<.4

/d 7 T

L. E. Ellershaw, Reactor Inspector, Region IV

fate'

.

CPSES. Group

.(paragraphs 1, 5.d, 5.g-5.1, 5.k-5.n, 5.t-5.v)

,,

/2 4!h'

-

W. F. Smith, Resident-. Reactor Inspector (RRI),

Date'

Region IV CPSES Group

(paragraphs 1, 5.j)_

$$

.

C. J. Male, Reactor Inspector, Region IV CPSES

'Date~

'

' Group

(paragraphs 1, 2.a-2.b, 3, 4, 5.e, 5.f, 5.o-5.s)

.

_

)

W*'

-

G

.

i

"2

,

}i , ' * "

J _.

t,

_

.

E

.

.

2

V

?'

<

%

&

102 dyl"

'

A. R.-Johnson, Reactor Inspector,' Region IV

~Date

"

CPSES Group

(paragraphs

1,~ 2.c-2.e, 5.a-5.c, 5.v)

Consultants:

EG&G - R. Bonnenberg, L. Jones, A. Maughan, W. Richins,

R. VanderBeek

,

Parameter - J. Birmingham, D. Brown, J. Gitison, K. Graham,

D. Jew, T. Young

.

Reviewed By:

8-

/a /I7Mu'

I. Barnes, Group Leader, Region IV CPSES Group

Date

f // j)/

/>/2 r/>f

Approved:

T. F. Westerman, Chief, Region IV CPSES Group

Date

,

Inspection Summary

' Inspection Conducted:

September 1-30, 1985 (Report 50-445/85-13; 50-446/85-09)

Areas Inspected:

Nonroutine, unannounced inspection of applicant actions on

previous inspection findings, Comanche Peak Response Team (CPRT) procedures and

instructions, and CPRT issue - specific action plans (ISAPs). The inspection

involved 2339 inspector-hours onsite by 6 NRC inspectors and 11 consultants.

Results: Within the three areas, inspected, two violations (erroneous and'

missing conduit identification, paragraph 2.e; observation of an accepted

flange joint in a broken condition, paragraph 5.v); and three deviations (issue

of inspection verification packages with missing, incomplete and/or incorrect

documents, paragraphs 5.u and 5.v; failure of ERC inspectors to note conditions

which violated drawing requirements, paragraph 5.v; incorrect population

development for ISAP V.d, paragraph 5.m) were identified.

i,

,.

,

!

3

t

DETAILS

-

W

'

,,

1.

Persons Contacted

.

'J. Arros, TERA Civil / Structural Issue Coordinator

.

W. Bailey, ERC Supervisor, QA/QC Reinspection Engineering

,

J,.,

D.' W. Braswell, TUGC0 Engineering Superintendent

-

,

.

C..I. Browne,-Project Manager, R. L. Cloud & Associ nes, Inc.

  • R. E. Camp, Assistant Project General Manager, Unit 1 (Impell Corp.')

>

,

  • J. D. Christensen, ERC Deputy QA/QC Review Team Leader

'

< -

  • J. Finneran, TUGC0 Lead Pipe Support Engineer

.

  • S. M. Franks, Special Projects and Technical Support Lead (Impell-Corp.)

'

-

.

,

~

  • J. B. George, TUGC0 Vice President, Plant General Manager

.

  • P. E. Halstead, TUGC0 Site QC Manager

,

y

J. L.: Hansel, ERC QA/QC Review Team Leader

-

'*C. R. Hooten, TUGC0 Project Supervisor, Civil / Structural Engineering

  • J. _ C. Kuykendall, TUGC0 Manager, Nuclear Operations

H. A. Levin, CPRT Civil / Structural / Mechanical Review Team: Leader

,

-

  • D. M. McAfee, TUGC0 QA Manager

~

  • J. T.~ Merritt, Jr. , TUGC0 Assistant Project General Manager -

' *S. P. Helancon, CPRT Issue Coordinator

  • C. K. Moehlman, TUGC0 Project Mechanical Engineer
  • C. E. Scott,.TUGC0 Startup Manager-

G. M. McGrath, TUGC0 Licensing / Compliance Supervisor

r

.

W. J. Nixon, TUGC0 Results Engineering Supervisor

M. Obert, TRT Issue Coordinator

A. Patterson,'ERC Engineering Supervisor

C. Spinks, ERC Inspection Supervisor

T. G. Tyler, CPRT Program Director (Energex)

  • W. I. Vogelsang,'TUGC0 Electrical Coordinator

/*C. H. Welch, TUGC0 QC Services Supervisor

  • M. J. Wise, CPRT Testing Review Team Leader
  • Denotes those persons who attended the exit interview.

The NRC inspectors also contacted other CPRT and applicant employees

during this inspection period.

2.

Applicant Actions on Previous Inspection Findings

a.

(0 pen) Unresolved Item (445/8511-U-01):

Procedure CPP-001,

,

" Preparation of Project Procedures and Quality-Instructions," has

been revised (Revision 1) to provide additional guidance / direction in

the development of Quality Instructions (QIs). Unclear requirements

noted in NRC review of QI-008 (i.e., paragraphs 2.a, 4.d, 8.a, 8.b,

,

4

1

.

.

4

8.c, 10, 11, 12.a.1, 12.9.2, 12.b.1, 12.b.2, 12.c.2, 12.d.2,

12.e.2.b) have been suitably resolved in Revision 2 of this document

which was issued on September 9, 1985.

Addstional Region IV review

with respect to QI-014 has been deferred until after completion of

the NRR evaluation of statistical populations.

This unresolved item

will remain open pending resolution of QI-014 and completion of

evaluation of QIs applicable to all engineering disciplines.

b.

(0 pen) Deviations (445/8511-D-01 and 445/8511-D-02):

These items

will remain open pending receipt and evaluation of the applicant's

response.

c.

(0 pen) Open Item (445/8511-0-14):

Additional inspection of this open

item, pertaining to observation of a damaged fire wrap blanket on

conduit C14B11217, has been performed.

No other instances of fire

wrap blanket damage were observed during this reporting period.

TUGC0 has initiated Nonconformance Report (NCR) E-85-101340S with

respect to the conduit C14B11217 fire wrap damage.

This item will' remain open pending further NRC inspection.

d.

(Closed) Open Item (445/8511-0-15):

Further review of this open

item, pertaining to observation of two sections of cable tray with

covers removed, showed that the cover removal had been previously

authorized by Item Removal Notice (IRN) E05257CB and NCR E85-100513.

e.

(Closed) Open Item (445/8511-0-33):

Additional NRC inspection of

this open item was performed in this reporting period. . Procedure

QI-QP-11.3-8, Revision 0, issue date July 7, 1978, " Identification

and Color-Coding Inspections," requires that the presence of ccnduit

identification be verified at both sides of all walls and slabs

through which conduit passes.

Procedure QI-QP-11.3-23.7, Revision 1,

issue date January 5, 1980, " Verify Conduit Identification," requires

also that conduit be identified as stated above and addresses the use

of identification. templates for embedded conduits which are flush

with the surface of walls and floors.

The NRC inspection showed

several instances where required sleeve conduit identification was

missing. 'One example was-also noted of an incomplete identification

marking.

ERC inspections have'also identified-instances where

conduit sleeves have not been included in the cable routing

schedules.

-

The failure to sccomplish required conduit identification to provide

for control of cable routing is a a violation (445/8513-V-01).

f.

(Closed) Open Item (445/8511-0-34):

Further inspection of this open

item, pertaining to absence of identification tags on the outboard

side.of electrical-penetration assemblies, showed that tags were not

4

_

J

.

-_

_

.

,

c

s

,

5

.

required by the applicable specifications; i.e., Specification

Nos. 2323-ES-100 and 2323-ES-12/12A.

g.

(C-losed) Open Item (445/8511-0-35):

Further inspection of this open

item, pertaining to the presence of 1-inch openings in the bottom of

cable. tray section T130ECG41 and T130CCP80, showed that the opening

(i.e. , potentially representing a separation deficiency) in tray

T130ECG41 had been previously identified by the applic. ant and was

being corrected by Ccnstruction Operation Traveler AM85-309D-9400.

Additional examination of tray T130CCP80 showed that no other trays

or conduit were below the opening in the tray and therefore a

separation deficiency did not exist.

.

3.

CPRT Program

Detailed NRC staff comments on the CPRT Program Plan, Revision 2, were

forwarded to the applicant by NRC letter of September 30, 1985.

ERC

has controlled procedures addressing their activities and TERA is

developing procedures for formal control of their activities (four are

issued).

Future Region IV inspection activities in these subject areas

are dependent upon issue of the umbrella QA program and the results of

NRC staff review.

4.

CPRT Procedures and Instructions

a.

Implementation of ERC Comanche Peak Procedures and Instructions

The NRC audits were conducted to determine if the ERC activities were

consistent with the requirements identified in the Comanche Peak

Procedures (CPPs).

(1) Audit of CPP-001,-002 and-004:

The NRC inspectors audited

CPRT's implementation of CPP-001, Revision 0, " Preparation

Review and Approval of Project Procedures and Instructions";

CPP-002, Revision 0, " Control of Correspondence and QA/QC Review

Team Documents"; and CPP-004, Revision 0, " Project Working

Files." No deviations from the commitments in CPP-002 and

CPP-004 were noted.

Several deviations from CPP-001,

Revision 0, were identified concerning the control of procedure

~

revisions to CPP distribution manual holders and the retention

of' procedure review comments.

Two days after this NRC audit,

CPP-001, Revision 1, was issued resolving these deviations.

1

.

O

E.

.

.

6

(2)

Inspector Certification and Personnel Objectivity:

This is a

continuation of the NRC inspection of the implementation of

CPP-003, " Indoctrination, Training and Certification of

Personnel," that was initiated and documented in NRC Inspection

Report 50-445/85-11; 50-446/85-06.

Included in this inspection

are the results of reviews of the objectivity statements of all

CPRT personnel and the testing of ERC inspection personnel.

Personnel Objectivity:

One of the founding principles of the

CPRT program is that the program be conducted in such a manner

that its objectivity and credibility will not be questioned.

To

this end, the CPRT developed an objectivity questionnaire that

all personnel, except for clerical and certain administrative

personnel, were required to complete and sign. The NRC has

reviewed all currently completed questionnaires and compared

them with the individual resumes.

Errors were found in many of the completed questionnaires due to

individuals not being aware of contracts previous employers have

had with TUEC. These errors were satisfactorily corrected.

However, during this review two members of the Senior Review

Team (SRT) and two key members of the CPRT were noted to have

described previous contractual involvement with CPSES on their

objectivity questionnaires. Additional NRC review of this

matter will be made after receipt of the information requested

by the transmittal letter for NRC Inspection Report 50-445/85-11;

50-446/85-06.

Inspector Testing:

CPP-003 requires that all inspection,

examination, and test personnel take a written examination in

general QA principles and in their specific discipline, except

for those individuals coming directly from the Braidwood site.

The individuals were associated with ERC at that facility in a

similar corrective action program to CPSES and were consequently

permitted to transfer certifications obtained by examination at

that location. CPP-003 further requires a minimum passing grade

of 80%, failures may be retested only once and not in less than

three days.

Written tests have been given to inspection personnel beginning

-

in December 1984, with the largest majority being given during

July and August 1985, when most of these personnel reported to

the site. The test questions are carefully controlled with

only limited and authorized access permitted.

All test

questions are maintained in a computer program.

Each type of

test (e.g. General QA, Mechanical Level II Specific, etc.) has a

pool of questions that is at least twice as large as the number

of questions that wculd appear on a given test.

.

.

.

..

_

_

_

- - _

.

.

7

NRC review of two pools of test questions (General QA and

Mechanical Level II Specific) and a comparison of tests given at

different times verified that the practices described above were

being implemented.

Twenty-eight inspectors were. required to be retested.

Each of

these inspector's files was reviewed for test and retest dates,

and the questions on the tests and retests were compared for

duplication.

Six individuals were given retests in less than

3 days, five in December 1984, and one in January 1985. These

departures from the 3-day requirement for retest occurred, how-

ever, before the issuance of CPP-003, Revision 0, dated July 2,

1985, and appear to be isolated occurrences when retesting first

began.

No NRC deviations were identified.

'

(3) Audit of CPPs-005,-006,-007 and-008: The following CPPs define

requirements for preparation of documents critical to the'

reinspection process: (1) CPP-005, " Establishing Populations";

(2) CPP-006, " Sample Selection"; (3) CPP-007, " Preparation of

Checklists and Data Base Reports"; and (4).CPP-008, " Preparation

i.

,

of Verification Packages."

'

-

The NRC audit of these four CPPs was based on the selection of

nine completed verification packages from the ERC QA/QC Review

Team Records Center.

The Records Center also had files for the master population

list, population descriptions, population items list, and random

sample identification lists. The master population list was

'

checked to assure each of the selected verification packages was

included.

In all cases the proper population description and

i

population items list were on file for each verification package

audited. The applicable random sample identification lists

existed but these lists were formally checked out to the

engineers who were preparing verification packages. The

engineers were contacted and the lists produced. The NRC

inspector was informed that the lists would be returned to the

Records Center after preparation of all verification packages

and completion of the field reinspections.

The random sample identification list includes provisions for

documenting whether an accessibility check was made.

Justification is required if the accessibility check is not

made. The verification packages, according to CPP-007, should

contain inspection checklists and data base reports. All

packages in the sample contained both.

l

,

,,

,c.

. . _ _ .

,-

_

_

__-

_ _ . _ . ,

_ _ _ _

,

_

. . .

. ,

_

. ._ ._ . .

_

_ _

_ _ _

r.

c

,

..

. o.

,

,

,

L

,

s

8

-

.

.

.h

'

A verification package'index,E required by CPP-008, was included

in each verification package. _ Supplementary in'spection-instruc-

tions, optional according to'CPP-008, were included in two of-

the nine verific& tion packages.

The,' adequacy of the documents

referenced in each verification package is a. subject considered

,

in NRC audits of each ISAP No. VII.c population.

No NRC deviations were identified in the audit of these CPPs.

(4) Audit of CPPs-009 and-010: . The method chosen to audit the

,

implementation of these CPF2 was to review the nine verification

packages referred to above to determine if CPP-009, " Performance

of Reinspections and Documentation Reviews," and CPP-010,

" Preparation of Deviation Reports," had been implemented.

t

The inspection checklist in all nine verification packages was

'

completed, reviewed,.and approved as required by CPP-009.

4

j

'Of the verification packages reviewed, three included Deviation

Reports (DRs).. These were reviewed and approved by first and

second reviewers, in accordance with CPP-010.

No NRC deviations were identified,

,

b.

Review and Implementation of TERA Onsite Procedures

l

[TERAis'inthe,processofdevelopingandimplementing20. Design

LAdequacy Procedures.(DAPs) for use in controlling their Design

Adequacy Program onsite and offsite. At present, four DAPs have been

,

-released and five have been released for interim use only.

The

l

T

remaining 11 are in the final review process.

In addition, five

f.

civil structural and mechanical (CSM) procedures have been used as

!

interim procedures until the DAPs are developed.

An'NRC inspection.was conducted to determine if the onsite TERA

effort in conducting the assigned ISAP tasks complied with the CPRT

Policies and Guidelines and, as applicable, DAPs or CSM procedures.

This inspection included four areas defined by the CPRT Policies and

'

Guidelines: (1) " Policy on Testing and Inspection Personnel used in

Third Party Verification Activities", (2) " Developing Sampling Plans

and Random Samples for TRT Issues," (3) " Guide on Central and Working

Files," and (4) " Guide for Safety Significance Evaluations." .The

inspection also addressed, in part, the previously identified _open

'

item (445/8511-0-37) which remains open until the site applicable

DAPs are issued, implemented,' and inspected.

,

'

.

b

k

.

t -

t

, -

.-..--------,,-,%

, ~ , , ~ ,

-,c

. -

y-

-

,,-,,.--,-,.---,-,-y-

, , -

,,y

, -

-9

, w--v,,

=

- - - , - < - - , . - - - - - ,

,

- - -

-.

-

, - _ .

,

1;

'

'

,

,

9

,

.

d

(1) Training Records:

This activity will be covered by DAP-15,

'

' " Training and. Qualification," which has not been released.

This

,

-

-

audit was. conducted using the TERA work instruction CSM-1.

A review of the TERA files showed that there was a Training and

' Qualification file on each onsite TERA employee, at present 12

individuals. Each file included a resume, an objectivity state-

ment, a training record, and a record of required reading. The

file for one individual was reviewed in detail and established

to contain all of the required information and approval.

No NRC deviations were identified.

(2) Sampling Methods:

No TERA DAP will be issued to cover sampling.

Therefore, the. TERA effort was inspected for compliance with the

CPhi Policies and Guidelines.

ISAP No. II.a, " Reinforcing Steel in the Reactor Cavity," was

chosen and the Issue Coordinator's file was inspected.

The ISAP

included tasks requiring sampling, review of pour cards, and

study of embeds.

The file concerning pour cards contained a population list, a

random number ordering of the population, a tabulation of the

results of the inspection, and a summary report on the pour

cards.

The file concerning embeds showed that the number of

embeds was small, so 100% were reviewed.

ISAP V.a, " Inspection for Certain Types of Skewad Welds in NF

Supports," was inspected for sampling methods.

A computer based list of hangers was used by TERA which identified

all hangers that contained skewed welds.

This list defined a

population of 359 hangers with skewed welds from which a

statistical random sample of 60 had been taken.

No NRC deviations were identified.

(3) Discrepancy Responsing:

Documentation and tracking of issues

and discrepancies is covered by DAP-2, which has been issued,

and by CPRT Policies and Guidelines on reportability of

deficiencies.

The file on Discrepancy / Issues Resolution reports (DIRs) was

audited and contained copies of three TERA originated DIRs dated

August 27, September 17, and September 25, 1985.

These had been

sent to the Generic Implication Coordinator for processing. One

of the three was considered by TERA to be potentially reportable

under 10 CFR 50.55(e) and the form, "Reportability Evaluations

1

%

-r

y--

,

. , -

,

-

-

-

- - - ~ - -

--

.

_

.

.

10

Check List," had been completed and attached to the DIR.

Disposition of the potentially reportable finding is and open

item (445/8513-0-01).

No NRC deviations were identified.

(4) Documentation System: TERA has developed a procedure, DAP-ll,

" Document Control." to control the documentation system. To

date, the procedure has not been released, so the audit compared

the TERA document control system to the CPRT Policies and

Guidelines.

The TERA onsite documentation system utilizes file numbers, file

indices, and file content logs and is being maintained in

accordance with the CPRT Policies and Guidelines.

The impact of

the procedure on work performed prior to its issue is currently

anopenitem;i.e.,(445/8511-0-37).

No NRC deviations were identified.

5.

CPRT ISAPs

a.

NCRs on Vendo- Installed AMP Terminal Lugs (ISAP No. I.a.5)

Status of CPRT Activity

In conjunction with the review of the AMP Incorporated Engineering

Evaluation Report EER-136, CPRT-Electrical is reviewing military

specification MIL-T-7928G which was utilized by AMP in the testing of

their terminal lugs. The CPRT-Electrical is currently assessing the

completeness of the central records files and finalizing actions on

this ISAP.

The results report has not yet been issued for this

activity.

Status of NRC Inspection Activity

The NRC inspector reviewed the process for the redispositioning of

NCRs E-84-01066 through E-84-01081 and the referenced NCR E-84-00972.

The NRC inspector identified that replacement of terminal lugs was

performed under Startup Work Authorization (SWA) No.19116 which was

verified to have been completed on May 3, 1984.

This SWA was worked

in conjunction with SWA No. 19249.

The NRC inspector examined 9 of the 16 6.9KV cubicles in which the

terminal lugs of concern are located.

The nine cubicles examined

contain approximately 80% of the terminal-lugs of concern. The NRC

inspector observed no terminal lugs bent in excess of 90 or twists

in excess of 45 .

No flaking, cracks, or other physical character-

istics were observed which could result in a loss of mechanical

strength. As a result of these observations, the NRC inspector found

_

_

_. _-

. -.

- ._.

.

_

_

_ _ _ _

,

,

11

no reason to disagree with the conclusion of the disposition that

the terminals can be used "as is" and do not pose a service problem.

The NRC inspector is reviewing MIL-T-7928G concurrently with the

. review of the AMP Engineering Evaluation Report EER-136. The NRC

inspector has also made an initial review of the ERC central file for

ISAP No. I.a.5.

No NRC violations or deviations were identified,

b.

Flexible Conduit to Flexible Conduit Separation (ISAP No. I.b.1)

Status of CPRT Activity

The control board internal wiring analysis, (Revision 1) required by

the ISAP, was submitted by Gibbs & Hill (G&H) to TUGC0 on July 24,

1985, to demonstrate that existing circuits in main control panels

are protected, exclusive of existing SERVICAIR flexible conduit; and

to preclude the need for additional separation barriers. G&H is

currently modifying this analysis to address NRC comments.

The physical tests (short circuit and heat transfer) conducted on the

SERVICAIR flexible conduit to evaluate its adequacy as a barrier

under design bases conditions, have been partially completed.

Testing to establish worst case current condition in the heat

transfer test is in process as a result of further analysis by G&H.

Status of NRC Inspection Activity

The NRC inspector has reviewed ISAP No. I.b.1, Revision 3, and the

implementing CPRT QI; i.e., QI-004, Revision 4.

The NRC inspector is currently in the process of reviewing the G&H

control board internal wiring analysis, Revision 1.

No NRC violations or deviations were identified,

c.

Barrier Removal (ISAP No. I.b.4)

Status of CPRT Activity

NCRs were issued by TUGC0 as a result of TRT activities to assure

replacement of removed barrier material and rework of field

cabling which was in violation of the separation criteria.

Upon

completion of the dispositioning of the NCRs, CPRT-Electrical

requested ERC to inspect the rework. As a result of the inspection,

another cable separation violation was noted.

CPRT-Electrical

requested TUGC0 to issue a Design / Construction Significant

Deficiency Analysis Report for potential reportability

.

.

12

under the provisions of 10 CFR 50.55(e).

The deficiency analysis

report was issued and addressed by TUGCO.

It was determined that the

noted deficiency was not reportable.

A revision was made to CPSES

Operations Maintenance Procedure INC-101 to address concerns of'

barrier material removal during maintenance.

Further activities on this issue will depend on the results of the

control board and vertical panel internal wiring separation analysis

associated with ISAP No. I.b.1.

The CPRT-Electrical is currently in the process of determining which

other separation issues will be addressed in the ISAP.

Status of the NRC Inspection' Activity

The NRC inspector has reviewed ISAP No. I.b.4, " Barrier Removal,"

Revision 3, dated June 26, 1985.

No CPRT quality instruction governs

this activity, other than the Senior Review Team (SRT) Draft Policies

and Guidelines which were approved for use by the SRT on February 28,

1985.

Assessment of the adequacy of this approach is an open item

(445/8513-0-02).

No NRC violations or deviations were identified.

d.

Electrical Conduit Supports (ISAP No. I.c)

Status of CPRT Activity'

A third party review is to be performed by TERA as part of ISAP

No. II.d, which deals with seismic design of control room ceiling

elements and will focus on the Unit 1 Damage Study Program for

greater than 2-inch conduit.

TERA is conducting a review of as-built

drawings for the selected 1 1/2-inch and 2-inch nonsafety-related

conduit runs which are being analyzed by G&H for seismic effects.

Some supports in seven conduit runs have been found to have stresses

greater than the specified allowables, when subjected to the G&H

seismic loads.

Two approaches are underway in an attempt to resolve the problem.

One approach deals with establishing a test program in an attempt to

obtain plastic deformation versus load data that will justify

increasing the allowable stress of certain support components.

In

conjunction, guidelines are being established for a walk-down evalua-

tion of predicted interactions with safety-related items resulting

from support failure and/or sway.

9

n

.c

,

,

.

.

. ..

13

'

. -

s

Status of NRC Inspection Activity

The ISAP: and ~ related procedures have been reviewed for consistency

'

with FSAR requirements and NRC Technical Review Team (TRT) concerns

, '

pertaining to nonsafety-related conduit interactions with

4

safety-related items.

Procedures for selection of random samples

'

.were: reviewed for compliance with Appendix D of the CPRT Program

s

.

. Plan.

The engineering sample selection procedure is being reviewed.

>

~

' Review of the Damage Study for greater than 2-inch nonsafety-related

E,

conduit as'well as verification of the total population of 1.1/2-inch

' and 2-inch conduit has not been completed.

As-built drawings, which

,

will comprise a part of the final seismic analysis package, will be

reviewed along with the analysis.

No NRC violations or deviations were identified.

'

'e.

QC Inspector-Qualification (ISAP No..I.d.1)

,

.In.; response to the TRT reporting of a lack of supporting documentation

~in. inspector qualification files, ISAP No. I.d.1 was developed ~to

review and evaluate' all current inspector qualifications and also

historical electrical inspector qualifications.

The ISAP is structured

to be performed in three phases.

Phase One is a screening of' inspector

files by the ERC Certification Administrator (ERC-CA) for ASME

inspectors, and by TUGC0 Audit Group (TAG) for non-ASME inspectors.

Phase Two is an' evaluation of the qualifications by a Special Evalua-

tion Team (SET). -Phase Three is sampling reinspection of hardware

originally inspected by any inspector deemed to have insufficient

paper _ qualifications.

Status of CPRT Activity

Phase One is complete.

TAG and the ERC-CA have completed screening

of inspector files and transmitted the results to the SET.

This

screening documented discrepancies / deficiencies of various importance

j

from clerical errors to lack of a high school diploma.

Evaluation of

'

the effect'of these discrepancies / deficiencies is the role of.the SET

in Phase Two.

~

j

,

SET has completed Phase Two review of all current non-ASME inspector

'

and historical electrical inspectors.

Review of ASME related

inspectors is approximately two thirds complete.

In performing its

review, the SET obtained additional clarification or backup documenta-

tion from TUGCO.

Phase Two status of current non-ASME and historical

i

7

-

,

,

~.:

.

9

4

Y,

-

14

.

\\

. 3

'

L'

electrical. inspectors had not'been-issued as of the end of this

~

finspection period. .To date, six inspectors have been identified

.

4

for-Phase Three.

The sample reinspections for these individuals have

been completed.and results reports for each are in preparation.

Status of NRC Inspection Activity

)For Phase One, the NRC inspector compared 12 screening reports with

-

.

the certification files. .This comparison found the reports to be

.

. accurate'and~ complete with the exception that non-ASME certifications

held by ASME inspectors had not been reviewed.

This exception has

been discussed with the issue coordinator and is an open item

.(445/8513-0-03).

.

For Phase'Two, the1NRC inspector reviewed five inspector qualification

files and compared them to evaluations by the SET.

In general, the

compIarisons agreed with the SET evaluations.

One exception was noted

with respect to an inspector's education level being insufficient as

documented; i.e., record of passing General Equivalency Diploma test

scores without copy of actual diploma.

This is an open item

(445/8513-0-04).

For Phase Three, the NRC inspector witnessed 24 of approximately 240

Phase Three'reinspections.

These inspections are controlled by

QI-005, " Procedure for Evaluation of Inspector Performance." This

procedure was reviewed by the'NRC inspector.

Comments on the procedure

were directed to the Issue Coordinator and were resolved by ERC memo

QA/QC-RT-483 or included in a subsequent revision.

,

The 24.w'itnessed ERC'reinspections showed ERC noting deficiencies and

' documenting them on the inspection' record.

The deficiencies were

also cocumented by an NCR fe cesolution.

No additional deviations

were noted by the NRC.instec'. r during these inspections.

Independent

reinspections of the LU 4ct. .ity is planned to be performed during a

subsequent inspectio.

The NRC inspector noted that deficiencies attributable to the original

,

inspector could potentially be missed in items that had been changed

by NCR rework.

This is an open item (445/8513-0-05).

No NRC violations or deviations were identified.

v

i

b

i

l

_a

-

_

..

.

__

. _ _ _ .

_. .

._.

_

._ _

..

.

.

,

~

15

i

f.

Guidelines for Administration of QC Inspector Tests (ISAP No. I.d.2)

Status of CPRT Activity

Review and comment on Procedures CP-QP-2.1, " Training of Inspection

Personnel," and CP-QP-2.3, " Documentation with QA/QC Personnel

.

Qualification File," performed by the SET is complete. The applicant

has issued CP-QP-2.1, Revision 19, which addresses;the comments of

SET.

Review by SET of Revision 19 is not. complete.

4

Status of NRC Inspection Activity

The NRC inspectors have. reviewed Procedure CP-QP-2.1 for incorporation

of the TRT comments._ This review found all TRT comments addressed

-

except for the lack of a defined vehicle for familiarization of QC

-

. inspectors with changes in inspection procedures.

This is an open

item (445/8513-0-06 ).

,

4

No NRC violations or deviations were identified.

. -

- g.

Reinforcing Steel in the Reactor Cavity (ISAP No. II.a)

,

,

Status of CPRT Activity

TERA personnel informed the NRC inspector that the actions committed

to by ISAP No. II.a are complete with'the exception of a final

Everification of the completenesslof the pour card population. The-

.

,

final results report has been prepared and is currently being reviewed-

internally.by TERA.

,

Status of NRC Inspection Activity

Review of G&H analysis of the as-built condition of the Unit i

reactor cavity is complete. An evaluation of other plan items is

underway.pending the issuance of the final results report.

No NRC violations or deviations were identified.

'

~ h.

Seismic Design of Control Room Ceiling Elements (ISAP II_.d)

Status of CPRT Activity

-The TRT review of the seismic design of the ceiling elements installed

in the control room wAs conducted to verify design in accordance with

Regulatory Guide 1.29, " Seismic Design Classification," and FSAR

Section 3.78.2.8.

These documents require that seismic Category II

,

y

3

m.

. - - ,

y . ~ - , _

, , - - - - . - . . - - . . .

. - .

.

-- .,, ,

.

. , _ _

_ - , . . _ _ . _ _ ,

-

,

16

and nonseismic items be designed in such a way that their failure

will not adversely affect the function of safety-related components

or cause injury to operators.

For the nonseismic items (other than the sloping suspended drywall

ceiling), and for nonsafety related conduits whose diameter is 2

inches or less, the TRT could find no evidence that the possible

effects of a failure of these items had been considered.

In addition,

the TRT determined that calculations for seismic Category II components

(e.g., lighting fixtures) and the calculations for the sloping

suspended drywall ceiling did not adequately reflect the rotational

interaction with the nonseismic items, nor were the fundamental

frequencies of the supported masses determined to assess the influence

that seismic response spectrum at the control room ceiling elevation

would have on the seismic response of the ceiling elements.

The applicant has evaluated the potential ir.teractions and determined

that the installation of seismic restraints to resist horizontal

motion would be required.

It was also decided to remove the sloping

suspended drywall along with its supports and replace. it with a

seismically qualified sloped ceiling.

Status of NRC Inspection Activity

During this inspection, ongoing measurements being taken of control

room ceiling anchorages to concrete were observed. A review of

drawings showing the proposed modifications was also conducted.

This item will be further reviewed during subsequent inspections.

No NRC violations or deviations were identified.

i.

Rebar in the Fuel Handling Building (ISAP No. II.e)

Status of CPRT Activity

TERA personnel informed the NRC inspector that the actions committed

to by ISAP II.e are complete.

The final results report has been

prepared and is currently b'ing reviewed internally by TERA.

e

Status of NRC Inspection Activity

Review of G&H calculai. ions is complete.

An evaluation of additional

plan items is being performed including:

(1) a review of the adequacy

of procedural controls governing rebar cutting, (2) a review of all

,

i

.

.

17

.

n

cases'for Units 1~and 2 where rebar cutting was requested for installa-

tion of Hilti bolts, (3) a review of the determination of the possibil-

ity of additional unauthorized rebar cutting, and (4) a review of

Hilti bolt installation work as performed by the construction crew

that installed the subject Hilti bolts.

No NRC violations or deviations were identified.

j

Hot Functional Testing (HFT) Data Packages (ISAP No. III.a.1)

.

In order to maintain a correlation between areas inspected and the

applicable sections of the ISAP, this inspection report will address

each area using the ISAP paragraph number assigned by the applicant.

During the previous inspection period of August 1-31, 1985, (See

Appendix E of Inspection Report 50-445/85-11), paragraphs 4.1.1

through 4.1.6 were followup inspected, and paragraph 4.1.7 was

- -

started but not completed as indicated below:

4.1.7

There were seven HFT preoperational test data packages that

were not previously reviewed by the TRT.

In this section

of the ISAP, the applicant committed to reevaluate these

~

packages in accordance with the guidelines established in

Attachment 1 of the ISAP. The NRC followup inspector

reviewed the documentation associated with the reevaluation

of each data package to determine that:

The applicant's reevaluation appeared to follow the

guidelines established by Attachment 1 of the Plan,

The documented questions raised by the reevaluation

were properly dispositioned and approved by the Joint

Test Group (JTG), and

The disposition approved by the JTG was not contrary

to regulatory requirements.

The following test data package reevaluations were followup

inspected:

(a) 1CP-PT-49-02, 1CP-PT-49-05, and 1CP-PT-55-10 were inspected

during the last reporting period.

The results are reported

in NRC Inspection Report 50-445/85-11, Appendix E.

(b) ICP-PT-57-09, " Check Valves and Hot Functional Safety

Injection." The reevaluation was documented on Test

Deficiency Report (TDR) 3987.

There were no comments made

by the applicant's reviewers, however, the NRC followup

inspector noted that several check valves did not pass the

_.

.

.

18

acceptance criteria for leakage, and as such were documented

on six TDRs. The TDRs were closed on the basis that after

repair the retesting would be deferred to the post fueling

startup test program. This deferral was necessary at the

time, because the plant conditions (normal operating

temperature and pressure) required for testing were not

scheduled to be achievable until then. The NRC inspector

followed up to ensure all of the deferred valve retests

were clearly identified, so that documentation would show

that all of the objectives of ICP-PT-57-09 would be met

prior to initial criticality. The NRC inspector found that

all of the check valves except 1S1-8815 were retested

satisfactorily during December 1984, when the plant was

heated up to normal operating pressure and temperature for

thermal expansion retesting.

1S1-8815 was deleted from the

list of deferred valves on the basis that it was not a

reactor coolant system boundary as defined in Technical

Specification (TS) Table 3.4-1.

After this decision was

questioned by the NRC inspector, the applicant's representa-

tives produced a draft change to the Deferred Preoperational

Test Report showing the valve would be retested when

required plant conditions became available, but prior to

initial criticality (Mode 2). The NRC inspector was told

by the applicant's representative that this change would

have been made whether or not the original decision to

delete the valve was questioned by the NRC inspector,

because on April 9, 1985, TUEC had informed the NRC in a

letter (TXX-4431) that 1S1-8815 and four others would be

incorporated into TS Table 3.4-1.

During earlier reviews

of the TS, the NRC had requested TUEC to incorporate

ISI-8815 and 1-8900A, B, C and D into Table 3.4-1 because

they should be considered reactor coolant system boundary

valves whose operability should be verified through

surveillance testing.

1-8900A, B, C and D were already

tested during the preoperational test program in accordance

with ICP-PT-57-09.

For tracking and followup purposes, the

satisfactory retesting of 1S1-8815 is an open item

(445/8513-0-07).

During preoperational testing, TDR 1337 identified excessive

leakage during the seat leak test of 1-8900A, B, C and D.

Section 2.1 of ICP-PT-57-09 specified a maximum leak rate

of 45 milliliters per hour (ml/hr) for each valve. The

four valves were tested in parallel, which yielded a

combined leak rate of 84 ml/hr. The TDR was dispositioned

" acceptable" with a justification stating that the combined

leak rate could be as high as 180 ml/hr; i.e., 4 times 45.

When the NRC inspector questioned this rationale, the

.

4

-- -

, . , ,

. ';, u

-

'

.

,u;:. ..

,

y

-

..c

,

,

,

.;

,

V

s

(:'

b. ' , -

-

,

.

. . _

g

.

,

e

~*

-19

m

.

r

  • '
  • >

.

, , ,

,

's

qf ,

j : ,, *

>

'

~

'

cu.

.

.

.

,

.

Japplicant's representative indicated that the TDR ~justifica-

S

J-

q

-

,

'.

"

'

Ntion was incomplete, and.would be revised to explain why 84

ml/hr/;is an acceptab1'e leak rate.

Thel surveillance-leak

'

9

i

test acceptance criteria for;these valves.is 1 gallon per

minute.

The'preoperational test acceptance criteria.are

~

f;J

.

, the valves have significant leakage.

The JTG considered'a

designed toLprecipitate;a. technical' evaluation if any of;

.

'

l'

-

J

~

leak rate of.84fml/hr from all four. valves acceptable and -

,

,

,

F not indicative of a val've~ seating problem requiring repair.

'

g

-

q'

, Clarification of the test data package by revising the,

~

'

,

-justification:accordingly is Open Item (445/8513-0-08);

'

7

'

'

%

,

.

.

.

.

'

s

(c) ICP-PT658-02,^" Residual Heat Removal at' Hot Functional:"

'

The' reevaluation was' documented in TDR 3990.

The NRC

- - >

s:

<

_

,

. c inspectors found no violations or deviations.

'

<

-

.(d) 1CP-PT-74-02, "Incore TC and RTD Cross Calitsration." . The

-

~

reevaluation was documented in TDR 3876.

The NRC-inspectors

e

found no violations or deviations,

w

'

c

m

-

..

,

' ' , ' '

'

The reevalua-

(e) - 1CP-PT-91-01, " Loose . Parts Monitoring System."

-

-tion was~ documented in TDR-3988.

The NRC, inspector.found

'~ '

- '

%

-_

no violations ~or. deviations.

,

'

.

, g' ,

. . ,

,.

-

~

+.

g

,

.

.

.

. _

~

4!1.8-

The applicant committed to_ reevaluate 20 completed test

,

.

data packages?not associated with HFT. 0f.the 20 packages

-

,

'

-

<

sampled,~13 had been reviewed previously by.the'NRC' operations

'

.

'

-

resident inspectors. :The results of those. reviews'are documented-

..

,

y

'L

,

in variousiroutine inspecti.on reports.

'

Y'

I The'NRC followup inspector vei'ified that the following tests,

'

4

-

<which have been previously1 reviewed by the NRC operations

J

>

.

-

-

^

resident' inspectors', have been reevaluated in accordance with

s

' ~

A

.

.n' ,5Att'achment 1 ofithe<ISAP-

e

n

3,

-

-

.

,

,

(a) .1CP-PT-04-01, " Station-Service' Water," documented in

f"<

<;,

+

1

TDR 3918 as-satisfactorily reevaluated.

<

4

,

,

,

,

" '

7(b) ICP-PT-29-02, RT1, " Diesel Generator Control Circuit

Functional and Start Test,' Retest 1," documented in

-*

'.

TDR 3902 as satisfactorily reevaluated.

'

.

.

.

.

,

.

(c) 1CP-PT-29-04, " Diesel Generator Sequencing and Operational

~ Stability Test," documented in TDR 4066 as satisfactorily

-

reevaluated.

~

4

.

,

+

i

.

$

f

$

en

-

6_

'

X '.

' '

,.

r

'-

.

..

p.

20

.

M

(d) 1CP-PT-37-01, RT1, " Auxiliary Feedwater System (Motor

Driven Pumps),-Retest 1,"

documented in TDR 3929 as

'

satisfactorily reevaluated.

(e) 1CP-PT-48-01, " Containment Spray' System," documented in

TDR 3930 as satisfactorily reevaluated.

(f) ICP.-PT-57-01, RT2, " Safety Injection Pump Performance,

-

Retest 2," documented in TDR 3920 as satisfactorily

,

reevaluated.

'

(g) 1CP-PT-57-02, " Centrifugal Charging Pemp Test," documented

in TDR 3921 as satisfactorily reevaluated.

', '

(h)' 1CP-PT-57-05, " Safety. Injection Accumulators Test,"

documented in TDR 3938 as satisfactorily reevaluated.

.

(i) 1CP-PT-57-06, "RHR ECCS Performance," documented in

-

TDR 3939 as satisfactorily reevaluated.

,

(j) ICP-PT-57-08, " Integrated SI-Emergency Power," documented

in TDR 3940 as satisfactorily reevaluated.

-

(k) 1CP-PT-64-02, RT2, " Reactor Protection Systems, Retest 1,"

documented in TDR 3931 as satisfactorily reevaluated.

(1) -1CP-PT-64-07, " Solid State Safeguards Sequence System,"

documented in TDR 3906 as satisfactorily reevaluated.

(m) 1CP-PT-64-10, " Safeguards Actuation Relay Test," documented

in TDR 3941 as satisfactorily reevaluated.

The NRC followup

inspector noted that there was_an unresolved inspection

report item that was identified during the prior review

conducted by the NRC resident inspector in February 1985.

'

The item (8502-10) was generated by NRC Inspection Report

50-445/85-02 dated September. 11, 1985.

The issue was the

apparent incomplete incorporation of a complex change to

the procedure using Test Procedure Deviation (TPD) No

1.

-

One of the changes was omitted from the:TPD, but the

justification was left in. Withou0 the' change being fully

-

implemented, the NRC resident inspector was unable to

determine if the test was satisfacurily completed.

In an

effort to determine why this problem did not appear in the

reevaluation summary report, the NRC followup inspector

interviewed three of the applicant's reevaluators and found

,

-

,

.

._. - .

_ _ _ _

_

_ ._

__ .__ _ _ _ _ . _ - _

.. ~

.

,

'

.a

-

s

',y

'

'

.-

21

4

.

,

.

_

\\s

,

ithat this problem had been previously identified during the

,

'

N

'

reevaluation and was resolved.

The applicant's representa-

tive indicated that-a documented resolution to Item 8502-10

  • *

-

  • *

~

was forthcoming 'o the resident inspector. Since this-

>_

.

problem is.already being tracked..it is'not necessary to

?~

- ,

identify it further.

F

'

.

2

'

l ',

Th'e remaining seven-completed preoperational test data packages

f

reevaluated in accordance with Attachment 1 of the ISAP were not

previously reviewed by the NRC resident inspectors. Therefore,

-

.the followup inspection was conducted on the following data

packages using the same inspection attributes listed in 4.1.7

above:

\\.

'

_

,

(a)

1CP-PT-01-03, "125 Volt DC System," documented in TDR 3927

as satisfactory reevaluated.

i

(b)

ICP-PT-02-01, "118 Volt AC Class 1E Inverters," documented

in TDR 3917 as satisfactorily reevaluated.

<

!

(c)

ICP-PT-02-10, RT1, "480 Volt Class 1E Switchgear and Motor

l

Control' Centers," documented in TDR 3928 as satisfactorily

reevaluated.

i

(d)

ICP-PT-02-17

"6.9 KV and 480 Switchgear Undervoltage

'

Functional Test," documented in TDR 3937 as satisfactorily

1

reevaluated.

,

(e) XCP-PT-07-01, " Control Room Heating and Ventilation System,"

4

!

documented in TDR 3919 as satisfactorily reevaluated.

L

(f)

ICP-PT-58-01, " Residual Heat Removal System," documented in

,

TDR 3904 as satisfactorily reevaluated.

(g) ICP-PT-49-01, " Letdown, Charging and Sealwater System",

>s

documented in TDR 3905 as satisfactorily reevaluated.

'

No NRC violations or deviations were identified.

k.

Inspection for Certain Types of Skewed Welds in NF Supports

.

(ISAP No. V.a)

Status of CPRT Activity

,

>

The reinspection of 60 field fabricated NF supports containing 99

type 2 skewed welds has been completed.

The inspection attribute

i

which was the technical focus of'this issue dealt with geometric and

i

dimensional configurations in locations where a typical fillet weld

'

,

d

i'

>

.

'

,

,k


_f

. , .

_ _ s c, _

__..._.,,_;.__a__._____.,__.__._._,,,_

_ , . _ . _ _ _ _ _ _ _ _ _ _ . _ , _ _ _ _ _ _ , _ _ _ _ .

.

.

22

'

gage measurement was not possible. The welds were reinspected by ERC

inspectors using QI-006. The reinspection identified 14 type 2

skewed welds which deviated from drawing requirements; i.e., an

undersize condition existed.

Subsequent evaluation showed that one

of the conditions was valid, however, the applicable drawing also

showed that the weld was not required for structural integrity.

Another condition was identified as being a vendor fabricated

weldment, thus falling outside of the scope of this ISAP.

However,

the condition is valid and a NCR was initiated and evaluated

separately. That particular evaluation was conducted by identifying

all supports with type 2 skewed welds supplied by that vendor. A

total of 32 supports were identified and a random sample of 7 was

selected for reinspection. -The random sample of 7 supports contained

13 type 2 skewed welds, 12 of which were accessible. No further

undersized welds were identified. The remaining 12 conditions were

evaluated as being valid and NCRs were initiated.

Status of NRC Inspection Activity

The NRC inspector verified that Brown & Root weld inspection

Procedure Nos. CP-QAP-12.1, QI-QAP-11.1-26, QI-QAP-11.1-28 had been

revised to properly address type 2 skewed welds, including their

inspection and subsequent documentation. The NRC inspector

witnessed, in the previous reporting period, reinspections of seven

NF supports; each containing one type 2 skewed weld.

ERC inspectors

identified one undersize weld, which was documented in a NCR. The

results of independent NRC reinspections of type 2 skewed welds are

documented in Appendix F of this inspection report.

No NRC violations or deviations were identified.

1.

Design Consideration for PiJing Systems Between Seismic Category I

and Non-seismic Category I

3uildings (ISAP No. V.c)

Status of CPRT Activity

A list identifying all Units 1, 2 and common piping with a

seismic /nonseismic interface has been completed by Comanche Peak

Project Engineering. The results report has been prepared and is in

the review stage.

Status of NRC Inspection Activity

The review of the list identifying all Units 1, 2, and common piping

with seismic /nonseismic interface has been completed in order to

verify the validity of the list and to assure that no pipe lines have

_.

-

.

.

23

been omitted. The NRC review of the information relative to

the auxiliary steam line and the recommendations to project Piping

-

and Supports Program and/or Design Adequacy Program will not begin

until issuance of the final results report.

No NRC violations or deviations were identified,

m.

Plugwelds (ISAP'No. V.d.)

Status of CPRT Activity

' Reinspection has been completed of (1) component supports and

baseplates, and (2) cable tray hangers, for presence of unauthorized

or undocumented plug welds. Generic design change authorization (DCA)

DCA 5347 permits plug welds in cable tray supports.

ISAP No. V.d

commits to third party review of the adequacy of this DCA.

The

implementation of this review will be inspected by Region IV in a

subsequent report period.

Plug welds in ASME,Section III component

supports are not permitted except by specific engineering authorization.

The reinspection was performed on the following four random samples:

(1) Random sample No. 1 consisted of 64 component supports and

baseplates representing Unit 1 and common.

(2)

Random sample No. 2 consisted of 61 component supports and

baseplates representing Unit 2.

-(3)

Random sample No. 3 consisted of 60 cable tray hangers

representing Unit 1.

(4) Random sample No. 4 consisted of 61 cable tray hangers

representing Unit 2.

The reinspection resulted in the identification of 23 plug welds in

14 cable tray hangers and no plug welds in component supports and

baseplates.

Documentation for all cable tray hangers containing plug welds was

reviewed. The results of this review showed that the plug welds in

13 of the cable tray hangers were authorized and~ documented, while

the documentation for cable tray FSE-00159-4182 was found to be

incomplete. These documentation packages are now undergoing a third

party review by TERA.

Status of NRC Inspection Activity

The NRC inspector witnessed approximately 15% of the 246 reinspections

conducted by ERC; i.e.,15 pipe supprts and baseplates and 23 cable

tray hangers.

Five plug welds in' cable tray hangers were identified

-

.

24

.:-

during the NRC witnessed reinspections.

A review of the respective

documentation packages revealed that these welds were properly

authorized and documented.

In addition, the NRC inspector independently inspected three component

supports and baseplates, and three cable tray hangers, none of which

were within the CPRT random samples.

Four plug welds were found and

verified on two baseplates which were part of a common component

support.

The documentation package was reviewed and it revealed that

the plug welds were authorized and documented.

During review of ISAP No. V.d, the NRC inspector established that the

two random samples of component supports and baseplates were required

to be exclusively ASME Code,Section III supports and baseplates.

However, subsequent to the completion of the CPRT reinspection

effort, a review of the two random samples revealed that just 39 out

of 64 and 35 out of 61, respectively, were actually ASME Code,

Section III supports and baseplates.

The failure to meet the commitments of ISAP No. V.d is a deviation

(445/8513-D-01).

n.

Installation of Main Steam Pipes (ISAP No. V.e)

Status of CPRT Activity

The specific engineering investigation of the main steam line installa-

tion is 100% complete and is undergoing review.

The report describing

the analytical evaluation of stresses and ::upport load changes has

been issued by R. L. Cloud & Associates (RLCA), and has been reviewed

by TERA.

Review and revision of procedures for pipe erection and

placement of temporary and permanent supports as well as engineering

significance of these procedures is also complete.

The TERA draft

results report is currently being reviewed.

Status of NRC Inspection Activity

About 75% of the RLCA stress report has been reviewed for adequacy

with respect to the methods of analysis.

The adequacy of the remainder

of the report cannot be assessed until the supporting computer

output, calculations, and piping models, received onsite September

26, 1985, are reviewed.

The assessment of NCRs and Piping Deviation

Request Forms that RLCA identified as being similar to the main steam

line installation problem has been completed.

All other items will

be reviewed when the final results report is issued.

No NRC violations or deviations were identified.

4

4-

O'

A -

25

'

-

o.

Document Control (ISAP No. VII.a.3)

Problems in"the document control area have been identified both by

the applicant and NRC Region IV.

This ISAP requires verification

that, latest design informat:on has been physically incorporated

and/or. considered for.other activities, as appropriate.

-Status of CPRT Activity

Verification of the above is being accomplished by ISAP Nos. III.d,

" Pre-Operational Testing," and VII.c, "Self-Initiated

Reinspection / Documentation Review Program." The issue coordinator is

>

awaiting input from these.

Status of NRC Inspection Activity

ISAP Nos. III.d. and VII.c. activities are currently being inspected

by NRC personnel.

NRC inspection of this ISAP will be initiated when

it achieves an active status.

p.

Audit Program and Auditor Qualification (ISAP No. VII.a.4.)

Status of CPRT Activity

The ERC issue coordinator reviewed the development of the TUEC Audit

Program dating back to 1978.

Support verification activities for

this time frame were also reviewed.

The results report is in prepara-

tion.

Status of NRC Inspection Activity

NRC inspection of this activity will commence upon issue of the

results report.

q.

Management Assessment (ISAP No. VII.a.5)

Status of CPRT Activity

ERC action has been deferred until results of an INP0 audit made in

July and August 1985 can be utilized by ERC to assess what improvements

should be made to the management assessment program.

Status of NRC Inspection Activity

NRC inspection will be initiated when this ISAP achieves an active

status.

1

.

.

26

r.

Fuel Pool Liner Documentation (ISAP No. VII.a.8)

Status of CPRT Activity

ERC has developed a check list for the review of fuel pool liner

documentation.

Sixty traveler packages have received an initial

review which identified a need to revise the check list to provide a

more indepth check of backup information on welders / welding.

A total

of 300 traveler packages will be selected from the sample population

for ERC review.

Status of NRC Inspection Activity

NRC inspection of this ISAP will be initiated during a subsequent

reporting period.

s.

Onsite Fabrication (ISAP No. VII.b.1)

Status of CPRT Activity

ERC has revised CPP-019, " Cluster Sampling for Issue Specific Action

Plan VII.b.1," to change the sampling method.

The ISAP is with the

SRT for review of the proposed revision.

Review of records or

inspections are being delayed until the SRT review is complete.

The

issue coordinator expects further activity in October.

Status of NRC Inspection Activity

NRC inspection will be initiated when CPRT inspection and review

activities achieve an active status.

t.

Valve Disassembly (ISAP No. VII.b.2)

Status of CPRT Activity

Reinspection of 92 valves from the combined random and engineering

sample of 101 has been completed.' Four DRs were initiated with

respect to installed bonnets having identification numbers which are

different from the identification numbers on their respective QA/QC

documents.

Two of the deviations were dispositioned as being nonsafety

significant by the Safety Significance Evaluation Group (SSEG) based

on a review of the applicable quality records, which revealed that

while the identification numbers differed the bonnets were of the

same type specified for these valves.

1

-~,

- - ,

--n--

c

ry.g

-

.

L

y

,

,

27

.

,

'I

An SSEG effort to find quality records for the remaining two

'

incorrectly identified bonnets was not successful.

The bonnets have,

however, been identified by the SSEG as being of nuclear quality as

indicated by the NP marking observed on them.

ITT Grinnell, the

valve manufacturer, has stated that any nuclear grade valves shipped

t'o the CPSES site have a pressure rating of at least 255 psig.

,

' Maximum line operating and design pressures listed in the line

' designation tables for one of the two. valves in question are less

. than the 255 psig pressure rating and the deviation has been disposi-

tioned as nonsafety significant.

However, the design pressure for

the chemical volume control line associated with the remaining valve

is listed as 300 psig.

The safety significance of this deviation is

being evaluated.

Status of NRC Inspection Activity

.

The associated QI-018 has been reviewed for compliance with the CPRT

Program. Plan and referenced documents.

The ERC sample selection plan

has been reviewed for compliance with the CPRT program plan and has

been verified as having been implemented 'accordingly.

Seven reinspec-

'

'

tions have been witnessed and checklists for the 92 reinspected

valves have been reviewed for proper disposition of descrepancies or

deviations.

All DRs have been reviewed for concurrence and processing

in accordance with the CPRT program plan and ERC written procedures.

-

Safety Significant Evaluation Nos I-M-VALV-44-001 and I-M-VALV-56-001

have been reviewed for concurrence and procedure compliance, iThe

remaining two safety significance evaluations are currently under

review.

No NRC violations or deviations were identified.

u.

Pipe Support Inspections (ISAP No. VII.b.3)

Status of CPRf Activity

The reinspections being performed under ISAP No. VII.b.3 deal with

pipe supports located in' Room 77N and the 42' pipe supports previously

inspected by the TRT.

All other pipe support populations and their

samples are being reinspected under ISAP No. VII.c, " Construction

'

_

Reinspection / Documentation Review Plan."

"

.

One hundred and seventy-eight pipe supports in Room 77N have been

reinspected, resulting in the identification of 229 deviations; 36 of

N

which have been established as valid while the remainder are currently

being evaluated for validity and safety significance by ERC engineering.

ERC has not yet issued a QI with respect to reinspection of the TRT

,

42 pipe supports.

'

F

-

-

-

-

.

.

28

,

Status of NRC Inspection Activity

The NRC inspector has reviewed 01-037 and witnessed the following

seven reinspections to assure compliance with inspection procedure

requirements:

Verification Package No.

Unit No

I-S-PS7N-015

1

I-S-PS7N-027

1

I-S-PS7N-028

1

I-S-PS7N-064

1

I-S-PS7N-144

1

I-S-PS7N-170

1

I-S-PS7N-187

1

During the above reinspections, ERC identified the followint,

conditions to the NRC inspector as subject to evaluation as 70tential

deviations:

I-S-PS7N-015: Broken cotter pin.

.

I-S-PS7N-027:

pipe clamp parallelism was out of tolerance,

.

spherical bearing gap discrepancy, and

clamp bolts did not have locking devices.

~

I-S-PS7N-028:

(a) Pipe clamp parallelism was out of tolerance,

and

(b) locking devices for bolting missing.

I-S-PS7N-064:

Clamp bolts did not have locking devices.

I-S-PS7N-144:

Pipe clamp parallelism was ou' of tolerance,

excessive spherical bearing gap, and

clamp bolts did not have locking devices.

I-S-PS7N-170:

(a) Clamp bolts did not have locking devices, and

(b)cotterpinwasundersize.

Dispositions of the above findings are open items (445/8513-0-09

through 445/8513-0-14).

During review of inspection checklists, the NRC inspectors identified

a deviation from commitment (445/8513-D-02).

CPP-007, Revision 1,

requires the QA/QC Lead Discipline engineer to review the inspection

checklist package for accuracy, completeness, and conformance with

--

_ _ _ . _ . . .

_ . . .

. _ _ . _ -

- - _ _ - .

.___ __. _ _ - _ . . . - _ _ _ _ _ . - _

..

.

'

,a-

'

r

,

h

29

'

i

L

-

,

7

procedure.; Package Not I-S-PS7N-187, which had been approved by the

rq

_

QA/QC Lead Discipline Engineer, did not contain the required number

%

,

of inspection forms for snubber brackets ~and also contained a form-

'

-

for pipe clamp inspections although a pipe clamp did not exist.

'

<

'

~

L

lv.

Construction Reinspection / Documentation Review Plan (ISAP No. VII.c)

o+

(1) Large Bore Piping Configuration

'

.

" Status of CPRT Activ'ity _

i

-

<

.

.

~

.

Reinspection of the 60 random sample large bore piping runs has

-

.

.

,

_

been completed and has resulted in the issuance of 16 DRs.

The

deviations ^ generally involve out-of-tolerance linear measurement

and location variations, insufficient pipe clearance between

'

t

'

'

. sleeves and ' adjacent equipment, and valve identification and

3

,

.

,

flow direction not being verifiable.

Evaluation of four DRs has

,

been completed, with the resultant conclusion that they were

,

nonsafety-related.

Reinspection of an dditional 39 items,

'

.

.

required to complete the engineering s

,,le,

is being initiated.

'

,

Status of NRC Inspection Activity

Inspection of this activity included review of QI-025, Revision 1,

~

,

,

.

!

dated' August 16, 1985, and examination of the sampling process

used for selection of large bore piping runs for reinspection.

1

Three ERC reinspections were witnessed by the NRC inspector;

}

i.e., Verification Package Nos. I-M-LBC0-050, I-M-LBC0-067, and

-

,

I-M-LBC0-074.

'

During the above reinspections, LiiC identified the following

conditions to the NRC inspector as subject to evaluation as

'

potential deviations:

'I-M-LBC0-050:

Expansion joint number not documented and a

flange at end of the pipe run was not installed. Note:

Subsequent

to the reinspection, the verification package was removed from

the sample due to construction being incomplete.

I-M-LBCO-067: Flanged section approximately 4 feet long was not

installed.- A decision had not been made on this verification

package'as of the end of the inspection period with respect to

retention in the sample.

Disposition of this finding is an open item (446/8509-0-01).

,

a

l

,

f'_..~,-,..-.__.l.___.~_._..~____.

.. _ .-. _ _ ._ ..- _ _ , - , .__ __ _ _.,..__,_

--

,

c'

.

'

.

,

,

,

l

- t '.

l'

30

,

.

~

,

,

,

~

.

a

l

( g

'

-It was ascertained, as a result of these inspection findings,

.

that accessibility walkdowns conducted on large bore piping runs

,

,

' '

prior to reinspection do not address a check for completion of

'

construction.

This.isanopenitem(446/8509-0-02).

.

.No NRC violations or deviations were identified.

!

'

- (2). Small Bore Piping Configuration

Status of CpRT Activity

Reinspection of the 60 random sample small bore piping runs has

been completed and has resulted in the issuance of 3 DRs.

The

,

identified deviations are related to out-of-tolerance linear

'

'

piping dimensions and inadequate clearance between the pipe and

adjacent piping. The evaluations'to assess safety significance

have not yet been performed. Reinspection of an additional 35

items required to complete the random engineering sample of

small bore piping runs has not been initiated.

l

l

Status of NRC Inspection Activity

Inspection of this activity included review of QI-026, Revision 0,

dated August 16, 1985, and examination of the sampling process

'

used for selection of small bore piping runs for re'nspection.

Three ERC reinspections were witnessed by the NRC inspector;

i.e., Verification Package Nos. I-M-SBC0-010, I-M-SBC0-052, and

I-M-SBCO-062.

l'

l

During the above reinspections, ERC identified the following

l

conditions to the NRC inspector as subject to evaluation as

l

potential deviations:

I-M-SBCO-052: Flow direction was not indicated on a valve.

I-M-SBCO-062: A linear pipe dimension and a valve stem angle

were not in accordance with the applicable isometric drawing.

l

Dispositions of the above findings are open items (446/8509-0-03

i

and 446/8509-0-04).

No NRC violations or deviations were identified.

(3)~ HVAC Plenums and Ducts

,

e

t

y ;~.

'

.

31

Status'of CPRT Activity

Reinspections.have been performed on 37 of the 60 items in the

random sample associated with the HVAC plenums and ducts.

The

reinspections have identified conditions which necessitated the

issuance of 31 DRs, none of which have been validated at this

time.

Status of_NRC Inspection Activity

E

Inspe.: tion of this activity included review of QI-039, Revision 0,

,

dated August 23, 1985, and examination of the sampling process

used for selection of HVAC plenums and ducts for reinspection.

Four ERC reinspections were witnessed by the NRC inspectors;

'

i.e. , Verification Package Nos. I-M-DUPL-015, I-M-DUPL-017,

I-M-DUPL-019, and I-M-DUPL-040.

,

During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-M-DUPL-015:

Pittsburgh seam construction (level 2) found

,

.rather than required welded seam (level 3).

I-M-DUPL-017:

(a) Inadequate companion angle weld length and

excessive companion angle stitch weld spacing, and~(b) groove in

,

,.

weld from use of a grinder.

v

I-M-DUPL-019: (a) Companion angle thickness found to be 3/16-inch

rataer than specified 1/4-inch; (b) companion angle mating

groove weld had 3/8-inch long underfill, and (c) inadequate weld

length on access door flange corner tabs.

I-M-DUPL-040: (a) Vent lock caps not tight, (b) gasket was not

in full contact in two places, (c) short companion flange weld

lengths in two locations, and (d) excessive gap between companion

angle and duct.

-

Dispositions of the above findings are open items (445/8513-0-15

through 445/8513-0-18).

ERC also noted the following deficiencies outside of the defined

inspection scope:

I-M-DUPL-015:

Bent companion flange screws.

I-M-DUPL-040:

Close proximity of an instrument tubing support

and, bent companion flange screw.

- _ _

..

.

32

Dispositions of the above findings are open items (445/8513-0-19

and 445/8513-0-20).

No NRC violations or deviations were identified.

(4) HVAC Equipment Installation

.

Status of CPRT Activity

Reinspections have been performed on 34 of the 60 items in the

random sample associated with HVAC equipment installation.

The

reinspections have identified conditions which necessitated the

issuance of 55 DRs, none of which have been validated at this

time.

Status of NRC Inspection Activity

,

Inspection of this activity included review of QI-023, Revision 0,

dated August 29, 1985, and examination of the sampling process

used for selection of equipment items for reinspection.

No ERC

reinspections were witnessed by the NRC inspector.

No NRC violations or deviations were identified.

(5) Piping System Bolted Joints / Materials

Status of CPRT Activity

ERC completed 66 reinspections of piping system bolted

joints / materials as of September 24, 1985.

This is from the

combined random and engineering sample total of 74.

Status of NRC Inspection Activity

The following eight ERC reinspections of piping system bolted

joints / materials were witnessed by the NRC inspector:

Verification Pkg. No.

Drawing No.

Flange No.

I-M-PB0M-31

BRP-CS-1-AB-001

1

I-M-PB0M-42

BRP-SI-1-SB-012

1

I-M-PB0M-41

BRP-CC-1-FB-001

6

I-M-PB0M-48

BRP-SW-1-SB-003

1

I-M-PB0M-53

BRP-WP-X-AB-210

1

I-M-PB0M-59

BRP-VA-X-AB-025

2

I-M-PB0M-62

BRP-CH-1-EC-0048

3

I-M-PB0M-63

BRP-CC-2-AB-022

1

,

_

-

. _

p.-

,

i'

t

[

-

33

i

'

i

During the above witnessed reinspections, ERC identified the

l

following conditions to the NRC inspector as subject to evaluation

'

as potential deviations:

'I-M-PBOM-48: Flange No. 1 (Drawing BRP-SW-1-SB-003) had a loose

,

nut.

l

I-M-PB0M-62: Flange No. 3 (Drawing BRP-CH-1-EC-004B) had two

studs without.the required one thread past the outer face of the

!

nut.

t

Dispositions of the above findings are open items (445/8513-0-21

and 445/8513-0-22).

'

--No NRC violations or deviations were identified with respect to

'

-

~

the witnessed activities.

.

During a NRC independent reinspection of Verification Package

.No.~I-M-PB0M-23 (i.e., flange No. 4 on Drawing BRP-SW-2-SB-018),

,

it was'noted that flange No. 6, about 1 foot away from flange

-

,

.

,

,

No. 4 on the same line, had 4 out of 12 studs with loose nuts.

'

e

,

q

,

Flange No. 6 was not part of the ERC population sample.

Further.

e

d

investigation revealed that flange No. 6 had Construction

Operation Traveler No. MP-82-4117-0400 signed off by construction

'

,

.and accepted by QC.

Paragraph 3.5.2.1 in Revision 7 of Brown

'

p

,

'and Root Procedure CPM-6.9E requires an IRN when breaking an

-

inspected flange.

No IRN had been issued to document the

observed condition.

The failure to comply with procedural

'

requirements for accomplishing this activity is a violation.

(446/8509-V-04).

,s

,

(6) Electrical Cables

Status of CPRT Activity

,

ERC completed 49 reinspections of sampled electrical cables as

'

of September 23, 1985.

Status of NRC Inspection Activity

The following three ERC.reinspections of sampled electrical

cables were witnessed by the NRC inspectors:

Verification Pkg. No.

Cable No.

~

I-E-CABL-007

EG104636

I-E-CABL-004

EG123625Z

I-E-CABL-030

ESBI-34

.

.

-.

.-

,

,

4

- 34

.

r,

5

During the above rein ~spections, ERC did not identify any condi-

tions to the NRC inspectors'as subject to evaluation-as potential

'

deviations.

-

.

No NRC violations or deviations were identified.

(7)= Electrical Conduit

,

,

Status of CPRT Activity

^

ERC completed 59 reinspections of electrical conduit as of

September 23, 1985.

Status of NRC Inspection Activity

The following six ERC reinspections of sampled electrical

conduit were witnessed by~the;NRC:

Verification Pkg. No.

Conduit No.

~

I-E-CDUT-027

ESB6-5

I-E-CDUT-035-

C12G03270

I-E-CDUT-044

ECB3-29

I-E-CDUT-076

C12008750

I-E-CDUT-077

C13G05532

I-E-CDUT-086

- C13030044

.During the above reinspections, ERC identified the following

conditions to the NRC inspectors as subject to evaluation as

potential deviations:

I-E-CDUT-027:-(a) Three piece connection fitting on run not

handtight, (b) less than the required 1-inch separation between

conduits ESB6-5 and C14013763, (c) less than the required 1-inch

separation between conduit ESB6-5 and tray T13KECH, and (d)

conduit is 1-inch rather than the required 3/4-inch size.

I-E-CDUT-044: (a) Locknut on conduit CB3-24-29 not tight, and

.

(b) locknut and bushing on conduit CB3-29 were not tight.

ERC

has subsequently validated deviations for these items.

I-E-CDUT-086: (a) Three piece coupling on conduit as it penetrates

ceiling was loose, (b) inside coupling loose but locknut tight,

and (c) less than 1-inch separation between conduit C13030044

and CIPACRZ2.

Dispositions of the above findings are open items 445/8513-0-23.

through 445/8513-0-25).

m c;7 - -

- .

.

k,

'

.

.

-

- -

35

m

.

,

,

'

.

ERC also noted the following deficiencies outside of the defined

inspection scope:

I-E-CDUT-027: (a) 3-inch stub on outlet box was not plugged per

requirements, and (b) an outlet box had two stripped cover

retaining bolts / screws.

I-E-CDUT-077: Cable from conduit C13G05532 to cable tray was

thermal lagged within 2-inches of conduit.

This removed the

2-inch slack requirement specified in Section 5.4 of

Procedure QI-014, Revision 0.

A notification was made by three

part memo SER101 to TUGC0 on September 16, 1985.

NCR

E85-101226SX has been initiated for this out of scope item.

-

Dispositions of the above findings are open items (445/8513-0-26

and 445/8513-0-27).

No NRC violati'ns or deviations were identified.

(8) Cable Trays

Status of CPRT Activity

ERC completed 55 reinspections of sampled cable trays as of

September'23, 1985.

Status of NRC Inspection Activity

c

,

The following ERC reinspection of sampled electrical cable tray

was witnessed by the NRC inspector:

e

Verification Pkg. No.

Cable Tray No.

I-E-CATY-129

T120RBK17-

x

_D'uring the above reinspection, ERC identified the following

condition to the NRC inspector as subject to evaluation as a

potential deviation:

The tray node identification was not

located per the drawing.

Disposition of the above-finding is an open item

(445/8513-0-28).

-

Y

.

L

.

.

t

36

The NRC inspector also noted that an adjacent cable tray,

<

T130RCJ36 had a tray cover which was misaligned and improperly

secured.

TUGCO, when notified of this condition, generated NCR

No. E-85-101361S to initiate corrective action. The NRC

inspectors examined other trays in the general area of this

occurrence and determined that this was an isolated case.

t

No NRC violations or deviations were identified.

(9) Electrical Equipment Installation

Status of CPRT Activity

ERC completed 21 reinspections of electrical equipment installa-

tions as of September 20, 1985.

Status of NRC Inspection Activity

The following nine ERC reinspections of sampled electrical

equipment installations were witnessed by the NRC inspectors:

Verification Pkg. No.

Equipment No.

I-E-EEIN-45

IE15

I-E-EEIN-01

ECSA-1-8890B-1,2 & 3

I-E-EEIN-03

ECSA-1-HV-4725-1, 2 & 3

I-E-EEIN-012

ECSA-1-HV-4172-1, 2 & J

I-E-EEIN-039

ESCA-1-HV-5561

I-E-EEIN-052

ECSA-1-HV-4169-1, 2 & 3

I-E-EEIN-024

I-E-066

I-E-EEIN-029

ECSA-1-8512B

I-E-EEIN-042

ECSA-1-8511B

During the above reinspections, ERC identified the following

conditions to the NRC inspectors as subject to evaluation as

potential deviations.

I-E-EEIN-45: (a) Tag on the inspected penetration flange was

2E15 instead of the required IE15; (b) design change tag number

DCA6881 was attached to the flange, whereas the inspection

package had not identified the design change; and (c) the flange

bolt at location 9 o' clock was not fastened flush with the top

of nut as specified in the supplemental inspection instructions

to QI-010, Revision 0.

DRs I-E-EEIN-45-01 and I-E-EEIN-45-02

have been issued with respect to these findings and NCR

E85-101272SX has been initiated by TUGC0 to address the items.

_-. __ _ --_____ __

_ _ - . __

l

..

.;

,

.

37

L

i

I-E-EEIN-052: The electricil conductor seal assemblies (ECSAs)

were longer than the 20 plus or minus 1-inch requirement.

I-E-EEIN-039: (a) Assembly ECSA-1-HV-5561 had a bend radius

'

.

under the required 5-inch minimum, and (b) length of

ECSA-1-HV-5561 was longer than the 20 plus or minus 1-inch

requirement.

I-E-EEIN-03: (a) Assembly ECSA-1-HV-4725-3 had'a fitting that

- was not handtight, and (b) all three (ECSA-1-HV-4725-1, 2 and 3)

assemblies were longer than the 20 plus or minus 1-inch require-

i

ment.

t

I-E-EEIN-Oli (a) Two assemblies were missing their identification

tags, and (b) flex conduits C1388908-2 and 3 had bend radii

,

under the required 5-inch minimum.

1

I-E-EEIN-012: (a) A three piece coupling on ECSA-1-HV-4172-2 was

not handtight, (b) all three (ECSA-1-HV-4172-1, 2 & 3) assemblies

were longer than the 20 plus or minus 1-inch requirement, and

(c) assemblies ECSA-1-HV-4172-2 and 3 had bend radii that were

under the required 5-inch minimum.

,

Dispositions of the above findings are open items (445/8513-0-29

,

through 445/8513-0-34).'

During witnessing of I-E-EEIN-029 and I-E-EEIN-042, the NRC

-

. inspector r.oted that the verification packages indicated three

-

required cable seal assemblies per valve, but only one was

i

-installed per valve (on the closed limit switch assembly).

This

- anomaly was resolved through another document search.

Two

,

. generic change documents, DCA 19076 and FCN 10589, had been

issued, but not specifically identified against the package

,

drawings.

These change documents revised the number of cable

seal assemblies required per valve to one.

,

The failure by ERC Engineering to reference DCA 19076 and FCN

'

10589 in the verification package is a deviation (445/8513-D-02).

,

s

,

ERC also noted the following deficiencies outside of the defined

inspection scope:

,

I-E-EEIN-01: (a) Conduit identification on runs from JBIC-152G

to ECSA-1-8890B-1, 2 and 3 were illegible; and (b) the solenoid

valve's flex conduit had a missing digit on its identification

tab.

.

,

,

g,

,,e-+,

, ,,,,+---

-y,---,m,-

---m,---r

n,,,

we--,n-ww~-~-

,w.nn

nm

-nrm-en -- -

--w-

,,,-,---n.~~-nwn,,

,

.

..

38

I-E-EEIN-03: Rigid conduit identifications for runs from JBIC-2450

to ECSA-1-HV-4725-1 and 3 were illegible.

I-E-EEIN-024: (a) Conduits entering the top of the penetration

box enclosure were not properly terminated; (b) conduit C12018896

contained a nylon pull rope; and (c) at elevation 832 feet, in

the reactor building near the personnel hatch, the electrical

attachment to the sensing transmitter associated with the

accumulator No. 1 nitrogen insolation valve no. 1-8875A, safety

injection system was loose and appeared to be damaged.

Dispositions of the above findings are open items (445/8513-0-35

through 445/8513-0-37).

No NRC violations or additional deviations to 445/8513-0-02 were

identified.

(10) Instrumentation Equipment Installation

Status of CPRT Activity

ERC completed 57 reinspections at sampled instrumentation

equipment installations as of September 23, 1985.

ERC has attempted on three occasions to implement instrumentation

equipment installation documentation reviews.

These efforts

were unsuccessful due to the need for additional instructions in

the QIs for performing material traceability reviews (tubing).

Status of NRC Inspection Activity

The following three ERC reinspections of sampled instrumentation

equipment installation were witnessed by the NRC inspector:

Verification Pkg. No.

Instrument No.

I-E-ININ-005

1-LS-4795

I-E-ININ-016

1-LS-3378

I-E-ININ-060

1-LS-3376

During the above reinspections, ERC identified the following

condition to the NRC inspector as subject to evaluation as a

potential deviation:

I-E-ININ-005: The anti-torque indicators on the flexible hose

g

connections were misaligned by approximately 45 , indicating

posible excessive twist.

,

. #

.

39

,

4

N

Disposition of the above finding is an open item (445/8513-0-38).

The tubing size also could not be initially verified by ERC on

performing this inspection due to the absence of three required

documents in the verification package.

The ERC inspectors

subsequently obtained the three documents and verified that the

tubing was the correct size.

~

The failure of ERC Engineering to include necessary documents in

the verification package is a deviation (445/8513-D-02).

'

ERC also noted the following deficiency o'tside of the defined

u

,

inspection scope:

i

I-E-ININ-016: Train B (green) channel lighting conduit, at the

entrance to Room 99C, had a loose switch box.

The lights worked

r

intermittently when the box was moved.

Disposition of the above fin' ding is an open item (445/8513-0-39).

No NRC violations or additional deviations to 445/8513-D-02 were

identified.

(11) Reinspection of Concrete Placement

Status of CPRT Activity

A random sample of 60 concrete pours was, selected from a total

population of 7617 individual pours.

Those pours ranged in size

r

from 0.07 cubic yards (for 1 foot x 1 foot x 2 feet blockouts)

'

to several hundred cubic yards (walls, slabs, etc.).

Brown and

Root pour cards identify from 1 to'10 or more individual pours.

.In some cases a pour cards lists, for example, concrete pours

for a floor slab and several small concrete blockouts. . Sample

selection was based on a population of individual pours rather

.

than pour card thus greatly increasing the number of small (less

than 1-cubic yard) concrete placements that are inspected.

Nineteen of the 60 concrete placement inspection packages are

,

blockouts with less than 1-cubic yard of concrete.

A second

random sample of safe shutdown system related concrete pours has

not yet been identified.

Reinspection of the first random sample of 60 concrete pours was

initiated using QI-043, Revision 0, and is approximately 20%

complete.

Two deviations'have been identified relating to

,

m -

_

-

.

,

40

unfilled holes, voids, and debris in the concrete surface.

These deviations are currently being reviewed for validity and

safety significance by ERC Engineering.

Documentation review

procedures have not yet been issued.

Status of NRC Inspection Activity-

The NRC inspectors reviewed QI-043, Revision 0, and witnessed 6

reinspections representing 10% of the first random sample of 60

concrete placements.

ERC DR dispositions are being evaluated by

the NRC inspectors.

The following 6 ERC reinspections were

witnessed by the NRC inspectors:

Verification Pkg. No.

Concrete Placement No.

Unit

I-S-CONC-06

CPC-003-4832-003

C

'~

I-S-CONC-08

CPC-105-M81D-191

1

I-S-CONC-12

CPC-002-I842-068

C

I-S-CONC-41

CPC-101-7853-001

1

I-S-CONC-47

CPC-201-9808-008

2

I-S-CONC-52

CPC-105-5844-001

1

During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-CONC-52: (a) Unfilled holes were identified in two locations,

and (b) insulation was identified in one construction joint.

Disposition of the above findings is an open item (445/8513-0-40).

No NRC violations or deviations were identified.

(12) Small Bore Pipe Supports

Status of CPRT Activity

A random sample of 60 small bore pipe supports (2-inch and

smaller) was selected from a total population of 7947 derived

from the Hanger Installation Tracking System (HITS) as used by

construction site personnel.

The random sample consists of

approximately 68% box frame supports; 20% U-bolt type supports;

and 12% combined snubbers, sway struts and spring can/ constant

supports.

Reinspection is now approximately 95% complete.

Forty-five DRs relating primarily to Hilti bolt embedment, hole

spacing and edge distance in base plates, and pipe clearances,

have been initiated.

Reports are currently being reviewed for

validity and safety significance by ERC Engineering.

c-

'

~

.,

.

E

41

-

.

A second random sample of 60 small bore pipe supports associated

with safe shutdown systems is being selected.

Forty-two supports

from the first random sample have been identified as being

related to safe shutdown systems;.thus, are included in the

second sample's population.

Therefore, an additional 18 supports

will be selected for reinspection pending issuance of the

associated verification packages.

Documentation review of small bore pipe supports was initiated

using QI-020, Revision 0, issued September 16, 1985, and is

approximately 20% complete.

.

Seven DRs pertaining to documentation have been issued and are

currently being reviewed for validity by ERC Engineering.

Status of NRC Inspection Activity

NRC personnel have reviewed QI-019, Revision 1, (physical

inspection ) and QI-020, Revision 0, (documentation review).

Six reinspections have been witnessed representing 10% of the

first random sample.

Approximately 10% of the remaining ERC

-

reinspections are planned to be witnessed by NRC inspectors.

Independent NRC inspections have been initiated.

The following six reinspections were witnessed by the NRC:

Verification Pkg. No

Pipe Support No.

Unit

- I-S-SBPS-009

CH-1-AB-033-002-3

1

I-S-SBPS-019

CC-1-RB-004-007-3

1

I-S-SBPS-028

WP-X-AB-018-012-3

C

I-S-SBPS-035

CH-2-AB-015-008-3

2

I-S-SBPS-038

WP-X-AB-018-013-3

C

I-S-SBPS-049

CC-1-SB-043-009-3

1

During~the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

.

potential deviations:

I-S-SBPS-028: (a) Incorrect bolt hole spacing, and (b) excessive

gap between the pipe and shim.

l

'

I-S-SBPS-035: Insufficient Hilti bolt embedment.

I-S-SBPS-038: Incorrect bolt hole spacing.

,

. , .

-

_. _ . _ _ . - _ . . - . _ .

_ - _ _ - _

.____m._

__m_._._

_.___-__.____m_

__. _ - _ _ . - . _ - _ . . _ _ . . _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ --- _

__.___.__.

-

-a:i.._-m-_.

x

-

- .;

~~

'

.e

,

.

/

9

-

.

-

,

n -

.

'

'

~

-

t

.

,

,

,

s

, .

42-

-

,

,

,

!

. Dispositions of the above findings are open items (445/8513-0-41;

,

,

,

through 445/8513-0-43).

-

,

No NRC violations or deviations ^were identified.

,

(13) Large Bore Pipe Supports - Non-Rigid

Status of'CPRT Activity

'

.

s.

The selected random samples consist of 60 safety-related pipe

. supports from the general population and 22 safety-related pipe

.

'

'

supports-from safe shutdown systems.

Reinspection by ERC is in-

process and is approximately 60% complete.

A total:of 126

. deviations have~been identified of which 31 have been determined

'to be valid. .The remainder are currently being evaluated for

validity and safety significance by ERC Engineering.

4

Status of NRC Inspection Activit.y

~

The NRC inspector has reviewed QI-029 and witnessed the following

' '

, three reinspections to assure , compliance with inspection procedure

requirements:

Verification Pkg. No.

Unit No.

I-S-LBSN-023

l'

I-S-LBSN-031

-

1

.

I-S-LBSN-037

1

Duri$gtheabovereinspections,-ERCidentifiedtherfollowing

conditions to the NRC inspector as subject to evaluation as

potential dev.iations:

.I-S-LBSN-023: .(a) Material identification missing from~one item;

(b) bill of material quantities for two items differed from

'

actual installed quantities; (c) bolt hole location, attachments

to base plate, and a component member location were out of

-

'

tolerance; (d) U-bolts had zero clearance; (e) base plate

violated' perimeter contact requirements; (f) locking devices on

nine 2-inch diameter bolts were missing;.(g) item 13 Hilti bolts

violated embedment requirements; (h) snubber extension piece

thread engagement could not be determined; (i) paint on spherical

bearings; (j) no welder identification.on integral Attachment

, ,

,

No. 4; and (k) seven undersize welds were identified.

-

I-S-LBSN-037: (a) Clamp bolts did not have locking devices, and

'

(b), paint was identified on spherical bearings.

e'

1

i

'

+

,

.,

'

s

,

'

p

>

-

-

, _

__

.

_ .

,

>

f

8

'

43

>

>

.

Dispositionso'fthe1aboveIindingsareopenitems(445/8513-0-44

and 445/8513-0-45).

No NRC' violations or deviations were identified.

(14) Large Bore Pipe Supports - Rigid

Status of CPRT Activity

The selected random samples consist of 61 safety-related pipe

supports from the general population and 28 safety-related pipe

supports from safe shutdown systems.

Reinspection by ERC is in

process and is approximately 57% complete.. A total of 90

deviations have been identified of which 25 have been determined

to be valid.

The remainder are currently being reviewed for-

validity and safety significance by ERC Engineering.

Status of NRC Inspection Activity

The NRC inspectors has reviewed QI-027 and witnessed the following

four reinspections to. assure compliance with inspection procedure

requirements:

Verification Pkg. No.

Unit

I-S-LBSR-047

1

I-S-LBSR-029

1

I-S-LBSR-048

1

I-S-LBSR-053

1

During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-LBSR-047: (a) Inadequate thread engagement for Richmond

insert; (b) undersize fillet weld; and (c) cotter pin not

installed properly.

I-S-LBSR-029: Missing locking devices and dimensional

.

discrepancies.

I-S-LBSR-048: Shim not located properly and minimum clearance

'

discrepancies ~.

I-S-LBSR-053: Installation. tolerances were discrepant.

Dispositions of the above findings are open items (445/8513-0-46

through 445/8513-0-49).

.

L

.

.

.

44

During the reinspection of I-S-LBSR-047, the NRC inspector

identified two deviations from commitment in the areas of

verification package preparation adequacy and reinspection /

. verification. The responsible QA/QC discipline engineer indicated

.that Richmond inserts were not applicable for inspection on the

~ hecklist, when_both the bill of material and the design drawing

c

-listed Richmond inserts as being present (445/8413-D-02).

'

Paragraph 5.0 of QI-027, Revision 0, identifies note 30 as an

applicable inspection note which requires the inspector to

document any item that appears out of the ordinary as related to

construction of'the inspected item.

The ERC inspectors failed

to. document the existence of four 9/16" diameter drilled holes

in item 2 of ASME pipe support Mk. No. CT-1-053-436-C52R that

were not shown on the design drawing (445-8513-D-03).

It was

additionally noted that ASME N-5 Data Report activity was

complete for this support.

(15) Containment Liner and Tank Stainless Steel Liner

Status of CPRT Activity

'

A minimum number of 60 liner packages will be inspected using

QI-031, Revision 0.

Ninety-one packages have been issued and

inspection is approximately 80% complete based on the minimum

sample of 60.

Forty-seven deviations have been identified,

primarily due to excessive weld reinforcement. These deviations

are currently being reviewed for validity and safety significance

by ERC Engineering.

Status of NRC Inspection Activity

The NRC inspectors has reviewed QI-031, Revision 0, and witnessed

four reinspections.

ERC DR dispositions are being evaluated by

the NRC inspector. The four ERC reinspections witnessed by the

NRC were as follows:

Verification Pkg. No.

Joint No.

Unit

I-S-LINR-03

P-290

1

I-S-LINR-30

P-356

1

I-S-LINR-50

P-366

1

I-S-LINR-60

P-387

1

I-S-LIRN-06

17E

1

I-S-LINR-13

P-57

1

1-S-LINR-21

10E

1

I-S-LINR-51

15E

1

I-S-LINR-55

15-16(B2)

1

.

45

During the above reinspections, E;M identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-LINR-03: Excessive weld reinforcement.

I-S-LINR-30: Excessive weld reinforcement.

I-S-LINR-60: (a) Excessive weld reinforcement, (b) weld undercut,

and (c) unacceptable weld seam surface.

I-S-LINR-06:

Excessive weld reinforcement.

I-S-LINR-13:

Excessive weld reinforcement.

I-S-LINR-51: Unacceptable weld seam surface.

I-S-LINR-55: Weld undercut.

Dispositions of the above findings are open items 445/8513-0-50

through 445/8513-0-56).

During the reinspection of verification package Nos. I-S-LINR-06 and

I-S- LINR-51, the ERC inspector noted that the responsible QA/QC

discipline engineer wrote "NA" for not applicable on the checklists

for two base material local contour attributes. The attributes were

found during the physical inspection by the ERC inspector to be, in

fact, inspectable. New checklists were requested by the ERC inspector.

The failure of the discipline engineer to issue correct verification

packages is a deviation (445/85-13-0-02).

6.

Exit Interview

An exit interview was conducted on October 4, 1985, with the applicant

representatives denoted in paragraph 1 of this appendix. During this

interview, the NRC inspectors summarized the scope and findings of the

inspection. The applicant acknowledged the findings.

_ _