ML20151N898

From kanterella
Jump to navigation Jump to search
Const Insp Repts 50-445/85-13 & 50-446/85-09 on 850823-0930. Violations Noted:Failure to Provide Protection of Equipment Stored in Place & Failure to Establish Procedures Re Control of Deleterious Matl Around Stainless Steel Piping
ML20151N898
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/23/1985
From: Barnes I, Kelley D, Norman D, Phillips H, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20151N849 List:
References
50-445-85-13, 50-446-85-09, 50-446-85-9, NUDOCS 8601030186
Download: ML20151N898 (8)


See also: IR 05000445/1985013

Text

n

4

.

.

APPENDIX D_

.

CdNSTRUCTIONINSPECTIONREPORT

'

,

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Reports:

50-445/85-13

Permit: CPPR-126

50-446/85-09

CPPR-127

Dockets:

50-445

Category:

A2

50-446

,

Applicant: . Texas Utilities Electric Company (TUEC)

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

Facility Name:

Comanche Peak Steam Electric ^ Station (CPSES), Unit 1 and 2

-

Inspection At:

Glen Rose, Texas

'

F

' Inspection Conducted: August 23 through September 30, 1985

y

r'

-

-

Inspectors:

97,

/2//7/47~

'~

-

R.. S. Phil' lips, Sehior Residenc Reactor

Date

'

Inspsctor (SRRI), Construction, Region IV

,

,

i:

CPSES Group (paragraphs 1,2,3,4,5,6,

.,

.and 9)

,

s

-

,

.-

,

Noa W

n/drs'

'

_'

D. L. Kelley, SRRT', Op'e}atio

, Region IV

Date'

~

CPSES Group (paragrapns 1,

, and 9)

j

,

E wm&~

i2//?As-

D. E. Norman, Reactor Inspector

'Date

Region IV CPSES Group

(paragraphs 1, 2, 4, 5, 6, 7, and 9)

- ,-

8601030186 B51224

'

-

PDR

ADOCK 05000445

G

PDR

. %

<,17

4

(.__.'

m

_

, _ .

'

,

. .

.

2

'

Consultant:

Parameter-T. H. Young

,

Rev.iewed'by:

Nwo -

/n,// 7/W

'

I. Barnes, Group Leader, Region IV CPSES Group

Date

Approved:

NI

/2/27//f

.T. F. Westerman, Chief, Region IV CPSES Group

Date

Inspection Summary

Inspection Conducted:

August 23 through September 30, ~1985

(Report 50-445/85-13)

Areas. Inspected:

Routine, unannounced inspections of Unit 1 which included a

review of plant status and applicant actions on previous NRC inspection

findings.

The inspection involved 24 inspector-hours onsite by 2 NRC

inspectors and one consultant.

'

Results:

Within the two areas inspected, no violations or deviations were

identified.

Inspection Conducted:

August 23 through September 30, 1985

(Report 50-446/85-09)

Areas Inspected:

Routine, announced and unannounced inspections of Unit 2

which included review of plant status; plant tours; installation / storage of

reactor pressurizer and piping; structural welding on CRD support platform;

review of. welding procedures; inspection of welding of safety injection piping;

'

review of electrical /QC procedures and' applicant actions on previous NRC

inspection findings.

The inspection involved 100 inspector-hours onsite by

3 NRC inspectors.

,

Results: Within the eight areas' inspected, two violations (failure to

establish procedures which describe control of. deleterious materials'around

stainless steel piping and NSSS equipment, paragraph 4.a; failure to provide

protection of equipment stored in place, paragraph 4.b) were identified.

..

A

7

s

e

3

DETAILS

1.

Persons Contacted

J. Merritt, Assistant Project General Manager, TUGC0

C. Welch, QA Supervisor, TUGC0

L. Smith, Engineer, Brown & Root (B&R)

W. Baker, Engineer, B&R

B. Wright, Engineer, B&R

The NRC inspectors also interviewed other applicant employees during this

inspection period.

2.

Construction Status

The percentage completion for Unit 1 and 2 is 99% and 77%, respectively.

Current work on Unit 1 relates to Comanche Peak Response Team (CPRT)

activities.

Unit 2 work on large and small bore piping is about 95%

complete.

Electrical cable trays are 100% complete while seismic conduit

dnd supports are about 97% and 89% complete, respectively.

Cable pulling

is about 78% complete.

The heating and cooling ductwork and supports are

about 93% and 60% complete, respectively.

3.

Applicant Actions on Previous NRC Inspection Findings

'

a.

(0 pen) Unresolved Item (445/8226-06):

Excessive deflections in

supports.

The NRC inspector reviewed a study entitled " Piping Seismic Analysis

- Parametric Study of Support Stiffness" dated March 31, 1983, which

addressed stiffness and deflection questions and justified the

.

equipment as designed.

This item will remain open pending completion

of NRC staff review of CPRT/ Stone & Webster (S&W) design activities.

b.

(0 pen) Unresolved Item (445/8226-07):

Stress analysis of pipe

'

support No. CC-1-107-008-E23R.

The NRC inspector reviewed the background of this item on page 41 of

NRC Inspection Report 50-445/82-26, 50-446/82-14, which showed the

stiffness of the support to be 1/8th of the generic stiffness used in

the original calculations.

However, an NRC consultant (Dr. Chen)

'

stated (during testimony before the ASLB in May 1983 Questions and

Answers 19 and 20) that the value was 1/360th of the generic value.

In addition, he stated that the mounting plate was increased to a

thickness which increased the stiffness to an acceptable level.

i

,

.

4

Subsequently, TUGC0 requested and made further modifications to mount

the pipe support off of square tube steel instead of the stairway

platform I beam.

The NRC inspector requested the documentation for

this modification but it was not immediately available.

This item

remains open pending a review of this documentation and completion of

NRC staff review of CPRT/S&W design activities.

c.

(0 pen) Unresolved Item (445/8226-05): Moment restraints and local

pipe stress due to welded stanchions on pipes.

The NRC inspector reviewed pages 38-40 of NRC Inspection

Report 50-445/82-26 and 50-446/82-14 concerning this technical issue.

In an affidavit dated October 14, 1983, page 1, Questions and

Answers, NRC consultant (Dr. Chen) considered the applicant's work in

this area acceptable.

This item will remain open pending completion

of NRC staff review of CPRT/S&W design activities.

4.

Routine Plant Tours (Unit 2)

a.

At various times during the inspection period, the NRC inspectors

conducted general tours of the reactor building, safeguards building,

and electrical building.

During the tours, the NRC inspector

observed housekeeping practices, preventive maintenance on installed

equipment, ongoing construction work, and discussed various subjects

with personnel engaged in work activities.

The NRC inspector observed that the cleanliness controls in the

reactor building does not appear to be well defined.

For example,

during the previous inspection period (June 22 through August 22,

1985), the NRC inspectors found evidence of chewing tobacco and

-

cigarette butts on.the 905 feet elevation of the reactor containment

building (RCB).

This was pointed out to the applicant management at

the previous exit interview.

During this inspection period,

cigarette butts were again found in the area around the pressurizer

head on this 905 feet elevation, on the top of the control rod drive

seismic support platform, and scattered throughout the RCB.

The

applicant is not committed, however, to the housekeeping practices

defined in ANSI N45.2.3.

Gibbs and Hill Specifications 2323-MS-100 and 2323-MS-101 dated

July 5, 1984, address the subject'of contamination through use of

temperature crayons, machinery lubricants / coolants, instruments

containing mercury, temporary plugging with rags, taping and the

prohibition of halogens, copper, low melting point metals (lead,

zinc, cadmium, tin, antimony, bismuth, sulfur and mischmetals).

The NRC inspector contacted the B&R welding organization to inquire

where the control of such materials was discussed (QA or working

.

.

5

procedures).

After a brief review they found that one paragraph

discussing the subject of mercury had been unintentionally deleted

from General Piping Procedure CP-CPM-69, Appendix E.3.2.

Personnel

in the applicant's site QC department were also contacted to identify

procedures which address protection and preservation.

B&R Procedure

MCP-10, Revision 9, dated July 2, 1985, was identified as the

procedure with such controls.

These procedures do not adequately

addr c.is material / personnel control to prevent contamination and also

do not reference use of only materials which have been procured in

accordance with Gibbs & Hill sper.ification requirements.

^

This failure to establish such proceduies is a violation of

Criterion XIII of 10 CFR Part 50, Appendix B (446/8509-V-02).

s

b.

In reactor building room 16 near the bottom of the pressurizer, the

NRC found a wooden two by four which had been laid across 3/4-inch

line RC-2-095-2501-R-2 to serve as a step.

The wooden step was about

one.and one half feet from where this line enters the tank.

The use

'

of such personnel supports is prohibited without engineering

approval, and is a violation of Criterion V of 10 CFR Part 50,

Appendix B, and B&R procedure MCP-10 (446/8509-V-03).

c.

Cleanliness in the area of the pressurizer from the 905 to 854 feet

elevation was inspected. As discussed previously,, tobacco was

observed and a sign was also noted in the reactor building elevator

which prohibited tobacco or food at the 905 feet elevation.

At the

bottom of the pressurizer a used grinding wheel and wire brush were

found, yet no visible work had recently occurred.

Since such

uncontrolled or unaccounted for tools could potentially be used

interchangeably on stainless and carbon steel, this subject was

brought to the applicant's attention.

Region IV will continue to

monitor the applicant's cleanliness controls.

5.

Reactor Pressurizer and Piping, Housekeeping and Welding

The NRC inspector reviewed FSAR Volume VI, Section 5.0, " Reactor Coolant

System & Connected Systems", Subsection 5.4.10, which describes the

pressurizer system design bases, design analysis and performance

characteristics, test, and inspection.

" Flow Diagram Reactor Coolant System Sheet 2 of 2" shown on Drawing

No. 2323-M2-0251, Revision CP-1, was used to physically trace all piping

entering into the pressurizer dome. -Both pressurizer spray lines were

traced to the 860 foot elevation and one was traced to the cold leg of

Loop 4 of Steam Generator No. 4.

All piping was traccd up to the inlets

of the three safety relief valves (2-8010A, B and C) and two power

operated relief valves (2 PCV-455 and 456).

Approximately 100 welds

within this system were visually inspected for surface condition.

No

- . _ ~

_.

.

.

>

6

'

>

unacceptable surface conditions were found in this system except as

follows:

i

The NRC-inspector determined that welding performed on a ,b,:nger base plate

located above ' completed weld No. 42 in 6-inch line RC-2-09b-2501R-1 had

caused deposition of carbon steel weld spatter on the surface of the

stainless steel piping line.

This failure to adequately protect equipment

from construction damage is a violation of Criterion V of 10 CFR Part 50,

Appendix B, and B&R Procedure MCP-10, Revision 9, dated July 2, 1985,

'

(446/8509-V-03).

6.

Structural Steel Welding on Control Rod Drive Seismic Support

Platform

,

i

The NRC inspector observed structural welding on the platform.

Messenger

, wire posts were installed on top of the platform and NDE personnel were

liquid penetrant testing the welds which connected these posts to the top

.

aof the platform-in accordance with Drawing 2323-52-0599-19, Revision 0.

l

The drawing symbol showed a 1/4-inch fillet weld all around the post base

which connected it to the platform.

The liquid penetrant test was

'

accomplished in accordance with B&R Procedure QI-QAP-10.2-1, Revision 3,

i

February 18, 1983. Welding Data Card Serial No. 004167, Traveler

MW 85-7330-6802, and Design Control Authorization 23203 R.0. controlled

these work activities.

i

The applicant's inspectors had inspected weld No. 2 for cleanup, fitup,

preheat, final ultrasonic testing (IOM 25944), and liquid penetrant

testing was in process.

Welding was accomplished in accordance with Weld

Process Specification 11032.

4

No violations or deviations were identified.

7.

Safety-Related Piping

,

a.

Procedures and Instructions

.This inspection was conducted to verify the adequacy of documents

used by the site contractor for field welding of safety-related

piping.

The NRC inspector reviewed QA and other welding related

documents to determine whether QA plans, instructions, and procedures

,

had been established and whether procedures had been established for

preparing, qualifying, distributing and revising welding procedure

specifications (WPSs).

Two WPSs and supporting procedure

qualification records (PQRs) were reviewed to determine whether

stated welding variables and mechanical tests complied with

requirements of the applicable editions of Sections III and IX of the

ASME Code. .The following documents were reviewed during the

~ inspection:

i

a

e

e

-- , - , , -

y

,

w,-

r-,-

, , - - - - - - -

, , - , - . - - . - - , - . -

--

,,,..ne

-

~.y-

-- --.-- -

_.

.

.

7

B&R QA Manual, Section 10, October 31, 1984, " Control of Special

Processes"; CP-CPM-6.9, Revision 2. November 7, 1980, " General Piping

Procedure"; QI-QAP-11.1-26, Revision 17, August 17, 1985, "ASME Pipe

Fabrication and Installation Inspections"; WES-030, Revision 2,

July 19, 1984, " Specification for Control, Testing and Documentation

of Weld Procedures Qualifications";

Index of CPSES Welding

Procedures, April 15, 1985; WPS 88012, Revision 7, October 10, 1984

and PQR 0803AB203, Revision 6, March 14, 1980, " Gas Tungsten Arc and

,

Shielded Metal Arc Process"; and WPS 88032, Revision 9, October 22,

1984, and PQR 0808BB112, Revision 4, February 12, 1981, " Shielded

Metal Arc Process."

b.

Observation of Work

The NRC inspector inspected a 24-inch line at the 815 feet

elevation.

At this location, the pipe exits the refueling water

storage tank and goes down into the pipe tunnel as shown on Drawing

2323-A2-0500. Work had been stopped on SI-2-YD-02.2 because of a

mixup on paperwork for welding one 1-inch plate identified as

S1-2-0029-412-Y42R.

Subsequent fuitowup of this item revealed that

Nonconformance Report (NCR) 18651 had been written to correct the

paperwork problem.

No violations or deviations were identified.

8.

Review of QA Manual - Electrical

The NRC inspector began a review of the applicant's QA/QC program and

procedures relating to the installation of electrical components and

cables.

The areas covered in the review are organizational structure and

personnel; audits; quality requirements; work and quality inspection

procedures; control of material; control of processes; corrective action;

document control; test control and control of test equipment; quality

records; and onsite design control.

This portion of the inspection was conducted to identify the QA/QC program

specifics and procedures which pertain to the installation of electrical

components and cables.

The program and procedures were then compared to

the commitments contained in Sections 7, 8, and 17 of the FSAR and

10 CFR 50, Appendix B, to determine if the program and procedures

adequately addressed the required criteria.

To date, the following have been_ reviewed; Sections 7, 8, and 17 of the

applicant's FSAR; TUGC0/TUSI(now TNE) CPSES QA' Plan; B&R Quality Assurance-

Manual; B&R Quality Assurance Procedures Manual; and implementing

Procedures CP-QP-2.0, Revision (R)-1; CP-QP-2.1, R-18; QI-QP-2.1-23, R-0;

CP-QP-2.2; R-E, CP-QP-3.0, R-15; CP-QP-6.0, R-8; CP-QP-7.1, R-12;

CP-QP-11.3, I-4; QI-QP-11.3-24, R-14; QI-QP-11.3-25, R-23; and

QI-QP-11.3-26, R-23,-(in part).

- . ;

.,

o

e

,

.

-

.

,

'

r

^

,

w:

+

,

,

'

  1. ',

{;. ,-

s

- *

3

- 8

'

'

'

-

,

Ond'other, aspect that will be included in the present and subsequent

.> .. :

reviews and. inspections will be to determine if the " lessons learned" on

'

Unit.No. 1 have been incorporated.into the Unit No. 2 QA/QC inspection

programs and procedures

Thus far, review has begun in the following

areas:~ organization and structure (personnel is ongoing); quality

requirements; work.and quality' inspection procedures; corrective actions;

document control; and quality records.

The remaining areas are yet to be

. started. ~To date, no problem areas have been encountered.

No' violations or deviations were identified. ~

-

' 9.

~ Exit Interview

,

An' exit interview was conducted October 4, 1985, with the applicant

.-representatives identified in paragraph 1 of Appendix E of this report.

,

During this interview, the NRC inspectors summarized the scope and

>

findings of the inspection.

The applicant acknowledged the findings.

.

8

9

6

b

A' '

,

+

__ -

4

r

,

+

.6

.

-I

p,

'

.,

-

l

'

_

'

i i

r

av

.

.

4

s

>

?

. '_

e

'

J

y

fr

Uj

+

'

1

'

.

4

A

. %y

-c-,---,p

,- -+ ,

N,

i--.

se-

a

e---.

-, , ,- , - - - , . .

-4

--

q

- . - - - - , , . , - - -