Std Order for DOE Work: Review of Pumps & Valve Inservice Testing Program for OL Plants, Issued to Inel.Statement of Work Encl
ML20151H135
Person / Time
Site: Fermi, Susquehanna, Summer, Diablo Canyon, San Onofre, Comanche Peak, LaSalle, 05000000, Shoreham
Issue date: 11/09/1981
From: Vollmer R
Office of Nuclear Reactor Regulation
To:
Shared Package
ML082390697 List:
References
CON-FIN-A-6430, FOIA-88-99 NUDOCS 8112100572
Download: ML20151H135 (7)


Text

.

i NRC s ew 171 v s Nuct a An at on a tom i covvissioN t wot u svust a 12 78 20-82-011 STANDARD ORDER FOR DOE WORK IS$Ul O T O IOOE Oiful 115UE 0 8Y INRC OH.ce)

ACCOUNTINO CIT ATION ldaho Operations Office Office of Nuclear Reactor apaaoa=iatioH 5vusoc Regulation, DE 31X0200.201 ma Hvust a 20-19-04-09 PEMORMING ORG ANIZ ATION AND LOCATION

* g Idaho National Engineering Laboratory g

Idaho Falls, Idaho WOR 4 PC RIOO. TMi$ ORDE R FIN TITLE Fixe 0 O lESTiM ATED L Review of Pumps and Valve Inservice Testing Program for FROu To Operating License Plants 5/1/81 11/30/82 OBLIG ATION AVAILABILITY PROVIDED BY:

7 N' P IN~'

A In 5 0ADER 5

8 YYit' 06 OH OE R S at Act O F HIOH 10 T HIS D A T E WIT M IME PERf OAMING ORG ANIZ AflON

~~

U'40E R T h E S AME APPROPRI ATION SYMBOL" AND THE flR$7 F OUR OlGITS Of THE

'n,' _ 4 t= Au NUMBE R" CIT E D ABOvf 6,299,000 C TOT AL ORDERS TO OATE iTOT At A a 8' s6,299,000 O AYCvN T iNCLUCE 0 iN ' C'* APPLIC ABLE TO THE 8IN NUMBE R" CsTE D IN THis ORCE R

$ F IN A'.Ci A L F '.E x t BILITY C FUNOS ?.1LL NOT BE REPROGR AMMED BETWEEN FINS LINE D CONSTITUTE.e A LIMITAflON ON O8 LIGATIONS AU TMORIZ E D G FUNOS MAY BE REPROGR AMMEO NOT TO E xCE ED 210% OF FIN LEVE L UP TO S50K LINE C CONSTITUTES A limit ATION ON OSLiGAteONS AUTHORIZE D

$7AND ARD TEnMs AND CONDITIONS PRoVIDED DOE ARE CONSIDERED PART OF THl$ ORDER UNI.E$s OTHE*tWISE NOTED.

A? f ACHYENTS THE FOLLOWING AT TACHMENTS ARE HE RE 8Y SECURITY MADE A PART OF THIS ORDE R.

O WORK ON THis ORDE R IS NOT CL AL$18 tED C ST ATEME NT OF WORx (Modi (jCation)

C WORK ON TMIS ORDER INv0Lvt s CL ASSi8iED C ADDITION AL TE RMS AND CONoiTIONS INFORMATION NRC 8 0AM 187 t$ AT T ACHf D

] OTHER l aEvAnss

[ This order modifies the !NEL proposal dated June 11, 1981 and requests that a revised i

pr0?osal that reflects the entire effort of this project be submitted within 30 days.

Af ter acceptance, please send to the NRC Office of the Controller, ATTN: D. Dandois, and provide a copy to the Of fice Qf Nuclear Reactor Regulation, D. Corley.

ISSUING _A4T HORITY ACCE PTING ORG ANIZ ATION l

C. 4. l ;...

Vollmc/

y sac.N a t vat f

.._J.

W Rich 3rd H.

g.....

/

ime i Director, Divicion of Engineering t

o m ii i

,, n c..... m. a u i l

c ' mnn&

M_

j

_cr

%k N.

6 Pw -.-

i-1 j*:

ENCLOSURE 1 STATEMENT OF WORK

Title:

Review of Pump and Valve Inservice Testing Program for Operating Licensing Plants FIN #: A6430-BI,R Number:

20-19-04-09 Technical Monitor: Anthony.J. Cappucci, Jr., 492-9476 Cognizant Branch Chief: Robert J. Bosnak, 492-7456 Add the following tasks to the original Statement of Work.

SPECIFIC WORK REQUIREMENTS Est. Completion Task 4.

Diablo Canyon Date Estimated level of Effort - FY82:

0.3 my Subtask A.

Review the IST program and the relief requests for Diablo Canyon. Provide the 11/1/81 evaluation and the requests for additional information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified, 11/30/81 Subtask C.

Prepare and sobmit the summary report of the results of the review.

1/30/81 Task 5.

San Onofre 2 and 3 Estimated level of Effort - FY82: 0.3 my Subtask A.

Review the IST program and the relief requests for San Onofre 2t,3.

Provide the 11/6/81 evaluation and the requests for additional information or clarification.

Subtask 8.

Meet with the applicants to clarify and resolve the deficiencies identified, 11/30/81 Subtask C.

Prepare and submit the sumrary report of the results 2/15/82 l

of the review.

l L.

2 E s t.. Comple tion Task 6.

Summer 1 Date Estimated Level of Effort - FY82: 0.3 my

' Subtask A.

Review the IST program and the relief requests for Sumer 1.

Provide the 12/15/81 evaluation and the request for additional information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

2/1/82 Subtask C.

Prepare and submit the summa y report of the results of the reivew.

4/l/82 Task 7.

LaSalle 1 and 2 Estimated Level _of Effort - FY82: 0.3 my Subtask A.

Review the IST program and the relief requests for LaSalle it.2.

Provide the 3/1/82 evaluation and the request for additional information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

4/1/82 Subtask-C.

Prepare and submit the summary report of the results of the review, 6/1/82 Task 8.

Shoreham Estimated Level of Effort - FY82:

0.3 my Subtask A.

Review the IST program and the relief requests for Shoreham. Provide the 3/15/82 evaluation and the request for additional information or clarification.

' /.-

-3 Est. Completion Date Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

4/15/82 Subtask C.

Prepare and submit the summary report of the results of the review.

6/15/82 Task 9.

Fermi 2 Estimated Level of Effort - FY82: 0.3 my Subtask A.

Review the IST program and the relief requests for Fermi 2.

Provide the evaluation and the request for additional 5/1/82 information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

6/1/82 Subtask C.

Prepare and submit the summary report of the results of the review.

8/1/82 Task 10.

Susauehanna 1 and 2 Estimated Level of Effort - FY82: 0.3 my Subtask A.

l l

Review the IST program and the relief l

requests for Susquehanna 1&2. Provide the 7/1/82 evaluation and the request for additional information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

8/I/82 Subtask C.

Prepare and submit the summary report of the results of the review.

10/15/S2 i

j '

4 Est. Completion Date Task 11. Comanche Peak 1 and 2 L

Estimated level of Effort. FY82: 0.3 my Subtask A.

Review the IST program and the relief I

requests for Comanche Peak.

Provide the 8/15/82 evaluation and the request for additional information or clarification.

Subtask B.

Meet with the applicants to clarify and resolve the deficiencies identified.

10/1/82 Subtask C.

Prepare and submit the surtrnary report of the results of the review.

11/30/82 LEVEL OF EFFORT AND PERIOD OF PERFORMANCE l

The additional level of effort for this modification is estimated at 2.4 staff l

years over a 1.2 year period ending November 30, 1982. Twelve staff weeks has been estimated as the average effort per plant review.

MEETINGS AND TRAVEL l

It is estimated that one meeting with the applicant and URC staff of two to three days duration will be required for each task. These meetings will be held at either the applicant's office, the plant site, or in Bethesda, MD.

NRC FURNISHED laTERIALS The NRC will provide the contractor with one copy of the inservice testing program and one set of piping and instrumentation diagrams corresponding to the safety related systems and components addressed in the IST program for nach plant under this work order.

4

F T>

  • ENCLOSURE 2 PROPOSAL CONTENT The minimum items required in all proposals are:

1.

Performing organization's name and location.

2.

FIN Title, Fin Number, and Bl.R Number (NRC's) (as on statement of work).

3.

Performing organization's key personnel, program manager, or principal investigator, their resumes and FTS phone number.

4 Background (definition of the problem including the objective (s) to be attained).

5.

Work to be performed (Provide a concise description of tasks to be performed and expected results for the period of performance.

Note technical data requirements, potential problems, and other technical information needed to fully explain the effort. Highlight changes from prior authorized 50W's, if any, identify changes in performance, schedule, orcosts).

6.

Identify major subcontracts, including consultants.

7.

Costs estimated to be incurred by DOE contractors, subcontractors, and consultants.

List by fiscal year to completion:

a.

ManyearsofTechnicalSupport(MTS) b.

Costs:

(1) Direct Salaries (Labor) for HTS (2) Material and Services (excluding ADP)

(3) Total ADP Support (4)

Subcontracts (5) Capital Equipment (6)

DirectTravelExpense(Foreigntravelmustbeshownseparately)

(7)

General and Administrative Expense (Jnclude indirect labor cost) c.

Total Estimated Cost; l

8.

Forecasts:

H; k-tone Chart for accomplishing the work.

,.t'

.t.

~

b.

Planned monthly rate of costs by fiscal year.

This may be provided with the first report of an authorized program if not known at time of proposal submittal. At the beginning of each subsequent year, reports should include the planned monthly rate of costs for the ensuing year.

9.

Conflict of Interest:

In order to assist the Connission in its evaluation, the DOE Contracting '

Officer shall describe any significant contractual and organizational relationships of the DOE, its contractor, their employees, or expected subcontractors or consultants on this proposal, with industries regulated by the NRC (e.g. utilities, etc.) and suppliers thereof (e.g. architect engineers end reactor manufacturers, etc.) that might give rise to an apparent or actual conflict of interest.

10.

Reportird nequirements (as on statement of work).

_