IR 05000263/2020012
| ML20147A637 | |
| Person / Time | |
|---|---|
| Site: | Monticello |
| Issue date: | 05/26/2020 |
| From: | Aaron Mccraw NRC/RGN-III/DRP/TSS |
| To: | Conboy T Northern States Power Co |
| References | |
| EA-13-109 IR 2020012 | |
| Download: ML20147A637 (9) | |
Text
May 26, 2020
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - INSPECTION OF THE IMPLEMENTATION OF EA-13-109: ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE HARDENED CONTAINMENT VENTS CAPABLE OF OPERATION UNDER SEVERE ACCIDENT CONDITIONS REPORT 05000263/2020012
Dear Mr. Conboy:
On May 7, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Aaron T. McCraw, Team Leader
Technical Support Staff
Division of Reactor Projects
Docket No. 05000263 License No. DPR-22
Enclosure:
As stated
Inspection Report
Docket Number:
05000263
License Number:
Report Number:
Enterprise Identifier: I-2020-012-0008
Licensee:
Northern States Power Company, Minnesota
Facility:
Monticello Nuclear Generating Plant
Location:
Monticello, MN
Inspection Dates:
May 04, 2020 to May 07, 2020
Inspectors:
D. Krause, Resident Inspector
S. Sheldon, Project Engineer
Approved By:
Aaron T. McCraw, Team Leader Technical Support Staff
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an Inspection of The Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
2515/193 - Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions
Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions (1 Sample)
- (1) Inspectors reviewed documentation, conducted walkdowns, and held discussions with licensee staff to verify implementation of a reliable hardened containment vent as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession No. ML19255F582) to determined compliance with NRC Order EA-13-109 Phase 1, Reliable, Severe Accident Capable Wetwell Venting System (ADAMS Accession No. ML13143A321).
The inspectors verified that the licensee satisfactorily:
- Installed the Hardened Containment Vent System (HCVS) to meet the performance objectives outlined in Section A.1.1 of Attachment 2 to the Order EA-13-109;
- Installed the HCVS system with the design features specified in Section A.1.2 of Attachment 2 to the Order EA-13-109;
- Designed the HCVS to meet the quality standards described in Section A.2 of 2 to the Order EA-13-109;
- Developed and implemented adequate maintenance and testing of HCVS equipment to ensure their availability and capability;
- Developed and issued procedures to safely operate the HCVS using normal power supplies, during Extended Loss of AC Power (ELAP), and a postulated severe accident scenario, and integrated the procedures into existing plant procedures; and
- Trained their staff to ensure personnel can proficiently operate the HCVS.
Inspectors reviewed documentation, conducted walkdowns, and held discussions with licensee staff to verify implementation of a reliable hardened containment vent as described in the plant specific submittal and the associated safety evaluation (ADAMS Accession No. ML19255F582) to determine compliance with NRC Order EA-13-109 Phase 2, Reliable, Severe Accident Capable Drywell (or alternative strategy) Venting System (ADAMS Accession No. ML13143A321).
The inspectors verified that the licensee satisfactorily developed a strategy making it unlikely that the licensee would need to vent from the containment drywell, that includes the following:
- Implemented the Severe Accident Water Addition (SAWA)/Severe Accident Water Management (SAWM) systems as defined and fulfilled functional requirements for installed and portable equipment;
- Installed and/or identified the previously-installed instrumentation necessary to implement SAWM;
- Developed and implemented adequate maintenance and testing of SAWA/SAWM equipment to ensure availability and capability;
- Developed and issued procedures to safely operate the SAWA/SAWM during an ELAP and during postulated severe accident scenario, and integrated their procedures into their existing plant procedures such that entry into and exiting from the procedures are clear when using existing plant procedures; and
- Trained their staff to ensure personnel can proficiently operate the HCVS during an ELAP and accident scenario.
The inspectors verified that any noncompliance with requirements, and standards identified during the inspection was entered into the licensee's corrective action program.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On May 7, 2020, the inspectors presented the Inspection of The Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions results to Mr. T. Conboy, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2515/193
Calculations
PRA-CALC-14-
003
Monticello MAAP Thermal Hydraulic Calculations to Support
Extended Loss of AC Power (ELAP) Mitigating Strategies
Corrective Action
Documents
501000002224
Hard Pipe Vent Rad Monitor Failure
501000008583
RM-4544 Signal Failure During Rounds
501000021681
B.5.B Vehicle Needs New Oil Pan
501000023266
Flex/Alternate Emergency Access Point
501000026426
RFO29 Flex Lead Bolt Issue
501000026766
Fuel Leak from FLEX Pump P-506
501000028840
Hole Developed on 5" 50ft Discharge Hose
501000030038
Potential FLEX Generator PM Enhancement
501000032050
HPV Rad Monitor Failed Off Scale Low
501000034669
FLEX Fire Hose Connection Icing Issue
501000035387
Snow Removal for FLEX Not Followed
501000035574
501000036074
RM-4544 Spiking/ Losing Power
501000036090
Hard Pipe Vent Rad Monitor Found Failed
501000038161
Hard Pipe Rad Monitor Power Loss
501000038252
RM-4544, HPV Rad Monitor failed
501000039165
Adverse Trend of HPV Rad Monitor
501000039448
SAWA Maint Plan Issue Not Addressed
Corrective Action
Documents
Resulting from
Inspection
501000040276
HCVS 2020 - Procedure Enhancement
05/05/2020
501000040360
HCVS 2020 - NRC Question on Procedures
05/06/2020
Drawings
NH-116629
Hard Pipe Vent System
Miscellaneous
Monticello Nuclear Generating Plant FLEX Validation and
Staffing Addendum
2/01/2018
MT-OPS-CYCLE
18B RO
Training Attendance: Licensed Operator Requal for Cycle
18B
2515/193
Miscellaneous
Diverse and Flexible Coping Strategies (FLEX) Program
Document
LOR-17B-005L
Training Lesson Plan
M-8107L-041
Initial Licensed Training Plan
M8119S-007
Training Simulator Scenario
MT-ILT-FLX-001L
Training Lesson Plan
MT-LOR-18B-
004L
Training Lesson Plan
MT-LOR-20B-
001S
Training Simulator Scenario
MT-NL0-18B-
001L
Training Lesson Plan
MT-NLO-FLX-
001-L
Training Lesson Plan
MT-OPS-CYCLE
17B LOR
Training Attendance: Licensed Operator Requal for
Cycle 17B
03/29/2017
MT-OPS-CYCLE
18B NLO
Training Attendance: Non-Licensed Operator Requal for
Cycle 18B
MT-OPS-CYCLE
18B SRO
Training Attendance: Licensed SRO Requal for Cycle 18B
QF 1040-16 - MT-
ILT-FLX-001L
Training Attendance Sheet
06/12/2018
Procedures
1415
Primary Containment Hard Pipe Vent Valve Exercise
AWI-04.05.01
General Work Controls
AWI-08.16.01
Monticello Emergency Operating Procedure and Beyond-
Design-Basis Guideline Maintenance Program
C.5-1200
Primary Containment Control
C.5-3203
Use of Alternate Injection Systems for RPV Makeup
C.5-3505
Venting Primary Containment
C.5-4050
SBO without High Pressure Injection
C.5-4051
Energize LPCI Swing Bus During SBO
C.5-4201
FLEX Portable Diesel Pump Staging and Hose Connection
C.5-4202
Portable Diesel Pump (PDP) Operation
C.5-4301
Spent Fuel Pool Makeup with FLEX Portable Diesel Pump
C.5-4453
Energize Hard Pipe Vent During SBO
FP-BDB-EQP-01
Equipment Important to BDB Compliance
FP-G-DOC-03
Procedure and Work Instruction use and Adherence
FP-OP-COO-27
Work Management
FP-PA-ARP-01
CAP Process
Work Orders
00491481
Hard Pipe Vent LLRT
05/12/2017
00533714 01
1415 PCT Hard Pipe Vent Valve Exercise
05/08/2017
00540339 07
HPV N2 Supply and Alternate Operating Station For
05/09/2017
00540342 19
EC26083 - Permanent Power Installation All Post Installation
Testing
05/03/2017
00540342 24
EC26083 - Initial Charge and Capacitance Testing
03/09/2017
700014154 0010
Primary Containment Hard Pipe Vent Valve Exercise
04/21/2019
700026369 0070
ECR6MOD0002692I - PDG Phase Rotation Check
03/26/2018
700026369 0080
ECR6MOD00026921 - B4353 Phase Rotation Check
03/15/2018
700040377 0010
P.507 Portable Diesel Pump Testing
06/12/2019
700040561 0010
- 11 Portable Diesel Water Pump Testing
06/21/2019
700046725 0010
P-506 Diesel Fire Pump 12M PM
01/07/2020
700069919 0010
Periodic Cycle of Flex Valves
04/27/2020