IR 05000445/1985010

From kanterella
(Redirected from ML20138C545)
Jump to navigation Jump to search
Insp Repts 50-445/85-10 & 50-446/85-10 on 850605-07.No Violation or Deviation Noted.Major Areas Inspected:Previous Emergency Preparedness Appraisal.One App a Item Closed & 35 App B Items Closed
ML20138C545
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/19/1985
From: Baird J, Terc N, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20138C539 List:
References
50-445-85-10, 50-446-85-10, NUDOCS 8510220458
Download: ML20138C545 (6)


Text

'

.

APPENDIX U. S. NUCLEAR REGULATORY Co m ISSION

REGION IV

NRC Inspection Report: 50-445/85-10 Construction Permits: CPPR-126 50-446/85-10 CPPR-127 Dockets: 50-445 50-446 Licensee: Texas Utilities Electric Company Skyway Tower 400 N. Olive Street L.B. 81 Dallas, Texas 75201 Facility Name: Comanche Peak Steam Electric Station Inspection At: Comanche Peak Site, Glen Rose, Texas Inspection Conducted: June 5-7, 1985

Inspector: *

-

i #'DU i N. M. Terc, Emergency Preparednets Analyst Date Emergency Preparedness and Safeguards Programs Section Approved: h M Nez N JV B. Baird, Acting Chief J/1/y5~

Date'

i Emergency Preparedness and Safeguards Programs

!

Section i 2 f,W - & /er T.' F.' Westerman, Chief, Comanche Peak Region IV Date

'

Group h0220458851011 G ADOCK 05000445 ~

PDR i

_-_-__---__--_--__a

.

. .

Inspection Summary Inspection Conducted June 5-7, 1985 (Report 50-445/85-10 50-446/85-10)

Areas Inspected: Special, announced inspection of areas identified in previous emergency preparedness appraisal (NRC Report 50-445/83-33; 50-446/83-17). The inspection involved 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of in-office review and 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of on-site inspectio Results: One remaining Appendix A item was close In addition, out of 41 Appendix B ttems inspected 35 were closed. This leaves a total of 15 Appendix B items for a future inspection. No violations or deviations were identified.

- - . __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - . - .. .

.

.,

.

-

.

DETAILS Persons Contacted Licensee Personnel

  • G. Bell, Sr. Emergency Planner R. Beleckis, Staff Health Physicist B. Clements, Vice President-Nuclear Operations
  • T. Gosdin, Support Services Superintendent
  • R. Jones, Manager Plant Operations
  • J. Kuykendall, Manager Nuclear Operations
  • G. Laughlin, EP Supervisor

~

  • Denotes those present at the exit intervie . Appraisal Appendix A - Significant Preparedness Deficiency (Closed) (445/8333-116; 446/8317-117): The NRC inspector verified that an accountability drill was held on September 28, 1984, and that results of the same show that the licensee.has the capability.of accounting for all onsite personnel within 30 minute ' Appraisal Appendix B - Improvement Items Closed (Closed) (445/8333-06; 446/8317-06): The NRC inspector noted that the continuity of coordination between corporate and onsite emergency preparedness staffs was assured by methods formalized in procedures revisions, e.g., EP-101 and EP-10 (Closed) (445/8333-08; 446/8317-08): The NRC inspector reviewed the position descriptions and resumes of the emergency preparedness staff and concluded that they were satisfactor (Closed) (445/8333-16; 446/8317-16): The NRC inspector reviewed training records and verified that training for'offsite fire department, medical, and ambulance personnel had been conducted and that provisions existed for continuing to perform the same on annual basi (Closed) (445/8333-17; 446/8317-17): The NRC inspector noted that training records had been placed in'a computer storage and retrieval syste (Closed) (445/8333-25; 446/8317-25): The NRC inspector toured the control room and verified that the radiation monitoring and safety display system had been fully installed, tested, and made operationa (Closed) (445/8333-26; 446/8317-26): The NRC inspector verified that the RM-21 system used for dose projections was fully installed, tested, and operational.

_ . . . . . . . . . . -

,

. _ _ _ _ _

.

-

.

(Closed) (445/8333-36; 446/8317-36): The NRC inspector noted that revised procedures exempted the Technical ~ Support Center (TSC) advisor from data transfer and updat (Closed) (445/8333-49; 446/8317-49): The NRC ' inspector verified that a statement on the use of potassium iodide from the company physician was availabl (Closed)(445/8333-53;446/8317-53): The NRC inspector noted that news briefings will be held in the Nuclear Operations Safeguard Facility (N0SF)

and that a public address system is in place in locations where news media personnel would congregat (Closed)(445/8333-64;_446/8317-64): The NRC inspector verified that the seismic monitoring system was turned over to TUGCO, that operational tests were performed, and that reactor operators were trained to use the syste ,

(Closed) (445/8333-71; 446/8317-71): The NRC inspector reviewed EPP-304,

- Revision 6, and noted that the new revision adequately incorporated the concept of "affected downwind sectors."

(Closed)(445/8333-72;446/8317-72): The NRC inspector toured the control "

room and verified that the new strip-chart recorder display was improve The recorder speed was increased from 1 inch per hour to 3 inches per hour, and Delta T scales'were expanded to.a [-5,5] rang (Closed)(445/8333-73;446/8317-73): The NRC inspector toured the TSC and the NOSF and noted that new recorders were installed to provide means to obtain the various meteorological parameter (Closed)(445/8333-77;446/8317-77): The NRC inspector noted that a complete description of meteorological provisions were included in Revision 8 of the emergency pla (Closed)(445/8333-80;446/8317-80): The NRC inspector reviewed records of tests performed during the site evacuation drill held on November 2, 1983, and verified that-evacuation alarms were effectiv (Closed)(445/8333-91;446/8317-91): The NRC inspector noted that the new revision of EPP-109 specified the emergency coordinator's responsibilities !

for requesting federal assistanc (Closed)(445/8333-92;446/8317-92): The NRC inspector noted that the new revision of EPP-109 was internally consisten (Closed)(445/8333-93;446/8317-93): The licensee stated that the *

chemistry supervisor reporting chain will be incorporated in the upcoming revision of the emergency plan.

'

_ _ _ _ _ _ _ _ .

.

. .

.

(Closed) (445/8333-94; 446/8317-94): The NRC inspector noted that the new revision of EPP-109 included the contents of Attachments 3, 4, and 5 previously in EPP-20 (Closed) (445/8333-97; 446/8317-97): The NRC inspector noted that a flow chart was incorporated in EPP-304, Rc. vision (Closed) (445/8333-98; 446/8317-98): The NRC inspector noted that EPP-109, Revision 4, requires the evacuation alarm to be sounde (Closed) (445/8333-108; 446/8317-108): The NRC inspector verified that guidance for defining the plume boundary was incorporated into EPP-30 (Closed) (445/8333-120; 446/8317-120): The NRC inspector noted that EPP-308 and the emergency plan reference EPP-11 (Closed) (445/8333-121; 446/8317-121): The NRC inspector noted that a debriefing statement was incorporated in EPP-11 (Closed) (445/8333-122; 446/8317-122): The NRC inspector verified that EPP-121 was correcte (Closed) (445/8333-123; 446/8317-123): The NRC inspector noted that EPP-115 was revised to incorporate news media telephone numbers, and that CEPP-108 provided a mechanism for updat (Closed) (445/8333-126; 446/8317-126): The NRC inspector noted that EPP-104 addresses backshift drills. Furthermore, the NRC inspector noted that the licensee had provisions to ensure that all personnel participated in drill (Closed) (445/8333-127; 446/8317-127): The NRC inspector noted that a policy for media coverage of emergency drills and exercises was incorporated into EPP-207 and EPP-10 (Closed) (445/8333-128; 446/8317-128): The NRC inspector noted that a formalized method for documenting a quarterly review of call list will be incorporated in the new revision of EPP-20 (Closed) (445/8333-129; 446/8317-129): The NRC inspector verified that provisions were in place to ensure that controlled copies of emergency response plans and procedures were provided to offsite agencies and the same were kept update (Closed) (445/8333-131; 446/8317-131): The NRC inspector noted that the new revision of EPP-104 contained the requirement to conduct an annual field exercise news media orientation semina (Closed) (445/8333-134; 446/8317-134): The NRC inspector reviewed records and verified that adequate training for control room personnel pertaining to notifications and communications was conducte .. _

,

.-

,

t (Closed) (445/8333-135; 446/8317-135): The NRC inspector reviewed training records confirming that offsite authorities had been trained on a monthly ,

basi (Closed) (445/8333-136; 446/8317-136): The NRC inspector verified that '

additional training had been given to control room personnel to ensure '

that emergency classifications and notifications are made promptly, e

4. Exit Interview At the conclusion of the inspection, the NRC inspector met with persons identified in paragraph 1 and summarized the status of the various follow-up item !