MONTHYEARML20096C9121984-08-0606 August 1984 Requests Extension to 841215 for Response to Generic Ltr 84-15 Re Diesel Generator Reliability.Extension Requested Due to Manpower Constraints,Time Needed to Collect,Verify & Analyze Data & Time Required to Formulate Future Actions Project stage: Other ML20101N6601984-12-28028 December 1984 Forwards Response to 840702 Generic Ltr 84-15 Re Reduction in Number of Cold Fast Starts Surveillance Tests for Diesel Generators & Diesel Generator Reliability Data Project stage: Other ML20101S5361985-01-28028 January 1985 Forwards Revised Pages to 841228 Response to Generic Ltr 84-15 Re Diesel Generator Reliability Data.Revised List of Failures & Causes of Failures for Each Diesel Generator for Last 20 & 100 Demands Encl Project stage: Other ML20101R8571985-01-31031 January 1985 Informs That Diesel Generator Reliability Info Submitted in in Response to Generic Ltr 84-15 Precludes Separate Response to Generic Ltr 83-41 Re Fast Cold Starts of Diesel Generators Project stage: Other ML20134A1321985-10-25025 October 1985 Advises of Review of Tech Specs & Intent to Prepare Application for Amend in Response to Generic Ltr 84-15 Re Diesel Generator Reliability.Schedule Discussed W/Nrc Project Manager on 851008 Project stage: Request ML20140F8511986-03-21021 March 1986 Proposed Tech Spec Sections 2 & 3 Incorporating Surveillance Requirements for Solid Radwaste.Discussion,Justification & Significant Hazards Consideration Encl Project stage: Other ML20140F8391986-03-21021 March 1986 Application for Amend to License DPR-40,changing Sections 2 & 3 of Tech Specs to Incorporate Surveillance Requirements for Solid Radwaste Project stage: Request ML20140F8161986-03-28028 March 1986 Forwards Application for Amend to License DPR-40,changing Sections 2 & 3 of Tech Specs to Incorporate Surveillance Requirements for Solid Radwaste.Certificate of Svc Encl. Fee Paid Project stage: Request ML20205M3801986-04-0909 April 1986 Application for Amend to License DPR-40,revising Tech Specs Re Surveillance Requirements for Emergency Diesel Generator Project stage: Request ML20205M3641986-04-0909 April 1986 Forwards Application for Amend to License DPR-40,revising Tech Specs,Re Surveillance Requirements for Emergency Diesel Generators Project stage: Request ML20207S1161987-03-13013 March 1987 Forwards Response to Questions Raised on 860321 Application for Amend to License DPR-40 Re Testing of Emergency Diesel Generators to Complete Generic Ltr 84-15 Actions Project stage: Request ML20216D0571987-06-22022 June 1987 Proposed Tech Specs Re Deletion of Requirement to Start Diesel Engine Project stage: Other ML20216D0271987-06-22022 June 1987 Update to 860321 Application for Amend to License DPR-40, Incorporating Discussion,Justification & Significant Hazards Considerations Re Deletion of Requirement to Start Diesel Engine Project stage: Request ML20235G8961987-09-24024 September 1987 Safety Evaluation Supporting Amend 111 to License DPR-40 Project stage: Approval ML20235G8881987-09-24024 September 1987 Amend 111 to License DPR-40,incorporating Revised Surveillance Requirements for Diesel Generators Into Tech Specs,Per Generic Ltr 84-15, Proposed Staff Actions to Improve & Maintain Diesel Generator Reliability Project stage: Other ML20235G8721987-09-24024 September 1987 Forwards Amend 111 to License DPR-40 & Safety Evaluation. Amend Incorporates Revised Surveillance Requirements for Diesel Generators Into Tech Specs,Per Generic Ltr 84-15, Proposed Staff Actions..., Per Util 860328 Request Project stage: Approval 1986-03-21
[Table View] |
Text
Omaha Pubilc Power District 1623 Harney Omaha. Nebraska 68102 402/536-4000 October 25, 1985 LIC-85-362 Mr. Edward J. Butcher, Acting Chief Operating Reactors Branch #3 Division of Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Conmission Washington, DC 20555
Reference:
Docket No. 50-285
Dear Mr. Butcher:
Generic Letter 84-15 Diesel Generator Reliability The Omaha Public Power District responded to the subject Generic Letter in correspondence dated December 28, 1984.
In that response, OPPD stated that testing requirements as specificd in the Fort Calhoun Station Technical Specifications would be reviewed.
If deemed excessive, or counter to relia-bility considerations, an Application for Amendment would be prepared. OPPD has reviewed the existing Technical Specifications and does intend to prepare an Application for Amendment. Our schedule for doing so is tentatively set for one month after returning to full power operation from the current re-fueling outage. This schedule was discussed with our NRC Project flanager in a telephone conversation on October 8, 1985.
This letter serves to formalize that conversation.
If you have questions concerning this matter, please contact us.
Sincerely, R. L. Andrews Division Manager Nuclear Production RLA/DJf1/tj b cc: