OPERATING DATA REPORT (REVISED DATA)
UNIT NAME Millstone Unit 2 DATE 12/10/96 COMPLETED BY S. Doboe TELEPHONE (860)447 1791 EXT 4678 OPERATING STATUS 1.
Docket Number 50-336 Notes:
2.
Reporting Period March 1996 (revised)
"' Revised data. Redefined 3.
Utility Contact S.Doboe outage to forced outage.
4.
Licensed Thermal Power (MWt):
2700
- Cumulative weighted 5.
Nameplate Rating (Gross MWe):
903 averages. Unit operated at 6.
Design Electrical Rating (Net MWe):
870 2560 MWTH prior to its uprate 7.
Maximum Dependable Capacity (Gross MWe):
901.63 to current 2700 MWTH power level 8.
Maximum Dependable Capacity (Net MWe):
870.63 9.
If Changes Occur in Capacity Ratings (ltems Number 4 Through 8) Since Last Report, Give Reasons:
N/A "8
- 10. Power Level To Which Restricted, if any (Net MWe):
0 "3
- 11. Reasons For Restrictions, if Any:
NRC letter, issued March 7,1996, requiring design basis verification risponse pursuant to 10CFR50.54(f).
This Month Yr.-To-Date Cumulative
- 12. Hours in Reporting Period 744.0 2184.0 177648.0 l
- 13. Number Of Hours Reactor Was Critical 0.0 1223.6 121911.7
- 14. Reactor Reserve Shutdown Hours 0.0 0.0 2205.5
- 15. Hours Generator On-Line 0.0 1222.1 116611.9
- 16. Unit Reserve Shutdown Hours 0.0 0.0 468.2 i
- 17. Gross Thermal Energy Generated (MWH) 0.0 3240377.0 300862506.4
- 18. Gross Electrical Energy Generated (MWH) 0.0 1085422.5 98709460.0
- 19. Net Electrical Energy Generated (MWH)
-3892.0 1042593.5 94662039.6
- 20. Unit Service Factor 0.0 56.0 65.6
- 21. Unit Availability Factor 0.0 56.0 65.9
- 22. Unit Capacity Factor (Using MDC Net) 0.0 54.8
- 62.2
- 23. Unit Capacity Factor (Using DER Net) 0.0 54.9
- 61.4
- 24. Unit Forced Outage Rate
"' 100 "8 37.4
"' 15.4
- 25. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
Shutdown at the time of this report
- 26. If Unit Shutdown At End Of Report Period, Estimated Date of Startup:
To be determined
- 27. Units in Test Status (Prior to Commercial Operation):
Forecast Achloved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY
_ _ N/A _
N/A COMMERCIAL OPERATION
_ _ N/A N/A 9612180210 961216 PDR ADOCK 05000336 R
UNIT SHUTDOWNS AND POWER REDUCTIONS REVISED DATA DOCKET NO. 50-336 UNIT NAME Millstone Unit 2 DATE 12/10/96 COMPLETED BY S. Doboe TELEPHONE (8601 447-1791 EXT 4678 j
REPORT MONTH: March 1996 (revised) 2 No.
Date Type' Duration Reason Method of License System Component Cause & Corrective (Hours)
Shutting Event Code' Code' Action to Down Reactor' Report #
Prevent Recurrence 96-03 02/26/96 S
144 B
4 N/A N/A N/A Continued mid-cycle surveillance testing outage from previous month.
'96-04 03/07/96 S/F 600 B/D 4
N/A N/A N/A Forced: NRC order requiring design basis verification for response to NRC pursuant to 10CRF50.54(fl.
'F: Forced
' Reason Method
- !EEE Standard 805-1984, 3
S: Scheduled A - Equipment Failure (Explain) 1 - Manual
" Recommended Practices B - Maintenance or Test 2 - Manual Scram for System identification in C - Refueling 3 - Automatic Scram Nuclear Power Plants and D - Regulatory Restriction 4 - Continued from Previous Month Related Facilities" E - Operator Training & Ucense Examination 5 - Power Reduction (Duration = 0)
F - Administrative 6 - Other (Explain)
'IEEE Standard 803A-1983, G - Operational Error (Explain)
" Recommended Practices H - Other (Explain) for Unique identification in Power Plants and Related Facilities - Component
- Revised data: Redefined outage beginning 3/7/96 to forced outage Function Identifiers"
-