ML20121A239

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000498/2020001 and 05000499/2020001
ML20121A239
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/30/2020
From: Jeffrey Josey
NRC/RGN-IV/DRP/RPB-A
To: Gerry Powell
South Texas
References
IR 2020001
Download: ML20121A239 (23)


See also: IR 05000498/2020001

Text

April 30, 2020

Mr. G. T. Powell

President and CEO

STP Nuclear Operating Company

P.O. Box 289

Wadsworth, TX 77483

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION,

UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000498/2020001

AND 05000499/2020001

Dear Mr. Powell:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at South Texas Project Electric Generating Station, Units 1 and 2. On April 16, 2020, the NRC

inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding

involved a violation of NRC requirements. We are treating this violation as a non-cited

violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,

ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at South Texas Project.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at South Texas Project.

G. Powell

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Jeffrey E. Josey, Chief

Reactor Projects Branch A

Division of Reactor Projects

Docket Nos. 05000498 and 05000499

License Nos. NPF-76 and NPF-80

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML20121A239

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE SRI:DRP/A

RI:DRP/A

C:DRS/EB1

C:DRS/EB2

C:DRS/OB

NAME

ASanchez

CStott

VGaddy

NTaylor

GWerner

DATE

04/28/2020

04/24/2020

04/24/2020

04/24/2020

04/23/2020

OFFICE C:DRS/RCB

C:DNMS/RxIB

TL:DRS/IPAT

SPE:DRP/A

C:DRP/A

NAME

MHaire

GWarnick

AAgrawal

HFreeman

JJosey

DATE

04/23/2020

04/24/2020

04/23/20

04/21/2020

04/30/2020

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers:

05000498 and 05000499

License Numbers:

NPF-76 and NPF-80

Report Numbers:

05000498/2020001 and 05000499/2020001

Enterprise Identifier: I-2020-001-0012

Licensee:

STP Nuclear Operating Company

Facility:

South Texas Project

Location:

Wadsworth, TX 77483

Inspection Dates:

January 1, 2020 to March 31, 2020

Inspectors:

B. Baca, Health Physicist

T. DeBey, Resident Inspector

J. Ellegood, Senior Resident Inspector

L. Flores, Project Engineer

J. O'Donnell, Senior Health Physicist

A. Sanchez, Senior Resident Inspector

C. Stott, Resident Inspector

Approved By:

Jeffrey E. Josey, Chief

Reactor Projects Branch A

Division of Reactor Projects

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at South Texas Project, in accordance with

the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Perform an Operability Determination for the Unit 2 Reactor Containment Building

Side Auxiliary Air Lock Door

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000499/2020001-01

Open/Closed

[H.11] -

Challenge the

Unknown

71111.15

The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings associated with the licensees failure to

follow the operability procedure, 0POP01-ZO-0011, Operability, Functionality, and

Reportability Guidance, Revision 12, and perform an operability determination on degraded

equipment. Specifically, the operations personnel failed to assess the operability for the

Unit 2 reactor containment building auxiliary air lock door that degraded from exposure to

environmental (atmospheric) conditions while performing maintenance on the interlock

mechanism. This reactor contain building auxiliary air lock door was relied upon to meet

Technical Specification 3.6.1.3 for containment integrity during the maintenance activity.

Additional Tracking Items

None.

3

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On March 13, 2020, Unit 1

commenced a reactor shutdown to begin refueling outage 1RE22 and entered Mode 3. Unit 1

remained in refueling outage 1RE22 for the reminder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection

procedures (IPs) in effect at the beginning of the inspection unless otherwise noted.

Currently approved IPs with their attached revision histories are located on the public

website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-

procedure/index.html. Samples were declared complete when the IP requirements

most appropriate to the inspection activity were met consistent with Inspection Manual

Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase.

From January 1-March 19, 2020, the inspectors performed plant status activities

described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews

using IP 71152, Problem Identification and Resolution. The inspectors reviewed

selected procedures and records, observed activities, and interviewed personnel to

assess licensee performance and compliance with Commission rules and regulations,

license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the

President of the United States on the public health risks of the coronavirus (COVID-19),

resident inspectors were directed to begin telework and to remotely access licensee

information using available technology. During this time the resident inspectors

performed periodic site visits each week and during that time conducted plant status

activities as described in IMC 2515, Appendix D; and observed risk-significant activities

when warranted. In addition, resident and regional baseline inspections were evaluated

to determine if all or portions of the objectives and requirements stated in the IP could

be performed remotely. If the inspections could be performed remotely, they were

conducted per the applicable IP. In the cases where it was determined the objectives

and requirements could not be performed remotely, management elected to postpone

and reschedule the inspection to a later date.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to

the onset of seasonal cold temperatures for the following systems:

Unit 2 Essential Cooling Water Intake Structure room temperature control and alarm

functions on February 20, 2020

4

External Flooding Sample (IP Section 03.03) (1 Partial Sample)

(1)

(Partial)

The inspectors evaluated external flooding activities in accordance with

Sections 03.03.a, 03.03.b, and 03.03.c as it pertained to the Units 1 and 2 essential

cooling water intake structure and all emergency diesel generator flood panel areas

on January 29, 2020.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

Unit 1, train D auxiliary feedwater system during train B emergency diesel generator

maintenance on February 7, 2020

(2)

Unit 2, train C essential cooling water intake structure during train B essential cooling

water maintenance on February 12, 2020

(3)

Unit 1, feedwater booster pumps while the startup feedwater pump maintenance on

March 10, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Unit 2, train C essential cooling water pump room, Fire Area 55, on February 11,

2020

(2)

Unit 1, containment building, Fire Area 63, on March 16, 2020

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated the onsite fire brigade performance during a simulated fire

in the Unit 2 mechanical auxiliary building on January 14, 2020.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Partial Sample)

(1)

(Partial)

The inspectors evaluated heat sink activities in accordance with Sections 02.01.b and

02.01.d as it pertained to the Unit 1 train B emergency diesel generator 6-year

maintenance that opened and inspected the lube oil and jacket water heat

exchangers on February 4, 2020.

5

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed a Unit 1 operating crew during plant shutdown on

March 13, 2020, in preparation for a refueling outage 1RE22.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated a Unit 2 operations crew in the simulator for a

training scenario involving an excessive steam demand, essential cooling water

strainer clogging, and a loss-of-coolant accident on February 27, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Partial Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1)

(Partial)

The inspectors evaluated the effectiveness of maintenance in accordance with

Section 03.01.a as it pertained to the Unit 1 train B emergency generator replacement

of K1 relay resulted in miswiring of the relay and failed post-maintenance testing of

the emergency diesel generator on February 20, 2020.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample 5 Partial Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed. For the five partial samples documented below,

the inspectors evaluated risk assessment and management in accordance with

Sections 03.01.a, and 03.01.c.

(1)

Unit 1, planned risk due to train C 125Vdc battery and inverter maintenance and use

of the Configuration Risk Management Program on January 16, 2020

(2)

(Partial)

Unit 1, unplanned risk due to train B essential cooling water maintenance resulting in

entering the Configuration Risk Management Program on February 9, 2020

(3)

(Partial)

Unit 1, unplanned risk due to maintenance on train B emergency diesel generator

going longer than expected and resulted in entering the Configuration Risk

Management Program on February 17, 2020

(4)

(Partial)

Unit 1, train D 125vdc battery and inverter maintenance that resulted in the planned

entry into the Configuration Risk Management Program on February 19-20, 2020

6

(5)

(Partial)

Unit 1, train A 125vdc battery and inverter maintenance that resulted in the planned

entry into the Configuration Risk Management Program on February 26-27, 2020

(6)

(Partial)

Unit 1, train B 125vdc battery and inverter maintenance that resulted in the planned

entry into the Configuration Risk Management Program on March 4-5, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

Unit 2, train A sequencer due to sequencer trouble alarm received in control room on

January 9, 2020

(2)

Unit 2, auxiliary air lock inner (reactor containment building) door that experienced a

significant step change in the allowable leakage during interlock maintenance on

January 30, 2020

(3)

Unit 1, train B emergency diesel generator buildup of joint sealant material observed

in the wrinkle belly joints in two cylinders on February 4, 2020

(4)

Unit 1, turbine driven auxiliary feedwater pump governor valve corrosion and pitting

found on March 19, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post maintenance test activities to verify system

operability and functionality:

(1)

Unit 2, train A essential chilled water chiller following preventive maintenance

between January 6-9, 2020

(2)

Unit 2, train A engineered safeguards feature sequencer testing following

replacement of a DC input module opto-isolator on January 10, 2020

(3)

Unit 1, train B emergency diesel generator testing following a 5-year maintenance

activity on February 16, 2020

(4)

Unit 2, auxiliary air lock reactor containment building side door following seal

replacement due to degradation on February 7, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial Sample)

(1)

The inspectors evaluated refueling outage 1RE22 activities in accordance with

Sections 03.01.a, 03.01.b, 03.01.c(1), 03.01.c(5), 03.01.c(6), 03.01.c(8), 03.01.c(9),

and 03.01.d(2) on March 31, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

7

Surveillance Tests (other) (IP Section 03.01) (2 Samples, 2 Partial Samples)

(1)

Unit 1, train B emergency diesel generator monthly surveillance test on January 8,

2020

(2)

Unit 1, train B emergency diesel generator surveillance test on February 16 and 17,

2020

The inspectors evaluated the surveillance testing activities in accordance with

Sections 03.01(1), 03.01(2):

(3)

(Partial)

Unit 1, train B residual heat removal pump surveillance test on March 11, 2020

(4)

(Partial)

Unit 1, train C emergency diesel generator surveillance test on March 11, 2020

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed the licensee's enhanced emergency plan drill that involved

failed fuel, a reactor coolant leak greater that the capacity of one charging pump, a

large break loss-of-coolant accident, and a containment breach which exercised all

emergency classification levels on March 4, 2020.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels and the concentrations and quantities of radioactive materials and

how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated radiological protection-related instructions to plant workers.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination

and radioactive material. The inspectors observed the following activities:

(1)

Radiation protection technicians surveyed items in which workers brought for free

release from the radiologically controlled area, as well as items which did not clear

the small article monitors. Workers surveyed hand held items with available small

article monitors and exiting the radiologically controlled area.

(2)

Radiation protection technician established a High Efficiency Particulate Air (HEPA)

unit for control of contamination during maintenance work on a residual heat

removal 1A pump valve and reactor vessel water level indicator system probe

8

removal. In addition, the inspector observed the use of the HEPA units by the

technicians and workers for these activities.

(3)

Radiation protection technicians surveyed and controlled the levels of contamination

on workers' gloves and equipment during the thimble tube retraction activity.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and

observation of radiological work activities. The inspector observed the following activities

with regard to radiological hazard control and work coverage:

(1)

Reactor head lift activities which involved a moving technical specification high

radiation area, high contamination levels, and the potential for an airborne area to be

generated (Radiation Work Permit 2020-1-0121, "1RE22 - Reactor Head Lift Activities

(Locked High Radiation Area (LHRA)) - High Radiological Risk", Revision 0)

(2)

Reactor vessel water level indicator system activities with irradiated components and

potentially elevated contamination levels (Radiation Work Permit 2020-1-115,

"1RE22 - Maintenance Support For Work in and around Reactor Cavity, Spent Fuel

Pool and Transfer Canal (High Radiation Area (HRA)) - Medium Radiological Risk,"

Revision 0)

(3)

Residual heat removal 1A pump maintenance with discrete high radiation areas

within the work area and high contamination level with the system breached

(Radiation Work Permit 2020-1-0147, "1RE22 - Repair/Replace Residual Heat

Removal (RHR) 1A Pump Seal (HRA) - Medium Radiological Risk," Revision 0)

(4)

Thimble tube retraction activities with high radiation areas from irradiated components

and high contamination levels (Radiation Work Permit 2020-1-0123, "1RE22 -

Retract/Re-Insert Thimble Tubes (LHRA) - High Radiological Risk," Revision 0)

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very

High Radiation Areas:

(1)

Unit 1, refuel 22 reactor head lift activities which involved access to the reactor cavity

and the reactor head movement

(2)

Unit 1, refuel 22 thimble tube retraction activities

(3)

Unit 1, refuel 22 reactor vessel water level indicator system activities

(4)

Unit 1, mechanical auxiliary building - Letdown Heat Exchanger room, Solid Waste

Process Aisle, Chemical and Volume Control System (CVCS) Volume Control Tank

room, and Mezzanine to Room 218J

Radiation Worker Performance and Radiation Protection Technician Proficiency

(IP Section 03.06) (1 Sample)

(1)

The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

9

71124.02 - Occupational ALARA Planning and Controls

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (4 Samples)

The inspectors evaluated the licensees communication of as low as is reasonably

achievable ALARA and radiological work controls for the following work activities:

(1)

Radiation Work Permit 2020-1-115, "1RE22 - Maintenance Support For Work in and

around Reactor Cavity, Spent Fuel Pool and Transfer Canal (HRA) - Medium

Radiological Risk," Revision 0, specifically covering Reactor Vessel Water Level

Indicator System probe removal

(2)

Radiation Work Permit 2020-1-0121, "1RE22 - Reactor Head Lift Activities (LHRA) -

High Radiological Risk," Revision 0

(3)

Radiation Work Permit 2020-1-0123, "1RE22 - Retract/Re-Insert Thimble

Tubes (LHRA) - High Radiological Risk," Revision 0

(4)

Radiation Work Permit 2020-1-0147, "1RE22 - Repair/Replace Residual Heat

Removal (RHR) 1A Pump Seal (HRA) - Medium Radiological Risk," Revision 0

Radiation Worker Performance (IP Section 03.04) (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance.

The inspectors observed and evaluated the implementation of as low as is reasonably

achievable techniques for the following selected work activities:

(1)

Reactor head lift activities

Reactor Vessel Water Level Indicator System probe removal

Thimble tube retraction activities

Residual Heat Removal 1A pump maintenance activities

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01) (2 Samples)

(1)

Unit 1, January 2019 through December 2019

(2)

Unit 2, January 2019 through December 2019

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02)

(2 Samples)

(1)

Unit 1, January 2019 through December 2019

(2)

Unit 2, January 2019 through December 2019

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1)

Unit 1, January 2019 through December 2019

(2)

Unit 2, January 2019 through December 2019

10

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

October 1, 2019 through December 31, 2019

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample

(IP Section 02.16) (1 Sample)

(1)

October 1, 2019 through December 31, 2019

71153 - Follow-up of Events and Notices of Enforcement Discretion

Event Follow-up (IP Section 03.01) (1 Sample)

Event Follow-up for Loss of Both the 345kV South Bus and Standby Transformer 2

(1)

On March 24, 2020, while Unit 1 was defueled in refueling outage 1RE22 and Unit 2

was at full rated power, the station experienced a loss of the 345kV south bus and

standby transformer 2 at 10:46 a.m. Unit 1 experienced an undervoltage on train A

and C engineered safety features (ESF) buses, which resulted in an emergency start

of each of the train A and C diesel generators, as designed. Unit 1 also lost one of

two trains of spent fuel pool cooling. At the time, time-to-boil in the spent fuel pool

was 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> with the full core offloaded. Spent fuel pool cooling in Unit 1 was

restored in 10 minutes. Unit 1 also had a suspended bundle in the spent fuel pool.

The spent fuel pool fuel handling bridge failed in a safe condition and afterward

secured the bundle with no issues.

Unit 2 experienced an undervoltage on the train B ESF bus, which resulted in an

emergency start of that trains emergency diesel generator as designed. Unit 2 also

lost one of two trains of spent fuel pool cooling and the time-to-boil in the spent fuel

pool was 45 hours5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br />. Unit 2 spent fuel pool cooling was restored within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. All

safety equipment responded as designed without any issues or operator intervention.

The lockout relays for both the 345kV south bus and standby transformer two were

reset and power restored to those components at 9:07 p.m. All electrical alignments

and equipment restorations were completed at 10:05 p.m. for both units.

Due to the COVID-19 pandemic and NRC directives for inspectors to practice social

distancing to the maximum extent possible, inspectors monitored and confirmed

information via phone and through face-to-face briefings in the outage control center

for Unit 1 outage. The inspectors had no concerns for equipment or operator

performance during the event. The inspectors also kept abreast of restoration

activities throughout the day of the event until full restoration with no concerns. The

inspectors also reviewed the initial notification to verify it met the requirements

specified in NUREG-1022, Event Reporting Guidelines, Revision 3.

No findings were identified.

11

INSPECTION RESULTS

Failure to Perform an Operability Determination for the Unit 2 Reactor Containment Building

Side Auxiliary Air Lock Door

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Barrier Integrity

Green

NCV 05000499/2020001-01

Open/Closed

[H.11] -

Challenge the

Unknown

71111.15

The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings associated with the licensees failure to

follow the operability procedure, 0POP01-ZO-0011, Operability, Functionality, and

Reportability Guidance, Revision 12, and perform an operability determination on degraded

equipment. Specifically, the operations personnel failed to assess the operability for the

Unit 2 reactor containment building (RCB) auxiliary air lock door that degraded from exposure

to environmental (atmospheric) conditions while performing maintenance on the interlock

mechanism. This RCB auxiliary air lock door was relied upon to meet Technical

Specification 3.6.1.3 for containment integrity during the maintenance activity.

Description:

On November 27, 2019, following the Unit 2 refueling outage 2RE20, the auxiliary air lock

reactor containment building (RCB) door was tested via a local leak rate test (LLRT) with a

20 sccm leak rate -- well below the acceptance criteria of 7584 sccm. Once every seven

days the auxiliary air lock is inspected to determine if the tamper seal is still present,

indicating the air lock has not been opened. If the seal is intact, no LLRT surveillance would

be required. On January 23, 2020, performance technicians were testing the air lock interlock

when the mechanism failed. Condition Report 20-849 was written to document the failure.

The air lock was immediately declared inoperable and the licensee met Technical

Specification 3.6.1.3.b by ensuring the RCB (inner) side auxiliary air lock door was closed and

locked by an equipment clearance order. The yard (outer) side door would be opened to

effect repairs on the interlock.

One week later, on January 30, 2020, an LLRT was required on both inner and outer doors of

the auxiliary air lock. The inner door experienced a step increase in allowable leak rate to

approximately 7550 sccm, which was 99.7 percent of the allowable leak rate. Condition

Report 20-1205 was written and coded as closed to trend based on requesting that the

preventative maintenance activity to replace the O-rings and clean the sealing surfaces

ASAP following the repair of the interlock. This condition received no operability

determination because, although close to the acceptance limit, the licensee determined that it

met the surveillance requirement. At this time the residents began asking questions about

the sudden and dramatic step change in the LLRT leak rate. In a meeting with engineering

on February 6, 2020, the residents discovered that the most likely cause of the change in the

LLRT results for the inner air lock door was its exposure to the environmental conditions as a

result of having to open the outer auxiliary air lock door while working on the air lock interlock.

The residents asked why the inner air lock door, which was being relied on to meet technical

specifications, was operable considering that the door continued to be exposed to

environmental condition over the balance of the following week. Engineerings answer was

that it met its technical specification surveillance test and that the program and procedure was

being followed by initiating a condition report and requesting seal replacement after the

interlock was repaired.

12

Maintenance performed a seal replacement and a cleaning of the sealing areas on the inner

auxiliary air lock door. The door was then tested via the LLRT satisfactorily at 20 sccm. The

auxiliary air lock and the inner and outer doors were declared operable in accordance with

technical specifications. Unit 2 declared the auxiliary air lock door operable and exited all

technical specifications on February 7, 2020.

On March 4, 2020, the residents again met with engineering, operations and licensing to

review the sequence of events, past LLRTs of the inner and outer auxiliary air lock doors and

discussed the potential cause(s) of the RCB door leakage. Again, engineering and licensing

took the position that the inner door was operable because it met its surveillance

requirements, even if when given that an apparent despite that an apparent degrading

mechanism, the environment, was still present on the inner door.

The residents determined that the unexpected step change in the LLRT leak rate for the inner

auxiliary air lock door coupled with the most likely cause of the degrading mechanism being

the environmental conditions, which were going to continue to exist over the following week to

repair the auxiliary air lock interlock mechanism, cast doubt on the reasonable assurance for

operability. The licensee failed to recognize that reasonable assurance was lost and failed to

enter the operability determination program and procedure. The inspectors determined that

Procedure 0POP01-ZO-0011, Operability, Functionality, and Reportability Guidance,

Revision 12, contained the following guidance:

  • Section 6.1.2 Technical Specification surveillances are performed periodically to verify

that SSCs are operable. Satisfactory performance of a surveillance is usually considered

sufficient to demonstrate operability. However, IF conformance to the Current License

Basis (CLB) criteria requirements are questionable due to a possible degraded or

nonconforming condition, AND reasonable expectation of component operability is unclear,

THEN performance of the surveillance may be INSUFFICIENT to demonstrate operability.

An example of when a surveillance would NOT be sufficient to establish operability is the

satisfactory completion of Technical Specification surveillance, but with results that show a

degrading trend and indicate that acceptance criteria might NOT be met before the next

surveillance test. In this case, the surveillance actually identifies the conditions when the SSC

will become inoperable and an operability evaluation would be warranted.

following:

Notification to the Control Room of a condition potentially affecting functionality.

Inspectors determined that the licensee became myopic and only considered the surveillance

performance as the input into the operability decision. The inspectors determined that the

licensee failed to challenge the circumstances surrounding the significant step change in the

inner doors LLRT leak rate and thus recognize that the presumption of operability was

compromised by the environmental condition, that was most likely degrading the door, and

that the operability determination process should have been entered.

Corrective Actions: The licensee has the taken corrective action to enter the issue into the

corrective action program, as Condition Report 20-1589, and is in the process of evaluating it.

The Unit 2 auxiliary air lock and its inner and outer doors are currently operable, and no

immediate safety issue exists.

13

Corrective Action References: Condition Reports: 2020-1589, 2020-1205, 2020-849

Performance Assessment:

Performance Deficiency: The failure to implement the operability determination procedure for

a degraded condition was a performance deficiency. Specifically, on January 30, 2020, the

Unit 2 control room operations failed to implement the operability determination procedure,

0POP01-ZO-0011, Operability, Functionality, and Reportability Guidance, Revision 12 for a

degraded condition of the Unit 2 reactor containment building (inner) auxiliary air lock door.

This degraded condition represented a loss of reasonable expectation of operability and

should have been evaluated for operability. The inspectors determined that the performance

deficiency was within the licensees ability to foresee and correct.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the human performance attribute of the Barrier Integrity

cornerstone and adversely affected the cornerstone objective to provide reasonable

assurance that physical design barriers protect the public from radionuclide releases caused

by accidents or events. The performance deficiency was determined to be more than minor

because it was associated with the Human Performance attribute of the Containment Barrier

Integrity Cornerstone objective and adversely affected the cornerstone objective to provide

reasonable assurance that physical barriers protect the public from radionuclide releases

caused by accident or events. Specifically, the license failed to enter and use the operability

determination procedure for a degraded RCB side auxiliary air lock door while it was being

relied upon to meet technical specification for reactor containment boundary while the air lock

interlock was being repaired.

Significance: The inspectors assessed the significance of the finding using Appendix A, The

Significance Determination Process (SDP) for Findings At-Power. The inspectors used

IMC 0609, Appendix A, Exhibit 3, Barrier Integrity Screening Questions, issued

December 13, 2019 to determine the finding was of very low safety significance, Green.

Specifically, the finding did not represent an actual open pathway in the physical integrity of

reactor containment and did not involve an actual reduction in function of hydrogen igniters in

the reactor containment, therefore screened to Green.

Cross-Cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with

uncertain conditions. Risks are evaluated and managed before proceeding. Specifically,

operations relied on the satisfactory surveillance and did not question the circumstances

around the significant step change in LLRT leak rates for the Unit 2 auxiliary air lock inner

door and thus did not recognize the operability determination procedure should have been

entered.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings, requires, in part, activities affecting quality shall be prescribed by documented

instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be

accomplished in accordance with those instructions, procedures, or drawings The

licensee developed procedure, 0POP01-ZO-0011, Operability, Functionality, and

Reportability Guidance, Revision 12, to comply with determining operability of safety-related,

technical specification equipment and to be in compliance with the above stated regulation.

Specifically, step 6.1.2 (under Presumption of Operability), states, in part, IF conformance

14

to the Current Licensing Basis (CLB) criteria requirements are questionable due to a possible

degraded or nonconforming condition, AND reasonable expectation of component operability

is unclear, THEN performance of the surveillance may be INSUFFICIENT to demonstrate

operability.and an operability evaluation would be warranted.

Contrary to the above, on January 30, 2020, an activity affecting quality prescribed by

procedures of a type appropriate to the circumstances was not accomplished in accordance

with procedures appropriate to the circumstances. The licensee failed enter the operability

determination process when a condition when the conformance of the current licensing basis

requirements was questionable due to a possible degraded or nonconforming condition, and

reasonable expectation of component operability was unclear. Specifically, the licensee did

not enter the operability determination process when a significant step change in the local

leak rate (consumed 99.7 percent of the allowable leakage rate) on the Unit 2 inner auxiliary

air lock door was identified and the degrading mechanism, atmospheric environment,

remained present for approximately one week while being relied upon to meet technical

specifications.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public

disclosure.

On March 30, 2020, the inspectors presented the results for the occupational radiation

safety 71124.01, 71124.02, and 71151 inspections to Mr. J. Connolly, Executive Vice

President and Chief Nuclear Officer, and other members of the licensee staff.

On April 16, 2020, the inspectors presented the integrated inspection results to

Mr. G. Powell, President and Chief Executive Officer, and other members of the

licensee staff.

15

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

CR-YYYY-NNNN

2020-1493 2020-1494 2020-1495 2020-1496 2020-

1497

2020-1498 2020-1499 2020-1500 2020-1612 2020-

1613

2020-1614

Drawings

5R289F05038

P&ID Essential Cooling Water, Sheet 2

5R289F05039

P&ID Essential Cooling Water, Sheet 1

5S141F00024

P&ID Auxiliary Feedwater, Sheet 1

13

Procedures

0PGP03-ZM-

0016

Installed Plant Instrumentation Calibration Verification

Program

30

0PMP08-ZI-0011

Generic Temperature Switch Calibration

22

0POP02-AF-0001

Auxiliary Feedwater

52

0POP02-EW-

0001

Essential Cooling Water Operations

82

Work Orders

Work

Authorization

Numbers

572373 572367

71111.05

Corrective Action

Documents

CR-YYYY-NNNN

2020-872

Fire Plans

20-01-02

Procedures

0MAB03-FP-0130

Fire Pre-plan Mechanical Auxiliary Building Service Areas

and BRS Recycle Holdup Tanks

5

0PGP03-ZF-0011

STPEGS Fire Brigade

18

0PGP03-ZF-0018

Fire Protection System Functionality Requirements

21

1ECW55-FP-

0602

Fire Preplan Essential Cooling Water Intake Structure Pump

Room Train C

4

71111.06

Miscellaneous

STPNOC Blue team Combined Functional Drill Scenario

Manual

03/04/2020

71111.07A

Procedures

0PMP02-ZG-

0004

Bolted Joint Procedure

18

Work Orders

Work

569663 569664

16

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Authorization

Numbers

71111.11Q Miscellaneous

RST 220.16 RCS

LOCA to ES12

Simulator Lessons Plan

Procedures

0POP03-ZG-0006 Plant Shutdown From 100% to Hot Standby

75

71111.12

Corrective Action

Documents

CR-YYYY-NNNN

2020-1854

Procedures

0PMP02-NZ-0013 Cable Terminations

32

Work Orders

Work

Authorization

Numbers

627615

71111.13

Corrective Action

Documents

CR-YYYY-NNNN

2019-1665 2018-14454 2018-14772 2019-1989

2017-23022 2019-4852 2018-11467 2019-3947

2019-4404 2019-1494

CREE-YYYY-

NNNN

2019-3905-3 2019-9047-2 2020-1860-1

Miscellaneous

LOR 201.07 PRA

Refresher

Communicating

Risk

Licensed Operator Training

RictCal Sequence

3546 3560

Station log

1/15/20 09:31,

10:31

Logs

Procedures

0PGP03-ZG-0091 Configuration Risk Management Program

14

0POP01-ZO-0011 Operability, Functionality, and Responsibility Guidance

11

0POP11-DJ-0002

Online Class 1E 125V DC Battery and Inverter Removal

from Service and Restoration

15

Work Orders

Work Activity Risk

(WAR)

2768

1 and 2

Work

Authorization

Numbers

626074 582691

17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

CR-YYYY-NNNN

2020-300 2020-849 2020-1205 2020-1589

Procedures

0PGP03-ZO-9900 Operability Determinations and Functionality Assessments

Program

8

0PMP04-ZG-

0014A

Auxiliary Air Lock Inspection and Maintenance, RCB End

Door

4

0POP01-ZO-0011 Operability, Functionality, and Reportability Guidance

12

0POP01-ZO-0011 Operability, Functionality, and Reportability Guidance

13

0POP09-AN-

03M3

Annunciator Lampbox 3M03 Response Instructions

34

0PSP11-XC-0004

LLRT Penetration: M-91 Auxiliary Door Airlock Door Seals

16

Work Orders

Work

Authorization

Numbers

626878 607399

71111.19

Corrective Action

Documents

CR-YYYY-NNNN

2020-1184 2020-1196 2020-1197 2020-1815 2020-

1860

2020-1589 2020-1205

Work

Authorization

Numbers

578147 563085 581863 583884 617585 582691

581621 626828 607399

Procedures

0PMP04-DG-

0023

Standby Diesel Generator Governor Oil Change and

Overspeed Trip Test

12

0PMP04-ZG-

0014A

Auxiliary Air Lock Inspection and Maintenance, RCB End

Door

4

0PMP05-CH-

0003

York Chiller Inspection and Maintenance 300 Tons

13

0PSP03-DG-0002 Standby Diesel 12(22) Operability Test

65

0PSP11-XC-0004

LLRT Penetration: M-91 Auxiliary Door Airlock Door Seals

16

Work Orders

Work Activity Risk

(WAR)

2768

1 and 2

71111.20

Miscellaneous

Shutdown Risk Assessment Group (SRAG) Report,

Amendment 1

03/09/2020

1RE22 Level II Schedule

04/03/2020

Shutdown Risk Assessment Group (SRAG) Report

02/27/2020

18

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.22

Procedures

0OOI01-OL-0005

Operations Logs - Diesel Generator (Diesel Generator 12

(22) Operating Log Sheet

16

0PSP03-DG-002

Standby Diesel 12 (22) Operability Test

65

71124.01

Corrective Action

Documents

CR-

2019-06705 2019-11422 2019-1209 2019-12400

2019-12590 2019-13299 2019-13305 2020-00270

2020-01410 2020-01857 2020-02910 2020-03096

2020-03188 2020-03214 2020-03377 2020-03768

Miscellaneous

WAN 545822

Radioactive Source Surveillance

07/30/2019

WAN 556980

Radioactive Source Surveillance

01/23/2020

Procedures

0PGP03-ZR-0050

Radiation Protection Program

14

0PGP03-ZR-0051

Radiological Access Controls/Standards

43

0PRP03-ZR-0004

Inventory and Leak Testing of Radioactive Sources

9

0PRP04-ZR-0013

Radiological Survey Program

39

0PRP04-ZR-0015

Radiological Postings and Warning Devices

38

0PRP04-ZR-0019

High Radiation Area Access Controls

0

Conduct Of

Operations for

Radiation

Protection:

Chapter 25

Locked High Radiation Area (LHRA) Unique Locking

Mechanisms

0

Radiation

Surveys

108732

1-RCB+068: Shut Down Survey, Ladders Down Posted

03/13/2020

108756

1-RCB+068-501: Vibration checks on CRDM vent fan

motors

03/14/2020

108884

1-RCB-011-003: Initial Room 003 entry for disconnect of

seal table from valve rack and lift valve rack

03/16/2020

108919

1-RCB-011-003: Thimble Retraction Job Coverage

03/17/2020

109259

1-RCB+019-201: Routine verification of conditions on

walkways after Generators were opened

03/25/2020

109274

1-RCB+019-201: Routine Survey of B & C bullpen

03/25/2020

109285

1-MAB+060: Routine Shiftly RCB Egress

03/25/2020

109286

1-RCB-011: Contamination Survey of RCB-011' ONLY, due

to Airborne activity in RCB

03/25/2020

109287

1-RCB+019: Follow-up survey during period of elevated

03/25/2020

19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

airborne radioactivity

Radiation Work

Permits (RWPs)

2019-2-203

2RE20-Remove / Reinstall Reactor Cavity Stairwell (LHRA) -

Medium Radiological Risk

5

2020-1-114

1RE22 - Maintenance Support for Work in And Around

Reactor Cavity, Spent Fuel Pool and Transfer Canal (HRA)

0

2020-1-115

1RE22 - Maintenance Support for Work in And Around

Reactor Cavity, Spent Fuel Pool and Transfer Canal (HRA) -

Medium Radiological Risk

0

2020-1-121

1RE22 - Reactor Head Lift Activities (LHRA) - High

Radiological Risk

0

2020-1-123

1RE22 - Retract / Re-Insert Thimble Tubes (LHRA) - High

Radiological Risk

0

2020-1-147

1RE22 - Repair/Replace RHR 1A Pump Seal (HRA) -

Medium Radiological Risk

0

71124.02

ALARA Plans

20-812-4

1RE22 Room 003 Activities

3/12/2020

20-812-5

1RE22 Steam Generator Inspections

3/14/2020

20-812-7

1RE22 Non-Rapid Refuel

3/13/2020

Corrective Action

Documents

CR-YYYY-NNNN

2018-12157 2018-01339 2019-12668 2019-182339,

2020-00696 2020-01857 2020-01878 2020-02539

2020-03370

Miscellaneous

Action Number

19-4004-5

Perform industry peer benchmark on Rad-Worker

engagement and accountability for dose projections,

performance, and goal in high performing with low source

term reactors

10/31/2019

Action Number

19-8524-1

Determine Gaps in Understanding [ALARA]

02/27/2020

March 16 - 18,

2020

Daily Operations Report

Procedures

0PGP03-ZR-0050

Radiation Protection Program

14

0PGP03-ZR-0052

ALARA Program

18

0PRP07-ZR-0010

Radiation Work Permits/Radiological Work ALARA Reviews

40

0PRP07-ZR-0033

Radiological Briefings

7

0PRP07-ZR-0034

Radiological Risk Management

5

Conduct of

ALARA Planning

4

20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Operations for

Radiation

Protection,

Chapter 18

Radiation Work

Permits (RWPs)

2020-1-122

1RE22 - FHB Fuel Transfer Tube Area Entry (LHRA)

0

2020-1-135

1RE22 - SG-Eddy Current Testing (LHRA) - High

Radiological Risk

0