MONTHYEARB11495, Application for Amend to License DPR-65,authorizing Rev to Tech Spec 3.7.5.1 Re Flood Level.Fee Paid1985-03-28028 March 1985 Application for Amend to License DPR-65,authorizing Rev to Tech Spec 3.7.5.1 Re Flood Level.Fee Paid Project stage: Request ML20112J2931985-03-28028 March 1985 Proposed Tech Spec 3.7.5.1 Re Flood Level & Operation of Svc Water Pump Motor Project stage: Other ML20100G7081985-03-29029 March 1985 Proposed Tech Spec Clarifying That During Type a Integrated Leak Rate Testing,Containment Gaseous & Particulate Radiation Monitors Not Required to Be Operational Project stage: Other B11493, Application for Amend to License DPR-65,revising Tech Specs to Clarify That Containment Gaseous & Particulate Radiation Monitors Not Required to Be Operable During Type a Integrated Leak Rate Testing.Fee Paid1985-03-29029 March 1985 Application for Amend to License DPR-65,revising Tech Specs to Clarify That Containment Gaseous & Particulate Radiation Monitors Not Required to Be Operable During Type a Integrated Leak Rate Testing.Fee Paid Project stage: Request B11499, Application for Amend to License DPR-65,deleting Footnotes from Tech Spec Sections 4.4.5.1.3 & 3.4.6.2 & Table 4.7-2 Re Cycle 5 Refueling Outage & Operation.Fee Paid1985-03-29029 March 1985 Application for Amend to License DPR-65,deleting Footnotes from Tech Spec Sections 4.4.5.1.3 & 3.4.6.2 & Table 4.7-2 Re Cycle 5 Refueling Outage & Operation.Fee Paid Project stage: Request B11492, Application for Amend to License DPR-65,deleting Tech Spec Diesel Generator Surveillance Requirement 4.8.1.1.2.c.5.d Per Generic Ltr 85-30.Fee Paid1985-03-29029 March 1985 Application for Amend to License DPR-65,deleting Tech Spec Diesel Generator Surveillance Requirement 4.8.1.1.2.c.5.d Per Generic Ltr 85-30.Fee Paid Project stage: Request ML20100G2241985-03-29029 March 1985 Proposed Tech Spec 3/4 8-4 Re Electrical Power Sys Surveillance Requirements Project stage: Other ML20100G4261985-03-31031 March 1985 Proposed Tech Spec Deleting cycle-specific Footnotes from Tech Spec Sections 4.4.5.1.3 & 3.4.6.2 & Table 4.7-2 Re Cycle 5 Refueling Outage & Operation Project stage: Other B11500, Application for Amend to License DPR-65,revising Tech Specs to Delete Ref to Physical Description of Trisodium Phosphate Dodecahydrate.Fee Paid1985-04-0404 April 1985 Application for Amend to License DPR-65,revising Tech Specs to Delete Ref to Physical Description of Trisodium Phosphate Dodecahydrate.Fee Paid Project stage: Request ML20100L1021985-04-0404 April 1985 Proposed Tech Specs Deleting Ref to Physical Description of Trisodium Phosphate Dodecahydrate Project stage: Other ML20133N9481985-08-0202 August 1985 Safety Evaluation Supporting Amend 101 to License DPR-65 Project stage: Approval ML20133N9371985-08-0202 August 1985 Amend 101 to License DPR-65,changing Tech Specs to Delete Ref to Station Emergency Procedure & Revise Surveillance Requirement to Make Diesel Generator Testing Consistent W/Requirements of Generic Ltr 83-30 Project stage: Other 1985-03-31
[Table View] |
Text
-
ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) c)
Verifying that on the safety injection actuation signal, all diesel generator trips, except engine overspeed, generator differential current, voltage restraint overcurrent, and low lube oil pressure (2 out of 3) are automatically bypassed.
I 6.
Verifying the diesel generator operates for160 minutes while loaded to 2 2750 kw.
7.
Verifying that the auto-connected loads to each diesel
~
generator do not exceed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 3000 kw.
8504000124 850329 PDR ADOCK 05000336 P
PDR MILLSTONE - UNIT 2 3/48-4