Proposed Tech Spec Change Request 110,allowing Operation of Certain Containment Isolation Valves Provided That Dedicated Operator Posted to Isolate Valve When NecessaryML20084C549 |
Person / Time |
---|
Site: |
Crystal River |
---|
Issue date: |
04/23/1984 |
---|
From: |
FLORIDA POWER CORP. |
---|
To: |
|
---|
Shared Package |
---|
ML20084C548 |
List: |
---|
References |
---|
NUDOCS 8404300082 |
Download: ML20084C549 (10) |
|
|
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20212C0961999-09-16016 September 1999 Proposed ITS & Bases Changes Strikeout & Shadowed Text & Revision Bar Format,Increasing Licensed Capacity for Spent Fuel Assembly Storage in SFP & Revising Configuration for Storage of Fresh Fuel ML20211L1011999-09-0202 September 1999 Proposed Tech Specs Re Once Though SG Tube Surveillance Program,Alternate Repair Criteria (ARC) for Axial Tube End Crack (Tec) Indications ML20209D2971999-07-0808 July 1999 Proposed Tech Specs,Changing ITS for CREVS & VFTP & Correcting Typo in ITS Section 5.6.2.12 ML20195B8091999-05-26026 May 1999 Proposed Tech Specs,Revising ITS Bases That Will Update NRC Copies of ITS ML20195B7081999-05-17017 May 1999 Proposed ITS Section 3.3.8, EDG Lops, SR 3.3.8.1,revising Note for Surveillance & Deleting Note for Frequency ML20206S7691999-05-12012 May 1999 Proposed Improved Tech Specs Pages 3.4-21 Through 3.4-21D ML20206N1401999-05-10010 May 1999 Proposed ITS Administrative Controls Section 5.8, High Radiation Area ML20206M0961999-05-0707 May 1999 Proposed Tech Specs,Revising Wording for SR 3.5.2.5 to Be More Consistent with NUREG-1430,Rev 1 & Clarifying Process of Valve Position Verification ML20206H6541999-05-0505 May 1999 Proposed Tech Specs,Proposing Alternate Repair Criteria for Axial Tube End crack-like Indications in Upper & Lower Tubesheets of CR-3 OTSGs ML20204D9211999-03-18018 March 1999 Proposed Tech Specs Re OTSG Tubes Surveillance Program,Tube Repair Roll Process ML20202E6551999-01-27027 January 1999 Proposed Tech Specs Re OTSG Tubes Surveillance Program,Insp Interval Extension ML20196D6761998-11-30030 November 1998 Proposed Tech Specs LCO 3.9.3,allowing Both Doors in Personnel Air Locks & Single Door in Oeh to Be Open During Refueling Operations ML20195K4551998-11-24024 November 1998 Proposed Tech Specs,Installing diesel-driven EFW Pump to Remove Interim ITS & Provide Resolution to EDG Capacity Limitations ML20195K0031998-11-23023 November 1998 Proposed Tech Specs Re LAR Number 241,rev 0 for High Pressure Injection Sys Mods ML20195H6581998-11-17017 November 1998 Proposed Improved Tech Specs (Its),Revising 5.7.2 by Changing Type of Structural Integrity Assessment Required from Probabilistic to Deterministic ML20155F4501998-10-30030 October 1998 Proposed Revised Improved Tech Specs (ITS) Deleting Note Re Number of Required Channels for Degrees of Subcooling Function & Subdividing Core Exit Temp Function Into Two New Functions in ITS Table 3.3.17-1 ML20155F4021998-10-30030 October 1998 Proposed Revised Improved Tech Specs (ITS) Section 5.6.2.19, ITS Section 3.4.11,Bases 3.4.11 & 3.4.3 Re PTLR & LTOP Limits ML20155F9551998-10-30030 October 1998 Proposed Tech Specs Pages to LAR 245,changing Methodology for Sf Pool B Criticality Analysis ML20154P3101998-10-16016 October 1998 Proposed Tech Specs Resolving USQ by Leaving Valves DHV-34 & DHV-35 Normally Closed ML20154C1581998-09-30030 September 1998 Proposed Tech Specs Pages Re LAR 238,to Correct RCS Leakage Detection Capability of RB Atmosphere Gaseous Radioactivity Monitor Described in ITS Bases & FSAR ML20238F4761998-08-31031 August 1998 Proposed Tech Specs,Proposing New Repair Process for Plant OTSGs ML20151X0431998-08-31031 August 1998 Proposed Tech Specs Adding Three Addl Reg Guide 1.97 Type a Category 1 Pami Variables & One Type B Category 1 Pami Variable to ITS Table 3.3.17-1, Pami ML20236V8831998-07-30030 July 1998 Proposed Tech Specs Pages Re CREVS & Ventilation Filter Test Program ML20236E9851998-06-30030 June 1998 Proposed Tech Specs Re Exigent License Amend Request 228,rev 1 for Once Through SG Tube Surveillance Program ML20249B2671998-06-18018 June 1998 Proposed Tech Specs Pages Re one-time Exigent License Amend to Allow Operation W/Number of Indications Previously Identified as Tube End Anomalies & Multiple Tube End Anomalies in OTSG Tubes ML20247P8931998-05-22022 May 1998 Proposed Improved Tech Specs 5.2.1 Re Onsite & Offsite Organizations ML20217P5181998-04-28028 April 1998 Proposed Tech Specs Re Reactor Coolant Pump Motor Flywheel Insp ML20217G0121998-04-23023 April 1998 Proposed Improved Tech Specs Section 5.7.2, Special Repts, Clarifying That Complete Results of OTSG Tube Inservice Insp Shall Be Submitted to NRC 90 Days After Startup (Breaker Closure) ML20217C6341998-03-20020 March 1998 Proposed Tech Specs Re Editorial Changes to Improved TS Saftey Limits & Administrative Controls to Replace Titles of Senior Vice President,Nuclear Operations & Vice President, Nuclear Production W/Position of Chief Nuclear Officer ML20217C4931998-03-20020 March 1998 Proposed Improved Tech Specs 5.6.2.8.c Re Reactor Coolant Pump Motor Flywheel Insp ML20203D1611998-02-20020 February 1998 Proposed Tech Specs,Providing Revs to CR-3 Improved TS Bases That Update NRC Copies of Improved TS ML20198S9151998-01-22022 January 1998 Proposed Tech Specs Consisting of Rev 1 to TS Change Request 210,correction of Typo & Addition of Footnotes ML20202G8511997-12-0505 December 1997 Proposed Tech Specs Establishing New Improved TSs (ITS) Surveillance Requirement for Performance of Periodic Integrated Leak Test of Cche Boundary & Revising ITS Bases 3.7.12 to Define Operability of Cche ML20202G7991997-12-0505 December 1997 Proposed Tech Specs Revising Description of Starting Logic for RB Recirculation Sys Fan Coolers to Ensure That Only One RB Fan Starts on Es RB Isolation & Cooling Signal ML20199G8461997-11-21021 November 1997 Proposed Tech Specs Pages Involving Additional Restrictions, Editorial Clarifications & Typos ML20212F2741997-10-31031 October 1997 Proposed Tech Specs Pages Re Decay Heat Removal Requirements in Mode 4 ML20212C9801997-10-25025 October 1997 Proposed Tech Specs Re Power Operated Relief Valve Lift Setpoint TS Limit That Has Been Revised for Instrument Uncertainty ML20217F5231997-10-0404 October 1997 Proposed Tech Specs Pages Addressing Revision to Description of Electrical Controls for Operating Reactor Building (RB) Recirculation Sys fan/cooler,AHF-IC,as Discussed in FSAR & Improved TS ML20217D2741997-10-0101 October 1997 Proposed Tech Specs Adding Methodology to Monitor first-span Intergranular Attack (Iga) Indications & Disposition Growth During Future B OTSG Eddy Current Exams ML20210T9771997-09-12012 September 1997 Proposed Tech Specs Replacement Pages Re New Improved TS 3.4.11 Re Low Temp Overpressure Protection Sys ML20216F8481997-09-0909 September 1997 Proposed Tech Specs Re Analysis Rev for Makeup Sys Letdown Line Failure Accident as Discussed in FSAR ML20217Q2121997-08-26026 August 1997 Proposed Tech Specs Changing Design Basis of EDG Air Handling Sys ML20217N2501997-08-20020 August 1997 Proposed Improved Tech Specs 5.6.2.10 Re Tube Surveillance ML20210K8921997-08-16016 August 1997 Proposed Tech Specs 3.8.1.3,requesting one-time Outage on Each EDG to Perform Necessary Mod & Maint ML20151L7541997-08-0404 August 1997 Proposed Tech Specs Extending Frequency of EDG Surveillances During Period of Time CR-3 EDGs Are Being Modified ML20196J1431997-07-29029 July 1997 Proposed Tech Specs Adding EDG Kilowatt Indication to post- Accident Monitoring Instrumentation to Support CR-3 Restart Issue of EDG Load Mgt ML20196H0281997-07-18018 July 1997 Proposed Tech Specs Changes Establishing Requirements for Low Temperature Overpressure Protection Sys ML20148K7811997-06-14014 June 1997 Proposed Tech Specs Re Efw,Hpi,Emergency Feedwater Initiation & Control Sys ML20138H8781997-05-0101 May 1997 Proposed Tech Specs Replacing Prescriptive Requirements of 10CFR50,App J,Option a w/performance-based Approach to Leakage Testing Contained in 10CFR50,App J,Option B ML20137X5361997-04-18018 April 1997 Proposed Tech Specs,Providing Revs to CR-3 Improved TS Bases That Update NRC Copies of Improved TS 1999-09-02
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20212C1121999-09-16016 September 1999 Criticality Safety Analysis of W Spent Fuel Storage Racks in Pool B of Crystal River Unit 3 ML20212C0961999-09-16016 September 1999 Proposed ITS & Bases Changes Strikeout & Shadowed Text & Revision Bar Format,Increasing Licensed Capacity for Spent Fuel Assembly Storage in SFP & Revising Configuration for Storage of Fresh Fuel ML20211L1011999-09-0202 September 1999 Proposed Tech Specs Re Once Though SG Tube Surveillance Program,Alternate Repair Criteria (ARC) for Axial Tube End Crack (Tec) Indications ML20212C0991999-08-31031 August 1999 Criticality Safety Analysis of Crystal River Unit 3 Pool a for Storage of 5% Enriched Mark B-11 Fuel in Checkerboard Arrangement with Water Holes ML20209D2971999-07-0808 July 1999 Proposed Tech Specs,Changing ITS for CREVS & VFTP & Correcting Typo in ITS Section 5.6.2.12 ML20195B8091999-05-26026 May 1999 Proposed Tech Specs,Revising ITS Bases That Will Update NRC Copies of ITS ML20195B7081999-05-17017 May 1999 Proposed ITS Section 3.3.8, EDG Lops, SR 3.3.8.1,revising Note for Surveillance & Deleting Note for Frequency ML20206S7691999-05-12012 May 1999 Proposed Improved Tech Specs Pages 3.4-21 Through 3.4-21D ML20206N1401999-05-10010 May 1999 Proposed ITS Administrative Controls Section 5.8, High Radiation Area ML20206M0961999-05-0707 May 1999 Proposed Tech Specs,Revising Wording for SR 3.5.2.5 to Be More Consistent with NUREG-1430,Rev 1 & Clarifying Process of Valve Position Verification ML20206H6541999-05-0505 May 1999 Proposed Tech Specs,Proposing Alternate Repair Criteria for Axial Tube End crack-like Indications in Upper & Lower Tubesheets of CR-3 OTSGs ML20204D9211999-03-18018 March 1999 Proposed Tech Specs Re OTSG Tubes Surveillance Program,Tube Repair Roll Process ML20205A7651999-03-18018 March 1999 Rev 29 to AR-305, Es E Annunciator Response ML20205A7961999-03-15015 March 1999 Rev 22 to AR-301, ESA Annunciator Response ML20205A8051999-03-15015 March 1999 Rev 33 to AR-303, ESC Annunciator Response ML20205A8211999-03-15015 March 1999 Rev 35 to AR-403, PSA H Annunciator Response ML20205A3441999-03-12012 March 1999 Rev 25 to AR-402, PSA G Annunciator Response ML20204D5781999-03-0909 March 1999 Rev 10 to AP-513, Toxic Gas ML20204D5821999-03-0808 March 1999 Rev 22 to AR-603, Tgf O Annunciator Response ML20207H7741999-03-0303 March 1999 Rev 15 to AR-602, Tgf N Annunciator Response ML20207J6591999-03-0202 March 1999 Rev 18 to AR-504, ICS L Annunciator Response ML20207J6461999-03-0202 March 1999 Rev 21 to AR-301, ESA Annunciator Response ML20206S7561999-02-28028 February 1999 Rev 2 to Pressure/Temp Limits Rept, Dtd Feb 1999 ML20203C7461999-02-0303 February 1999 Rev 2 to AR-801, FSA Annunciator Response ML20202E6551999-01-27027 January 1999 Proposed Tech Specs Re OTSG Tubes Surveillance Program,Insp Interval Extension ML20202B1411999-01-22022 January 1999 Rev 22 to AR-401, PSA F Annunciator Response ML20199G5201999-01-15015 January 1999 Rev 11 to AP-961, Earthquake ML20199G5581999-01-12012 January 1999 Rev 4 to AP-404, Loss of Decay Heat Removal ML20199G5691999-01-12012 January 1999 Rev 4 to AP-604, Waterbox Tube Failure ML20198T2411999-01-0606 January 1999 Rev 19 to AR-701, Ssf P Annunciator Response ML20196G6771998-12-0101 December 1998 Rev 17 to Annunciator Response AR-702, Ssf Q Annunciator Response ML20196D6761998-11-30030 November 1998 Proposed Tech Specs LCO 3.9.3,allowing Both Doors in Personnel Air Locks & Single Door in Oeh to Be Open During Refueling Operations ML20196G5851998-11-25025 November 1998 Rev 32 to AR-303, ESC Annunciator Response ML20196G3371998-11-25025 November 1998 Reissued Rev 15 to AR-702, Ssf Q Annunciator Response ML20195K4551998-11-24024 November 1998 Proposed Tech Specs,Installing diesel-driven EFW Pump to Remove Interim ITS & Provide Resolution to EDG Capacity Limitations ML20196F6691998-11-24024 November 1998 Rev 11 to AP-330, Loss of Nuclear Svc Cooling ML20195K0031998-11-23023 November 1998 Proposed Tech Specs Re LAR Number 241,rev 0 for High Pressure Injection Sys Mods ML20196F7721998-11-23023 November 1998 Rev 3 to EOP-12, Station Blackout ML20196F7031998-11-23023 November 1998 Rev 3 to AP-404, Loss of Decay Heat Removal ML20196F7541998-11-23023 November 1998 Rev 7 to EOP-08, LOCA Cooldown ML20196F7461998-11-23023 November 1998 Rev 6 to EOP-07, Inadequate Core Cooling ML20196F7241998-11-23023 November 1998 Rev 2 to AP-510, Rapid Power Reduction ML20196F7161998-11-23023 November 1998 Rev 9 to AP-470, Loss of Instrument Air ML20196F8711998-11-23023 November 1998 Rev 28 to AR-305, Es E Annunciator Response ML20196F9451998-11-19019 November 1998 Rev 7 to AP-1080, Refueling Canal Level Lowering ML20196F9381998-11-19019 November 1998 Rev 27 to AP-770, Emergency Diesel Generator Actuation ML20195H6581998-11-17017 November 1998 Proposed Improved Tech Specs (Its),Revising 5.7.2 by Changing Type of Structural Integrity Assessment Required from Probabilistic to Deterministic ML20196D8321998-11-13013 November 1998 Rev 1 to Crystal River Unit 3 ASME Section Xi,Isi Program Interval 3 & Ten Yr NDE Program ML20195H8761998-11-0505 November 1998 Rev 23 to AR-302, Esb Annunciator Response ML20155F4021998-10-30030 October 1998 Proposed Revised Improved Tech Specs (ITS) Section 5.6.2.19, ITS Section 3.4.11,Bases 3.4.11 & 3.4.3 Re PTLR & LTOP Limits 1999-09-02
[Table view] |
Text
. .- .- . - . _ _ - . - _- .- _-- - . - - . . .- -
1 I
n- ,
l 1"
l
( FLORIDA POWER CORPORATION s Crystal River Unit 3 Docket No. 50-302/ License No. DPR-72 Request No. I10, Revision 0 Operation of Closed Containment Isolation Valves
?- i
, LICENSE DOCUMENT INVOLVED:
Technical Specifications (Appendix A) j PORTION:
3/4.6.3 Containment Isolation Valves DESCRIPTION OF REQUEST:
This submittal requests the Nuclear Regulatory Commission to approve a Technical '
Specification amendment to allow operation (opening) of certain containment isolation valves when they would normally be required to be isolated provided that a dedicated operator is posted to isolate the valve when necessary.
~
REASON FOR REQUEST:
Since initial startup Florida Power Corporation, like other Standard Technimi Specification plants, has been allowed to continue POWER OPERATION with containment isolation 1 valve (s) inoperable provided, at least one of the following criteria is satisfied:
- a. The inoperable valve (s) are restored to operability in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />,
- b. The penetration is isolated using at least one deactivated and isolated automatic valve in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, or .
- c. The penetration is isolated using at least one closed manual valve or blind flange
, in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
Such ACTIONS, although allowing continued POWER OPERATION, significantly reduced operator flexibility with regard to other Technical Specification requirements and/or plant operation of ten even making it impossible to fulfill other requirements.
! . 07e example of isolation of an inoperable containment isolation valve affecting another i \ , Technical Specification requirement was brought to light by IE Inspection Report 83-10.
l 3 Containment isolation valve, CAV-6, had been declared inoperable because it would not L ' close under system pressure. In accordance with Action b, above, the penetration was isolated. Upon reaching 15% RTP, Environmental Technical Specification 2.4.1.0 requires that a sample from the Steam Generators be obtained and analyzed every four hours. Yet to V obtain this sample CAV-6 must be operated, which is not allowed by Technical Specification l 3.6.1.3. These two specifications therefore have placed Florida Power Corporation in a
.g a necessitates an immediate plant shutdown or violation of Technical
?~
l^
[,,' position
'~
Specifications. that A plant shutdown subjects the plant to unnecessary transients that are not
- w commer.surate with the pra.eu at hand (i.e. an inoperable containment isolation valve).
i t 4
i 8404300082 840423 i PDR ADOCK 05000302- ;
- P. PDR ,,
Since Inspection Report 83-10, Florida Power Corporation has reviewed other Technical Specifications to identify additional conflicts. The Technical Specifications that are affected by the inoperability and isolation of certain valves are described in the " Basis for Operation" for applicable valve (s) in the Enclosure.
Additionally there are some valves that are required to be locked closed due to lack of an ES actuation signal. For several reasons, stated in the Enclosure, Florida Power Corporation would also like to be able to use these isolated penetrations.
EVALUATION This submittal requests that Florida Power Corporation be allowed to open certain isolated containment isolation valves, as suggested in NUREG 0103, Standard Technical Specifications Revision 4. When one of the specified valves is opened, a dedicated operator will be stationed at a valve to isolate the affected penetration. The dedicated operator is considered to be sufficient to assure that the penetration is isolated upon receipt of a containment isolation signal. For several of these valves the Commission has previously granted temporary approval to operate the valve intermittently. Amendment 27, dated January 23, 1980, granted temporary approval to intermittently operate CAV-1, to allow sampling of the pressurizer steam space. Additionally, Florida Power has requested and been granted (verbal) permission to operate CAV-6 and 7, SAV-23 and 24 and LRV-70,71,72 and 73.
The attached Enclosure describes which valves Florida Power is requesting approval for operation using a dedicated operator. The valves' function and the basis for the request is also included for each valve.
In most cases, described on the Enclosure, operation of the isolated valves is necessary to comply with surveillance or sampling requirements in the Technical Specifications. To prevent these activities would cause the unit to' shutdown due to failure to fulfill these l specifications. This is not a reasonable or desirable course of action when considering that
- i these valves can be controlled adequately by a dedicated operator.
1 1
I i
1 4
I
.. - . . . - . .- , , . . . , .- . -....~: -.a.-
ENCLOSURE
- 1. Yalves: CAV-1,2,3 and 126 Function: These automatic valves are the Reactor Coolant System sample valves. The samples are used to assure that the specific activity and chemical concentrations are maintained within Technical Specification limits.
Basis for Operatiom Technical Specifications 3.4.7 and 3.4.8 require that the Reactor Coolant System chemistry and specific activity be determined to be within limits as often as every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. When inoperability of any of these valves causes isolation of the entire penetration, the samples required by 3.4.7 and 3.4.8 can not be obtained.
- 2. Valves: CAV-4, 5, 6 and 7 Function: These automatic valves are the Steam Generator Sample Valves (Shell Side). The samples obtained are one method of detecting a primary to secondary Steam Generator leak.
Basis for Operation:
Environmental Technical Specification 2.4.1.0 requires that the Steam Generators be sampled every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> daring low power bleeds.
With any of the valves inoperable and isolated this Specification can not be met.
- 3. Valves: CFV-25 and 26 Function: These automatic valves supply water to the Core Flood Tanks from the Make-up System.
Basis for Operation:
Technical Specification 3.5.1.b. requires that each core flood tank have a volume of borated water between 7555 and 8005 gallons. With either of these valves inoperable and isolated, additional borated water cannot be added to these tanks if necessary.
- 4. Valves: CFV-II,12 and 42 Function: These automatic valves are the core flood tank sample valves. The samples are used to assure that an adequate boron concentration is maintained in the core flood tanks.
Basis for Operation:
Technical Specification 3.5.1.c requires that the boron concentration in the core flood tanks be determined at least once every 31 days.
With any of these valves inoperable and isolated this specification can not be met.
- 5. Valves: CFV-27 and 28 Function: These automatic valves provide nitrogen cover - pressure to the core flood tanks. The cover - pressure assures that there is sufficient motive force to cause the core flood tanks to discharge cooling water into the Reactor Coolant System during an accident.
Basis for Operation:
Technical Specification 3.5.1.d requires that the nitrogen cover -
pressure be maintained between 575 and 625 psig. With either of these valves inoperable and isolated, additional nitrogen cannot be added to these tanks to maintain the pressure if necessary.
- 6. Valves: SAV-23 and 24 (Manual)
Function: These manual valves supply air to the Reactor Building for breathing.
Basic for Operation:
During HOT STANDBY or HOT SHUTDOWN respirators are often necessary when performing maintenance in the Reactor Building. Air supply for these respirators is supplied by the station air system.
Operation of these valves allows Florida Power to perform maintenance during plant operation.
4
i
- 7. Valves: LRV-70,71,72 and 73 Function: These normally locked closed automatic valves provide a flow path for a " mini" hydrogen purge system. Although the valves and piping are installed, the system is still incomplete.
Basis for Operation:
Operation of these valves allows Florida Power to decrease the Reactor Building pressure during power operations. These releases will be monitored by the Reactor Building Radiation Monitor, RM-A1.
__mo..
TABLE 3.6-1 CONTAINMENT ISOLATION VALVES
~
VALVE NUMBER FUNCTION ISOLATION TIME (seconds)
A. CONTAINMENT ISOLATION
- 1. BSV-27 check # closed dur. nor, operation NA and open dur. RB spray BSV-3 # 60 BSV-26 check # NA BSV-4 # 60
- 2. CAV-126 (A)*+ iso. CA sys. fr. RC letdn. 60 CAV-1 (A)*+ iso. CA sys. fr. pzr. 60 CAV-3 (A)*+ 60 CAV-2 (B)*+ iso. CA sys. fr. RB 60 CAV-4 # (A)*+ isolate liquid sampling system 60 CAV-6 # (B)*+ 60 CAV-5 # (A)*+ 60 CAV-7 # (B)*+ 60 CAV-429
- iso. CA fr. RC NA CAV-430
- iso. CA fr. RB 60 CAV-432
- 3. CFV-20 check iso. N2 supply fr. CFT-1 A NA CFV-28 (A/B)*+ "
60 I CFV-17 check iso. N2 supply fr. CFT-1B NA CFV-27 (A/B)*+ 60 l CFV-18 check iso. MU system fr. CFT-1B NA
" I CFV-26 (A/B)*+ 60 CFV-19 check iso. MU system fr. CFT-1 A -NA 60 I CFV-25 (A/B)*+ '
CFV-42 (B)*+ . iso. liquid sampling fr. CF system 60 l CFV-15 (A)* iso. WD sys fr. CF tanks 60 CFV-16 (A)* 60 CFV-29 (B)* 60 CFV-II (A)*+ iso. CF tanks fr. liquid sampling 60 system CFV-12 (A)*+. 60
' CRYSTAL RIVER - UNIT 3 ~3/46-17
TABLE 3.6-1 (continued)
CONTAINMENT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME (seconds)
- 4. CIV-41* iso. Cl sys. fr. RB 60 CIV-40* 60 CIV-34* 60 CIV-35* 60
- 5. DHV-93 check iso. DH system fr. pzr. NA DHV-91
- 60 DHV-43 # iso. DH sys. fr. RB sump 120 DHV-42 # 120 DHV-4# & 41# iso. DH sys. fr. RC 120 DHV-6 # iso. DH system from Reactor Vessel 60 DHV-5 # 60
- 6. DWV-162 check iso. DW system fr. RB NA DWV-160 (A/B)* 60
- 7. FWV-44 check # iso. feedwater from RCSG-1A NA FWV-45 check # NA FWV-43 check # iso. feedwater from RCSG-1B NA FWV-46 check # NA
- 8. LRV-70 *+ iso. H2 Purge sys. from RB NA
" NA LRV-71 *+
LRV-72 *+ NA LRV-73 *+ NA
- 9. MSV-130 #(A/B)* iso. MDT-1 from RCSG-1 A 60 MSV-148 #(A/B)* iso. MDT-1 from RCSG-1B 60 MSV-411 #
- iso. mala steam lines from RCSG-1 A 60 MSV-412 #
- e. .
l
.; 1 TABLE 3.6-1 (continued)
CONTAINMENT ISOLATION VALVES VALVE NUMBER FUNC riON ISOLATION TIME (seconds)
LRV-51 iso. atmos, vent and RB NA LRV-35 & 47 purge exhaust system from RB NA LRV-49 iso, atmos vent from RB NA LRV-38 & 52 NA LRV-45 iso. LR test panel from RB NA LRV-44 NA LRV-46 NA
- 3. MSV-146# iso. misc. waste storage NA tank from RCSG-1B
- 4. NGV-62 iso. NG system from NA steam generators NGV-81 # NA NGV-82 iso. NG system from pzr. NA
- 5. SAV-24+ iso. SA from RB NA SAV- 23+ NA SAV-122 NA
- 6. SFV-18 iso. SF system NA SFV-19 NA SFV-Il9# iso. Fuel Transfer tubes NA from F. T. Canal SFV-120# NA
- 7. WSV-1 iso. containment monitoring NA system from RB WSV-2 NA D. . PENETRATIONS REQUIRING TYPE B TESTS Blind Flange 119 iso. RB NA Blind Flange 120 NA Blind Flange 202 NA s
I CRYSTAL RIVER - UNIT 3 3/4 6-21
r
TABLE 3.6-1 (continued)
CONTAINMENT ISOLATION VALVES VALVE NUMBER FUNCTION ISOLATION TIME (seconds)
D. PENETRATIONS REQUIRING TYPE B TESTS Blind Flange 348 iso. fuel transfer tube from Transfer Canal NA Blind Flange 436 NA Equipment Hatch iso. RB NA Personnel Hatch NA
- Not subject to Type C Leakage Test The provisions of Specification 3.0.4 are not applicable.
+ May be opened under administrative control.
(A) Isolates on Diverse Isolation Actuation Signal A (B) Isolates on Diverse Isolation Actuation Signal B (A/B) Isolates on Diverse Isolation Actuation Signal A or B CRYSTAL RIVER - UNIT 3 - 3/4 6-21a
r :.
NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION Docket No: 50-302 Facility: Crystal River Unit 3 Licensee: Florida Power Corporation Date of Application:
Request For:
Florida Power Corporation requests an amendment to the Technical Specifications to allow operation of certain containment isolation valves when they would normally be required to be isolated provided that a dedicated operator is posted to isolate the valve if necessary.
Significant Hazards Consideration Determination:
(x) Amendment involves no significant hazards considerations.
( ) Amendment involves significant hazards considerations.
Basis for Determination:
This amendment is considered not likely to involve significant hazards considerations because the change is clearly within the criteria of NUREG-0103, referenced in chapter 16 of the Standard Review Plan.
Requested Implementation Date:
Florida Power Corporation does not request a specific implementation date.
1
--