MONTHYEARML20063E3441982-08-24024 August 1982 Responds to IE Bulletin 80-11, Masonry Wall Design, Per NRC 820721 Request.Responses to Questions 2,4 & 14 Re Stack Bonding & Modeling Techniques Encl Project stage: Request ML20073J3051983-03-16016 March 1983 Advises That Emergency Operations Facility Located Approx 12 Miles from Technical Support Ctr in Ft Lupton,Co,Per .Protection Factor Considerations or Ventilation Protection Not Required Per NUREG-0696 Project stage: Other ML20073M1481983-04-14014 April 1983 Forwards Info Re Status of Implementation of Suppl 1 to NUREG-0737 Concerning Requirements for Emergency Response Capabilities,In Response to Generic Ltr 82-33.Affidavit, Tables & Computer Configuration Diagrams Encl Project stage: Other ML20077C7091983-07-0505 July 1983 Clarifies 830414 Response to Generic Ltr 82-33 Re Emergency Response Facilities (Erf).Safety Parameter Display Sys,Reg Guide 1.97 Instrumentation,Control Room Design Review & ERF Activities Will Be Completed by Fourth (Dec 1985) Refueling Project stage: Other ML20087J2851984-03-0909 March 1984 Forwards Revised Schedule for Supplying Info Re Emergency Response Capabilities Requested by Generic Ltr 82-33,per 840223 Telcon.Reg Guide 1.97 Rept Will Be Completed by 850228 Project stage: Other ML20090H9391984-07-19019 July 1984 Requests That NUREG-0737,Item I.C.1 Be Closed & Implementation of Detailed Program Generation Package Be Delayed Until Completion of Preimplementation Audit of Detailed Control Room Design Review Project stage: Other ML20116N9181985-04-30030 April 1985 Forwards Updated Schedule for Providing Info on Emergency Response Capabilities Detailed Summary of Transpired Activities Required Per Generic Ltr 82-33 Project stage: Other ML20203P8481986-04-25025 April 1986 Requests NRC Concurrence to Change Upgrade & Implementation of Emergency Operating Procedure to Restart After Fourth Refueling to Make All Commitments Required by Suppl 1 to NUREG-0737 & SPDS Consistent Project stage: Other 1983-07-05
[Table View] |
Text
3 p)}to public service company ce cone n do July 5, 1983 Fort St. Vrain Unit No. 1 k f'g Mr. John T. Collins, Regional Administrator U. S. Nuclear F.egulatory Commission 611 Ryan Plaza Drive, Suite 1000
, g,6 Arlington, Texas 76011 Attn:
Mr. Phil Wagner
SUBJECT:
Completion Date for ERFs
REFERENCE:
1.) Generic Letter 82-33 2.) PSC Letter P-83147 (Lee to Denton, dated 4/14/83)
Dear Mr. Wagner:
The following is supplied as a clarification of PSC's letter P-83147 in regards to the completion date for PSC's Emergency Response Facilities (ERFs).
~PSC is proceeding in a parallel mode concerning the implementation of the Safety Parameter Display System, Regulatory Guide 1.97 Instrumentation, the Control Room Design Review and.
finalization of the ERFs. These activities will be initially completed and in service by Fort St. Vrain's 4th refueling (currently scheduled for December, 1985). These activities will then be evaluated by a verification and validation effort. Any problems
~
identified during this verification and validation review will be resolved by Fort St. Vrain's 5th refueling.
I hope this clarifies the original intent of PSC's letter l
P-83147.
If you have any questions please call Mike Niehoff at (303) 785-2223, extension 403.
Very truly yours, NW H. L. Brey, Manager I
5 Nuclear Engineering Division f
k HLB / MEN /sca