ML20203P848
| ML20203P848 | |
| Person / Time | |
|---|---|
| Site: | Fort Saint Vrain |
| Issue date: | 04/25/1986 |
| From: | Brey H PUBLIC SERVICE CO. OF COLORADO |
| To: | Berkow H Office of Nuclear Reactor Regulation |
| References | |
| RTR-NUREG-0737, RTR-NUREG-737 GL-82-33, P-86331, TAC-57646, NUDOCS 8605080243 | |
| Download: ML20203P848 (2) | |
Text
-
OPublic Service ~
e m s-*a Company of Colorado 2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 April 25, 1986 Fort St. Vrain Unit No. 1 P-86331 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555 ATTN: Mr. H.N. Berkow, Director Standardization and Special Projects Directorate Docket No. 50-267
SUBJECT:
Upgrading and Implementation of Emergency Operating Procedures (E0P's)
REFERENCES. 1) PSC Letter, Warembourg to Johnson, Dated 4/30/85 (P-85143)
- 2) PSC Letter, Gahm to NRC, Dated 10/30/85 (P-85386)
- 3) NRC Letter, Butcher to Lee, Dated 8/2/85 (G-85345)
- 4) NRC Letter, Eisenhut to Distribution, Dated 12/17/82(G-83009) vear Mr. Berkow:
In Reference 1, Public Service Company of Colorado (PSC) ccmmitted to revise, implement, and provide training on the Fort St.
Vrain (FSV)
Emere n cy Operating Procedures (EOP's).
PSC advised the NRC that this.ammitment would be completed 18 months after PSC's Procedures Generation Package (PGP) submittal. Since PSC submitted our PGP on October 30, 1985, (Reference 2) the upgraded E0P's are currently scheduled to be implemented by April 30, 1987. NRC's understanding of this date is reflected in Reference 3.
49 i
8605000243 860425 0
PDR ADOCK 05000267 1
P PDR
P-86331 Page 2
~
April 25, 1986 PSC's commitment to upgrade and implement the FSV E0P's is one of several commitments that resulted from Supplement I to NUREG-0737,
" Requirements for Emergency
Response
Capability", which was transmitted by Generic Letter 82-33 (Reference 4). PSC's comitments to:
(1) make the Safety Parameters Display System (SPDS) operational and fully train FSV operators; (2) the installation of Regulatory Guide 1.97 equipment for post-accident monitoring; (3) completion of the control room design review for human factors engineering considerations, are all scheduled for restart after fourth refueling.
As discussed earlier, PSC's comitment to upgrade and implement the 1
E0P's is scheduled for completion on April 30, 1987.
Since work on the E0P's is closely tied to the SPDS and other NUREG-0737, Supplement I requirements, changes in those areas could impact the E0P's. Therefore, to make all these commitments consistent, PSC requests NRC concurrence to change the upgrade and implementation of the E0P's to restart after the fourth refueling. This change will permit comprehensive integration of SPDS enhancements and other NUREG-0737 requirements into the Emergency Operating Procedures.
I appreciate your concurrence on this matter.
If you have any questions, please call Mr. M.H. Holmes at (303) 480-6960.
Sincerely, IL L. 0< <
7 & 7>).a &
H. L. Brey, Manager Nuclear Licensing and Fuels Division HLB:KP0:jw Reviewed By:
m k
~ ~,