Forwards Revised Schedule for Supplying Info Re Emergency Response Capabilities Requested by Generic Ltr 82-33,per 840223 Telcon.Reg Guide 1.97 Rept Will Be Completed by 850228
ML20087J285
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 03/09/1984
From: Brey H
PUBLIC SERVICE CO. OF COLORADO
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
RTR-REGGD-01.097, RTR-REGGD-1.097 GL-82-33, P-84079, TAC-57646, NUDOCS 8403220138
Download: ML20087J285 (3)


Text

_ _ - _

L public Senlee Company fP Odicrado 6

March 9, 1984 Fort St. Vrain Unit No. 1 P-84079

  • M@20MS 4 John T. Collins, Regional Administrator MAR l 6 $4 U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 S

Arlington, Texas 76012 Attn:

Mr. Phil Wagner

SUBJECT:

Emergency Response Capabilities

REFERENCES:

PSC Letter P-83147 Dated April 14, 1983 Lee to Denton PSC Letter P-83234 Dated July 5, 1983 Brey to Collins PSC Letter P-83360

' Dated November 4, 1983 Brey to Collins

Dear Mr. Collins:

The purpose of this letter is to provide a revised schedule for supplying the information originally requested by NRC Generic Letter 82-33, as requested in a February 23, 1984 phone call between Messers P. Wagner (NRC), C. H. Fuller (PSC), and M. E. Niehoff (PSC).

As discussed between the above parties there was a necessity for the NRC to delay the on-site SPDS pre-implementation review from September, 1983 to March, 1984.

Since the SPDS must be integrated with the other Emergency Response Capability (ERC) activities (i.e.

R.G. 1.97 and Control Room Design Review) the schedule for these activities has also been impacted. Attached to this letter is a marked up copy of the original schedule (submitted by reference 1 above) marked up to reflect the current schedule.

Please note that PSC made a commitment in our April 14, 1983 letter (reference 1, above) to confirm the estimated schedules by Apri1 14, 1984 or give reasons for slippage. This letter should also be considered as the fulfillment of this commitment.

840322013e 840309 PDR ADOCK 05000267 PDR g

F 1

  1. M If there are any questions regarding this letter please contact Mr. M. E. Niehoff at (303) 785-2223, extension 403.

Very truly yours, MC j

H. L. Brey, Manager Nuclear Engineering Division HLB / MEN /sem

P-83147 Page 9 h

ATTACHMENT P-84079 SCHEDULE Based on our current operating schedule, PSC projects that the process through the " integration of all control room elements" stage can be completed by the time the plant starts back into operation after the 4th refueling, which is projected to occur late in 1985.

Because all the ingredients in this program are not entirely controllable by PSC, there is a possibility that this date may slip.

With our current knowledge and understanding PSC believes the fourth refueling date is achievable.

By April 15, 1984, PSC will confirm this schedule or provide a revised schedule and the reasons for any slippage.

The EPs training program and required design modifications will be implemented. after the Verification and Validation process has been completed, anomalies resolved, and the appropriate procedures, training program or designs revised.

PSC currently projects this process will be accomplished before plant startup after the 5th refueling, which is projected to occur in mid-1987.

This date obviously has many variables which are not controllable by PSC. Since hardware modifications may be included, design, procurement, assembly, testing, qualification, delivery and installation all become variables in tnis schedule.

PSC will reconfirm this schedule or give a better estimate and the reasons for any slippage by April 15, 1984.

In addition to schedules discussed above, PSC expects to submit the information requested in Generic Letter 82-33 for NRC review in accordance with the following schedule:

Generic Letter 82-33 Submittal Reference Estimated Schedule Revised Schedule i

1.

SPDS Safety Analysis 4.la Mecch -BG,--l964-September: 20, 1984 2.

CRDR Program Plan 5.2a Jule-1-5,--l-9G3-Complete l

3.

CRDR Summary Report 5.2b Octobec -R,--1984-April 30, 1985 4.

RG 1.97 Report 6.2 Auguet-41,--1464 February 28, 1985 5.

EP Technical 7.2a Complete Complete Guidelines (Generic) 6.

EP Procedures 7.2b Complete Complete Generation Package O

.