Proposed Tech Specs Re Administrative Controls & Include line-item Improvements,Per GL 93-07
ML20072U195
Person / Time
Site: Beaver Valley
Issue date: 08/31/1994
From:
DUQUESNE LIGHT CO.
To:
Shared Package
ML20072U180 List:
References
GL-93-07, GL-93-7, NUDOCS 9409160163
Download: ML20072U195 (70)


Text

.. =

t i

i ATTACHMENT A-1 i

I

{

Beaver Valley Power Station, Unit No. 1 j

Proposed Technical Specification Change No. 216 a

A 1

The following is a list of the affected pages:

i i

1 l

3/4 0-2 6-1

)

6-3 6-5 4

6-7 l

6-8 l

6-10 i

6-11 l

6-12 1

I t

i l

l s

i i

i l

i t

4 I

l 1

i j

l 4

1 i

9409160163 940831 PDR ADOCK 05000334 i

P PDR i

'DPR-66 114.0 APPLICABILITY SURVEILLANCE REQUIREMENTS 1.

At least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, 2.

At least HOT SHUTDOWN within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and 3.

At least COLD SHUTDOWN within the subsequent 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

This specification is not applicable in MODES 5 or 6.

4.0.1 Surveillance Requirements shall be met during the OPERATIONAL MODES

~or other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement.

4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a maximum allowable extension not to exceed 25% of the surveillance interval.

4.0.3 Failure to perform a Surveillance Requirement within the allowed surveillance

interval, defined by Specification 4.0.2, shall constitute noncompliance with the OPERABILITV requirements for a

Limiting condition for Operation.

The time limits of the ACTION requirements are applicable at the time it is identified that a Surveillance Requirement has not been performed.

The ACTION requirements may be delayed for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to permit the completion of the surveillance when the allowable outage time limits of the ACTION requirements are less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Surveillance Requirements do not have to be performed on inoperable equipment.

4.0.4 Entry into an OPERATIONAL MODE or other specified condition shall not be made unless the Surveillance Requirement (s) associated with a

Limiting Condition for Operation has been performed within the stated surveillance interval or as otherwise specified.

This provision shall not prevent passage through or to OPERATIONAL MODES as required to comply with ACTION requirements.

4.0.5 Surveillance Requirements for inservice inspection and testing of ASME Code Class 1, 2 and 3 components shall be applicable i

as follows:

a.l Inservice inspection of ASME Code Class 1, 2 and 3 components j

l cnd inccrvicc testing of ASME Codc Class 1, 2 and 3 pumyo und

/civcc shall be performed in accordance with Section XI of the l

ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(g). :::ccpt

  • crc cpccific

-uritten rclicf hoc bcen granted by the Corniccicr purcucnt'to l

-10 CFP 50, Eccticr 50.55c(g) (5) (i)

$10063AL A b.

Surveillance intervals specified in Section XI of the ASME.

l Boiler and Pressure Vessel Code and applicable Addenda for the inservice inspection and testing activities required by the ASME Boiler and Pressure Vessel Code and applicable Addenda shall be applicable as follows in these Technical Specifications:

BEAVER VALLEY - UNIT 1 3/4 0-2 Amendment No.

M l

,c,

Attachment to Surveillance Reauirement 4.0.5 Insert "A"

a.2 Inservice testing of ASME Code Class 1, 2 and 3 pumps and valves shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(f).

L l

i l

i l

i i

I l

I

+

t l

l l

l 4

)

1 BEAVER VALLEY - UNIT 1 Insert A - Page 1 of 1 (Proposed Wording)

4 DPR-66 ADMINISTRATIVE CONTROLS 6.1 RESPONSIBILITY General Manager, Nuclear Operations shall be responsible l 6.1.1 The for overall facility operation and shall delegate in writing the succession to this responsibility during his absence.

6.2 ORGANIZATION 6.2.1 ONSITE AND OFFSITE ORGANIZATIONS Onsite and offsite organizations shall be established for facility operation and corporate management, respectively.

The onsite and offsite organizations shall include the positions for activities affecting the safety of the nuclear. power plant.

a.

Lines of authority, responsibility and communication shall be establ.ished and defined for the highest management l

levels through intermediate levels to and including all operating organization positions.

These relationships shall be documented and

updated, as appropriate, in the form of organization
charts, functional descriptions of departmental responsibilities and relationships, and job l

descriptions for key personnel positions, or in equivalent forms of documentation.

These requirements shall be documented in the FSAR.

b.

The General Manager, Nuclear Operations shall be responsible I for overall unit safe operation and shall have control over those onsite activities necessary for safe operation and maintenance of the plant.

Msg MDWNWS c.

The A Vice President, Nuclear 4r-sup shall have corporate responsibility for overall plant nuclear safety and shall take any measures needed to ensure acceptable performance of the staff in operating, maintaining, and providing technical support to the plant to ensure nuclear safety.

d.

The individuals who train the operating staff and those who 1

carry out health physics and quality assurance functions l

may report to the appropriate onsite manager; however, they l

shall have sufficient organizational freedom to ensure their independence from operating pressures.

BEAVER VALLEY - UNIT 1 6-1 Amendment No.

b M

W\\

=.

-..=

= --_ __~_= - -- _. _ _ - -. _ - - ~

l DPR-66 ADMINISTRATIVE CONTROLS UNIT STAFF (Continued) i c.

A break of at least eight hours should be allowed between work periods, including shift turnover time.

d..

Except-during extended shutdown

periods, the use of overtime should be considered on an individual basis and not for the entire staff on a shift.

Any deviation from' the above guidelines shall be authorized by the l

General Managerj Nuclear Operations or predesignated alternate, or higher levels of' management.

Authorized deviations to the working hour guidelines shall be documented and available for NRC review.

l t

n l

t l

t i

l BEAVER VALLEY - UNIT 1 6-3 Amendment No.

b

\\

'*-*e

--me

_-_,m,,

DPR-66 ADMINISTRATIVE CONTROLS i

1 6.3 FACILITY STAFF OUALIFICATIONS 6.3.1 Each member of the facility and Radiation Protection staff shall meet or exceed the minimum qualifications of ANSI N18.1-1971 for comparable positions, except for the Health Physics Manager who shall meet or exceed the qualifications of Regulatory Guide 1.8, September

1975, and the technical advisory engineering representative who shall have a bachelor's degree or equivalent in a scientific or engineering discipline with specific training in plant design and response analysis of the plant for transients and accidents.

6.4.1 A

retraining and replacement training program for the facility staff shall be maintained under the direction of the Nuclear Training Manager and shall meet or exceed the requirements and recommendations of Section 5.5 of ANSI N18.1-1971 and Appcndix

"?."

Of 10 CFR Part 55.

6.5 REVIEW AND AUDIT 6.5.1 ONSITE SAFETY COMMITTEE (OSC)

FUNCTION 6.5.1.1 The OSC shall function to advise the General Manager Nuclear Operations on all matters related to nuclear safety and shall provide review capability in the areas of:

a.

nuclear power plant operations b.

radiological safety c.

maintenance d.

nuclear engineering i

nuclear power plant testing e.

f.

technical advisory engineering i

g.

chemistry h.

quality control i.

instrumentation and control I

COMPOSITION 6.5.1.2 The Onsite Safety Committee Supervisor is the OSC Chairman and shall appoint all members of the OSC.

The membership shall consist of a

minimum of one individual from each of the areas designated in 6.5.1.1.

OSC members and alternates shall meet or exceed the minimum qualifications of ANSI N18.1-1971 Section 4.*

for comparable positions.

The nuclear power plant operations indivianal shall meet the qualifications of Section 4.2.2 and the maintenance individual shall meet the qualifications of Section 4.2.3.

i BEAVER VALLEY - UNIT 1 6-5 Amendment No.

Db

DPR-66 ADMINISTRATIVE CONTROLS l

AUTHORITY 6.5.1.7 The OSC shall:

a.

Recommend to the General Manager Nuclear Operations written approval or disapproval of items considered under 6.5.1.6.a through.d above.

b.

Render determinations in writing with regard to whether or not each item considered under 6.5.1.6.a through.e above constitutes an unreviewed safety question.

h h ysww.

M W~

6 c.

Provide written n

ification within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the Vice President Nuclear-p-and the Of fsite Review Committee of disagreement between the OSC and the General Manager Nuclear Operations;

however, the General Manager Nuclear Operations shall have responsibility for resolution of such disagreements pursuant to 6.1.1 above.

RECORDS 6.5.1.8 The OSC shall maintain written minutes of each meeting and copies shall be provided to the General Manager Nuclear Operations and Chairman of the Offsite Review Committee.

6.5.2 OFFSITE REVIEW COMMITTEE (ORC)

FUNCTION 6.5.2.1 The ORC shall function to provide independent review and audit of designated activities in the areas of:

a.

nuclear power plant operations b.

nuclear engineering c.

chemistry and radiochemistry d.

metallurgy l

e.

instrumentation and control l

f.

radiological safety g.

mechanical and electrical engineering i

h.

quality assurance practices l

l BEAVER VALLEY - UNIT 1 6-7 Amendment No.

hk D

DPR-66 ADMINISTRATIVE CONTROLS l

COMPOSITIO gg 6.5.2.2 The chairman and all meaders of the ORC shall be appointed a i

by the Vice President, Nuclear G6eup.

The membership shall consist l.

of a minimum of five individuals who collectively possess a broad based level of experience and competence enabling the committee to review and audit those activities designated in 6.5.2.1 above and to recognize when it is necessary to obtain technical advice and counsel.

An individual may possess expertise in more than one

~

The collective competence of the committee will be specialty area.

maintained as changes to the membership are made.

ALTERNATES 6.5.2.3 All alternate members shall be appointed in writing by the ORC Chairman to serve on a temporary basis; however, no more than two alternates shall participate as voting members in ORC activities

,at any one time.

CONSULTANTS 6.5.2.4 consultants shall be-utilized as determined by the ORC Chairman to provide expert advice to the ORC.

l l

i i

l i

BEAVER VALLEY - UNIT 1 6-8 Amendment No.

D

DPR-66 ADMINISTRATIVE CONTROLS AUDITS 6.5.2.8 ' Audits of facility activities shall be performed under the cognizance of the ORC.

These audits shall encompass:

a.

The conformance of facility operation to provisions contained within the Technical

-Specifications and applicable license conditions at 1:20t cnce per 12 =enths.

l b.

The performance, training and qualifications of the entire I<

facility staff ct lasst cace per 12 months.

c.

The results of actions taken to correct deficiencies occurring in facility equipment, structures, systems, or methods of operation that affect nuclear safety ct 1 cast l

-ence per f renth.

d.

The performance of activities required by the Quality Assurance Program to meet the criteria of Appendix "B",

10 CFR 50, et le::t enc; per 24 months.

I e.

The Facility EmergencyPlanandimplementingproceduresaj least once per 12 months

\\bt:1_ uc,Wh. " Nct GeJ4" f.

The Facility Security Plan and implementing procedures at) least once per 12 months y g

g,. g gg..

g.

Any other area of facility operation considered appropriate by the ORC or the,,Vice President, Nuclear l

lb%%McA srest h.

The Facility Fire Protection Program and implementing I

procedures at ic;st once par 24 monthsr c-1.

An independent fire protection and loss prevention program]

inspection and audit shall be performed at least once per-licenseej 12 months utilizing either qualified off-site personnel or an outside fire protection firm.

g y

thefireprotectionand[oss j.

An inspection and audit of prevention program shall be performed by a

qualified g

outside fire consultant at lccet One p r 25. nthe.

k. % obM h% thhhh mheh\\ 6e6 A'trMshg KYOLN

\\ ML 3&l% hhb\\)qhtn trt\\\\vn}\\W CD 3 D M \\h N 3R I

M\\C:ihML. Whh.

i BEAVER VALLEY - UNIT 1 6-10 Amendment No.

V%O OG

f i

3 DPR-66 l

ADMINISTRATIVE CONTROLS AUTHORITY ggg g

I 6.5.2.9 The l ORC shall report to and advise the Vice President, Nuclear -Crcup on those areas of responsibility specified in Section i

6.5.2.7 and 6.5.2.8.

RECORDS 6.5.2.10 Records of ORC activities shall be prepared, approved and-distributed as indicated by the following:

a.

Minutes of each ORC meeting shall be prepared for and approved by the ORC Chairman or Vice-Chairman within 14 days following each meeting.

b.

Reports of reviews encompassed by Section 6.5.2.7 above, j

shall be documented in'the ORC meeting minutes.

l

's<

c.

Audit reports encompa ed by Section 6.5.2.8 abpve, shall be forwarded to the Vice President, Nuclear-0. cup and to l

l the management positions responsible for the areas audited within 30 days after completion of the audit.

j l

6.6 REPORTABLE EVENT ACTION J

6.6.1 The following actions shall be taken for REPORTABLE EVENTS:

a.

The Commission shall be notified in accordance with 10 CFR 50.72 and/or a

report be submitted pursuant to the requirements of Section 50.73 to 10CFR Part 50, and b.

Each REPORTABLE ' EVENT shall be reviewed by the OSC, and results of this review shall be submitted to the ORC.

6.7 SAFETY LIMIT VIOLATION 6.7.1 The following actions shall be taken in the event a safety Limit is violated:

a.

The facility shall be placed in at least HOT STANDBY within one (1) hour.

b.

The Safety Limit violation shall be reported to the Commission within one hour and to the General Manager, Nuclear Operations and to the ORC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

BEAVER VALLEY - UNIT 1 6-11 Amendment No.

5k OL

t DPR-66 ADMINISTRATIVE CONTROLS j

SAFETY LIMIT VIOLATION (Continued) i c.

A Safety Limit Violation Report shall be prepared.

The report shall be reviewed by the On-Site Safety Committee (OSC).

This report shall describe (1) applicable circumstances preceding the violation, (2) effects of the violation upon facility components, systems or structures, and (3) corrective action taken to prevent recurrence.

l d.

The Safety Limit Violation Report shall be submitted to the l

Commission, the ORC and the General

Manager, Nuclear Operations within 30 days of the violation.

l 6.8 PROCEDURES 6.8.1 Written procedures shall be established, implemented, and i

maintained covering the activities referenced below:

a.

The applicable procedures recommended in Appendix "A"

of i

Regulatory Guide 1.33, Revision 2, February 1978.

f b.

Refueling operations.

c.

Surveillance and test activities of safety related equipment.

h eurity Plan implementati h M RS LO\\

d.

hergencyPlanimplementatio3 MEL ON l

e.

f.

Fire Protection Program implementation.

g.

PROCESS CONTROL PROGRAM implementation.

j h.

OFFSITE DOSE CALCULATION MANUAL implementation.

6.8.2 Each procedure and administrative policy of 6.8.1 above and i

changes of intent thereto, shall be reviewed by the OSC and approved by the General Manager Nuclear Operations, predesignated alternate or a

predesignated Manager to whom the General Manager Nuclear Operations has assigned in writing the responsibility for review and l

approval of specific subjects considered by the committee, as applicable.

Changes to procedures and administrative policies of 6.8.1 above that do not receive OSC

review, such as correcting typographical
errors, reformatting procedures and other changes not affecting the purpose for which the procedure is performed shall independent review by a qualified individual and approved receive an by a designated manager or director.

BEAVER VALLEY - UNIT 1 6-12 Amendment No.

hb N ( d d\\M

)

ATTACHMENT A-2 Beaver Valley Power Station, Unit No. 2 Proposed Technical Specification Change No. 83 The following is a list of the affected pages:

License Page 4 License Page 5 3/4 0-2 6-1 6-2 6-3 6-6 6-8 6-9 6-10 6-11 j

6-12 1

i 1

l i

e

\\

i

)

I I

i i

i i

l A

I i

1 i

6 l

4 9

3

i a

j NPF-73

] %%R g fk"M' 1

e T

(3)

Initial Startup Test Program (Section 14 of the SER, and j

Supplements 3 ano 5) i Any changes to the Initial Test Program described in Section 14 i

of the FSAR made in accordance with the provisions of 10 CFR

{

50.59 shall be mported in accordance with 50.59(b) within j

Qne month of such change.

f (4) Fresh Fuel Storage The following criteria apply to the storage.and handling of l

new fuel assemblies in the fuel handling building:

j

-(a) No more than two fuel assemblies shall be out of approved i

shipping containers or fuel assembly storage racks at any j

one time.

i (b) The minimum edge-to-edge distance between the above two new i

assemblies, the shipping container array, and the storage j

rack arrays shall be at least 12 inches.

s l

(c) New fuel assemblies shall be stored in such a manner that water would drain freely from the assemblies in the event j

of flooding and subsequent draining of the fuel storage j

area.

(5) inservice Inspection (Section 6.6 of SEk Supplement Sh i

DLCo shall submit an inservice inspection program in accordance with 10 CFR 50.55a(g)(4) for staff review by'?

Uune1,1988.

f (6) Formal Federal Emergency Management Agency Finding j

In the event that the NRC finds that the lack of progress in completion of the procedures in the Federal Emergency Management Agency's final rule, 44 CFR Part 350, is an indication that a major substantive problem exists in achieving or maintaining an adequate state of emergency pmparedness, the j

provisions of 10 CFR Section 50.54(s)(2) will apply.

+

(7) r. Plant Safety Monitorino System (PSMS) i DLCo shall submit, on or before November 27, 1987, a verification and validation (V&V) plan which will be able to demonstrate the reliability of the PSMS software. The approved i

V&V plan must be implemented before startup after the second j

refueling outage.

I 3

\\ h t 9 \\. c \\ k D b 1

Amendment No.

h

\\

b NPF-73,

(8) Detailed Control Room Desien Review (DCRDR)

}

Before startup after the first refueling outage, DLCo shall complete all activities, satisfactorily resolve all open issues as described in Section 18.1 of SER Supplement 6, and implement all DLCo-proposed control room improvements resulting i

from this review. For items specified in the safety evaluation i

issued with Amendment No.16, implement before startup from

]

Qhe second refueling outage.

m

]

(9) Safety Parameter Display System (SPDS) uid

%dd Before startup after the first refueling outage, DLCo shall i

perfom the necessary activities, provide acceptable 1

responses, and implement all proposed corrective actions i

related to issues as described in Section 16.2 of SER Supplement 6. For items specified in the safety evaluation issued with Amen.iment No.16, implement before startup from Qhe second refueling outage.

i (10) IFire Protection Modificatiens (Section 9.5.1 of SER Supplement i

By September 30, 1987, DLCo shall complete the installation of back draft dampers to mitigate overpressurization caused by carbon dioxide system discharge. Until the time that

{

this work is complete DLCo shall maintain fire watches in those areas in accordance with the comitments made in 5

letters dated May 20 and 21, 1987 j

D.

Exemptions

\\%5S-Uddk. " RR\\M"

~

The following exemptions are authorized by law and will not endanger life or property or the comon defense and security, and certain l

special circumstances are present. With the granting of these exemptions, the facility will operate, to the extent authorized herein,

}

in confomity with the application, as amended, the provisions of the l

Act, and the rules and regulations of the Comission.

i i

(1) The facility requires an exemption from the requirements of General Design Criterion (GDC) 4. Appendix A to 10 CFR 50.

The 4

staff has described in detail in Supplement 4 and Supplement 5 to i

the Safet'y Evaluation Report the technical basis and "special l

circumstances". associated with this exemption. The staff's environmental assessment was published on March 27, 1987 i

i (52 FR 9979). Therefore, pursuant to 10 CFR 50.12(a)(1),

i 10 CFR 50.12(a)(2)(ii) and (iv), Beaver Valley Power Station.

Unit 2 is exempt from the requirements of GDC 4. Appendix A to 10 CFR 50 with respect to the dynamic loading effects associated with the postulated pipe breaks described in detail in Section 3

3.6.3 of Supplement 4 to the Safety Evaluation Report..These dynamic loading effects include pipe whip, jet impingement, and break-associated dynamic transit hts. Specifically, this i

eliminates the need to install ;et impingement barriers and pipe whip restraints associated with postulated pipe breaks in l

the pressurizer surge line, reactor coolant bypass system, 4

l f

NPF-73 j

APPLICABILITY l

SURVEILLANCE REQUIREMENTS 4.0.1 Surveillance Requirements shall be met during the.0PERATIONAL MODES or l

other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement.

4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a maximum allowable extension not to exceed 25% of the surveillance interval.

4.0.3 Failure to perform a Surveillance Requirement within the allowed surveil-lance interval, defined by Specification 4.0.2, shall constitute noncompliance with the OPERABILITY requirements for a Limiting Condition for Operation.

The time limits of the ACTION requirements are applicable at the time it is identi-fied that a Surveillance Requirement has not Deen performed.

The ACTION requirements may be delayed for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to permit the completion of the surveillance when the allowable outage time limits of the ACTION requirements are less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Surveillance Requirements do not have to be performed on inoperable equipment.

4.0.4 Entry into an OPERATIONAL MODE or other specified condition shall not be made unless the Surveillance Requirement (s) associated with a Limiting Condition for Operation has been performed within the stated surveillance interval or as otherwise specified.

This provision shall not prevent passage through or to OPERATIONAL MODES as required to comply with ACTION requirements.

4.0.5 Surveillance Requirements for inservice inspection and testing of ASME Code Class 1, 2, and 3 components shall be applicable as follows:

a.)

Inservice inspection of ASME Code Class 1, 2 and 3 components -eed-i 4aserv4ee-test 4*g--of AS"E C:d; C1::: 1, 2 :nd 3 p

:nd v:h::-

shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(g), ::::pt 2;r: :;;;ift: writt:n r:li:f h:: 5::n gr:nted by the C -iss4cn pur:urnt-to 10 CFR 50, 5::-

)

-ti:n 50. M :(g)(5)(i).

_.it%WL D b.

Surveillance intervals specified in Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda for the inservice 1

l inspection and testing activities required by the ASME Boiler and

)

Pressure Vessel Code and applicable Addenda shall be applicable as follows in these Technical Specifications:

l l

l l-BEAVER VALLEY - UNIT 2 3/4 0-2 Amendment No.

bt'DM bb i

i Attachment to surveillance Reauirement 4.0.5 l

Insert "B"

a.2.

Inservice testing of ASME Code Class 1, 2 and 3 pumps and valves shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable i

Addenda as required by 10 CFR 50, Section 50.55a(f).

1 l

i l

i l

l i

1 i

\\

\\

l i

l BEAVER VALLEY - UNIT 2 Insert B - Page 1 of 1 (Proposed Wording)

NPF-73 i

6.0 ADMINISTRATIVE CONTROLS 1

I 6.1 RESPONSIBILITY 6.1.1 The General Manager, Nuclear Operations shall be responsible for overall l

facility operation and shall delegate in writing the succession to this respon-I sibility during his absence.

4 6.2 ORGANIZATION 6.2.1 ONSITE AND OFFSITE ORGANIZATIONS j

I j

onsite and offsite organizations shall be established for facility operation and corporate management, respectively.

The onsite and offsite organizations 3

shall include the positions for activities affecting the safety of the nuclear j

power plant.

a.

Lines of authority, responsibility and communication shall be established l

and defined for the highest sanagement levels through intermediate levels to and including all operating organization positions.

These i

relationships shall be documented and updated, as appropriate, in the i

form of organization charts, functional descriptions of departmental l

responsibilities and relationships, and job descriptions for key 4

i personnel positions, or in equivalent forms of documentation.

These requirements shall be docusented in the FSAR.

b.

The General Manager, Nuclear Operations shall be responsible for overall i

unit safe operation and shall have control over those onsite activities necessary for safe operation and maintenance of the plant.

Mscf

~ib o r D f5 % %

The Vice President, Nuclear-Group shall have corporate responsibility for o

c.

overall plant nuclear safety and shall take any measures needed to ensure j

acceptable performance of the staff in operating, maintaining, and providing technical support to the plant to ensure nuclear safety.

i d.

The individuals who train the operating staff and those who carry out i

health physics and quality assurance functions may report to the appropriate onsite manager; however, they shall have sufficient i

i organizational freedom to ensure their independence from operating pressures.

6.2.2 UNIT STAFF J

The unit organization shall be subject to the following:

a.

Each duty shift shall be composed of at least the minimum shift crew composition shown in Table,6.2-1.

b.

At least one itcensed Operator shall be in the control room when fuel

{

is in the reactor.

c.

At least two licensed Operators shall be in the control room during reactor start-up, scheduled reactor shutdown and during recovery from reactor trips.

BEAVER VALLEY - UNIT 2 6-1 Amendment No.

i

\\

~

l i

}

j NPF-73 l

ADMINISTD.ATIVE CCNTROLS t

i UNIT STAFF (Continued) d.

An individJal qualified in radiation protection procedures shall be onsite when fuel is in the reactor, e.

All CORE ALTERATIONS after the initial fuel loading shall be directly supervised by either a licensed Senior Reactor Operator or Senior Reactor Operator Limited to Fuel Handling who has no other concurrent responsibilities during this operation.

f.

Administrative procedures shall be developed and implemented to limit the working hours of unit staff who perform safety-related functions-senior reactor operators, reactor operators, radiation control tech-nicians, auxiliary operators, meter and control repairman, and all personnel actually performing work on safety related equipment.

j l

The objective shall be to have operating personnel work a normal 8-hour day, 40-hour week while the plant is operating.

However, in the event that unforeseen problems require substantial amounts of overtime to be used, or during extended periods of shutdown for refueling, major maintenance or major plant modifications, on a temporary basis, the following guidelines shall be followed:

a.

An individual should not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight, excluding shift turnover time, b.

An individual should not ce permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in any 24-hour period, nor more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48-hour period, nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any seven day period, all excluding shift turnover time.

]

c.

A break of at least eight hours should be allowed between work periods, including shif t turnove time.

d.

Except during extended shutdown periods, the use of overtime should be considered on an individual basis and not for the entire staff on a shift.

Any deviation from the above guidelines shall be authorized by the General Manager, Nuclear Operations or predesignated alternate, or higher l

1evels of mariagement. Authorized deviations to the working hour guide-lines shall be documented and available for NRC review.

6.2.3 INDEPENDENT SAFETY EVALUATION GROUP (ISEG)

FUNCTION

)

6.2.3.1 The ISEG shall function to examine unit operating characteristics, NRC issuances, industry advisories, Licensee Event Reports, and other sources of unit design and operating experience information, including units of siai-i lar design, which may indicate areas for improving unit safety.

The ISEG shall make detailed recommendations for revised procedures, equipment modifications, maintenance activities, operations activities, or other means of improving unit safety to corporate management.

If not otherwise implemented, all recommenda-tions shall then be made to the i President, Nuclea g

BEAVER VALLEY - UNIT 2 6-2 Amendment No.

1

NPF-73 ADMINISTRATIVE CONTROLS COMPOSITION 6.2.3.2 The ISEG shall be composed of at least five, dedicated, full-time engineers located on site.

Each shall have either:

(1)

A bachelor's degree in engineering or related science and at least 2 years professional level experience in his field, at least 1 year of which experience shall be in th no: lear field, or (2)

At least 5 years of nuclear experience and hold or have held a Senior Reactor Operator license, or (3)

At least 10 years of professional level experience in his field, at least 5 years of which experience shall be in the nuclear field.

A minimum of 50% of these personnel shall have the qualifications specified in (1) above.

RESPONSIBILITIES 6.2.3.3 The ISEG shall be responsible for maintaining surveillance of unit activities to provide independent verification" that these activities are performed correctly and that human errors are reduced as much as practical.

RECORDS 6.2.3.4 Records of activit.ies performed by the ISEG shall be prepared, main-tained, and a summary report shall be forwarded each calendar month to the Vice y

President, Nuclear Crcup. 3Mn\\W gg h

  • Not responsible for sign-off function.

BEAVER VALLEY - UNIT 2 6-3 (next page is 6-5)

Amendment No.

(M Ghd QN\\

r NPF-73 ADMINISTRATIVE CONTROLS 6.3 FACILITY STAFF QUALIFICATIONS 6.3.1 Each member of the facility and Radiation Protection staff shall meet or exceed the minimum qualifications of ANSI N18.1-1971 for comparable positions, except for the Health Physics Manager who shall meet or exceed the qualifications of Regulatory Guide 1.8, September 1975, and the technical advisory engineering representative who shall have a bachelor's degree or equivalent in a scientific or engineering discipline with specific training in plant design and response analysis of the plant for transients and accidents.

6.4 TRAINING 6.4.1 A retraining and replacement training program for the facility staff shall be maintained under the direction of the Nuclear Training Manager and shall meet or exceed the requirements and recommendations of Section 5.5 of ANSI N18.1-1971 and Appedix "A" cf-10 CFR Part 55.

6.5 REVIEW AND AUDIT l

6.5.1 ONSITE SAFETY COMITTEE (OSC)

FUNCTION 6.5.1.1 The OSC shall function to advise the General Manager Nuclear Operations on all matters related to nuclear safety and shall provide review capability in the areas of:

a.

nuclear power plant operations b.

radiological safety c.

maintenance d.

nuclear engineering e.

nuclear power plant testing f.

technical advisory engineering g.

chemistry h.

Quality control 1.

instrumentation and control COMPOSITION

6. 5.1. 2 The Onsite Safety Committee Supervisor is the OSC Chairman and shall appoint all members of the OSC.

The seabership shall consist of a minimum of one individual from each of the ares designated in 6.5.1.1.

OSC members and alternates shall meet or exceed the minimum qualifications of ANSI N18.1-1971 Section 4.4 for comparable positions.

The nuclear power plant operations individual shall meet the qualifications of Section 4.2.2 and the maintenance individual shall meet the qualifications of Section 4.2.3.

I i

BEAVER VALLEY - UNIT 2 6-6 Amendment No.

I

f i

NPF-73 i

ADMINISTRATIVE CONTROLS AUTHORITY

6. 5.1. 7 The OSC Shall:

a.

Recommend to the General Manager, Nuclear Operations written approval or disapproval of items considered under 6.5.1.6. a through d above.

b.

Render determinations in writing with regard to whether or not each ites considered under 6.5.1.6. a through e above constitutes.an unreviewed safety question.

MS Provide written notification within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the^Vice President, c.

g Nuclear frroup and the Offsite Review Committee of disagreement g e 7 etween the OSC and the General Manager,4ee Nuclear Operations; however, the General Manager, fee. Nuclear Operations shall have responsibility for resolution of such disagreements pursuant to 6.1.1 above.

RECORDS

6. 5.1. 8 The OSC shall maintain written minutes of each meeting and copies shal1<

be provided to the General Manager, Nuclear Operations and Chairman of the Offsite

{

Review Committee.

6.5.2 0FFSITE REVIEW C0pWITTEE (ORC)

FUNCTION 6.5.2.1 The ORC shall function to provide independent review and audit of designated activities in the areas of:

a.

nuclear power plant operations b.

nuclear engineering c.

chemistry and radiochemistry d.

metallurgy e.

instrumentation and control f.

radiological safety g.

mechanical and electrical engineering h.

quality assurance practices BEAVER VALLEY - UNIT 2 6-8 Amendment No.

r NPF-73 ADMINISTRATIVE CONTROLS COMPOSITION bcMNN%%

i 6.5.2.2 ThechairmanandfallmembersoftheORCshallbeappointedbythe M Y3r Vice President, Nuclear 4 rete.

The membership shall consist of a minimum of five individuals who collectively possess a broad based level of experience and competence enabling the committee to review and audit those activities designated in 6.5.2.1 above and to recognize when it is necessary to obtain technical advice and counsel.

An individual may possess expertise in more than one speciality area. The collective competence of the committee will be maintained as changes to the membership are made.

ALTERNATES 6.5.2.3 All alternate members shall be appointed in writing by the ORC Chairman to serve on a temporary basis; however, no more than two alternates shall participate as voting members in ORC activities at any one time.

CONSULTANTS 6.5.2.4 Consultants shall be utilized as determined by the ORC Chairman to provide expert advice to the ORC.

MEETING FREQUENCY 6.5.2.5 The ORC shall meet at least once per calendar quarter during the j

initial year of facility operation following fuel loading and at least once per six months thereafter.

l QUORUM 6.5.2.6 A quorum of ORC shall consist of the Chairman or his designated alter-nate and at least four members including alternates.

No more than a minority of the quorum shall have line responsibility for operation of the facility.

REVIEW 6.5.2.7 The ORC shall review:

a.

The safety evaluations for 1) changes to procedures, equipment, or systems and 2) tests or experiments completed under the provision of Section 50.59, 10 CFR, to verify that such actions did not consitute an unreviewed safety question.

BEAVER VALLEY - UNIT 2 6-9 Amendment No.

bMM

2 i

NPF-73 ADMINISTRATIVE CONTROLS REVIEW (Continued) b.

Proposed changes to procedures, equipment or systems which involve an unreviewed safety question as defined in Section 50.59, 10 CFR.

l c.

Proposed tests or experiments which involve an unreviewed safety j

question as defined in Section 50.59, 10 CFR.

d.

Proposed changes in Technical Specifications or licenses.

d Violations of applicable statutes, codes, regulations, orders, e.

Technical Specifications, license requirements, or of internal procedures or instructions having nuclear safety significance.

f.

Significant operating abnormalities or deviations from normal and expected performance of plant equipment that affect nuclear safety.

j g.

All REPORTABLE EVENTS.

h.

All recognized indications of an unanticipated deficiency in some aspect of design or operation of safety-related structures, systems, or components.

1.

Reports and meeting minutes of the OSC.

Lyhwtved a

j.

The results of the Padiological^ Monitoring Program prior to submittal of the annual report provided in accordance with Specification 6.9.1.10.

AUDITS 6.5.2.8 Audits of facility activities shall be performed under the cognizance of the ORC. These audits shall encompass:

1 The conformance of facility operations to provisions contained within 2

a.

the Technical Specifications and applicable license conditions -et-3... -___ ___ so

..u.

i b.

The performance, training, and qualifications of the entire facility j

staff :t 1 ::t : :: p;r 12 ::-th:.

The results of actions taken to correct deficiencies occurring in c.

facility equipment, structures, systems, or methods of operation that affect nuclear safety --at les:t One: p r S : r.th:.

k d.

The performance ^ activities required by the Quality Assurance Program to meet the criteria of Appendix "B",10 CFR 504 :t le::t-enc +-pec-24 ::ath:.

ITheFacilityEmergencyPlanandimplementingproceduresatleastoncD 4

e.

per 12 months -

g4,, gg %4u.

u a

I BEAVER VALLEY - UNIT 2 6-10 O@sil LOLU

i b

NPF-73 ADMINISTRATIVE CONTROLS AUDITS (Continued) g gg&Mn f.

TheFacilitySecurityPlanandimplementingproceduresatleastong l

per 12 months. _

g.

Any other area of facility operation considered appropriate by the ORC or theqVice President, Nuclear hr yg Tv4dwm.

I h.

The Facility Fire Protection Program and implementing procedures -at-

' ::t :n:: per 2d :: nth:.

j I

i.

An independent fire protection and loss prevention program inspection and audit shall be performed at least once per 12 months, utilizing.

j either qualified off-site licensee personnel or an outside fire

< protection firm. -

4 ng qu j.

An inspection and audit of the fire protection and loss prevention program shall be performed by a qualified outside fire consultant et-I

,e

___.u.

d E M E 5ed d h \\Eutw. mhh\\ EM@hDQ AUTHORITY yQ %

t:s t % %

6.5.2.9 The ORC s rhttoandadv he Vice President, Nuclear Gretrp-l I

on those areas of responsibility specified in Section 6.5.2.7 and 6.5.2.8. Q D#

RECORDS 6.5.2.10 Records of ORC activities shall be prepared, approved, and distri-buted as indicated by the following:

a.

Minutes of each ORC meeting shall be prepared for and approved by the ORC Chairman or Vice Chairman within 14 days following each meeting.

b.

Reports of reviews encompassed by Section 6.5.2.7 above, shall be documented in the ORC meeting minutes.

D*O Audit reports encompassed by Sectipi'M lMS 6.5.2.8 above, shall be forwarded c.

to the Vice President, Nuclear Crcup and to the management positions l

responsible for the areas audited within 30 days after completion of the audit.

6.6 REPORTABLE EVENT ACTION 6.6.1 The following actions shall be taken for REPORTABLE EVENTS:

a.

The Commission shall be notified in accordance with 10 CFR 50.72 and/or a report be submitted pursuant to the requirements of Section 50.73 to 10 CFR Part 50, and b.

Each REPORTABLE EVENT shall be reviewed by the OSC, and the results

[

of this review shall be submitted to the ORC.

l l

BEAVER VALLEY - UNIT 2 6-11 Amendment No.

t l

b@M LCLEM i

1 NPF-73 1

1 ADMINISTRATIVE CONTROLS 6.7 SAFETY LIMIT VIOLATION

}

6.7.1 The following actions shall be taken in the event a Safety Limit is j

violated:

a.

The facility shall be placed in at least HOT STANDBY within one (1) hour.

l b.

The Safety Limit violation shall be reported to the Commission within one hour.

The Safety Limit violation shall be reported to the General Manager, l

Nuclear Operations and to the ORC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

c.

A Safety Limit Violation Report shall be prepared.

The report shall be reviewed by the On-Site Safety Committee (OSC).

This report shall describe (1) applicable circumstances preceding the violation, (2) effects of the violation upon facility components, systems or structures, and (3) correc-tive action taken to prevent recurrence.

d.

The Safety Limit Violation Report shall be submitted to the Commission, the ORC and the General Manager, Nuclear Operations within 30 days of the violation.

6.8 PROCEDURES 6.8.1 Written procedures shall be established, implemented, and maintained covering the activities referenced below:

a.

The applicable procedures recommended in Appendix "A" of Regulatory Guide 1.33, Revision 2, February 1978.

b.

Refueling operations.

c.

Surveillance and test activities of safety related equipment.

hurity Plan sple hmeMgDCSLdb"N d.

e. Q mergency Plan implementation.)

htL edk"NA ON f.

Fire Protection Program implementation.

g.

PROCESS CONTROL PROGRAM implementation.

l h.

OFFSITE DOSE CALCULATION MANUAL implementation.

6.8.2 Each procedure and administrative policy of 6.8.1 above and changes of intent thereto, shall be reviewed by the OSC and approved by the General Mana-ger Nuclear Operations, predesignated alternate or a predesignated Manager to whom the General Manager Nuclear Operations has assigned in writing the respon-sibility for review and approval of specific subjects considered by the com-mittee, as applicable.

Changes to procedures and administrative policies of 6.8.1 above that do not receive OSC review, such as correcting typographical errors, reformatting procedures and other changes not affecting the purpose for which the procedure is performed shall receive an independent review by a qualified individual and approved by a designated manager or director.

BEAVER VALLEY - UNIT 2 6-12 Amendment No.

)

(

tfd LOLN\\

J

ATTACHMENT B Beaver Valley Power Station, Unit Nos. 1 and 2 Proposed Technical Specification Change Nos. 216 and 83 REVISION OF ADMINISTRATIVE CONTROLS A.

DESCRIPTION OF AMENDMENT REQUEST The proposed amendment consists of the following:

1)

Elimination of the references to specific frequencies for each of the Technical Specification required audits.

2)

Elimination of the references to reviews and audits of the Emergency Plan and Security Plan.

3)

Separation of the Inservice Inspection and Inservice Testing Programs surveillance requirements and removal of the requirement that relief requests be granted before they are implemented for both IST and ISI.

4)

Editorial changes which were necessitated by a

reorganization.

5)

Elimination of the reference to Appendix A of 10 CFR Part 55.

6)

Elimination of the requirement to perform an independent fire protection and loss prevention program inspection annually.

7)

Inclusion of the Offsite Dose Calculation Manual and Process Control Program and associated implementing procedures into the list of required audits.

8)

Updates of the Beaver Valley Power Station (BVPS) Unit 2 License Conditions.

B.

BACKGROUND Currently, the Administrative Controls section of the Standard Technical Specifications for Westinghouse Plants (NUREG-1431, Vol.

1) states that the combination of reviews and audits should be integrated "into a

cohesive program that provides senior l

management with an assessment of facility operation and l

recommends actions to improve nuclear safety and plant reliability."

Therefore, these administrative tools should be sufficiently flexible to allow for senior management direction of resources to focus upon areas requiring increased attention.

The proposed changes to the Technical Specification administrative I

controls Section 6.5.2.8 would provide such flexibility through the elimination of certain rigid audit frequencies.

Additionally, references in Section 6.5.2.8 to reviews and audits of the facility's Emergency Plan and Physical Security Plan (and B-1 i

1 l

l ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 2 of their associated implementing procedures) would be removed from the Technical Specifications because those requirements presently exist within the individual plans.

This action reflects the guidance provided in Nuclear Regulatory Commission (NRC)

Generic Letter 93-07,

" Modification of the Technical Specification Administrative Control Requirements for Emergency and Security Plans," which was issued on December 28, 1993.

Also, the substance of the audits presently performed to assess the fire protection program at BVPS will be combined into one audit which will be performed biennially.

The one proposed audit that will be performed will encompass the technical specification requirements of the two audits that are presently performed per Section 6.5.2.8(h) and (i).

Editorial changes have been made to Section 6 of the technical specifications bacause of internal organizational changes made at BVPS.

Changes were made to Technical Specification 4.0.5 and Administrative Controls Section 6.4.1 to reflect revisions in the Code of Federal Reculations.

Six license conditions contained in Section 2.C of Facility Operating License No. NPF-73 for Unit 2 have been completed.

As

such, it is no longer necessary to continue to retain these items in the Unit 2 license.

C.

JUSTIFICATION l

The scope and schedule for audits performed under the direction of the Offsite Review Committee (ORC) are currently specified by Administrative Controls Section 6.5.2.8 of the BVPS Technical Specifications.

The specific audits and their associated frequencies have been developed and implemented to comply with requirements from various sources including the Code of Federal Reculations (Facility Security

Plan, Facility Emergency Plan, etc.),

Standard Technical Specifications, NRC Generic Communication (annual,

biennial, and triennial Fire Protection audits),

industry guidelines and standards (Conformance to Technical Specifications and Operating License, Effectiveness of Corrective

Actions, and Training audits).

The audits specified by these sources are meant to address programs which are deemed to be essential to the effective management of a

nuclear facility.

However, the rigid schedules dictated by the Technical Specifications Administrative Controls Section 6.5.2.8 do not allow management the flexibility to recognize exceptional performance by certain organizations.

Resources which could be devoted to areas with perceived weaknesses are diluted by the requirement to audit strong programs at the frequencies set forth in the Technical Specifications.

The proposed changes would provide for decreasing the frequencies of certain

audits, increasing the frequency of the triennial fire protection audit B-2

l ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 3 to

biennial, and maintaining the frequency of those audits presently scheduled biennially.

Additional flexibility would

[

also be introduced by allowing a

25 percent extension to the frequency of most audits (presently defined in the Duquesne Light l

Company commitment to NRC Regulatory Guide 1.144 " Auditing of Quality Assurance Programs for Nuclear Power Plants,"

and Regulatory Guide 1.33,

" Quality Assurance Program Requirements

[Operatica]")

The exceptions to this frequency extension or.

" grace perioc'.would be those audits which have frequencies specifically delineated by the Code of Federal Reaulations (i.e.,

Emergency Plan and Implementing-Procedures Audit and Facility Security Plan and Implementing Procedures Audit).

i l

l The proposed amendment would eliminate the references to specific

[

frequencies for each of the technical specification required j

l audits.

Instead, a statement will be added to the Updated Final Safety Analysis Report (Section 1.3.4.1 Unit 1 and Table.1.8 Unit 2,

see Attachment D) specifying that the audits listed in l

the Technical Specifications Administrative Controls Section 6.5.2.8 will be accomplished on a biennial (2 years) frequency as defined by Quality Services Unit Program commitments to NRC i

Regulatory Guide 1.144 and NRC Regulatory-Guide 1.23 and Eu; i

i directed by administrative procedures and/or management..This change will allow management the flexibility to allocate Quality Services Unit resources in the most efficient manner.

This will g

enhance the safety of the Beaver Valley Power Station by placing i

an emphasis on those functional areas that have perceived weaknesses.

Another program change which will enhance the Quality Assurance program at the' Beaver Valley Power Station is the introduction of i

a 25 percent grace period for audit frequencies.

The additional l

flexibility of a grace period would give auditors the opportunity to perform audits when certain activities are actually occurring.

The 25 percent grace period coupled with the relaxation of the strict schedules dictated by the technical specifications will provide the auditors the ability to actually observe the processes being audited rather than simply reviewing the procedures that are followed to perform the activities.

This will also allow the auditors to assess procedure compliance.

Additionally, the fire protection audit frequency will be increased from triennially to biennially.

Duquesne Light Company (DLC) is combil.3g the two fire protection audits which are currently listed in the Technical Specification Administrative Controls Section 6.5.2.8 into one audit because many requirements of the two audits are similar.

The combination of the two audits will allow greater scheduling flexibility with one audit addressing the requirements presently addressed in two.

The new inspection will reduce redundancies in evaluating the fire protection and loss prevention programs.

B-3

ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 4 4

1 The NRC issued Generic Letter 93-07 to provide guidance for relocating certain requirements from the technical specifications to other NRC-approved program documents.

Generic Letter 93-07 4

specifically addresses the reviews and audits of the Emergency 1

Plan and implementing procedures and the Security Plan and 4

implementing procedures.

Currently, the requirements for these reviews and audits are incorporated into the BVPS Emergency and Security Plans.

The proposed changes would delete the redundant references in the facility's Technical Specifications Administrative Controls Sections 6.5.2.8, 0.8.1, and 6.8.2 since the requirements already exist in Title 10 of the Code of Federal Reaulations

[10 CF3 50.54(t) for Emergency Preparedness and 10 CFR 50.54(p),

10 CFR 73.40, 10 CFR 73.55, and 10 CFR 73.56 for j

Security].

Generic Letter 93-07 does not require licensees to incorporate the requirements of Section 6.8.3 of the technical specifications into the Emergency and Security Plans.

Section 6.8.3 contains the requirements for temporary procedure change review and approval.

Also, Title 10 of the Code of Federal Reculations does not address temporary procedure changes.

Therefore, BVPS will no longer require that temporary changes to Security and EPP procedures be reviewed and approved by the i

Onsite Safety Committee as described in Section 6.8.3.

The proposed amendment will revise the Administrative Controls Section of the BVPS Units 1 and 2 Technical Specifications in accordance with the guidance provided in Generic Letter 93-07.

This amendment will not reduce the audit frequencies of the Emergency or Security Plans because the audit frequencies for these plans are defined in the Code of Federal Reaulations.

Therefore, the proposed changes would remove a redundancy only, not alter the audit or audit frequencies of the Emergency or Security Plans.

Due to changes in the Code of Federal Reaulations, the references in Technical Specification 4.0.5 associated with the Inservice Inspection (ISI) and Inservice Testing (IST)

Programs were revised.

This is because the requirements for these two programs are now contained in two separate paragraphs in 10 CFR Part 50.

Also, Appendix A to 10 CFR Part 55 was incorporated into the body of 10 CFR Part 55 which necessitates a reference change for Technical Specification 6.4.1.

Both of these changes are editorial only and were necessitated by changes to 10 CFR Part 50 and Part 55.

I The other change made to Technical Specification 4.0.5 involves the granting of relief requests prior to implementation for both ISI and IST.

This requirement was removed in accordance with the 4

guidance provided by draft NUREG-1482, " Guidelines for Inservice Testing at Nuclear Power Plants," dated November, 1993 as well as the requirements of 10 CFR Part 50.55a.

Title 10 allows a licensee up to a

full year after the beginning of the updated interval to request relief from those new Code requirements which cannot be met.

B-4

i l

ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 7

Page 5 Several of the license conditions for BVPS Unit 2 are being eliminated because the required actions have been completed.

Specifically:

1.

License Condition 2.C.(3)

The Initial Test Program no longer exists since Unit 2 started commercial operation in 3

November 1987.

I 2.

License Condition 2.C.(5) - The' Inservice Inspection Program was forwarded to the NRC by letter dated June 1, 1988.

3.

License Condition 2.C.(7) - The verification and validation plan which is used to demonstrate the reliability of the Plant Safety Monitoring System. was implemented priorLto r

startup from the second refueling outage.

The NRC was apprised of this in a letter dated December 4, 1990..

4.

License Condition 2.C.(8) - All detailed Control Room Design Review-corrective and other actions were implementad prior I

to the startup following the second refueling outage.

The

(

letter forwarding all pertinent information to the NRC was dated December 3, 1990.

5.

License Condition 2.C.(9)

The Safety Parameter Display i

system items identified' in the Technical Specification I

Amendment No. 16 Safety Evaluation were implemented prior to start-up from the second refueling outage.. A letter dated December 4, 1990, forwarded the information to the NRC.

i 6.

License Condition 2.C.(10)

A letter dated September 30,

1987, informed the NRC that the installation of back draft dampers had eliminated the overpressure problems associated with the CO discharge.

2 D.

SAFETY ANALYSIS The removal of the audit of the emergency and security plans and implementing procedures from the list of responsibilities of the BVPS ORC contained in Administrative Controls Section 6.5.2.8 is consistent with the guidance provided in Generic Letter 93-07.

Specifically, Parts 50 and 73 of Title 10 of the Code of Federal Reculations include provisions that are sufficient to address

{

these requirements.

The emergency and security plans also i

include the requirement that the Quality Services Unit audit the plans annually.

Therefore, this change eliminates redundant references only and no reduction in audit frequency will occur for the emergency and security plans.

This proposed change neither alters the functions nor diminishes the quality of the audit program.

Also, in keeping with the guidance provided in the generic letter the proposed change will remove the requirements in B-5

ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 6 Administrative Controls Section 6.8.1 for the safety review committee to review procedures, and procedure changes, for the implementation of the emergency and security plans.

The 1

requirements for safety committee reviews of procedures, and procedure

changes, for the implementation of the emergency and security plans currently exists in the respective plans.

Therefore, removal of this requirement from the Technical l

Specifications eliminates a

redundancy only.

No reduction in safety will ensue because of this elimination.

A further proposed change to the Technical Specifications Administrative Controls Section 6.5.2.8 involves the removal of the speci!ie audit frequencies for those audits listed.

Commensure a

' i.th the removal of the audit frequencies from the Technical Brecifications will be the addition of a statement in the Updated Final Safety Analysis Report (Section 1.3.4.1 - Unit 1

and Table 1.8 Unit 2; see Attachment D) specifying that the audits listed in the Technical Specifications will be accomplished on a

biennial (2

years) frequency.

The purpose,

scope, and thoroughness of Quality Assurance audits will not be
affected, management oversight of the audit process will not be diminished, and the audits will be performed at frequencies commensurate with safety significance and not less than biennially.

This will include the 25 percent grace period on the l

audit frequencies.

The use of an audit frequency grace period does not decrease the effectiveness of audits nor does it adversely affect safety.

The grace period allows scheduling flexibility that gives the auditors the opportunity to audit activities when they are performed.

As such, the above described changes are consistent with the intent of the regulations and are an acceptable alternative.

The other proposed change to the audits listed in Technical Specifications Administrative Controls Section 6.5.2.8 involves combining the aspects of the annual and triennial fire protection and loss prevention inspection and audit into one biennial audit.

A qualified outside consultant will be utilized every 2 years rather than every 3 years as is the current practice.

The proposed changes will not adversely impact the effectiveness of

(

either the Fire Protection / Loss Prevention Program or the Audit Program for the following reasons:

1) the proposed alternate audit program continues to evaluate the areas addressed in NRC Generic Letter 82-21,

" Technical Specifications for Fire Protection Audits";

2) utilizes the same recommended resources; and

3) is comprehensive in its review of fire protection and loss prevention features.

The Offsite Dose Calculation Manual and Process Control Program and associated implementing procedures are being added to the list of required audits in Technical Specification Administrative Controls Section 6.5.2.8.

Although they have always been audited as parts of other program audits, the inclusion of these programs B-6 i

i ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 7 l

into the Technical Specification will provide for a formal audit review of these areas which will enhance the review process.

The other changes to the Technical Specifications are purely

(

editorial.

Some of the changes to the Administrative Controls l

Section 6 were necessitated by an internal reorganization, others l

reflect changes to 10 CFR which include:

1.

The NRC revised 10 CFR Part 50 to separate the Inservice Testing (IST) requirements from the Inservice Inspection (ISI) requirements by placing the IST requirements into a new paragraph, 10 CFR Part 50.55a(f).

This necessitated a change in references in Technical Specification 4.0.5.

2.

Appendix A

to 10 CFR Part 55 was incorporated into the body of 10 CFR Part 55.

Therefore, Technical Specification 6.4.1 was revised to remove the reference to Appendix A.

Technical Specification 4.0.5 was also revised to remove "except where specific written relief has been granted" for both the ISI and IST programs.

This is in accordance with the guidance provided by draft NUREG-1482.

This revision reflects the NRC's position that licensees must establish and implement their IST program in accordance with 10 CFR Part 50.55a, which does not require that relief requests be granted before they are implemented.

Rather, the regulations allow a licensee up to a full year after the beginning of the updated interval to inform the NRC of those new Code requirements which cannot be met and to request relief.
Lastly, as described
above, several Unit 2 license conditions have been eliminated because they are no longer applicable.

E.

NO SIGNIFICANT HAZARDS EVALUATION The no significant hazard considerations involved with the proposed amendment have been evaluated, focusing on the three standards set forth in 10 CFR 50.92(c) as quoted below:

The Commission may make a final determination, pursuant to the procedures in paragraph 50.91, that a proposed amendment to an operating license for a

facil.ty licensed under paragraph 50.21(b) or paragraph 50.22 or for a testing facility involves no significant hazards consideration, if operation of the facility in accordance with the proposed amendment would not:

(1)

Involve a

significant increase in the probability or consequences of an accident previously evaluated; or (2)

Create the possibility of a new or different kind of accident from any accident previously evaluated; or B-7

l l

ATTACHMENT B, continued 1

Proposed Technical Specification Change Nos. 216 and 83 Page 8 (3)

Involve a significant reduction in a margin of_ safety.

The following evaluation is provided for the no significant hazards consideration standards.

1.

Does the change involve a

significant increase in the probability or consequences of an accident previously evaluated?

The likelihood that an accident will occur is neither increased or decreased by this proposed Technical Specification change which only affects review and audit frequencies, removes redundancies in the audit

program, l

corrects editorial information, and updates the Unit 2

l license conditions.

This Technical Specification change will not impact the function or method of operation of plant equipment.

-Thus, there is not a significant increase in the probability of a

previously analyzed accident due to this change.

No systems, equipment, or components are affected by the proposed change.

Thus, the consequences of a

i malfunction of equipment important to safety previously i

evaluated in the Updated Final Safety Analysis Report are not increased by this change.

The proposed change affects audit frequencies, types of audits listed in the technical specifications, references l

for some technical specification sections, the time frame I

for Inservice Testing (IST) and Inservice Inspection (ISI) l relief request submittals, and editorial changes necessitated by an internal reorganization.

As such, the proposed change has no impact on accident initiators or plant equipment, and therefore, does not affect the probabilities or consequences of an accident.

Therefore, the proposed change will not involve a

significant increase in the probability or consequences of i

an accident previously evaluated.

2.

Does the change create the possibility of a new or different i

kind of accident from any accident previously evaluated?

l The proposed technical specification revisions do not involve changes to the physical plant or operations.

Since l

program

audits, organizational
titles, and technical l

specification references do not contribute to accident initiation, a

change related to the areas listed in the description section of this Attachment cannot produce a new i

accident scenario or produce a

new type of equipment I

malfunction.

Therefore, this change does not alter any existing accident scenarios.

The proposed change does not affect equipment or its operation.

l B-8

j ATTACHMENT B, continued Proposed Technical Specification Change Nos. 216 and 83 Page 9

?

Therefore, the proposed change does not create. the possibility of a'new or different kind of accident from any accident previously evaluated.

j 3.

Does the change involve a significant reduction in a margin of safety?

The proposed change concerns the conduct of

audits, technical specification references, ISI and IST relief request submittals, completed License conditions, and organizational title changes and does not'directly affect plant -equipment or operation.-

Safety limits and limiting safety system settings are not affected by this proposed change.

i Therefore, use of the proposed Technical Specification would not involve a significant reduction in the margin of safety.

t i

F.

NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION Based on the considerations expressed above, it:is concluded that

[

the activities associated-with this license amendment request ~

satisfies the no significant hazards consideration standards of 10 CFR 50.92(c)

'and, accordingly, a

no significant hazards i

consideration finding is justified.

r G.

UFSAR CHANGES l

Suggested UFSAR changes are provided in Attachments D-1 and D-2.

l l

l c

I l

l l

t i

l i

t l

I B-9 i

1

i l

ATTACHMENT C-1 1

1

(

i Beaver Valley Power Station, Unit No. 1 1

Proposed Technical Specification Change No. 216 L

i i

l Applicable Typed Pages 1

l t

l l

i

}

3 j

i I

i

ATTACHMENT TO LICENSE AMENDMENT NO.

i FACILITY OPERATING LICENSE NO. DPR-66 DOCKET NO. 50-334 Replace the following pages of Appendix A, Technical Specifications, j

with the enclosed pages as indicated.

The revised pages are identified by amendment number and contain vertical lines indicating i

the areas of change.

Remove Insert 3/4 0-2 3/4 0-2 3/4 0-3 6-1 6-1 6-3 6-3 6-5 6-5 6-7 6-7 6-8 6-8 6-10 6-10 6-11 6-11 6-12 6-12 i

(Proposed Wording)

DPR-66 3/4.0 APPLICABILITY SURVEILLANCE REQUIREMENTS 1.

At least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, 2.

At least HOT SHUTDOWN within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and 3.

At least COLD SHUTDOWN within the subsequent 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

This specification is not applicable in MODES 5 or 6.

4.0.1 Surveillance Requirements shall be met during the OPERATIONAL MODES or other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement.

4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a maximum allowable extension not to exceed 25% of the surveillance interval.

4.0.3 Failure to perform a Surveillance Requirement within the allowed surveillance

interval, defined by Specification 4.0.2, shall constitute noncompliance with the OPERABILITY requirements for a

Limiting Condition for Operation.

The time limits of the ACTION requirements are applicable at the time it is identified that a Surveillance Requirement has not been performed.

The. ACTION requirements may be delayed for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to permit the completion of the surveillance when the allowable outage time limits of the ACTION requirements are less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Surveillance Requirements do not have to be performed on inoperable equipment.

4.0.4 Entry into an OPERATIONAL MODE or other specified condition shall not be made unless the Surveillance Requirement (s) associated with a

Limiting Condition for Operation has been performed within the stated surveillance interval or as otherwise specified.

This provision shall not prevent passage through or to OPERATIONAL MODES as required to comply with ACTION requirements.

4.0.5 Surveillance Requirements for inservice inspection and I

testing of ASME Code Class 1, 2 and 3 components shall be applicable as follows:

a.1 Inservice inspection of ASME Code Class 1, 2 and 3 components l

shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(g).

BEAVER VALLEY - UNIT 1 3/4 0-2 Amendment No.

l (Proposed Wording)

I i

4

(

DPR-66 l

3/4.0 APPLICABILITY SURVEILLANCE REQUIREMENTS a.2 Inservice testing of ASME Code Class 1, 2 and 3 pumps and valves shall be performed in accordance with Section XI of the ASME Boiler.and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(f).

b.

Surveillance intervals specified in Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda for the l

inservice inspection and testing activities required by the ASME i

i Boiler and Pressure Vessel Code and applicable Addenda shall be applicable as follows in these Technical Specifications:

ASME Boiler and Pressure Vessel Required frequencies f;"

Code and applicable Addenda performing inservice terminology for inservice inspection and testing inspection and testina activities activities Weekly At least once per 7 days Monthly At least once per 31 days Quarterly or every 3 montis At least once per 92 days Semiannually or every 6 months At least once per 184 days Every 9 months At least once per 276 days Yearly or annually At least'once per 366 days c.

The provisions of Specification 4.0.2 are applicable to the above required frequencies for performing inservice inspection and testing activities.

d.

Performance of the above inservice inspection and testing activities shall be in addition to other specified Surveillance' Requirements.

e.

Nothing in the ASME Boiler and Pressure Vessel Code shall be construed to supersede the requirements of any Technical Specification.

BEAVER VALLEY - UNIT 1 3/4 0-3 Amendment No.

(Proposed Wording)

T NPF-73 ADMINISTRATIVE CONTROLS 6.1 RESPONSIBILITY 6.1.1 The General

Manager, Nuclear Operations shall be l

responsible for overall facility operation and shall delegate in writing the succession to this responsibility during his absence.

6.2 ORGANIZATION r

6.2.1 ONSITE AND OFFSITE ORGANIZATIONS Onsite and Offsite organizations shall be established for facility operation and corporate management, respectively.

The onsite and offsite organizations shall include the positions for activities affecting the safety of the nuclear power plant.

a.

Lines of authority, responsibility and communication shall be established and defined for the highest management levels through intermediate levels to and including all operating organization positions.

These relationships shall be documented and

updated, as appropriate, in the i

form of organization

charts, functional descriptions of departmental responsibilities and relationships, and job descriptions for key personnel positions, or in equivalent forms of documentation.

These requirements shall be documented in the FSAR.

]

b.

The General

Manager, Nuclear Operations shall be I

responsible for overall unit safe operation and shall have control over those onsite activities necessary for safe operation and maintenance of the plant.

c.

The Senior Vice President, Nuclear Power Division shall l

have corporate responsibility for overall plant nuclear safety and shall take any measures needed to ensure acceptable performance of the staff in operating, maintaining, and providing technical support to the plant J

I to ensure nuclear safety.

d.

The individuals who train the operating staff and those who carry out health physics and quality assurance functions may report to the appropriate onsite manager; however, they shall have sufficient organizational freedom to ensure their independence from operating pressures.

4 BEAVER VALLEY - UNIT 1 6-1 Amendment No.

(Proposed Wording)

DPR-66 ADMINISTRATIVE CONTROLS UNIT STAFF (Opntinued) c.

A break of at least eight hours should be allowed between work periods, including shift turnover time.

d.

Except during extended shutdown

periods, the use of overtime should be considered on an individual basis and not for the entire staff on a shift.

Any deviation from the above guidelines shall be authorized by the General

Manager, Nuclear Operations or predesignated alternate, or l higher levels of management.

Authorized deviations to the working hour guidelines shall be documented and available for NRC review.

1 1

l I

BEAVER VALLEY - UNIT 1 6-3 Amendment No.

f (Proposed Wording)

i DPR-66 ADMINISTRATIVE CONTROLS 6.3 FACILITY STAFF OUALIFICATIONS 6.3.1 Each member of the facility and Radiation Protection staff l

shall meet or exceed the minimum qualifications of ANSI N18.1-1971 for comparable positions, except for the Health Physics Manager who shall meet or exceed the qualifications of Regulatory Guide 1.8, September

1975, and the technical advisory engineering representative who shall have a bachelor's degree or equivalent in a scientific or engineering discipline with specific training in plant design and response analysis of the plant for transients and accidents.

l 6.4.1 A

retraining and replacement training program for the facility staff shall be maintained under the direction of the Nuclear Training Manager and shall meet or exceed the requirements I

and recommendations of Section 5.5 of ANSI N18.1-1971 and 10 CFR Part 55.

6.5 REVIEW AND AUDIT l

6.5.1 ONSITE SAFETY COMMITTEE (OSC)

FUNCTION 6.5.1.1 The OSC shall function to advise the General Manager Nuclear Operations on all matters related to nuclear safety and shall provide review capability in the areas of:

a.

nuclear power plant operations b.

radiological safety c.

maintenance d.

nuclear engineering e.

nuclear power plant testing f.

technical advisory engineering g.

chemistry h.

quality control i.

instrumentation and control COMPOSITION 6.5.1.2 The Onsite Safety Committee Supervisor is the OSC Chairman and shall appoint all members of the OSC.

The membership shall consist of a

minimum of one individual from each of the areas designated in 6.5.1.1.

OSC members and alternates shall meet or exceed the minimum qualifications of ANSI N18.1-1971 Section 4.4 for comparable positions.

The nuclear power plant operations individual shall meet the qualifications of Section 4.2.2 and the maintenance individual shall meet the qualifications of Section 4.2.3.

BEAVER VALLEY - UNIT 1 6-5 Amendment No.

(Proposed Wording)

i l

l DPR-66 ADMINISTRATIVE CONTROLS AUTHORITY 6.5.1.7 The OSC shall:

l a.

Recommend to the General Manager Nuclear Operations written i

i approval or disapproval of items considered under 6.5.1.6.a l

through.d above.

b.

Render determinations in writing with regard to whether or I

not each item considered under 6.5.1.6.a through.e above constitutes an unreviewed safety question.

l c.

Provide written notification within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the Senior Vice President, Nuclear Power Division and the Offsite Review Committee of disagreement between the OSC and the l

General Manager Nuclear Operations;

however, the General Manager Nuclear Operations shall have responsibility for resolution of such disagreements pursuant to 6.1.1 above.

RECORDS 6.5.1.8 The OSC shall maintain written minutes of each meeting and copies shall be provided to the General Manager Nuclear Operations and Chairman of the Offsite Review Committee.

6.5.2 OFFSITE REVIEW COMMITTEE (ORC)

FUNCTION j

6.5.2.1 The ORC shall function to provide independent review and audit of designated activities in the areas of:

a.

nuclear power plant operations J

b.

nuclear engineering c.

chemistry and radiochemistry d.

metallurgy e.

instrumentation and control f.

radiological safety g.

mechanical and electrical engineering h.

quality assurance practices BEAVER VALLEY - UNIT 1 6-7 Amendment No.

(Proposed Wording)

DPR-66 ADMINISTRATIVE CONTROLS i

COMPOSITION 6.5.2.2 The chairman and all members of the ORC shall be appointed by the Senior Vice President, Nuclear Power Division.

The l

membership shall consist of a

minimum of five individuals who collectively possess a

broad based level of experience and competence enabling the committee to review and audit those activities designated in 6.5.2.1 above and to recognize when it is necessary to obtain technical advice and counsel.

An individual may possess expertise in more than one specialty area.

The collective competence of the committee will be maintained as changes to the membership are made.

ALTERNATES 6.5.2.3 All alternate members shall be appointed in writing by the i

ORC Chairman to serve on a temporary basis; however, no more than

(

two alternates shall participate as voting members in ORC activities at any one time.

CONSULTANTS 6.5.2.4 Consultants shall be utilized as determined by the ORC Chairman to provide expert advice to the ORC.

l l

BEAVER VALLEY - UNIT 1 6-8 Amendment No.

(Proposed Wording)

DPR-66 ADMINISTRATIVE CONTROLS t

AUDITS 6.5.2.8 Audits of facility activities shall be performed under the cognizance of the ORC.

These audits shall encompass:

a.

The conformance of facility operation to provisions contained within the Technical Specifications and applicable license conditions.

l-a b.

The performance, training and qualifications of the entire i

facility staff.

I 1

4 l

c.

The results of actions taken to correct deficiencies occurring in facility equipment, structures, systems, or methods of operation that affect nuclear safety.

l d.

The performance of activities required by the Quality Assurance Program to meet the criteria of Appendix "B",

10 l

CFR 50.

e.

Not used.

f.

Not used.

g.

Any other area of facility operation considered appropriate by the ORC or Senior Vice President, Nuclear Power Division.

h.

The Facility Fire Protection Program and implementing procedures.

l i.

Not used.

l j.

An inspection and audit of the fire protection and loss prevention program shall be performed by a

qualified l

outside fire consultant.

k.

The Offsite Dose Calculation Manual and implementing procedures.

1.

The Process Control Program and implementing procedures for processing and packaging of radioactive waste.

BEAVER VALLEY - UNIT 1 6-10 Amendment No.

(Proposed Wording)

l DPR-66 l

ADMINISTRATIVE CONTROLS l

AUTHORITY l

6.5.2.9 The ORC shall report to and advise the Senior Vice I

President, Nuclear Power Division on those areas of responsibility specified in Section 6.5.2.7 and 6.5.2.8.

RECORDS i

6.5.2.10 Records of ORC activities shall be prepared, approved and distributed as indicated by the following:

a.

Minutes of each ORC meeting shall be prepared for and approved by the ORC Chairman or Vice-Chairman within 14 days following each meeting.

b.

Reports of reviews encompassed by Section 6.5.2.7 above, shall be documented in the ORC meeting minutes, i

c.

Audit reports encompassed by Section 6.5.2.8 above, shall be forwarded to the Senior Vice President, Nuclear Power l

Division and to the management positions responsible for I

the areas audited within 30 days after completion of the audit.

6.6 REPORTABLE EVENT ACTION 6.6.1 The following actions shall be taken for REPORTABLE EVENTS:

a.

The Commission shall be notified in accordance with 10 CFR 50.72 and/or a

report be submitted pursuant to the requirements of Section 50.73 to 10CFR Part 50, and b.

Each REPORTABLE EVENT shall be reviewed by the OSC, and results of this review shall be submitted to the ORC.

6.7 SAFETY LIMIT VIOLATION 6.7.1 The following actions shall be taken in the event a Safety Limit is violated:

a.

The facility shall be placed in at least HOT STANDBY within one (1) hour.

b.

The Safety Limit violation shall be reported to the commission within one hour and to the General Manager, Nuclear Operations and to the ORC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

BEAVER VALLEY - UNIT 1 6-11 Amendment No.

(Proposed Wording)

DPR-66 ADMINISTRATIVE CONTROLS SAFETY LIMIT VIOLATION (Continued) c.

A Safety Limit Violation Report shall be prepared.

The report shall be reviewed by the on-Site Safety Committee (OSC).

This report shall describe (1) applicable circumstances preceding the violation, (2) effects of the violation upon facility components, systems or structures, l

and (3) corrective action taken to prevent recurrence.

d.

The Safety Limit Violation Report shall be submitted to the l

Commission, the ORC and the General

Manager, Nuclear l

Operations within 30 days of the violation.

l 6.8 PROCEDURES 6.8.1 Written procedures shall be established, implemented, and maintained covering the activities referenced below:

a.

The applicable procedures recommended in Appendix "A"

of Regulatory Guide 1.33, Revision 2, February 1978.

b.

Refueling operations.

c.

Surveillance and test activities of safety related equipment.

d.

Not used, e.

Not used.

f.

Fire Protection Program implementation.

g.

PROCESS CONTROL PROGRAM implementation.

h.

OFFSITE DOSE CALCULATION MANUAL implementation.

6.8.2 Each procedure and administrative policy of 6.8.1 above and changes of intent thereto, shall be reviewed by the OSC and approved by the General Manager Nuclear Operations, predesignated alternate of a

predesignated Manager to whom the General Manager Nuclear Operations has assigned in writing the responsibility for review and approval of specific subjects considered by the committee, as applicable.

Changes to procedures and administrative policies of 6.8.1 above that do not receive OSC

review, such as correcting typographical
errors, reformatting procedures and other changes not affecting the purpose for which the procedure is performed shall j

receive an independent review by a qualified individual and approved by a designated manager or director.

BEAVER VALLEY - UNIT 1 6-12 Amendment No.

(Proposed Wording)

ATTACHMENT C-2 Beaver Valley Power Station, Unit No. 2 Proposed Technical Specification Change No. 83 d

I Applicable Typed Pages i

J J

l i

s I

1 1

l 4

j l

l

ATTACHMENT TO LICENSE AMENDMENT NO.

FACILITY OPERATING LICENSE NO. NPF-73 DOCKET NO. 50-412 l

Peplace the following pages of Appendix A, Technical Specifications, I

with the enclosed pages as indicated.

The revised pages are l

identified by amendment number and contain vertical lines indicating the areas of change.

Eemove Insert i

License Page 4 License Page 4 License Page 5 License Page 5 3/4 0-2 3/4 0-2 3/4 0-3 6-1 6-1 6-2 6-2 6-3 6-3 6-6 6-6 6-8 6-8 6-9 6-9 6-10 6-10 6-11 6-11 6-12 6-12 (Proposed Wording)

NPF-73 (3)

Deleted (4)

Fresh Fuel Storace The following criteria apply to the storage and handling of new fuel assemblies in the fuel handling building:

(a)

No more than two fuel assemblies shall be out of approved shipping containers or fuel assembly storage racks at any one time.

{

1 (b)

The minimum edge-to-edge distance between the above two new assemblies, the shipping container array, and the storage rack arrays shall be at least 12 inches.

(c)

New fuel assemblies shall be stored in such a manner that water would drain freely from the assemblies in the event of flooding and subsequent draining of the fuel storage area.

(5)

Deleted l

(6)

Formal Federal Emercency Manaaement Acency Finding In the event that the NRC finds that the lack of progress in completion of the procedures in the Federal Emergency Management Agency's final

rule, 44 CFR Part 350, is an indication that a

major substantive problem exists in achieving or maintaining an adequate state of emergency preparedness, the provisions of 10 CFR Section 50.54 (s) (2) will apply.

(7)

Deleted (8)

Deleted (9)

Deleted (10)

Deleted D.

Exemotions l

The following exemptions are authorized by law and will not endanger life or property or the common defense and security, and certain special circumstances are present.

With the granting of these exemptions, the facility will

operate, to the extent authorized
herein, in conformity with the application, as
amended, the provisions of the Act, and the rules and regulations of the Commission.

l l

Amendment No.

l (Proposed Wording) e w

NPF-73 (1)

The facility requires an exemption from the requirements of General Design Criterion (GDC) 4, Appendix A to 10 CFR 50.

The staff has described in detail in Supplement 4

and supplement 5 to the Safety Evaluation Report the technical basis and "special circumstances" associated with this exemption.

The staff's environmental assessment was published on March 27, 1987 (52 FR 9979).

Therefore, pursuant to 10 CFR 50.12 (a) (1),

10 CFR 50.12 (a) ( 2 ) (ii) and (iv),

Beaver Valley Power Station, Unit 2 is exempt from the requirements of GDC 4, Appendix A to 10 CFR 50 with respect to the dynamic loading effects associated with the postulated pipe breaks described in detail in Section 3.6.3 of Supplement 4 to the Safety Evaluation Report.

These dynamic loading effects include pipe

whip, jet impingement, and break-associated dynamic transients.

Specifically, this eliminates the need to install jet impingement barriers and pipe whip restraints associated with postulated pipe breaks in the pressurizer surge line, reactor coolant bypass system, Amendment No.

(Proposed Wording)

I NPF-73 APPLICABILITY SURVEILLANCE REQUIREMENTS 4.0.1 Surveillance Requirements shall be met during the OPERATIONAL MODES or other conditions specified for individual Limiting Conditions for Operation unless otherwise stated in an individual Surveillance Requirement.

4.0.2 Each Surveillance Requirement shall be performed within the specified time interval with a

maximum allowable extension not to exceed 25% of the surveillance interval.

4.0.3 Failure to perform a Surveillance Requirement within the allowed surveillance

interval, defined by Specification 4.0.2, j

shall constitute noncompliance with the OPERABILITY requirements for l

a Limiting Condition for Operation.

The time limits of the ACTION requirements are applicable at the time it is identified that a Surveillance Requirement has not been performed.

The ACTION requirements may be delayed for up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to permit the completion of the surveillance when the allowable outage time limits of the ACTION requirements are less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Surveillance Requirements do not have to be performed on inoperable equipment.

4.0.4 Entry into an OPERATIONAL MODE or other specified condition shall not be made unless the Surveillance Requirement (s) associated with a Limiting condition for Operation has been performed within the stated surveillance interval or as otherwise specified.

This provision shall not prevent passage through or to OPERATIONAL MODES as required to comply with ACTION requirements.

4.0.5 Surveillance Requirements for inservice inspection and testing of ASME Code Class 1,

2 and 3 components shall be applicable as follows:

a.1 Inservice inspection of ASME Code Class 1, 2 and 3 components j

shall be performed in accordance with Section XI of the ASME i

Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(g).

a.2 Inservice testing of ASME Code Class 1, 2 and 3 pumps and valves shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50, Section 50.55a(f).

BEAVER VALLEY - UNIT 2 3/4 0-2 Amendment No.

(Proposed Wording)

NPF-73 APPLICABILITY SURVEILLANCE REQUIREMENTS b.

Surveillance intervals specified in Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda for the inservice inspection and testing activities required by the ASME Boiler and Pressure Vessel Code and applicable Addenda shall be applicable as follows in these Technical Specifications:

ASME Boiler and Pressure Vessel Required frequencies for Code and applicable Addenda performing inservice terminology for inservice inspection and testing insoection and testina activities activities Weekly At least once per 7 days Monthly At least once per 31 days Quarterly or every 3 months At least once per 92 days Semiannually or every 6 months At least once per 184 days Every 9 months At least once per 276 days Yearly or annually At least once per 366 days c.

The provisions of Specification 4.0.2 are applicable to the above required frequencies for performing inservice inspection and testing activities.

d.

Performance of the above inservice inspection and testing activities shall be in addition to other specified Surveillance Requirements.

e.

Nothing in the ASME Boiler and Pressure Vessel Code shall be construed to supersede the requirements of any Technical Specification.

BEAVER VALLEY - UNIT 2 3/4 0-3 Amendment No.

(Proposed Wording)

l l

NPF-73 l

6.0 ADMINISTRATIVE CONTROLS l

6.1 RESPONSIBILITY 6.1.1 The General

Manager, Nuclear Operations shall be I

responsible for overall facility operation and shall delegate in writing the succession to this responsibility during his absence.

l l

6.2 ORGANIZATION 6.2.1 ONSITE AND OFFSITE ORGANIZATIONS Onsite and offsite organizations shall be established for facility operation and corporate management, respectively.

The onsite and offsite organizations shall include the positions for activities affecting the safety of the nuclear power plant.

a.

Lines of authority, responsibility and communication shall be established and defined for the highest management levels through intermediate levels to and including all operating organization positions.

These relationships shall be documented and updated, as appropriate, in the form of organization charts, functional descriptions of departmental responsibilities and relationships, and job descriptions for key personnel positions, or in equivalent forms of documentation.

These requirements shall be document'ed in the FSAR.

b.

The General Manager, Nuclear Operations shall be responsible for l

overall unit safe operation and shall have control over those onsite activities necessary for safe operation and maintenance of the plant.

c.

The Senior Vice President, Nuclear Power Division shall have l

corporate responsibility for overall plant nuclear safety and shall take any measures needed to ensure acceptable performance of the staff in operating, maintaining, and providing technical support to the plant to ensure nuclear safety.

d.

The individuals who train the operating staff and those who carry out health physics and quality assurance functions may report to the appropriate onsite manager; however, they shall have sufficient organizational freedom to ensure their independence from operating pressures.

6.2.2 UNIT STAFF The unit organization shall be subject to the following:

a.

Each duty shift shall be composed of at least the minimum shift crew composition shown in Table 6.2-1.

b.

At least one licensed Operator shall be in the control room when fuel is in the reactor.

BEAVER VALLEY - UNIT 2 6-1 Amendment No.

(Proposed Wording)

.~

~

=--

NPF-73 ADMINISTRATIVE CONTROLS UNIT STAFF (Continued) c.

At least _two licensed Operators shall be in the control room during reactor - start-up, scheduled reactor shutdown and during recovery from reactor trips.

d.

An individual qualified in radiation protection procedures shall be onsite when fuel is in the reactor.

e.

All CORE ALTERATIONS after the initial fuel loading shall be

[

directly supervised by either a licensed Senior Reactor Operator or Senior Reactor Operator Limited to Fuel' Handling who has no other concurrent responsibilities during this1 operation.

f.

Administrative procedures shall be developed and implemented to limit the working hours of unit staff who perform safety-related functions; senior reactor operators, reactor operators, radiation control technicians, auxiliary operators, meter and control repairman, and.all personnel actually performing work on safety l

related equipment.

The objective shall be to have operating. personnel work a normal 8-hour

day, 40-hour week while the plant is operating.
However, in the event that unforeseen problems require. substantial amounts of overtime to be used, or during extended periods of shutdowns for refueling, major maintenance or major plant modifications, on l

a temporary basis, the following guidelines shall'be followed:

a.

An individual should.not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight, excluding shift turnover time.

j b.

An individual should not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in-any 24-hour period, nor more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48-hour

period, nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any seven day period, all excluding shift turnover time.

c.

A break of at least eight hours should be allowed between work periods, including shift turnover time.

i d.

Except during extended shutdown periods, the use of overtime should be considered on an individual basis and not for the entire staff on a shift.

I Any deviation from the above guidelines shall be authorized by the General

Manager, Nuclear Operations or predesignated l

alternate, or higher levels of management.

Authorized deviations to the working hour guidelines shall be documented and available for NRC review.

BEAVER VALLEY - UNIT 2 6-2 Amendment No.

(Proposed Wording)

+

NPF-73 ADMINISTRATIVE CONTROLS 6.2.3 INDEPENDENT SAFETY EVALUATION GROUP (ISEG)

FUNCTION 6.2.3.1 The ISEG shall function to examine unit operating characteristics, NRC issuances, industry advisories, Licensee Event

Reports, and other sources of unit design and operating experience information, including units of similar design, which may indicate areas for improving unit safety.

The ISEG shall make detailed recommendations for revised procedures, equipment modifications, maintenance activities, operations activities, or other means of improving unit safety to corporate management.

If not otherwise implemented, all recommendations shall then be made to the Senior l

Vice President, Nuclear Power Division.

COMPOSITION 6.2.3.2 The ISEG shall be composed of at least five, dedicated, l

full-time engineers located on site.

Each shall have either:

i (1)

A bachelor's degree in engineering or related science and at least 2 years professional level experience in his field, at least 1

year of which experience shall be in the nuclear field, or (2)

At least 5 years of nuclear experience and hold or have held a Senior Reactor Operator license, or (3)

At least 10 years of professional level experience in his

field, at least 5 years of which experience shall be in the nuclear field.

A minimum of 50%

of these personnel shall have the qualifications specified in (1) above.

RESPONSIBILITIES 6.2.3.3 The ISEG shall be responsible for maintaining surveillance of unit activities to provide independent verification

  • that these activities are performed correctly and that human errors are reduced as much as practical.

RECORDS 6.2.3.4 Records of activities performed by the ISEG shall be

prepared, maintained, and a

summary report shall be forwarded each calendar month to the Senior Vice President, Nuclear Power Division.

t

  • Not responsible for sign-off function.

BEAVER VALLEY UNIT 2 6-3 (next page is 6-5)

Amendment No.

(Proposed Wording) i

NPF-73 ADMINISTRATIVE CONTROLS 1

6.3 FACILITY STAFF OUALIFICATIONS 1

6.3.1 Each member of the facility and Radiation Protection staff shall meet or exceed the minimum qualifications of ANSI N18.1-1971 for comparable positions, except for the Health Physics Manager who shall meet or exceed the qualifications of Regulatory Guide 1.8, September 1975, and the technical advisory engineering representative j

who shall have a bachelor's degree or equivalent in a scientific or engineering discipline with specific training in plant design and response analysis of the plant for transients and accidents.

6.4 TRAINING 6.4.1 A

retraining and replacement training program for the facility staff shall be maintained under the direction of the Nuclear Training Manager and shall meet or exceed the requirements and i

recommendations of Section 5.5 of ANSI N18.1-1971 and 10 CFR Part 55.

i 6.5 REVIEW AND AUDIT 6.5.1 ONSITE SAFETY COMMITTEE (OSC)

FUNCTION l

6.5.1.1 The OSC shall function to advise the General Manager Nuclear l

Operations on all matters related to nuclear safety and shall provide review capability in the areas of:

l a.

nuclear power plant operations l

b.

radiological safety j

c.

maintenance i

d.

nuclear engineering e.

nuclear power plant testing l

f.

technical advisory engineering g.

chemistry h.

quality control i.

instrumentation and control l

I COMPOSITION l

l 6.5.1.2 The Onsite Safety Committee Supervisor is the OSC Chairman and shall appoint all members of the OSC.

The membership shall consist of a

minimum of one individual from each of the areas j

designated in 6.5.1.1.

l OSC members and alternates shall meet or exceed the minimum qualifications of ANSI N18.1-1971 Section 4.4 for comparable positions.

The nuclear power plant operations individual shall meet the qualifications of Section 4.2.2 and the maintenance individual shall meet the qualifications of Section 4.2.3.

l l

i i

l BEAVER VALLEY - UNIT 2 6-6 Amendment No.

1 (Proposed Wording) i I

l

NPF-73 ADMINISTRATIVE CONTROLS AUTHORITY 6.5.1.7 The OSC shall:

a.

Recommend to the General Manager, Nuclear Operations written l

approval or disapproval of items considered under 6.5.1.6.a through d above.

b.

Render determinations in writing with regard to whether or not each item considered under 6.5.1.6.a through e above constitutes an unreviewed safety question.

c.

Provide written notification within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the Senior Vice President, Nuclear Power Division and the Offsite Review Committee of disagreement between the OSC and the l

General

Manager, Nuclear Operations; however, the General l
Manager, Nuclear Operations shall have responsibility for l

resolution of such disagreements pursuant to 6.1.1 above.

RECORDS l

l 6.5.1.8 The OSC shall maintain written minutes of each meeting and l

copies shall be provided to the General Manager, Nuclear Operations

}

and Chairman of the Offsite Review Committee.

6.5.2 OFFSITE REVIEW COMMITTEE (ORC) l FUNCTION 6.5.2.1 The ORC shall function to provide independent review and audit of designated activities in the areas of:

j l

a.

nuclear power plant operations b.

nuclear engineering l

c.

chemistry and radiochemistry d.

metallurgy e.

instrumentation and control f.

radiological safety g.

mechanical and electrical engineering h.

quality assurance practices BEAVER VALLEY - UNIT 2 6-8 Amendment No.

(Proposed Wording)

i NPF-73 ADMINISTRATIVE CONTROLS COMPOSITION 6.5.2.2 The chairman and all members of the ORC shall be appointed by the Senior Vice President, Nuclear Power Division.

The I

membership shall consist of a

minimum of five individuals who collectively possess a

broad based level of experience and competence enabling the committee to review and audit those activities designated in 6.5.2.1 above and to recognize when it is necessary to obtain technical advice and counsel.

An individual may possess expertise in more than one specialty area.

The collective competence of the committee will be maintained as changes to the membership are made.

ALTERNATES i

6.5.2.3 All alternate members shall be appointed in writing hv the ORC Chairman to serve on a temporary basis; however, no more than two alternates shall participate as voting members in ORC activities at any one time.

j CONSULTANTS i

6.5.2.4 Consultants shall be utilized as determined by the ORC Chairman to provide expert advice to the ORC.

l MEETING FREOUENCY 6.5.2.5 The ORC shall meet at least once per calendar quarter during the initial year of facility operation following fuel loading and at least once per six months thereafter.

OUORUM 6.5.2.6 A

quorum of ORC shall consist of the Chairman or his designated alternate and at least four members including alternates.

No more than a minority of the quorum shall have line responsibility for operation of the facility.

REVIEW 6.5.2.7 The ORC shall review:

a.

The safety evaluations for 1) changes to procedures, equipment, or systems and 2) tests or experiments completed under the provision of Section 50.59, 10 CFR, to verify that such actions did not constitute an unreviewed safety question.

BEAVER VALLEY - UNIT 2 6-9 Amendment No.

(Proposed Wording)

NPF-73 ADMINISTRATIVE CONTROLS REVIEW (Continued) b.

Proposed changes to procedures, equipment or systems which involve an unreviewed safety question as defined in Section 50.59, 10 CFR.

c.

Proposed tests or experiments which involve an unreviewed safety question as defined in Section 50.59, 10 CFR.

d.

Proposed changes in Technical Specifications or licenses.

e.

Violations of applicable

statutes, codes, regulations,
orders, Technical Specifications, license requirements, or of internal procedures or instructions having nuclear safety significance.

l f.

Significant operating abnormalities or deviations from i

normal and expected performance of plant equipment that 3

affect nuclear safety.

j g.

All REPORTABLE EVENTS.

l h.

All recognized indications of an unanticipated deficiency in some aspect of design or operation of safety-related structures, systems, or components.

i.

Reports and meeting minutes of the OSC.

j.

The results of the Radiological Environmental Monitoring l

Program prior to submittal of the annual report provided in accordance with Specification 6.9.1.10.

AUDITS l

L 6.5.2.8 Audits of facility activities shall be performed under the cognizance of the ORC.

These audits shall encompass:

a.

The conformance of facility operations to provisions contained within the Technical Specifications and applicable license conditions.

l t

b.

The performance, training, and qualifications of the entire facility staff.

c.

The results of actions taken to correct deficiencies occurring in facility equipment, structures, systems, or methods of operation that affect nuclear safety.

l d.

The performance of activities required by the Quality Assurance Program to meet the criteria of Appendix "B",

10 CFR 50.

l BEAVER VALLEY - UNIT 2 6-10 Amendment No.

(Proposed Wording) l

NPF-73 ADMINISTRATIVE CONTROLS i

AUDITS (Continued)

I e.

Not used.

f.

Not used.

l g.

Any other area of facility operation considered appropriate by the ORC or Senior Vice President, Nuclear Power Division.

h.

The. Facility Fire Protection Program and implementing procedures.

I 1.

Not used.

j.

An inspection and audit of the fire protection and loss prevention program shall be performed by a

qualified outside fire consultant.

l k.

The Offsite Dose Calculation Manual and implementing procedures.

1.

The Process Control Program and implementing procedures for l

processing and packaging of radioactive waste.

l l

AUTHORITY l

6.5.2.9 The ORC shall report to and advise the Senior Vice President, Nuclear Power Division on those areas of responsibility specified in Section 6.5.2.7 and 6.5.2.8.

RECORDS l

6.5.2.10 Records of ORC activities shall be prepared, approved and distributed as indicated by the following:

a.

Minutes of each ORC meeting shall be prepared for and approved by the ORC Chairman or Vice Chairman within 14 days following each meeting.

b.

Reports of reviews-encompassed by Section 6.5.2.7 above, l

shall be documented in ttce ORC meeting minutes.

c.

Audit reports encompassed by Section 6.5.2.8 above, shall be forwarded to the Senior Vice President, Nuclear Power Division and to the management positions responsible for the areas audited within 30 days atter completion of the audit.

I BEAVER VALLEY - UNIT 2 6-11 Amendment No.

l (Proposed Wording)

4 NPF-73 ADMINISTRATIVE CONTROLS 6.6 REPORTABLE EVENT ACTION 6.6.1 The following actions shall be taken for REPORTABLE EVENTS:

a.

The Commission shall be notified in accordance with 10 CFR 50.72 and/or a

report be submitted pursuant to the i

requirements of Section 50.73 to 10 CFR Part 50, and j

b.

Each REPORTABLE EVENT shall be reviewed by the OSC, and results of this review shall be submitted to the ORC.

1 l

6.7 SAFETY LIMIT VIOLATION 6.7.1 The following actions shall be taken in the event a Safety Limit is violated:

a.

The facility shall be placed in at least HOT STANDBY within one (1) hour.

b.

The Safety Limit violation shall be reported to the Commission within one hour and to the General Manager, j

Nuclear Operations and to the ORC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

c.

A Safety Limit Violation Report shall be prepared.

The report shall be reviewed by the On-Site Safety Committee (OSC).

This report shall describe (1) applicable circumstances preceding the violation, (2) effects of the violation upon facility components, systems or structures, and (3) corrective action taken to prevent recurrence.

d.

The Safety Limit Violation Report shall be submitted to the Commission, the ORC and the General

Manager, Nuclear Operations within 30 days of the violation.

6.8 PROCEDURES 6.8.1 Written procedures shall be established, implemented, and maintained covering the activities referenced below:

a.

The applicable procedures recommended in Appendix "A"

of Regulatory Guide 1.33, Revision 2, February 1978.

b.

Refueling operations.

c.

Surveillance and test activities of safety related equipment.

d.

Not used.

e.

Not used.

BEAVER VALLEY - UNIT 2 6-12 Amendment No.

(Proposed Wording)

4 ATTACHMENT D-1 l

Beaver Valley Power Station, Unit No. 1 Proposed Technical Specification Change No. 216 3

?

I l

Applicable UFSAR Changes l

Affected Page:

l 1.3-50 I

i I

i k

i l,

l I

i i

I l

e i

i t

1 1

b i

1 l

I t

i i

i 1

1 4

(

1 1

BVPS-1-UPDATED FSAR Rsv. 11 (1/93)

REGULATORY GUIDE 1.70.11:

INFORMATION FOR SAFETY ANALYSIS REPORTS QUALITY ASSURANCE SAFETY OPERATIONS PHASE The Duquesne Light Company Operations Quality Assurance Program requirements follow the guidance of Regulatory Guide 1.70.11.

REGULATORY GUIDE 1.88,

AUGUST, 1974:

COLLECTION, STORAGE, AND MAINTENANCE OF NUCLEAR POWER PLANT QUALITY ASSURANCE RECORDS The Duquesne Light Company Operations Quality Assurance Program follows the guidance of Regulatory Guide 1.88 with the exception that single Quality Assurance record storage facilities will be designed and constructed in accordance with the guidance of ANSI /ASME NQA-1-1983, Supplement 17S-1, Section 4.4.

REGULATORY GUIDE 1.144, SEPTEMBER 1930:

AUDITING OF QUALITY ASSURANCE PROGRAMS FOR NUCLEAR POWER PLANTS Beaver Valley Power Station - Unit 1(BVPS-1) will meet the intent of Regulatory Guide 1.144 for the auditing of its Quality Assurance Program during the operations phase with the following clarifications and alternatives:

Paracraoh C.1 The applicability of the referenced regulatory guides / ANSI standards (RG 1.28:

ANSI N45.2, RG 1.28:

ANSI N45.2.9, and RG 1.74:

ANSI N45.2.10] is as stated in the respective positions on these regulatory guides / ANSI standards as described in the UFSAR.

Paracraoh C.3 Scheduled internal audit frequency will be as specifie5IT in Paragraph C.4 of Regulatory Guide 1.33, Rev.

2, /

Qebruary 1978 y

The pre-audit and post-audit conferences required by Sections 4.3.1 and 4.3.3 of ANSI N45.2.12-1977 may be fulfilled by a variety of communications such as telephone conversations.

REGULATORY GUIDE 1.155, JUNE 1988: STATION BLACKOUT The utilization of BVPS emergency diesel generators as alternate AC (AAC) power sources for coping with station blackout, and the reliability program for these ggge{gtors follow the guidance of Regulatory Guide 1.155 (June 1988) t 1.3-50

Attachment to Unit 1 Updated FSAR Insert "C"

Paracraph C.3.a Except for audit frequencies mandated by Title 10 of the Code of Federal Regulations, internal audits of selected aspects of operational ph0se activities shall be performed with a frequency commensurate wir.h their safety significance and in such a manner as l

to ensure that audits described in each Unit's Technical l

Specifications a're completed within a period of 2 years (biennially).

l i

l 1

I l

1 i

?

i i

i BEAVER VALLEY - UNIT 1 Insert C - Page 1 of 1 (Proposed Wording) l

ATTACHMENT D-2 Beaver Valley Power Station, Unit No. 2 Proposed Technical Specification Change No. 83 Applicable UFSAR Changes Affected Pages:

Table 1.8-1 page 14 of 80 page 15 of 80 page 76a of 80 i

k i

i i

i N

A 4

i e

1 i

l l

i l

3 i

l 1;

BVPS-2 UFSAR TABLE 1.8-1 (Cont)

Following the guidance of any of the preceding document revisions was based primarily on the revision in effect on the date of the last specification revision wherein the regulatory guide was invoked. Since each revision of the regulatory guide is less restrictive than the foregoing, following the guidance of any of the revisions is considered acceptable.

RG No. 1.32, Rev. 2 UFSAR Reference Sections 7.5, 8.1.5, 8.2, 8.3.1,-8.3.2, 7.5.2.3.1.3 CRITERIA FOR SAFETY-RELATED ELECTRIC POWER SYSTEMS FOR NUCLEAR i

POWER PLASTS (FEBRUARY 1977)

)

The design of the safety-related electric power systems for i

Beaver Valley Power Station Unit 2 (BVPS-2) follows IEEE Standard 308-1974, and the guidance of Regulatory Guide 1.32, j

with the following clarifications:

i Two immediate access offsite power circuits are provided.

Each circuit is designed to be immediately available l

following a less of onsite alternating current power supplies I

l so that sufficient power capacity remains for an orderly l

shutdown and to supply all train related engineered safety feature loads Each battery charger that supplies Class IE 125 V de systems i

is designed with full capacity and capability to supply the l

largest combined demands of the various steady state loads i

while simultaneously providing sufficient power for adequate charging capacity to restore the battery from the design minimum charged state to the charged state irrespective of 1

the BVPS-2 status during which these demands occur.

For test methods, procedures, and intervals for all Class IE battery performance discharge and service tests, refer to the position on Regulatory Guide 1.129.

RG No. 1.33, Rev. 2 UFSAR Reference Sections 13.4, 13,5, 17.2 l

QUALITY ASSURANCE PROGRAM REQUIREMENTS (OPERATION)

(FEBRUARY 1978)

The Quality Assurance Program for the operating phase of Beaver Valley Power Station - Unit 2 will follow the guidance of this regulatory guide with the following clarification:

Paragraph C.2 The applicability of the referenced regulatory guides (1.8, j

1.17, 1.28, 1.30, 1.37, 1.38, 1.39, 1.54, 1.58, 1.64, 1.74, 1.88, 1.94, 14 of 80

9 BVPS-2 UFSAR TABLE 1.8-1 (Cont) 1.116, and 1.123) is as stated in the respective positions on these regulatory guides.

MSJCrk 3 RG No. 1.34, Rev. 0 UFSAR Reference Section 5.2.3 CONTROL OF ELECTROSLAG VELD PROPERTIES (DECEMBER 28, 1972)

The guidance provided by this regulatory guide regarding control of electroslag weld properties was followed for fabrication of applicable components for Beaver Valley Power Station - Unit 2.

RG No. 1.35, Rev. 2 INSERVICE INSPECTION OF UNGROUTED TENDONS IN PRESTRESSED CONCRETE C_0NTAINMENT STRUCTURES (JANUARY 1976) 0 This regulatory guide is not applicable to Beaver Valley Power Station - Unit 2.

RG No. 1.36, Rev. O UFSAR Reference Sections 5.2.3, 6.1.1 NONMETALLIC THERMAL INSULATION FOR AUSTENITIC STAINLESS STEEL (FEBRUARY 23, 1973) f Nonmetallic thermal insulation for austenitic stainless steel used at Beaver Valley Power Station - Unit 2 meets the intent of this regulatory guide.

As an alternative to controlled packaging and shipping described in Paragraph C.1, receipt inspection and tests are required by specification.

This testing and inspection consists of visual inspection for physical or water damage to all cartons.

Damaged cartons are segregated.

Potentially contaminated insulation is not accepted, unless randomly selected s amples from each carton are shown to be acceptable after being resubjected to the production test outlined in this regulatory guide.

RG No. 1.37, Rev. 0 UFSAR Reference Sections 6.1.1.1, 17.2, 5.2.3.4.1 QUALITY ASSURANCE REQUIREMENTS FOR CLEANING OF FLUID SYSTEMS AND ASSOCIATED COMPONENTS OF WATER-COOLED NUCLEAR POWER PLANTS (MARCH 16, 1973)

Quality assurance requirements for cleaning of fluid systems and associated components at Beaver Valley Power Station Unit 2 meet the intent of this regulatory guide with the following alternatives:

15 of 80

i

\\

Attachment to BVPS 2 Updated FSAR Insert "D"

Paragraph C.4 Except for audit frequencies mandated by Title 10 of the Code of Federal Regulations, internal audits of selected aspects of I

operational ph: se activities shall be performed with a frequency

{

commensurate with the_r safety significance and in such a manner as l

to ensure that audits described in each Unit's Technical Specifications are completed within a period of 2 years (biennially).

L i

l l

l l

I i

l i

BEAVER VALLEY - UNIT 2 Insert D - Page 1 of 1 (Proposed Wording)

BVPS-2 UFSAR TABLE 1.8-1 (Cont)

Paragraph C.5.2.2 Beaver Valley Power Station Unit 2 complies with this section, except that the spectra described in Sections 3.7B.1 and 3.7B.2 are used.

Paragraph C.S.2.3 Beaver Valloy Power Station Unit 2 uses the modal time-history technique to. generate floor response spectra.

Refer to Section 3.7B.2.

Paragraph C.S.2.4 Beaver Valley Power Station - Unit 2 uses ACI-318-71. This was the code in effect at the time of design.

The differences between this code and ACI-318-77 are insignificant.

Paragraph C.6 j

Quality assurance programs used for the design, manufacture, construction, and inspection of.the equipment used in the radwaste management systems-are in accordance with a QA Category II classification and the codes and standards specified in the equipment purchase specifications.

RG No. 1.144, Rev. 1 UFSAR Reference Section.17.2 AUDI*.T 2 UF QUALITY ASSURANCE PROGRAMS FOR NUCLEAR POWER PLANTS (SEPTEMBER 1980)

Beaver Valley Power Station Unit 2 (BVPS-2) will meet the intent of Regulatory Guide 1.144 for the auditing of its Quality Assurance Program during the operations phase with the following clarifications and alternatives:

The pre-audit and post-audit conferences required by Sections 4.3.1 and 4.3.3 of ANSI N45.2.12-1977 may be fulfilled-by a ~ variety of communications such as telephone conversation.