MONTHYEARML19351D2691980-10-0606 October 1980 Forwards Status Rept Re Implementation of NUREG-0578 Category B Tasks & Util Position Re Addl Requirements of TMI-2 Task Action Plan Per NUREG-0660.Requests Deferral Until Sept 1981 for Related Tasks Requiring Outages Project stage: Other ML19339A6741980-10-31031 October 1980 Forwrds Info Re Environ Qualification Tests to Be Conducted within 2 Yrs on Equipment to Be Used at Facility in Response to NRC 801001 Request.Schedules Are Set by Vendors & Util Contact Project stage: Request ML20005B5211981-02-18018 February 1981 Sys Description for Reactor Coolant Gas Vent Sys Project stage: Other ML20005B5121981-07-0101 July 1981 Forwards Five Drawings,Design Description & Procedural Guidelines Re Reactor Coolant Gas Vent Sys,Per NUREG-0737, Item II.B.1 Clarification Transmitted in NRC . Aperture Cards Are Available in PDR Project stage: Other ML20010J0261981-09-17017 September 1981 Forwards Corrected Discussion Section of 810701 Response to NUREG-0737 Re Reactor Coolant Gas Vent Sys Project stage: Other ML20038A9211981-11-19019 November 1981 Forwards Commitment to Meet Technical Requirements & NRC Implementation Schedule for NUREG-0737,Items II.F.1.1 & II.F.1.2,per 811020 Request Project stage: Request ML20039D6111981-12-28028 December 1981 Forwards Update on NUREG-0737 Items Implemented or Required for Completion Prior to 820101 Project stage: Other ML20040H1641982-02-0808 February 1982 Forwards Info to Be Provided to Franklin Research Ctr Re Environ Qualification of safety-related Electrical Equipment,In Response to NRC .Info Withheld (Ref 10CFR2.790) Project stage: Request ML20042A7121982-03-18018 March 1982 Informs That,Except for One Document,Info Requested in Part a of Franklin Research Ctr Request for Addl Info Re Environ Qualification of safety-related Electrical Equipment Was Forwarded in Project stage: Request ML20050B8731982-04-0101 April 1982 Requests Delay in Implementing Natural Circulation Cooldown Due to NUREG-0737,Item II.B.1 Which Precludes Use of Reactor Gas Vent Sys (Rgvs).Proposes Implementation of Natural Circulation Cooldown Procedure Upon NRC Approval of Rgvs Project stage: Other ML20052C0681982-04-30030 April 1982 Forwards Addl Info Per 820318 Request Re Pressurized Thermal Shock Issue.No near-term Pressurized Thermal Shock Problem Exists at Plant Project stage: Request ML20052D7131982-05-0303 May 1982 Advises That Addl Info Re NUREG-0737,Item II.B.1, RCS Vent Sys Will Be Provided by 820601,in Response to NRC .Delay Due to Extensive Scope of Work.Info Is Being Compiled by C-E Project stage: Other ML20053D7831982-06-0101 June 1982 Submits Addl Info Re NUREG-0737,Item II.B.1, RCS Vents. Util Has Completed & Included Instructions for Operation of RCS Gas Vents During Normal & Refueling Outage Operations in Operating Instructions Project stage: Other ML20062G4801982-08-0505 August 1982 Advises That Procedure for Natural Circulation Cooldown Implemented,Effective 820630.Procedure Will Be Modified to Incorporate Use of Reactor Gas Vent Sys.Sys Could Significantly Reduce Time to Achieve Cold Shutdown Project stage: Other ML20077K7821983-01-17017 January 1983 Selected Operating Reactors Issues Program Ii,Rcs Vents (NUREG-0737,Item II.B.2), Final Technical Evaluation Rept Project stage: Other 1982-02-08
[Table View] |
Text
-_
p
.O Omaha Public Power District 1623 HARNEY 8 OMAHA. NEBRASMA 68102 s TELEPHONE 536 4000 AREA CODE 402 March 18, 1982 LIC-82-130 p
g
<t;
~
/t v'%
if Mr. Robert A. Clark, Chief U. S. Nuclear Regulatory Commission
$ %,p'e o 2
/k
%,/[D Y;J Office of Nuclear Reactor Regulation Division of Licensing 6
Rd' Operating Reactors Branch No. 3 2n CS Washington, D.C.
20555 L.,
.d/
s
/
' " ~
Reference:
Docket No. 50-285
Dear Mr. Clark:
The Conunission's letter to Omaha Public Power District, dated February 18, 1982, forwarded a Franklin Research Center (FRC) request for additional information related to the environmental qualification of safety related electrical equipment installed at the Fort Calhoun Station.
Except for one document, the information requested in Part A of FRC's request was provided with the District's letter dated February 8,1982. The one document not provided was a final report by Wyle Laboratory on cable splices inside the Fort Calhoun Station containment.
This report is still incomplete and will not be available until April 4,1982 at the earliest. Once received, a copy will be forwarded to FRC.
The District's response to Part B of FRC's request has been forwarded directly to FRC as specified in your February 18, 1982 letter.
The Conax Corporation reports contained herein are deemed to be " cot mercial or financial information" within the meaning of 10 CFR S 9.5(a)(4),
as specified in 10 CFR 9 2.790(b)(2). Accordingly, the District re-quests that they be withheld from disclosure in their entirety pursuant to the provisions of that section.
A Sincer ly,
!)O W.
ones Divis(opManager Production Operations WCJ/KJM/TLP:jmm cc:
IeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.
3 Washington, D.C.
20036
/O Mr. Cyril J. Crane Franklin Research Center i
The parkway at Twentieth Street l
8203230707 820318 PDR ADOCK 05000285
.lvania 19103 P