ML20027C006

From kanterella
Jump to navigation Jump to search
Requests Concurrence That Expedited Review Schedule of Crbr Exemption Request Will Require Review Above That Anticipated in Eariler Estimates
ML20027C006
Person / Time
Issue date: 02/16/1982
From: Roberts T
NRC COMMISSION (OCM)
To: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
Shared Package
ML20027A734 List:
References
FOIA-82-205 NUDOCS 8210120161
Download: ML20027C006 (1)


Text

-

q e4

'~

UNITED STATES

/

NUCLEAR REGULATORY COMMISSION

/1 g

WASH 1N GTON, D.C. 20555 I

g February 16, 1982 cFFICE OF THE COMMISSIONER 9

MEMORANDUM FOR: William J. Dircks, Executive Director for Operations FROM:

Comissioner Roberts {

SUBJECT:

CRSR EXEMPTION REQUEST I

The Staff sent the Comissioners a memorandum on February 16,1982, indicating that trant of the exemption would exped'.ce construction of CRBR by 15 months. There has been a suggestion at several Comission meetings that this expedited schedule will require Staff review above t

that anticipated in earlier estimates.

Please advise if this is accu-rate and, if so, how many additional people will be required if the Commission were to grant the exemption.

cc:

SECY l

Rec'd Ort, gny Date,,,,

A -/ ig T!me.. 2, 6.4.g.'g. ' '. '

~

h 8210120161 820712 PDR FOIA UDELL82-205 PDR

-