EPID:L-2019-LLA-0069, Issuance of Amendments 167/165 and Granting of Exemptions Consolidation of Structural Building ITAAC (LAR-19-005) (Approved, Closed) |
|
MONTHYEARND-19-0162, Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005)2019-03-29029 March 2019 Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005) Project stage: Request ML19284C4242019-10-10010 October 2019 Revision to Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005R1) Project stage: Request ML19164A2632019-11-15015 November 2019 Issuance of Amendments 167/165 and Granting of Exemptions Consolidation of Structural Building ITAAC (LAR-19-005) Project stage: Request ML19164A2702019-11-15015 November 2019 Attachment - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2692019-11-15015 November 2019 Amendment 165 - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2682019-11-15015 November 2019 Attachment - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ML19164A2662019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2652019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ML19164A2642019-11-15015 November 2019 Cover Letter - Vogtle Electric Generating Plant, Units 3 and 4 (LAR 19-005) Consolidation of Structural Building ITAAC, Amendment 167/165 Project stage: Approval ML19164A2712019-11-15015 November 2019 Safety Evaluation - Vogtle Electric Generating Plant, Units 3 and 4 Amendment 167/165 (LAR 19-005) Project stage: Approval ML19164A2672019-11-15015 November 2019 Amendment 167 - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ND-19-1549, ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782)2019-12-27027 December 2019 ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782) Project stage: Request ND-19-1312, ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782)2019-12-27027 December 2019 ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782) Project stage: Request ML20008D5512020-01-0808 January 2020 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 3.3.00.04b (Index No. 782) for Vogtle Unit 4 Combined License (VOG4) Project stage: Request ML20008D5422020-01-0808 January 2020 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 3.3.00.04b (Index No. 782) for Vogtle Unit 3 Combined License (VOG3) Project stage: Request ML20006D7992020-03-10010 March 2020 Correction Letter for Vogtle Electric Generating Plant Units 3 and 4 Amendment Nos. 167 and 165 (LAR-19-005) Regarding Consolidation of Structural Building ITAAC Project stage: Approval ML20006D8082020-03-10010 March 2020 Appendix C (Amendment No. 167) - Page C-428 Corrected Project stage: Other ML20006D8222020-03-10010 March 2020 Appendix C (Amendment No. 165) - Page C-428 Corrected Project stage: Other ML20070J3542020-03-10010 March 2020 LAR-19-005 Safety Evaluation Consolidation of Structural Building ITAAC R1 Project stage: Approval 2019-12-27
[Table View] |
Text
C-428 Amendment No. 167 Table 3.3-6 Inspections, Tests, Analyses, and Acceptance Criteria No.
ITAAC No.
Design Commitment Inspections, Tests, Analyses Acceptance Criteria 781 3.3.00.04a Not used per Amendment No. 167 782 3.3.00.04b 4.b) Walls of the waste accumulation room in the radwaste building except for designed openings or penetrations provide shielding during normal operations.
Inspection of the as-built radwaste building wall thicknesses will be performed.
A report exists and concludes that the shield walls of the waste accumulation room in the radwaste building except for designed openings or penetrations are consistent with the minimum concrete wall thicknesses of 1'-4", and a minimum concrete wall thickness of 1'-8" near the radwaste bunkers, or the report documents an evaluation of thickness deviations identified during construction and demonstrates there is no impact to compliance with the radiation protection licensing basis.
783 Deleted.
784 3.3.00.05a 5.a) Exterior walls and the basemat of the nuclear island have a water barrier up to site grade.
An inspection of the as-built water barrier will be performed during construction.
A report exists that confirms that a water barrier exists on the nuclear island exterior walls up to site grade.
785 3.3.00.05b 5.b) The boundaries between rooms identified in Table 3.3-2 of the auxiliary building are designed to prevent flooding of rooms that contain safety-related equipment.
An inspection of the auxiliary building rooms will be performed.
A report exists that confirms floors and walls as identified on Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in Table 3.3-2.