Southern Nuclear Michael J, Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro. GA 30830 706-848-6459 October 10, 2019 Docket Nos.: 52-025 52-026 ND-19-1023 10 CFR 50.90 10 CFR 52.63 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Units 3 and 4 Revision to Request for License Amendment and Exemption:
Consolidation of Structural Buiidino ITAAC (LAR-19-005R1)
Ladies and Gentlemen:
By letter dated March 29, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19088A274) Southern Nuclear Operating Company (SNC), the licensee for Vogtle Electric Generating Plant (VEGP) Units 3 and 4, requested an amendment to Combined License (COL) Numbers NPF-91 and NPF-92, for VEGP Units 3 and 4 (respectively).
The requested amendment included changes to the VEGP Unit 3 and Unit 4 COL Appendix C (and corresponding plant-specific DCD Tier 1) information. Pursuant to the provisions of 10 CFR 52.63(b)(1), an exemption from elements of the design as certified in the 10 CFR Part 52, Appendix D, design certification rule was also requested for the plant-specific Tier 1 material departures.
The License Amendment Request (LAR) proposed the consolidation of certain building and structure related Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC). Specifically, SNC has determined that some building and structure related ITAAC Acceptance Criteria are duplicative. To correct this condition, SNC proposed to revise COL Appendix C (and plant-specific Tier 1 information) to consolidate duplicative ITAAC Acceptance Criteria for certain structures and clarify that evaluations of thickness deviations would be included in the reconciliation and thickness reports described in ITAAC Acceptance Criteria.
This revision to LAR-19-005 is being submitted to address comments provided by the U. S. Nuclear Regulatory Commission (NRC) staff during July 10, 2019, August 15, 2019 and September 10, 2019 public meetings and in draft Requests for Additional Information (RAIs) dated July 9, 2019, August 1, 2019 and September 5, 2019. Enclosures 1, 2, and 3 of LAR-19-005 are replaced in their entirety with Enclosures 4, 5, and 6 of this revised amendment request. Revision bars in the right-hand margin indicate the differences between Enclosures 1 and 4 and Enclosures 2 and 5. In addition, SNC's response to the draft RAI is provided in Enclosure 7 to this letter. provides the description, technical evaluation, regulatory evaluation (including the significant hazards consideration), and environmental considerations for the proposed changes.
U.S. Nuclear Regulatory Commission ND-19-1023 Page 2 of 4 provides the background and supporting basis for the requested exemption. provides the proposed license basis changes. Enclosure 7 provides the draft NRG RAI and SNC's response.
The Enclosures to this letter have been reviewed and confirmed to not contain security-related information. This letter contains no regulatory commitments.
The revised information provided in the enclosures does not change the scope of the requested license amendment or exemption, nor does it change the conclusions in the Technical Evaluation or the conclusions in the No Significant Hazards Consideration Determination.
SNC requests staff approval of this revised license amendment by November 15,2019 to support closure of VEGP Units 3 and 4ITAAC. Approval by this date will allow sufficient time to implement the licensing basis changes prior to the associated ITAAC activity. SNC expects to implement this proposed amendment (through incorporation into the licensing basis documents) within 30 days of approval of the requested changes.
In accordance with 10CFR 50.91, SNC is notifying the Stateof Georgia of this LAR by transmitting a copy of this letter and enclosures to the designated State Official.
Should you have any questions, please contact Mr. Nicholas Kellenberger at (706) 437-2333.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 10th day of October 2019.
Respectfully submitted, SOUTHERN NUCLEAR OPERATING COMPANY Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4 MJY/RAS/sfr Enclosures; 1)-3) Provided with original submittal.
- 4) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 -
Revised Request for License Amendment: Consolidation of Structural Building ITAAC (LAR-19-005R1)
- 5)
Vogtle Electric Generating Plant (VEGP) Units 3 and 4 -
Revised Exemption Request: Consolidation of Structural Building ITAAC (LAR 005R1)
- 6)
Vogtle Electric Generating Plant (VEGP) Units 3 and 4 -
Revised Proposed Changes to the Licensing Basis Documents (LAR 005R1)
- 7)
Vogtle Electric Generating Plant (VEGP) Units 3 and 4 -
Response to Draft Request for Additional Information, dated August 1, 2019
U.S. Nuclear Regulatory Commission ND-19-1023 Page 3 of 4 go; Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)
Mr. P. P. Sena ill (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones (w/o enclosures)
Mr. G. Chick Mr. M. Page Mr. D. L. McKinney (w/o enclosures)
Mr. T. W. Yelverton (w/o enclosures)
Mr. B. H. Whitley Ms. C. A. Gayheart Mr. C. R. Pierce Ms. M. Ronnlund Mr. D. L. Fulton Mr. M. J. Vox Mr. C. T. Defnall Mr. J. Tupik Ms. S. Agee Mr. M. Humphrey Ms. A. C. Chamberlain M
M M
S. Leighty N. Kellenberger E. Riffle Ms. K. Roberts Mr. J. Haswell Mr. D. T. BIythe Document Services RTYPE: VND.LI.LOO File AR.01.02.06 Nuclear Regulatory Commission Mr. W. Jones (w/o enclosures)
Ms. J. Dixon-Herrity Mr. C. Patel Mr. B. Kemker Mr. G. Khouri Ms. S. Temple Mr. F. Brown Mr. C. J. Even Mr. A. Lerch Mr. S. Walker Mr. N.D. Karlovich Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Ms. K. P. Carrington Mr. M. Webb Mr. P.J. Heher
U.S. Nuclear Regulatory Commission ND-19-1023 Page 4 of 4 State of Georgia Mr. R. Dunn Oalethorpe Power Corporation Mr. M. W.
Price Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company. LLC Mr. L. Oriani (w/o enclosures)
Mr. T. Rubenstein (w/o enclosures)
Mr. M. Corletti Mr. M. L. Clyde Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham NDDocumentinBox@duke-energy.com, Duke Energy Mr. S. Franzone, Florida Power & Light