Letter Sequence Approval |
|---|
EPID:L-2019-LLA-0069, Issuance of Amendments 167/165 and Granting of Exemptions Consolidation of Structural Building ITAAC (LAR-19-005) (Approved, Closed) |
|
MONTHYEARND-19-0162, Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005)2019-03-29029 March 2019 Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005) Project stage: Request ML19284C4242019-10-10010 October 2019 Revision to Request for License Amendment and Exemption: Consolidation of Structural Building ITAAC (LAR-19-005R1) Project stage: Request ML19164A2632019-11-15015 November 2019 Issuance of Amendments 167/165 and Granting of Exemptions Consolidation of Structural Building ITAAC (LAR-19-005) Project stage: Request ML19164A2702019-11-15015 November 2019 Attachment - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2692019-11-15015 November 2019 Amendment 165 - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2682019-11-15015 November 2019 Attachment - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ML19164A2662019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) Project stage: Approval ML19164A2652019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ML19164A2642019-11-15015 November 2019 Cover Letter - Vogtle Electric Generating Plant, Units 3 and 4 (LAR 19-005) Consolidation of Structural Building ITAAC, Amendment 167/165 Project stage: Approval ML19164A2712019-11-15015 November 2019 Safety Evaluation - Vogtle Electric Generating Plant, Units 3 and 4 Amendment 167/165 (LAR 19-005) Project stage: Approval ML19164A2672019-11-15015 November 2019 Amendment 167 - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) Project stage: Approval ND-19-1549, ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782)2019-12-27027 December 2019 ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782) Project stage: Request ND-19-1312, ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782)2019-12-27027 December 2019 ITAAC Closure Notification on Completion of ITAAC 3.3.00.04b (Index Number 782) Project stage: Request ML20008D5512020-01-0808 January 2020 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 3.3.00.04b (Index No. 782) for Vogtle Unit 4 Combined License (VOG4) Project stage: Request ML20008D5422020-01-0808 January 2020 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 3.3.00.04b (Index No. 782) for Vogtle Unit 3 Combined License (VOG3) Project stage: Request ML20006D7992020-03-10010 March 2020 Correction Letter for Vogtle Electric Generating Plant Units 3 and 4 Amendment Nos. 167 and 165 (LAR-19-005) Regarding Consolidation of Structural Building ITAAC Project stage: Approval ML20006D8082020-03-10010 March 2020 Appendix C (Amendment No. 167) - Page C-428 Corrected Project stage: Other ML20006D8222020-03-10010 March 2020 Appendix C (Amendment No. 165) - Page C-428 Corrected Project stage: Other ML20070J3542020-03-10010 March 2020 LAR-19-005 Safety Evaluation Consolidation of Structural Building ITAAC R1 Project stage: Approval 2019-12-27
[Table View] |
Text
SOUTHERN NUCLEAR OPERATING COMPANY, INC.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 3 DOCKET NO.52-025 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 167 License No. NPF-91
- 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Southern Nuclear Operating Company (SNC),
dated March 29, 2019, as revised October 10, 2019, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B.
The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to Appendix C of the facility Combined License as described in the licensees application dated March 29, 2019, as revised October 10, 2019. Paragraph 2.D(8) of Facility Combined License No. NPF-92 is hereby amended to read as follows:
(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 167, are hereby incorporated into this license.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 30 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION:
/RA/
Victor E. Hall, Chief Vogtle Project Office Office of Nuclear Reactor Regulation Date of Issuance: November 15, 2019
Attachment:
Page 7 of the Facility Combined License and affected pages of Appendix C of the Facility Combined License