ML20004E892

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-413/81-02 & 50-414/81-02 on 810126-0206. Noncompliance Noted:Measures Not Established to Assure Adequate Personnel Training Per Evaluation & Reporting Requirements & Controlling Procedures
ML20004E892
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/24/1981
From: Blake J, Brownlee V, Bryant J, Hunt M, Mcfarland C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20004E890 List:
References
50-413-81-02, 50-413-81-2, 50-414-81-02, 50-414-81-2, NUDOCS 8106160098
Download: ML20004E892 (27)


See also: IR 05000413/1981002

Text

.

8

%

UNITED STATES

I

8'

1

NUCLEAR REGULATORY COMMISSION

E,

E

REdlON 11

b[

101 MARIETTA ST., N.W., SulTE 313o

Q

ATLANTA, GEORGIA 30303

o

Report Nos. 50-413/81-02 and 50-414/81-02

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Facility Name: Catawba 1 and 2

Docket Nos. 50-413 and 50-414

License Nos. CPPR-116 and CPPR-117

Inspection at Catawba site near Rock Hill, South Carolina and Duke Power Company

(DPC) Corporate Offices, Charlotte, North Carolina

Inspectors:

'

8

s//P/

-bb

$^55

V

r6wnlee'

Dhte Sign'ed

~

GAL

v'u/n

,

.

[J/J. Blake

Date Signed

Y/

C. R. McFarland

Date Signed

NV PYHub

3}aN]Tl

M. D~. Htint:

'

D4te Signed

~

J/2N/P/

Approved by:

//C. 8'ryagf,' Sect 1on Chief, Division of

Dite signed

v

Resident and Reactor Project Inspection

l

SUMMARY

Inspection on January 26 - February 6,1981

Areas Inspected

This so-cial, announced inspection involved 345 inspector-hours on site and 15

hours at the Corporate office in the areas of quality assurance, on site design

cc .: trol s ,

site management,

site procurement,

construction controls and

activities, handling of nonconformances and reportable item evaluation.

Con-

i

struction activities inspected included electrical components and systems,

l

instrumentation, safety-related pipe support and restraint system, and mechanical

equipment installation.

i

8.106.I6009&

.

'

.

.

'

k

2

Results

'

Of the areas inspected, two violations were found concerning evaluation and

reporting of Part 21 and 50.55(e) items (Inadequate evaluation

paragraph 8.c

and inadequate training

paragraph 13.d); two violations were found in the area

of nonconforming items processir; (Inadequate evaluation for generic issues -

paragraph 12.b and 12.c and Inadequate documentation

paragraph 12.c); one

violation was found in mechanical installation (Inadequate procedures

paragraph

-

11.e.(2), (3)).

t

f

I

<

r-

1

! - .- , - - _ . _ _

_ _ _ . - . _ _ _ . _ _ _ . _ _ ,

. . .

- - - . .

- . . . _ _ , . ~ . . . - - _ . ~ . - - - - - . _ , , . . - -

. . - _ . . . _ . -

. . - - - - . , _ - - - - . - . _ . . . . - ,

--

-

.

.

.

DETAILS

1.

Persons Contacted

Licensee Employees

  • R. S. Alexander, Personnel Manager
  • L. R. Barnes, Manager, Supports / Restraints
  • D. G. Beam, Project Manager, Catawba

L. R. Davison, QA Manager, Construction

  • S. W. Dressler, Senior Construction Engineer
  • W. J. Foley, Principal Engineer, Electrical Division
  • D. L. Freeze, Manager, Construction Services
  • G. W. Grier, Planning Manager
  • W. O. Henry, QA Manager, Technical Services
  • R. A. Morgan, Project QA Engineer
  • E. C. Wall, General Superint endent

J. R. Wells, Corporate QA Manager

Other licensee employees contacted included 25 engineers and construction

supervisors and foremen, 47 construction craftsmen, 38 technicians, and 16

office personnel.

Other Organizations

T. Davis, Project Manager, MCC Powers

W. Rochester, QA Engineer, MCC Powers

NRC Resident Inspector

  • P. K. VanDoorn
  • Attended exit interview

2.

Exit Interview

!

The inspection scope and findings were summarized on February 6, 1981, with

!

those persons indicated in Paragraph 1 above. The violations were discussed

in detail.

On February 26, 1981, L. C. Dail, DPC Vice President Design Engineering and

'

J. R. Wells, Corporate QA Manager met with the Region II staff in the Region

II office to discuss inspection findings.

3.

Licensee Action on Previous Inspection Findings

(

Not inspected.

4.

Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve noncompliance or

. ,,

- - .

- . - - - - - - _ .

- -

- - - . - - _ , _

- _ . -

- - -

. ...

. _ .

-

.

,

2

deviations.

New unresolved items identified during this inspection are

discussed in paragraph 7.d.

5.

Site QA and Construction QA Program Implementation

a.

General

The purpose of this portion of the inspection was to complete an

overall review of implementation of the DPC program for control of site

QA and construction activities.

DPC Topical Report - Quality Assurance, Duke 1-A, Rev. 4, was accepted

by the Quality. Assurance Branch, Division of Project Management, NRR,

by letter dated June 29, 1978.

The Duke QA program commits to

applicable regulatory requirements such as 10 CFR 50, Appendix B and to

approved industry standards such as ANSI N45.2-1971 and corresponding

daughter standards, or to equivalent alternatives.

The QA program

commits to the regulatory position of the NRC Regulatory Guides listed

in table 17.0-1 of Duke-1-A with the exception of the clarifications,

modifications and alternatives stated in the table.

b.

Documents Examined

(1) DPC Topical Report on Quality Assurance, Duke 1-A, Amendment 4

(2) Corporate QA Manual

(3) Design Department QA Manual

,

(4) QA Department QA Manual

(5) Construction Department QA Manual

(6) Catawba Nuclear Station Construction Procedures Manual

(7) Catawba Nuclear Station Organization Chart

c.

QA Program Review

j

i

l

The inspector reviewed the documents listed in paragraph 5.b and held

l

discussions with responsible corporate and site management, QA, QC,

l

technical support and craft personnel, and concluded that the DPC QA

program and supporting manuals contain the following:

(1) A policy statement from upper management supporting the QA program

and objectives.

(2) Adequate definition in the program for control of contractor and

subcontractor activities.

(3)

Provisions in departmental QA manuals for interface control

between Engineering Design, QA, Construction, Consultants, Con-

tractors, and Procurement.

(4) A listing of commitments to regulatory requirements.

!

l

-

..

.

._.

-

..

-

-

.

.

.

~

3

'

(5) Provision for management audits to determine QA effectiveness.

(6) Clear cut organization charts and responsibility matrices.

(7)

Independence of the QA organization from design and construction.

(8) QA Department direct access to management.

(9) Complete departmental QA manuals with proceduros to implement the

scope of work and provide interface control with other depart-

ments.

(10) Departmental QA manuals which are controlled documents and which

contain procedures for change control.

(11) Stop work requirements established in the Topical Report and

implemented by departmental procedures.

d.

Program Implementation

By observation of ongoing activities, review of reports and discussions

with personnel at all levels, the inspector concluded that the DPC QA

program, supporting manuals and organizational / functional alignment are

consistent with project status and adequate to monitor project

activities in an effective manner. Personnel were knowledgeable of the

QA program and procedural requirements. The inspector identified one

area, lack of knowledge and understanding of NRC evaluation and

reporting requirements, for which a violation was issued.

This is

discussed in paragraph 13.d.

e.

Audits

I

There is a comprehensive system of audit and surveillance activities

which spans corporate, departmental and site activities. DPC belongs

'

to a joint Utility Management Organization which includes seven

l

utilities. This organization performs the corporate audit on an annual

l

basis.

The inspector reviewed the corporate audit report for the

October 6-10,1980 audit.

Departmental audits are performed by the QA Department Internal Audits

Group.

The inspector reviewed C-80-7,

Catawba Nuclear Station

(10/13-20/80), and C-80-8, McGuire Nuclear Station (11/3-7/80) audits.

Site surveillance activities are performed by site QA personnel.

The inspector found that the audit system provides effective inter-

facing. Audit plans are tailored to a function and are not superficial

checklists.

.

.

_

.

- .

_ _ . _ _ _

. _ - -

.

.

-

-

.

.

4

f.

Reorganization

On February 1,1981, all Quality Control personnel were transferred

from the Construction Department to the QA Department.

The Topical

Report does not reflect this organization. The inspector discussed the

change with NRR QA Branch, and with the DPC Corporate QA Manager. It

was agreed that DPC will submit a letter immediately to NRR describing

the new organization and will revise the Topical Report by March 31,

1981.

Neither NRR nor IE abjects to the reorganization and the

inspectors have no further questions on the subject.

As a result of this inspection, the inspector finds that the interface

activities between Design, QA and Construction is adequate.

Management

involvement at the work site is quite good.

It appears that management

supports the program.

6.

Project Management - Site

Portions of this inspection were directed toward methods used by site

management to determine that a quality product is produced and toward

participation of management and supervisory staff in handling of site

problems.

Also, it was directed toward craftsmen ond inspectors to

determine their competence and their perception of the following: work

quality; availability of technical assistance; accessibility of management;

freedom to express opinions; and protection from harassment.

a.

Organization

(1) There are no major contractors at the Catawba site other than the

NSSS, Westinghouse.

Except for a few small contractors, all

personnel on site, from the project manager through craftsmen and

laborers, are employees of Duke Power Company (Duke).

Many

employees are second or third generation Duke employees and many

are working on their third Duke nuclear power site.

Probably as a result of this Duke " family" relationship, the

organization is less formally structured than at some other

utility sites.

Organization charts are of current date; however, they do not

reflect exactly how the organization is functioning in some minor

aspects. This presented no problem, since everyone involved knew

the actual functions. Also, there is a major change of function

in progress to Corporate Quality Assurance rather than to the site

project manager.

This change is discussed in greater detail in

paragraph 5.f of this report.

(2) Position Descriptions

,

The site has Position Analyses for most jobs in the top two or

(

three levels, project manager excluded. These analyses are

1

r

_ _ -

,

_- ,.

, _ _ _ _ _ .

. _ . . _ _ _ _ _ _ _ . . _ . _ _ _ _ _ _ _ ,

- . . , _ _ . _ _ _ _ _ __.

_ _ ,

-

.

'

-

.

.

.

.

5

generic to the company and are not totally accurate relative to

Catawba. They do not match the organization chart completely.

Theca analyses give the broad scope of authority and responsi-

. ties of the positions. However, QA procedures place specific

iesponsibilities on positions in handling safety-related matters.

Position descriptions do not provide for assumption of authority

in the absence of superiors. Assignments to acting positions are

made, if needed, by superiors. There are certain signoffs which

are not delegated but are designated to be signed by a specific

rank.

(3) Communications

The program specifies only three types of reports to go to the

project manager.

These are site stop work orders, variation

notices (departure from design), and nonconforming

items

reportable to the Nuclear Regulatory Commission.

Internally,

numerous other reports are sent to him, such as trending reports,

personnel actions and others.

Communications within the organization are not formally structured

but are handled by managers as they see fit with only the most

serious requiring notification of receipt back to the originator.

On safety matters, the QA Manual describes required communications

in each procedure. These appear to be clearly understood.

(4) Change Controls

Change controls are mastly originated in corporate offices and

notices are disseminated from there. Design changes originated on

site are handled by variation notices which receive corporate

approval before implementation.

In summary, site organization interface and communications is relatively

informal. Written memos are not used when direct contact will serve, except

l

as required in the QA manual.

Due to the nature of the Duke " family"

organization, this system appears to be working.

No noncompliances or

l

safety concerns were found that could be attributed to the organization.

b.

Trending: Nonconformances and Rework

(1) Nonconformances

Site personnel reported that trends of Nonconforming Items (NCI)

reports are prepared annually in corporate offices. These were

not examined by the inspectors. Unofficial trends of NCI's are

developed quarterly on site by the senicr QA engineer. NCI's are

placed in the computer and trends are developed.

At least

quarterly, these are reported to the site manager and actions are

taken as indicated.

,

- , . , ,

.

-- ,.

,

- - - - -

. . - - , , , - - , - - , . - - , - - - -

- . -

- - - -

.

.

.

,

.

6

.

This system, while it apparently is of value in some respects, is

quite limited in other respects.

Items are entered in the

computer by a non-technical person and are assigned a key

designation based on wording of the NCI's.

NCI's of identical

items and failures were found by the inspectors to have received

different key designations, thus they would not appear on the

printout as repeat items.

Also, trending is based on changes in relatively large numbers (50

or more) and thus would not detect five failures, for example, of

a critical item.

(2) Rework

Extensive trending is done of all rework.

Trending reports are

developed for time periods throughout site history, by discipline,

by system, by crew, and by cause. Cause is generally defined as

repair or design, with a very low percentage due to repair.

Design may mean any change from original intent, from a regulatory

change to rerouting due to interference found in layout provided

,

in the field.

These trending reports are prepared for the planning manager and

are received by the site manager and others monthly.

They are

used extensively in planning and evaluation.

'

The NCI trending described above is not a requirement by NRC or Duke,

but is provided for information.

Though weaknesses are described in

the system, no noncompliance with regulation was found. Weaknesses in

the NCI system are described elsewhere in this report.

c.

Management Accessibility to Employees

(1) Availability of Technical Assistance

Discussions were held with craftsman, inspectors and engineers by

all of the NRC inspectors during condact of this inspection. As

described in other sections of this report, the site engineering

staff works very closely with construction forces. Problems are

approached together in the field and resolutions determined.

Construction personnel and inspectors stated that assistance was

always available.

(2)

Freedom to Express Opinions

Duke procedure Q-1 states that all employees are required to

report conditions adverse to quality.

There was evidence that

employees are encouraged to take any problem to their supervision

and to higher supervision, if they feel the need. Employee

_

_

.

. -

_ - _ , .

. _ ._ _ -._ _,___. _ ..

__

_

_ . . . _ . _ _

-

-

.

.

.

,

.

7

4

.

Relations has documented 255 cases in 1980 of employees going to

higher supervision and believes there may be many cases undocu-

mented.

(3) Employee Relations

There is an employee relations office on site located in the work

area.

Employees are encouraged to use these services for any

problem.

On all terminations for cause, Employees . Relations

conducts an investigation independent of other company investi-

gations.

(4) Grievance Procedure

The site has a Construction Department Employee Recourse Procedure

which expresses the belief that employee concerns should be

addressed promptly and should receive thorough consideration

without recrimination. The procedure directs Employee Relations

to assist in preparation of grievances as desired by employees; it

also details steps and required response times.

An informal procedure is described which provides for oral

discussions through four steps to the project manager. A formal

written procedure is described with steps up through the president

of Duke Power Company.

(5) Harassment

The company has a procedure which is posted on site forbidding

harassment of any employee for any reason by anyone and describing

penalties up through termination.

NRC inspectors discussed with QC inspectors and craftsmen the

possibility that they might be pressured or harassed about

rejecting work or into performing poor quality work.

Some of

those interviewed were amused at the thought of such pressure.

None of those talked to felt that such a situation might develop.

(6) Management Contact

In January 1981, the company instituted an Employee Forum program.

This provides for meetings with 20-30 employees, without their

supervision, by management.

The first meetings were held in

January and were attended by craftsmen and the project manager,

the general superintendent, and the personnel manager. Meetings

were described as totally open to any subject, completely confi-

dential, and followed up by answers, if the answer could not be

provided at the time.

.

.- - .

-.

_ _ _ .

.,

. - . .

.-.

_

-

_.

_

.

-

,

8

The Employee Forum announcement is posted in the general work

area.

The project manager stated that he hopes to reach 2000

employees in 1981. The personnel manager described the meetings

as very open.

The inspector has observed the project manager in the work areas

and noted that he was well known by the workers.

He was

frequently greeted by his first name.

In summary, it is the inspectors' opinion from interviews, observa-

'

tions, and review of site and c6mpany policies that top management and

supervision are available to employees at a very low threshold. It is

unlikely that harrassment detrimental to quality work could develop

under these conditions.

7.

Site Procurement, Receiving and Storage

a.

General

The bulk of equipment or materials received at the site are either NSSS

supplied or DPC Engineer procured.

Site requisitioned items are

primarily consumables, standard stock items and transfers,

b.

Documents Exanine.1

(1) Requisition 8337-00578S

P. O. No. F 6216-13

(2) Requisition 8337-00607S

P.O. No. E-98052-13

1

(3) Requisition 8337-00957S

P.O. No. F-33825

(4) Requisition 8337-02195D-3

P.O. No. F-34676

i

(5) Design Engineering Department QA Program -

l

Section 300 - Procurement

,

1

(6) Construction Department QA Program - Procedure E-3,

Field Procurement of Items and Construction Services

(7) QA Manual for ASME Code Work - Section E

c.

Program Implementation

The inspector examined the above noted requisitions, purchase orders,

and controlling procedures; held discussions with site QA personnel,

!

, _.

- .

- - -

.

, - - . - - . . .

. -

- . . . . .

- -

- _ _

,

-

. . .

. -

-

..

.

.

.

,

.

9

~

Technical Support personnel, Warehouse QC personnel, and Warehouse

personnel; and performed an inspection of warehouse and storage

facilities.

The inspector concluded that:

(1) The procurement documents examined included the applicable

technical, QA, Codes, standards and Part 21 requirements.

(2) The materials were ordered from suppliers which are on the

approved vendors list.

(3) The procurement documents specify packaging, handling storage and

documentation requirements.

(4) The receiving QC technicians have access to the procurement

documents at the warehouse.

(5) Site personnel were knowledgeable of site procurement, receiving

and storage policies, procedures and activ'ities.

(6) The site receiving, inspection, nonconforming, tagging, storage,

records and transfer activities are being handled in a controlled

manner.

(7) Class A, B, C and D storage facilities have been established.

d.

Weld Filler Material

During a review of purchasing / receiving records on Febr':ary 4,1981,

the inspectors noted that Purchase Order No. E93052-13 for type E110-18

electrodes ordered to ASME B&PV Code requirements only required typical

certifications rather than the actual certifications by heat and lot

required for ASME B&PV work. The inspectors were informed that the

material was ordered for a specific Non-ASME application and was not

used in ASME applications even though the material appears on the site

list of approved ASME materials. The inspectors informed the licensee

that this would be considered to be an unresolved item (50-413/414/

81-02-01 "Contrui of Weld Filler Material"), while the licensee

attempts to verify the following:

(1) The material was not used in any ASME application.

(2) No other material has been purchased in the same manner and used

I

in ASME applications.

(3) The system for control of filler material assures that material

with only typical certifications does not get used in ASME appli-

cations.

In the areas inspected, no violations were identified.

. , -

- - - - - , .

-

- - - - - - - - -

. - - .

_-. .-.

- . _ _ _ . _ _ - _ . . ,, __

_.

.

.

.

.

10

8.

Electrical (Components and Systems I) - Observation of Work and Work

Activities

a.

Emergency Diesel Generators Auxiliary Equipment

The inspector examined the inplace storage conditions of Diesel

Generators IA and IB and associated local control panels. Each diesel

engine and generator is enclosed in temporary enclosures to reduce the

accumulation of dust and dirt resulting from construction activities in

the immediate area.

Heaters are installed at the base of the

generators for protection from moisture. Weekly inspections are made

to insure that the heaters are functioning properly and recorded on

inspection Form 41-B.

Megger readings are taken every 3 months to

ensure that the protection is adequate for the generator windings.

The control panels and sequdncing panels are covered with wooden doors

to prevent damage to the control switches and meters. These panels are

inspected periodically for cleanliness and damage.

b.

4160 Volt Switchgear

The inspector reviewed the installed 4160V switchgear 2 ETA with the QC

inspectors to ascertain the depth of the QC installation inspection.

Records and discussions revealed that verifications of proper handling

methods, of correct location, and of proper orientation of the base and

equipment were made during the installation of the switchgear.

Inspection for damage is made at this time.

The electrical QC inspectors verify the correct torque values when

anchor bolts are used, but welding inspectors inspect and approve

welded equipment to base installations. The inspection is conducted in

accordance with Supplemental Inspection Instruction, Serial No.

4,

Electrical Equipment Installation.

c.

600V Switchgear and Motor Control Centers

During this inspection, it was found that thirteen 600V circuit

breakers had been nonconformed for broken contact blocks.

These

breakers had been found defective during calibration and adjustment by

the Transmisston Department and nonconformed in accordance with

Procedure Q-1, Control of Nonconforming Items, on Nonconforming Item

Report Nos. 9755,10665,10684,10721,10745,10752,10818 and 10852.

As of the beginning of the inspection, no request had been made for an

evaluation to determine the reportability of the breaker deficiencies.

The fact that breakers had been found defective during 6 successive

working days did not trigger any administrative mechanism that required

further evaluation for reportability.

-.

-.

-

-.

.

--.

_ _ _ .

__ __ _ _

.

__.

_ _ _

_

. _ _ _

-_

_ - .

'

.

.

.

.

.

.

'

11

'

1

~

Approximately 3 days into the inspection, a request for evaluation of

the breaker def Liencies was made by site personnel to corporate

offices. Shortly before the end of the inspection, the inspectors were

3

advised that evaluation had determined that the breaker deficiencies

were not reportable.

'

The inspector, however, identified the compartments in which the

breakers were to be used and found that 4 of the breakers served wither

i

as the normal feeder or alternate feeder breaker for the 600V Essential

Auxiliary Power System 600V Load Centers 2ELXB and 2ELXD.

Failure of these breakers would result in the loss of one train of 600V

motor control centers, which supply power for letdown heat exchanger

cooling water supply and suction valves; auxiliary feedwater to steam

generator 2B isolation valve; auxiliary feedwater pump 2B suction valve

from nuclear service water; and the pressurizer power operated relief

valve isolation valve.

,

It was further determined that one of the breakers identified as

i

deficient was to be installed as a feeder breaker in 600V Essential

j

Auxiliary Power System 2ELXA which is identified as the redundant power

i

train.

It would appear that were these breakers, as designated by

j

approved engineering drawings CN-2703-01.01 and CN-2703-01.01, to fail,

the capability to obtain and maintain safe shutdown conditions would be

'

greatly decreased.

Since the same model breakers are used throughout the other power

train, the possibility exists that the same deficiency exists in them.

The failure to adequately evaluate the breaker deficiencies appears to

be a violation and is identified as 414/81-02-02, Inadequate Evaluation

of Generic Deficiencies for Reportability.

'

Electrical Penetration Installation

.

'

l

The inspector observed partial installation of electrical penetration,

l

Serial No. 2629F, internals. Cleanliness during the installation was

l

closely controlled. All seals were installed and the torquing sequence

t

was in accordance with Procedure CNS-1390.01-00-0073, Mechanical

i

Installation Procedure for Electrical Penetration Types B, C, D, F, G,

H, J, K, L, & M.

Discussions with the cr-ftsmen and QC inspector

'

revealed that these personnel were knowledgeable of the installation

'

procedures as well as the requirements of installation of equipment

which required periodic calibration.

i

e.

Transmission Department

i

This department performs all circuit breaker tests, calibration and

inspections for the construction and operating departments.

In

addition, all adjustable relay calibrations are accomplished by this

department. The Transmission Department also performs the high

'

i-

.

. .

.u

.

.

.

-

-

.

-

.

'

.

12

potential testing of high voltage cables after installation by the

construction forces.

All work is performed in accordance with the construction QA program or

the operating plant QA program.

During construction activities,

surveillance activities are performed and documented by the electr cal

i

QC group.

Discussion with transmission department supervision revealed that the

existing department QA manual is being revised to define more clearly

the responsibilities of the department.

f.

Cable Installation and Terminations

No safety-related cable installations were made during this inspection.

Cable terminations were in progress in several areas but verification

by the QC inspectors is performed just prior to system turnover.

Discussions with the QC inspectors performing this task indicated that

they have an understanding of the procedure requirements. They further

advised the inspector that there was no difficulty in getting

corrections made when required.

g.

Electrical Motor Storage

Examination was made of electrical motor storage conditions while in

the warehouse or after being set in place.

Inspections are made and

documentrM in accordance with approved QA/QC procedures. The motors

are manually rotated quarterly and meggered monthly. Motors requiring

heat when not in operation have temporary power applied to the heaters

until thespermanent power wiring is installed. When this is completed,

the permanent breaker is closed and tagged so that power is applied to

the motor heaters.

h.

Electrical Equipment Qualification

The inspectors met with a Duke Power Company task force tnat had been

assigned the duty of quali fying electrical and instrumentation

equipment to meet the conditions of IEB 79-01B.

The group had just

been organized and had not had time to develop a complete program.

'

Discussions with the inspectors indicated that the group was well

informed and understood the task before them.

1.

Personnel Interviews

The inspector conducted interviews with several craftsmen, rt0

inspectors, engineering technical support and supervisory personnci.

All discussions indicated that safety concerns could be carried to the

highest level necessary to obtain satisfactory answers or resolutions.

No resentment was observed between the craftsmen and the inspection

personnel. The craftsmen were aware of the requirements to do the work

_

.

_

_

. _ _ _

. _ . _

_ _ __

__

.

.

-

'

-

.

.

.

13

properly. Most were aware of the separation criteria and power train

requirements for separation. All had access to procedures and drawings

and indicated that they used them frequently.

The QC inspectors appeared to be well versed in the inspection

procedure to which they were inspecting.

Throughout the organization, no problems appeared that would indicate

that there was not cooperation between all parties involved.

9.

Instrumentation and Control

a.

General

DPC, being its own AE/ Constructor, is responsible for final design and

layout of plant; plant systems; purchasing of balance of plant equip-

ment; site receiving, storage issue installation and associated QA/QC

activitie;.

NSS

supplied equipment is received on site, stored and

installed by DPC Construction Department.

The only contractor on site that has responsibility for installation

and checkout of safety-related instrumentation is for HVAC, Bahnsen

Service Co. (Bahnsen) contractor. Bahnsen has subcontracted to MCC

Powers (Powers) the instrumentation and control portion of the

contract. Powers does application engineering only.

Contractor work packages for system installation, which include

description of work, applicable drawing, equipment to be purchased,

etc. are submitted to DPC Design Engineering Department for review and

approval prior to start of work or purchase of equipment.

DPC has

reviewed and accepted Bahnson's QA/QC program.

Bahnsen has reviewed

and accepted Powers QA/QC program. DPC performs vendor audits and site

surveillance checks on Bahnsen and Powers activities.

b.

Documents Examined

(1) Catawba Oraanizational Chart

(2) Equipment location drawing CN-1499.01.11

(3) Equipment location drawing CN-1499.01.10

(4) Instrumentatici Surveillance Checklist, dated 1/28/81

(5) DPC Specification No. CNS-1210.04-00-0011, June 27, 1978, Rev. 1,

December 5,1978

(6)

Instrument Standards Installation Field Practices, Drawing Nos.

ICS-A-20, 20.1, 20.2, 20.3, 20.3, 20.4, 20.5, 20.6, 20.7, 20.8,

20.9 and 20.10.

- - _

-

..

_,_-. - -__

.

.

._ -, _ _

_ .

. - _ .

. - .

'

.

.

.

,

.

14

(7) Instrument Field Installation Detailed Drawings CN-1499-KC-30,

KC29, KC24.

(8) Specification No. CNS-1354.02.00.0001,10/19/77, Multi Conductor

Control Cable

(9) Specification No. CNS-1354-03-00-0001, 11/18/77, Shield Pair

Instrument Cable

c.

Systems Installation

To verify systems installations, the inspector performed the following:

(1) Held discussions with DPC Design Engineering engineers, site

technical support personnel, warehouse receiving and inspector

personnel, site QA/QC personnel, craft personnel and craft

foremen, and Bahnsen and MCC Powers Contractor personnel.

(2) ..eviewed the documents identified in paragraph 9.b above.

'

(3) Examined the field installation of the following instruments to

verify that installation is in accordance with the plans and

specifications:

1KCFT 5990

--

IKCFS 5990

--

IKCFS 5950

--

IKCFT 5950

--

IKCFS 6060

--

IFCFT 6060

--

IKCFS 5963

--

IKCFT 5960

--

1KCPG 5660

--

--

1RNPT 5020

2KCFE 6520

--

l

(4) Verified thnt selected drawings and variation notices were current

and at the proper locations.

(5) Witnessed QC personnel performing acceptance inspections.

(6) Witnessed QA personnel performing Surveillance Checklists on QC

personnel performing acceptance inspections.

l

d.

Findings

!

!

The inspector concluded the following:

(1) There appears to be good interface between Design Engineering and

site Instrument Technical Support personnel.

I

.

.

.

'

,

,

.

15

'

(P.j Site Instrument Technical Support personnel are providing the

needed guidance to the crafts,QA and QC.

-

(3)

Electrical / Instrumentation QC personnel are knowledgeable of QA

program and engineering document requirements.

(4) Craft foremen and craft personnel interviewed were knowledgeable

of engineering and QA requirements.

,

(5) The inspector could detect no cases where hostilities or

harrassment existed between craft, QC, technical support and

Design Engineering personnel.

(6)

Instrumentation and control equipment that was being received,

inspected, stored, installed and inspected for installation was

being handled in accordance with program requirements.

No violations or deviations were identified.

10.

Safety-Related Pipe support and Restraint Systems (Unit 1)

a.

Program

The applicable code for safety-related support and. restraint

installations is the ASME B&PV Code, 1974 Edition with Summer 1975

Addenda.

The inspectors reviewed selected procedures; interviewed technical,

quality control and craft supervisors; observed work activities; and

inspected installed supports and restraints to determine if the

,

licensee's program was adequate to ensure that installed supports and

restraints met the design requirements imposed by the applicable code.

Procedures reviewed included the following:

(1) CP-115 Installation of Concrete Expansion Anchors

!

(2) CP-385 Support / Restraint Erection Tolerances

(3) CP-432 Welding of Hangers, Supports and Seismic Controls

b.

Personnel

1

!

The supervisors were interviewed to determine the working relationship

l

between tne various groups involved with fabrication and installation

,

of the supports and restraints.

It was noted that the technical and

!

craft organizations have personnel assigned to specific areas of

support and restraint work (i.e., Reactor Building, Auxiliary Building

and Turbine Building) and that the tec.:nical people in a specific area

'

work closely with the craft personnel assigned to the same area.

l

-

-

.

-.

__ .

. .

-

--

..

,. .

_

.

..

.

.

.

.

16

4

The licensee's hanger group also includes a design liaison team

assigneJ to the site for the purpose of solving minor problems with

hanger and support installation and also to perform verification

inspections when a problem is of the type that requires reanalysis of

the support systems.

This design group appears to have established a good working relation-

ship with the construction technical and craft personnel and the design

response to problems is obviously facilitated by the problems being

'

.

translated into design terminology at the site level.

!

L

The inspectors noted that there appeared to be an obvious cooperative

attitude in the interaction between the construction technical, craft

and design liaison personnel.

'

!

l

c.

Work Observation

Work observed included the following activities:

(1) Observation of a pre-check team (one technical representative and

one _ craft representative) sighting locations of proposed hangers

and supports to see if they could be installed as designed.

The pre-check included verification by actual measurement and

establishing the location site with appropriate markings to

provide guidance to the installation crew. The completion of the

pre-check exercise was either a release for fabrication or a

design deviation or change request initiated by the technical

member of the team.

'

(2) Observation of support and restraint fabrication welding and

l

inspection activities in the Auxiliary Building.

(3) Observation of support and restraint installation activities in

the Auxiliary and Reactor Buildings.

DJr_ing the observation of work activities, the inspector

questioned the personnel involved to determine their knowledge of

job requirements. The personnel contacted during this inspection

appeared to be well trained in that welders, fitters, and QC

inspectors all seemed to understand the welding symbols used on

the design drawings, and installation mechanics all seemed to be

aware that if the drawing being worked did not provide tolerances

that CP-385 would provide the necessary information.

The installed supports and restraint systems inspected included

the following:

1AN1-4136

--

1RN1-1486

--

i

b-

, .

.- -

, - - - _

-

- , , - ,

- - . , - - . . - . - - - . . - . . - . . . - . - . - - - - . . . - - . - , - -

'

-

.

.

.

17

.

1RN1-1487

--

1RN1-1399

--

1RKC- 392

--

The inspector also examined the following mechanical type snubbers

which were a part of restraints being assembled in the Auxiliary

Building:

1RN1-1350

1500# Snubber

--

1RNV-1472

1500# Snubber

--

1RCF-1529

6000# Snubber

--

1RNV-1741

650# Snubber

--

--

1RNV-1738

1500# Snubber

1RCA- 079

1500# Snubber

--

1ANV-3249

1500# Snubber

--

1ANV-3286

650# Snubber

--

These snubbers were inspected for evidence of damage or mis-

handling.

The result of this inspection was that the inspector gained the

impression that licensee management is endeavoring to establish a

team environment in the area of hanger fabrication and

installation.

There were no violations or deviations in this srea of the

inspection.

11. Mechanical Equipment

a.

Scope

This portion of the inspection concerned on site design work and

installation relative to mechanical equipment. The inspector examined

completed work and work in progress relative to heat exchangers, tanks

and fuel racks.

!

b.

Organization

The mechanical equipment for the nuclear steam supply system (NSSS)

procured from Westinghouse Electric Corporation (Westinghouse) is

installed under the supervision of the mechanical construction

engineers. Mechanical equipment for the balance of plant is installed

under sapervision of the civil engineers.

The only documentation of

the civil engineers' evaluations is QA/QC documentation of acceptance

or rejection of work. Power house mechanics (millwrights) perform the

work of installation of all safety-related mechanical equipment.

QC engineers and technicians inspect work performance while QA

engineers and technicians perform surveillance of QC and craft work and

.

documentation of the work.

'

!

.

,

.

, . , . , - - , - -

, . , - - - -

,

.

-

, . . . -

,,

.

-

-

.

-

.

18

The inspector held discussions with personnel from each of the groups

listed above. All of those contacted demonstrated sufficient knowledge

of their assignments, the interface with the other groups and of the

QA/QC requirements to perform the work satisfactorily,

c.

Design Functions

The applicable specifications and drawings are prepared by the

corporate design engineering department and are readily Tvailable on

site as controlled documents.

Variation Notices (VN's) are processed for design changes deemed

necessary by on site construction engineers and on site design, and

result in revisions to design drawings. Minor changes may be worked

out by telephone between the two design groups but these are followed

up by drawing changes from corporate. The design groups meet regularly

either in the field or in corporate, usually weekly, to assure proper

understanding of problems.

d.

Document Review

The inspector reviewed the following VN's as representative of work in

progress and work completed: 1844, 1882, 6045, 7622, 7970, 8468, 10287,

12243, and 12992.

VN's are controlled by the requirements of QA

procedure R-3, Design Drawing and Specification Variation, documented

on Form R-3A and the status of VN's is logged on Form R-3B.

The inspector found that the task for each organization on site is

clearly planned, implemented and documented.

Complete work packages

were prepared for each task by the engineering section.

Prior to and during the inspection the inspector reviewed the PSAR and

QA procedures relative to mechanical design engineering and construc-

tion.

No violations were found in this area.

e.

Safety-Related Components - Observation of Work and Work Areas

(1) Upper and Lower Lateral Restraints, Steam Generators and

Pressurizers, Units 1 and 2.

The inspector reviewed specifi-

cations for the support framing of the pressurizer, steam

generators and reactor coolant pumps, CNS-114.05-3, and upper

lateral restraints of the steam generators, CNS-1144.05-00-0012.

He also reviewed drawings CN1070-11, CN1070-14 and CN1070-30 and

related details and construction procedures CP399 and 475. The

inspector also reviewed QA procedures L-80, M-4, 9,15,18,19, 21

and 51; QA procedures Q1 and R3; the QA surveillance checklist for

mechanical equipment installation and alignment, MWN-2; and the

monthly QA surveillance reports for inspection of installation of

mechanical equipment for June 1980 through January 1981.

-

- - - -

-

,

--

-

-

-

..

-

.

-

.

-

.

.

,

,

.

19

.

Discussions with construction engineers and craft foremen revealed

a reasonable knowledge of the above documents and related work.

The lower laterals are installed for the Units 1 & 2 steam

!

generators (SG). Upper laterals for Unit 1 SG's are about 25

t

percent complete. No field work has begun on upper laterals for

Unit 2 SG's. Upper and lower supports are installed for the Unit

1 pressurizer. The Unit 2 pressurizer lower supports erection is

about 75% complete; the upper supports are on site, but no field

work has been initiated.

- The inspector examined the completed work. No field erection was

in progress.

- (2) Pressurizer Relief Tanks - Units 1 and 2

Pressurizer relief tanks for Units 1 and 2 were inspected for

proper installation. The inspector reviewed drawings CNM1201.-

4-100, CP360A and QA procedure for reference.

The tanks. are

stored in place. The sliding supports for each tank are set on

embeds with two inch bolts. The elongated bolt holes in the base

of the sliding supports are designed to be 2.75 inches

long to

allow for thermal expansion of the tank and movement of the

,

sliding supports. Embeds for the sliding supports are not grouted;

the work is not complete.

Inspection of the elongated bolt holes is limited by washers and

nuts. By reaching under the sliding support plates, the inspector

was able to determine that the support plates apparently are

improperly positioned relative to the embed bolts. There was

clearance for about

inch of expansion on the Unit 1 tank and

inch on the Unit 2 tank; whereas, the design provides 3/4 inch.

Neither the equipment specification nor the installation procedure

,

(

provide acceptance criteria for this dimension.

Acceptance

criteria are related only to tank nozzles and piping.

i

Failure to provide acceptance criteria is contrary to Criterion V

of Appendix B as implemented by Duke Topical Report paragraph

!

17.1.5.2.

This is a violation identified as 413/414/81-02-03,

Inadequate Procedure.

i

(3) Containment Spray Heat Exchangers Supports - Units 1 and 2

Supports for the. containment spray heat exchangers are being

fabricated by welding I beams and cross braces in the site metal

fab shop and are being installed according to CP360A.

Approximately 4 of the required thickness of eaph weld

(approximately 200 welds per support) is being applied in the fab

shop. The supports are then transported to the Auxiliary Building

and are completed in place with the weight of the heat exchangers

on them.

-

i

i

,m,.--

-,4- - - ,e---

. . - ~- ,

.w

y%

.--.-,..---,---v_.

w..-

--.-..-#,,,,

,.mm,w,.w,w,-ww-.-..,,

,.-.,-,,,-,.,--,,,,,-,.r...m.m,,,,,..m.-

, , - . - - , . -

-

'

.

.

.

,

.

.

20

,

Welds are not completed in the fab shop and existing procedures,

drawings and instructions fail to define the status of work

completed in the fab shop. Thus, in the field, the supports must

be examined according to drawings and each of the

inch welds

increased to 3/8 to h inch.

Also, the welds are completed with

the weight of the heat exchangers on them; whereas, design intent

apparently was to ha.ve them welded in the shop without this load.

Failure to define the status of work completed prior to releasing

the equipment to another area is contrary to Criterion V of

Appendix B, as implemented by Duke Topical Report paragraph

17.1.5.2.

This is considered to be another example of the

violation identified as 413/414/81-02-03, Inadequate Procedures.

(4) Spent Fuel Racks - Units 1 and 2

The inspector reviewed the following drawings related to the spent

fuel racks:

CN1210-5, CN1210-13, CN1210-14, CN1210-20 and

Westinghouse drawing 875-7051, sheet 20. He also reviewed draft

procedure CP384 for the drag load test of fuel storage and fuel

handling equipment, and Westinghouse fuel assembly interface

specification, F-8, relative to new and spent fuel racks.

The inspector examined welding related work and inspected spent

fuel racks in the spent fuel pools for alignment and configura-

tion. Discussions with engineers, welders and inspectors revealed

that they were adequately knowledgeable of requirements and their

duties.

Except as noted in paragraphs 11.e(2),(3) above, no violations were

identified.

12.

Nonconforming Item Report Evaluation

a.

Scope

The licensee's handling of the broken circuit breaker contact problem

l

(discussed in paragraph 8.c.) as a series of isolated nonconformances,

without any apparent consideration of generic implications raised

i

l

questions about the =aconformance review and evaluation process at the

site.

The inspectors reviewed the licensee's procedure for reporting and

evaluating nonconforming items.

This procedure, QAP Procedure Q-1,

,

l

Control of Nonconforming Items, provides step-by-step instructions for

j

the initiation and processing of nonconforming items on NCI Report Form

Q-1A.

j

The inspectors next conducted a two part review of NCI Reports.

The

!

first part involved the review of r ecently initiated NCI's (those

listed in the past 3 to 4 months) to see if any trends or generic type

!

-

-,

. .

-.-- -

-.

- _ - - - _ - - - . _ _ - . - - _ - - _ , - -

, - . . .

..

.

.

-

.

.

21

of nonconformances could be identified.

The second part involved a

review of completed NCI Reports in the QA records vault to determine if

corrective actions and documentation appeared to be appropriate for the

nonconformances described.

b.

Active NCI's

The first nart of the review started with a review of the NCI Log Book,

followed by a review of the record copy of the NCI Reports for those

that were still being worked.

The inspectors immediately noted the

apparently large volume of NCI's being generated at the site - (The Log

indicated that NCI Number 9000 had been issued in July 1980 and number

10900 was issued during early February 1981 - This is nearly 300 NCI

Reports per month).

The subjects covered by these NCI's ranged from

relatively minor documentation problems through major problems with

safety-related hardware. This large volume of all types of problems

being handled in the same manner was pointed out to licensee management

as a possible contributor to the reason why generic items and/or trends

were apparently going unnoticed.

During the review of the active NCI's, the inspectors noted one NCI

(Number 10479 which described a linear indication the full length of

the outside surface of a piece of stainless steel pipe) on which the

originator had added a note to the effect that this was the same heat

of material as was reported on NCI 10311. The inspector found that NCI

10311 had been closed after the corrective action "These sections of

pipe shall be replaced and discarded" was accomplished, but that when

the pipe; identified in NCI 10479 was inspected in the pipe fabrication

shop, two other piping assemblies with the same problem were noted.

These assemplies had also been nonconformed (NCI's 10637 and 10638)

with the NCI containing a note to the effect that this was the same

heat of material as reported on NCI 10311 and 10479.

The only acknowledgement of generic implications was that NCI's 10311

and 10479 were assigned to construct'on for evaluation while 10637 and

10638 had been assigned to design.

The inspector's evaluation of the incications reported by these NCI's

was that they were a lack of fusion indication caused by improper

welding of this seamed stainless steel pipe.

NCI's 10637 and 10638

were initiated on January 3,

1981, and forwarded ta design for

evaluation on January 13, 1981.

At the time of the exit interview for this inspection on February 6,

1981, an evaluation from design had not been received and there had

been no hold put on the remaining material of the same heat which

remained in stock in the licensee's pipe storage area.

.

The handling of these NCI's was cited as one example of violation No.

414/81-02-04, Apparent Generic Items cr Trends Not Recognized nor

Forwarded to Management.

t

.

. .

.-

..

--

- - - -- ,

.-.

-

_ - . . .-

. . - . -

.

.

,

,

22

During this review of NCI's, the inspectors noted a number of NCI's

which reported that-the inside surface or roct face of a weld or welds

did not meet ASME B&PV Code acceptance criteria even though the weld

had already been accepted by QC. These %'I's included one (NCI 9902)

which reported unacceptable root condition on a weld joint which the

weld history records showed had been repaired as the correction to NCI

9295, which reported unacceptable root condition on a previously

accepted weld.

Another significant NCI was number 10786 listing a number of welds,

accessible for internal visual inspection, which did not meet

acceptance criteria even though the welds had been accepted by QC

visual inspection.

This NCI also referenced the Authorized Nuclear

Inspectors Report of January 30, 1981, which listed other welds with

the same unacceptable root conditions.

All of the NCI's which reported these weld ID surface problems had

three things in common: Disposition was to repair as necessary; Report

to management was checked "N0"; and not one of the NCI's reviewed by

the inspectors questioned how the inspection of the root surface was

missed originally and what action would prevent recurrence.

This situation was particularly surprising for NCI No.10786 which was

. initiated by the QA group because of the apparent significance of the

problem, but when construction decided not to report to management, QA

approved this decision.

This problem with the apparent inadt:quate visual inspection of the

internal surfaces of piping welds was cited as another example of

Apparent Generic Items or Trends Not Recognized nor Forwarded to

- Management (Violation No. 413/81-02-02)

l

c.

Completed f;CI's

l

i

During the second part of the NCI review, the inspector selected NCI's

numbered 9900 through 10000 which had been completed and filed in the

l

QA record vault.

During this review, the following i!CI's were

identified as problems to the licensee's QA personnel

,

l

l

NCI 9926 reported that a wear collar ring for a penetration was

5/16-inch thick and the plan required a thickness of 0.5312 to

.

0.5938-inch.

The NCI was dispositioned by the same person that

l

originated it with the statement that the material was right and the

plan was right.

l

Discussion with the originator showed that the plan required dimensions

were obtained by subtracting diameters and should have been divided by

two to find the actual requirement, therefore, there was no need for

the NCI.

<

~

.

.

.

23

~

NCI 9933 reported that a piping flow section did not meet smoothness

requirements. This NCI had been dispositioned on November 17, 1980, as

unacceptable, requiring refabrication. This disposition had been lined

out on December 17, 1980, and a new disposition " Acceptable as is"

added.

This change in disposition was done without any recorded

justification.

These two NCI's were cited as examples of violation No. 413/81-02-04,

Incomplete QA Documentation.

In this same group of NCI's, NCI 9959 was written concerning the fact

that an 8" class A weld (Weld No. INI-32-1) was welded with excessive

weld weave. The disposition required removal of improperly welded

material and reinstruction of the welder (s).

The inspector noted that the disposition did not require verification

of metal removal nor did it specify how much to remove. The question

of what other welds had been done by the welder (s) was not sked. A

review of the weld history record for this weld shows that the NCI

number was written on the weld joint record but there is no record of

any metal removal.

NCI 9984 was also noteworthy: it reported that an RHR pump unit had

apparently been fabricated improperly because when the seal water

flanges were unbolted, the piping moved out of alignment indicating

that when the unit was fabricated by Ingersoll-Rand for Westinghouse,

the piping was assembled with residual stresses caused by cold spring.

The documentation for this case showed that the corrective action was

to bend the piping to the proper configuration under the guidance of

'

' the Westinghouse site representative.

The NCI documentation did not

report how much movement was involved nor was there any provision for

control and documentation of the bending operation. As a result, there

was no evaluation to determine what effect, if any, the uncorrected

cold spring could have had on safe plant operation.

These two NCI's were considered to be additional examples of the

licensee's apparent lack of comprehensive evaluation of potentially

serious nonconformance situations. These will be considered a part of

Violation 413/81-02-02, Apparent Generic Items or Trends Not Recognized

'

nor Forwarded to Management.

13.

Reporting of Deficiencies, Defects and Noncompliances (10 CFR 50.55(e) and

10 CFR Part 21)

a.

General

The purpose of this inspection was to ascertain whether DPC, and

appropriate

responsible

officers,

established

and

implemented

procedures and other instructions as required to ensure compliance with

10 CFR Part 21, and 10 CFR 50.55(e) requirements relative to the

__

___

_

___ _ _ _

_ _ _ _ _ -

_ _ _ _ _ . _ . _

. _ _ _ _ _ _ _ _

_

_.

-=

.

~

.

.

.

,

.

24

evaluation and reporting of deficiencies, defects and noncompliances.

Inspector determinations are based on the requirements of 10 CFR Part 21 as c'.assified by staff positions in NUREG-302, Revision 1 and

additional IE guidance relative to 10 CFR 50.55(e).

b.

Documents Examined

(1) Procedure Q4-121, Rev. 2, June 1980, Nuclear Regulatory Commission

~

Reporting Requirements

(2) Procedure PR-202, Rev. O, November 1980, Design Nonconformance

(3) Procedure PR-220, Rev. 7, August 1980, Nonconforming Item Reports

,

(4) Procedure PR-290, Rev. 4, June 1980, Nuclear Regulatory Commission

Reporting Requirements

(5) Procedure Q-1, Rev.13, May 1980, Control of Nonconforming Items

(6) Procedure R-5, Rev. 2, June 1980, Nuclear Regulatory Commission

Reporting Requirements

c.

Program Review

The inspector reviewed the above controlling: procedures and verified

that procedures have been established to assure that the following

.

requirements of 10 CFR 21 will be met; the posting (21.6), evaluating

deviations (21.21(a)(1)), informing the director (21.21(b)), and to

assure that procurement documents specify that provisions of 10 CFR Part 21 will apply when apolicable (21.31), maintenance of records

(21.51(a)), and disposition of records (21.51(b)). The inspector also

verified that procedures have been established to assure that 10 CFR 50.55(e) identification, evaluation, and reporting requirements will be

met.

The inspector concluded that the procedures, if implemented by properly

trained personnel, could provide the necessary controls to implement

the evaluation and reporting requirements of 10 CFR 50.55(e) and 10 CFR

l

Part 21.

l

The lack of properly trained personnel is discussed below.

d.

Program Implementation

The inspector. held discussions with management, QA technical support,

QC and craft personnel relative to NRC requirements, NRC guidance, and

DPC controlling procedures for the evaluation and reporting of

deficiencies, defects and nonconformances.

The inspector concluded

that the personnel did not have sufficient knowledge and understanding

of NRC evaluation and reporting reqirements.and NRC guidance.

.. - - -.

--

. .

. - - . -.

- .

-

- - , - . . . _ - - - . . - - . - . - ,

,. . . .

.

.

.

,

.

!

25

Therefnre, the procedures were not being properly implemented. This

lack of knowledge and understanding of the requirements is evidenced by

the following:

(1) Personnel do not understand when a basic component is considered

to be deli /ered.

(2) Personnel do not understand when Duke becomes the responsible

evaluating agent.

(3) Personnel do not know how responsible individuals are informed of

possibly reportable matters when the concerned individual is not

assigned as the evaluator.

f

(4) Review of site training records and discussions with site

personnel reflect that training sessions, 10 CFR 50.55(e)

given

by site QA to site QA on 10/22/79, and 10 CFR 50.55(e) and Part 21

- given by DPC management to site QA and Construction on 11/27/79,

consisted of presentations of only the direct words of regulations

with no reference to NUREG 0302. There was no handout guidance.

No 4dditional training was in evidence at the site even though a

complete revision of procedures, as noted in paragraph "b"

above

was completed in mid 1980.

It was evident that evaluating personnel were not questioning, if

a basic componenet was involved; where the component was used, if

the component performed a safety-related function, what were the

consequences, and if the items were generic.

10 CFR 50, Appendix B, Criterion II requires that the program

shall provide for training of personnel performing activities

affecting quality as necessary to a:sure that suitable proficiency

is achieved and maintained.

The lack of adequate ~ training

relative to NRC evaluation and reporting requirements for

deficiencies, defects and nonconformances is idcntified as a

violation (413/81-02-05 and 414/81-02-05).

,

- , - - , - .

-r

v

.,-, , ,-.

.---y.m,

, , , , .- - - . . . . - . . - , - - , , . _ . - , - . . - ,

. - - - . _ ~ . .

.,,,.--..,-,--.,_.....,--v.-,_..-.--.--,-...,--,-,r-

..,,,,,