ML19347E434
| ML19347E434 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 04/22/1981 |
| From: | Utley E CAROLINA POWER & LIGHT CO. |
| To: | Eisenhut D Office of Nuclear Reactor Regulation |
| References | |
| RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.16, TASK-2.K.3.18, TASK-TM NO-81-714, NUDOCS 8104270372 | |
| Download: ML19347E434 (126) | |
Text
.
g @ l t-k
.[0 L
3 APR 2 4199g /-.c April 22, 1981 i g. v.s.
h
- W File: NG-3514(B)
Serial No.: NO-81-714 Mr. Darrell G. Eisenhut, Director Office of Nuclear Reactor Regulation Division of Licensing United States Nuclear Regulatory Commission Washington, D. C.
20555 BRUNSWICK STEAM ELECTRIC PLANT UNIT NOS. 1 AND 2 DOCKET Nos. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 FEASIBILITY STUDIES FOR NUREG-0737 ITEMS II.K.3.16 AND II.K.3.18
Dear Mr. Eisenhut:
As required by NUREG-0737, " Clarification of TMI Action Plan Requirements," Carolina Power & Light Company (CP&L) hereby submits feasibility studies on Item II.K.3.16, " Reduction of Challenges and Failures of Relief Valves," and Item II.K.3.18, " Modification of Automatic Depres-surization System Logic," for the Brunswick Steam Electric Plant, Unit Nos. 1 and 2.
These studies were performed by the BWR Owner's Group for participating utilities. CP&L has reviewed these reports and has the following positions on each item.
Item II.K.3.16 - CP&L needs more time to evaluate the relative benef t:s of the candidate modifications out-lined in the sti.dy.
CP&L, therefore, cannot presently commit to any of these modifications. However, CP&L is currently proceeding with replacement of the three stage Target Rock Safety / Relief Valves (S/RVs) with two stage Target Rock S/RVs. This replacement effort was planned prior to this study. CP&L will notify the NRC of its final position on this issue after the evaluation is complete.
8104fs0 M &
P
)'chr Sij 1
O Item II.K.3.18 - CP&L finds that no significant benefits can be gained by modifying the current Automatic Depressurization System (ADS) logic to cover automatic ADS for events which do not result in steam release to the drywell.
It is CP&L's position that the improvement in the emergency procedures gained by incorporating the guidance of the BWR Owner's C.oup Emergency Procedure Guidelines will provide adequate guidance for handling such transients. Therefore, CP&L plans no modifications in this area.
If you have any questions on this subject or would like to discuss these reports in detail, please contact our staff.
Yours very truly, Y L; E. E. Utley Executive Vice President Power Supply and Engineering & Construction 4
JHE/je (5509)
Attachments t
g-
-n-,
,,n,--
.a, n.---,-
7~..
X At h
l BWR OWNERS GROUP EVALUATION OF NUREG-0737 ITEM II.K.3.16 REDUCTION OF CHALLENGES AND FAILURES OF RELIEF VALVES 1
d I
a e
e
_ _ _,, _ _ ~,_,
--,---=r
=
r-m---
m
-- * - v r--
TABLE OF CONTENTS Section Page ABSTRACT..........................
i 1.
Introduction........................
1 2.
BWR Response to a Transient with a Stuck Open Relief Valve.
4 3.
Candidate Modifications Evaluated for Reducing SORV Event Frequency..........................
6 4.
Methodology 23 l
5.
Results 27 6.
Conclusion.........................
31 33 Appendix A - Participating Utilities 0
,g--=
=
w g-,,.w-e-.
y
-w-w
,_,,,sw
_, - + ---, _,.
p,
.gr
,y-g
-,,y.m---,
.w--
y, A
ww,-,--
3 m--
c
ABSTRACT This report documents a study performed in response to NUREG-0737 item II.K.3.16 which requires an evaluation of the feasibility and contrain-dications of reducing ' challenges to the relief valves by various methods in BWRs by April 1, 1981. The report reviews potential methods of reducing the likelihood of stuck open relief valve (SORV) events in BWRs and estimates the reduction in such events that can be achieved by implementing these methods. The reduction was estimated by computing the reduction in Safety Relief Valve (SRV) actuations achievable by various design and operating modifications and by estimating the relative probability of various types of SRVs to stick open. Using the BWR/4 plant as a measure of operating experience, it was concluded that BWR/2, BWR/3 with isolation condenser, BWR/5 and BWR/6 plants already include design features which yield a significant reduction in the occurrence of SORV events. The remaining plants can reduce the 50RV event frequency by methods evaluated herein. The report applies to the plants listed in Appendix A.
i 1
l 1
1.
INTRODUCTION This report documents a study performed in response to NUREG-0737 item II.K.3.16 which requires an evaluation of the feasibility and contrain-dictations of reducing challenges to the relief valves by various methods in BWRs by April 1, 1981. The report reviews potential methods of reducing the likelihood of stuck open relief valve (SORV) events in BWRs and estimates the reduction in such events that can be achieved by implementing these methods.
Reducing the likelihood of S/RV challenges will directly reduce the likelihood of a 50RV.
In addition, attention is also given to modifica-tions which could reduce spurious SRV blowdowns and to modifications which could reduce the probability of SRVs to stick open when challenged.
The report applies to the plants listed in Appendix A.
1.1 NRC Reouirement NUREG-0737 item II.K.3.16 requires that a feasibility study be performed to identify modifications to reduce S/RV challenges. The NUREG-0737 position states, "An investigation of the feasibility and contraindica-tions of reducing the challenges to the relief valves...should be conducted.
Those changes which are shown to reduce relief-valve challenges without compromising the performance of the relief valves or other systems should be implemented.
Challenges to the relief valves should be reduced substantially (by an order of magnitude)."
1.2 Objective,StandardandGoal Although the NUREG-0737 position deals primarily with reduction of challenges to S/RVs, its clear intent is to reduce the incidence of 50RV events.
Reducing challenges is only one of three approaches to reducing SORV events. The others are reducing the causes of spurious blowdowns and reducing the probability of S/RVs to stick open when challenged.
All three of these approaches present feasible and effective opportunities for reducing the incidence of uncontrolled blowdowns via S/RVs. Further, 1
as discussed in the study, the feasible approaches to reducing S/RV challenges do not by themselves accomplish the desired " order of magni-tude" (factor of ten) reduction in SORV events. Consideration of the other two approaches, however, shows a factor of ten reduction in the incidence of SORVs to be feasible.
Such a reduction is the objective of this study.
The NUREG-0737 position does not state a standard by which the desired factor of ten reduction should be judged. Using the number of S/RV years in plant operation as a criterion, it can be concluded from Table 1.1 that operating BWR/4 units provide the most representative basis for such judgements. The methods employed in this study make it desirable to take a single BWR product line as a benchmark, due to the differences in transient response, valve types, and other reactor systems (e.g.,
isolation condensers) among the product lines. Thus, the 50RV experienca of currently operating BWR/4s without the design improvements described in this study was selected as the criterion by which all plants are to be judged.
Considering all of the above, the goal of this study is to identify l
feasible modifications to BWR design and operation which reduce the frequency of uncontrolled S/RV blowdow 4 for each product line to a factor of ten below the. frequency experienced in BWR/4 units.
l M
2
i TABLE 1.1 S/RV OPERATING EXPERIENCE **
i SRV-Years of Operation" Product Line End of 1977 End of 1980 BWR/1 N/A N/A BWR/2 93 126 BWR/3 260 361 BWR/4 342 715 BWR/5 None None BWR/6 None None i
- Number of power-operated relief or safety / relief valves per plant, times number of years of operation of plant, totalled for all plants I
in product line through end of year.
- Includes US' experience only.
N/A - Not applicable since these plants were not considered in the study.
6 0
~
3
2.
BWR RESPONSE TO A TRANSIENT WITH A STUCK OPEN RELIEF VALVE The Boiling Water Reactor design assures that core integrity will be maintained following a stuck open relief valve (50RV) transient. The response of a typical BWR to a 50RV transient is discussed in this section in order to provide a perspective on typical sequences of events which lead to and follow SORV e/ents and the consequence of various manual or automatic actions.
The safety / relief valves (S/RVs) of a BWR are designed to protect the reactor coolant pressure boundary from overpressurization. Transients resulting in pressurization frequently raise the reactor vessel pressure to the S/RV setpoint causing the S/RVs to open so that safety limits are not reached.
If any relief valve fails to close after the pressure peaks and decreases, further steam release will deplete the water inventory in the reactor vessel and challenge the numerous water delivery systems which assure adequate core cooling.
In a few instances, S/RVs have spuriously opened.
Either event is termed a " Stuck Open Relief Valve (50RV)" event.
For any anticipated transient, if a 50RV is the only additional failure, the vessel inventory lost through the 50RV can be easily made up by l
various high pressure and/or low pressure water delivery systems.' The consequences of a 50RV are not a safety concern and reactor shutdown is uncomplicated, as proven by numerous field occurrences.
Following transients which result in loss of feedwater flow, a 50RV could challenge the emergency core cooling systems. There are several such transients which result in the loss of the feedwater system, e.g.,
l
" loss of feecwater ficw," "Icss of AC power," "HS!V Closure" or "Feedwater controller failure - naximura demand." The loss of feedwater flow event is a typi:ai trd bouncieg transient f om the core cooling viewpoint.
The 3WR response to tnis transient with a SCRV and with more severe degradations is discussed in detail in NE00-21708, Sections 3.1, 3.2 and 3.5 (Refs. 1-4).
These evaluations demonstrate that adequate core l
cooling is assured in the BWR following an 50RV event.
l 4
It is concluded that adequate core cooling is maintained in a BWR following an 50RV event even under degraded conditions.
It follows, then, that reduction of the frequency of SORV events is not of great concern from the standpoint of assuring adequate core cooling.
I e
h 5
~ - -...
3.
CANDIDATE MODIFICATIONS FOR REDUCING SORV EVENT FREQUENCY Three different approaches can be taken to reduce the frequency of 50RV events:
1.
Reduction of challenges to the S/RVs; 1
2.
Reduction of the probability of the S/RVs to stick open when challenged; 3.
Reduction of spurious : lowdown of S/RVs.
Each of these approaches leads to the identification of feasible and effective opportunities for reducing the incidence of uncontrolled blowdowns via S/RVs.
Based on the recommendations in NUREG-0737 and on the judgment and experience of GE and utility personnel, a number of candidate modifications have been selected for consideration in this study. A description of these candidate modifications is provided in this section. The benefit associated with the implementation of each candidate modification, as estimated in this study, is also presented.
Other candidate modifications may exist which are not addressed in this study.
The effectiveness of many of the candidate modifications will vary amongst the BWR product lines, due to design variations. Thus, a range of potential benefits are presented.
For instance, lower water level isolation is expected to result in a 24-36% reduction in S/RV challenges.
The 24% reduction is applicable for BWR/5 plants and 36% for BWR/3 plants without Isolation Condenser. Further, the values cited are maximum achievable benefits evaluated baseo on tne assumption that the canaidate modification will ccmcletely eliminate all of the chal' mges as3cc#atec with the modification.
3.1 Cancidate Modificatiens Which Reduce S/RV Challenges Most of the candidate modifications to reduce S/RV challenges reduce the frequency of transient events which cause S/RVs to open. The remaining 6
candidates reduce the number of relief valves which open during a given transient event.
3.1.1 Main Steam Line Isolation Two candidate modifications will reduce the frequency of main steam line isolation during transients. One involves lowering the water level isolation setpoint; and the other, lowering the pressure isolation setpoint.
3.1.1.1 Lower Water Level Isolation Setpoint Definition - Lower the RPV water level isolation setpoint for MSIV closure from level 2 to Level 1.
Discussion - This candidate modification would reduce the number of times the reactor is isolated from the main condenser. This results in reduced S/RV challenges by eliminating isolation cycling of the S/RV's resulting from transients such as feedwater controller failure, trip of bo+5 recirculation pumps, and loss of feedwater flow. This modification is expected to result in a reduction of 24 to 36% in S/RV challenges for plants without isolation condensers.
This modification is feasible for BWR/4-5. plants which do not already include the feature.
It is not feasible for BWR/2-3 because of the need for additional reactor water level instrumentation.'
)
3.1.1.2 Lower Reactor Pressure Isolation Setpoint Definition - If the reactor 's in the "run" mode and the main steam line pressure drops below 825 psig, the reactor is isolated in order to prevant a rapid cooldown resulting from a pressure control malfunction.
This a ndidate modification would reduce the pressure at which the reactor i: isolated under these conditions. The extent of reduction in pressure setpoint has not been established but is expected to be in the neighborhcod of 50 psig.
7
Discussion - Prior to 1975, the main steam line isolation was initiated at 850 to 880 psig depending upon the product line. Operating experience at that time showed that this setpoint was too close to the normal operating pressure. As a result, the noise level of the pressure switch hydraulic sensing line or small pressure transients in the main steam lines could initiate reactor isolation. After a careful review, General Electric determined that the isolation setpoint could be safely lowered to 825 psig. This setpoint provides adequate protection against spurious isolation events. A review of recent operating plant experience shows that the additional reduction in S/RV challenges resulting from further reduction in isolation setpoint would be less than 1%.
3.1.2 Feedwater Control System Modifications A number of candidate modifications improve the feedwater control system as a means to reduce S/RV challenges by reducing the number of main steam line isolation events.
Feedwater control system failures have contributed to about 0.7 isolation events per plant year. The thrust of the modifications is to control water level between the high water level trip and the ECCS initiction/MSIV isolation trip setting for various transients.
Water level is controlled in a BWR by a Feedwater Control System that i
utilizes a single primary channel for control. The control system utilizes a w er level sensor input (the primary alement) and the dif-l ference between two secondary elements, namely feedwater flow and steam flow. Water level must be under positive control by the Feedwater Control Systen curing plant cperation, because feedwater flow must responc to charges in steam flow while maintaining the water level in the vessal.
Therefore, when a compecent in the centrol system or in tne power stoply to the control systen fails, the satar level in the reactor vessel can crift out of limits, ultimate'y causing tne reactor to scram.
Such a water level excursion is usually so rapid that the reactor cperator is unable to respond in time to prevent a scram from an l
i 8
abnormal water level condition.
Frequently these scrams are followed by reactor isolation with consequent vessel pressurization causing the S/RV's to open.
3.1.2.1 Triple Redundant or Single Failure Proof Control System Definition - A triple redundant control system is a candidate modifica-tion which could reduce isolations. Such a system would have three channels of control, with the highest and lowest values being ignored.
Thus failure of the controlling element (either upscale or downscale) would result in another channel taking control. The single failure proof control system would have two channels of control, in which the second channel acts as a backup for transfer of control when a failure of the controlling channci is detected.
Discussion - The improved control system would reduce transients resulting from failure of components in the existing single channel Feedwater Control System. By eliminating these transients, the associated reactor scrams and isolation events are also eliminated, which reduces the number of S/RV challenges. This results in a reduction of about 2 to 4%
in S/RV challenges. The small reduction in S/RV challenges alone does not justify the high cost of implementing the modification.
3.1.2.2 Uninterrupted & Redundant Control System Power Definition - Failures in Feedwater Control System power supplies have caused reactor isolations in operating plants. This candidate provides for an uninterruptible and redundant source of power such that the controller is not affected by failures in the power supply system.
Discussion - This chai.gi could eliminate S/RV challenges associated with isolation events arising out of failures in the power supply. A maximum of 0.07 isolation events per plant year can be eliminated by implementing this modification, resulting in about a 1% reduction in S/RV challenges.
1 9
l
1 3.1.2.3 Condensate System Modifications and Condensate /Feedwater Integration i
Definition - The controls of the condensate system (including the demin-t eralizers), on which the feedwater system depends for proper' operation, l
could be integrated with the Feedwater Control System so that failures l
in the condensate system wculd be detected in such a way that resctor scram and isolation could be avoided.
l This candidate modification calls for an integration of the condensate and feedwater control systems in providing input signals for: reactor operation.
Examples of the possible integration and design modifications of the condensate system are as follows:
a)
Typically, three 50% or four 33% capacity condensate pumps are provided per plant.
If one of the condensate pumps fails, the redundant pump could be automatically started, b)
If there is high differential pressure across a condensate deminer-alizer, a signal could be provided to cut back reactor power by running back recirculation flow.
c)
The Feedwater Control System could be designed to assure that a loss of a single condensate or condensate booster pump or feed pump will not result in reactor scram or isolation.
Discussion - Implementation of these candidate modifications could result in a reduction in reactor isolation events for BWR/3 plants without Isolation Condense *, SWR /4 and BWR/5 plants, and consequently,
~ relief valve cnallenges resulting from failures in the concensate anc f2eewater systems. This could result in a. eduction of 3-4% in S/RV cha:Ienges.
I 10
~
N X The implementation of this modification would increase the complexity of the feedwater and recirculation control systems, and thereby introduce
~
additional failure modes. Therefore this modification could have an adverse impact on the reliability of these systems.
3.1.2.4 Feedwater Runback Definition - Feedwater runback is a method of controlling reactor water level to avoid high vessel water level (L8) trip, following certain transients. This would prevent tripping the feedwater pumps and subsequent reactor isolation on low water level.
Discussion - The implementation of this candidate modification would result in the elimination of S/RV challenges associated with the trip of both recirculation pumps and recirculation controller failure. A reduc-tion of 6 to 12% in S/RV challenges can be expected by implementing this modification.
The implementation of this modification would increase the complexity of the feedwater control system, and thereby introduce additional failure modes. Therefore, this modification could have an adverse impact on the reliability of that system.
3.1.2.5 Additional Anticipatory Scram on Loss of Feedwater Definition - A description of this candidate modification is quoted from NUREG-0626:
"...The challenge rate could be reduced by providing anticipa-tory signals on toe feedwater pump trip similar to the scram signal derived from turbine stop valve closure on a turbine trip. This modifi-cation will reduce the reactor power quickly and thereby reduce the severity or magnitude of the pressure spike."
Discussion - A review of the Loss of Feedwater Flow (LFWF) event in NEDO-24708 shows that LFWF causes a. low water level scram approximately 7-15 seconds following initiation of the transient at full power, depending upon the product line.
LFWF results in reactor isolation for BWR/1 thru 11
- M
% amr
- MV 49
?
BWR/5, and anticipatory scram on feedwater pump trip does not prevent
~
reactor isolaticn at reactor level 2 or the associated cycling of relief valves.
LFWF does not result in reactor isolation for BWR/6 due to isolation at reactor level 1.
This candidata modification is of no benefit in reducing S/RV challenges for BWR 1-5 'if the low water level isolation modification is also carried out, since the latter modifica-tion prevents reactor isolation following the LFWF event. A possible disadvantage of implementing this candidate modification is that it denies the operator the opportunity to prevent a scram by restarting feedwater pumps.
In summary, anticipatory scram or loss of feedwater is considered to be an insignificant contributor (less than 1%) to S/RV challenge reduction for all BWR product lines.
3.1. 3 SRV Control Logic /SRV Setooint Revision The following candidate modifications are expected to reduce S/RV challenges through changes to SRV control logic or through revision of S/RV setpoints.
3.1. 3.1 Low-Low Set Relief or Equivalent Manual Actions Definition ' Some BWR plants are equipped with a ' Low-Low Set' design feature which changes the setpoints of selected SRVs following the initial opening of a number of S/RVs. This assures that following tDe initial pressurization the pressure will be relieved by the ' Low-Low Set' valve alcae, and the remaining S/RVs will not experience any subse-quent actuation. This feature could be applied to plants which do not currently include it.
However, the BWR Emergency Precedure Guidelines (Ref. 5) call for the equivalent manual action.
Discussion - The ' Low-8.0w SC' design or equivalent,?anual action will recuce the total nuder of 5/?'. challanges by limitirg the sccord and subrMuent cpening of tne S/R'. i to the Law 3.aw 5et valve.
It is astimated that a 23-62% reduction in S/RV challenges can be acnieved by impiementing,
this modification. This modification is practical for all BWR product lines.
12
3.1.3.2 Revised Relief Valve Setpoints Definition - A description of this candidate modification is quoted from NUREG-0626:
"The relief valve setpoints could be revised upward to allow mora margin to the relief valve opening setpoint. Another method to provide margin is to lower the operating pressure. A combination of the rslief valve setpoint and operating pressure will increase the plant's ability to withstand a pressure increase transient without causing the relief valve to open."
Discussion - There are two setpoints associated with safety / relief valves, namely relief setpoint and safety setpoint. The relief setpoint, which is the lower of the two setpoints, is used to provide pressure relief following an overpressure transient. The safety setpoint limits the taactor pressure to the ASME code allowable limits.
Both the relief and spring setpoint values are constrained by a number of factors.
In the case of the Target Rock valve, the factors are:
1.
The ASME Code 2.
High pressure injection system (High Pressure Coolant Injection (HPCI), High Pressure Core Spray (HPCS), Reactor Core Isolation Cooling (RCIC)) design discharge pressure.
If the spring setpoints are higher than the pump discharge pressure, high pressure coolant cannot be injected into the reactor under all design conditions.
3.
A need to offset relief valve setpoints where applicable.
This is done to prevent all valves from opening simultaneously.
4.
Tolerance on the relief valve setpoints.
Setpoint drts in 1
one direction should not result in the valve opening in the l
safety mode, nor should a drift in the opposite direction result in relief valve operation for minor overpressure transients.
13
In the case of Crosby and Dikkers valves there exists another factor which is a practical consideration of requiring the valve to reclose in a relief mode rather than the spring mode, i.e., the spring node reclosure setpoint should be always higher than the relief mode reclosure setpoint, even after allowing for setpoint drifts.
In the case of Three Stage Target Rock valves, it has been determined that the spring setpoint could be raised by about 15 to 50 psig depending upon the plant. The impact of such a modification is a reduced incidence of spurious S/RV actuations, through increased simmer margin.
Based on a review of failure data and engineering judgment, a 5% reduction in SORV events in plants with Three Stage Target Rock valves is expected through increasing the spring setpoint to the maximum value possible.
No reduction in S/RV challenges is likely because a 15-50 psi increase in setpoint is insignificant compared to the pressure rise experienced in most overpressure transients.
In the case of Crosby and Dikkers valves (BWR/5-6 plants) the setpoints are already near their maximum possible value and can be increased by no more than about 15 psig. Such an increase in the relief setpoint will not cause any significant reduction in SRV challenges.
In the case of Two Stage Target Rock valves, pilot valve leakage does not lead to spurious opening. Therefore, the conclusion for Crosby and Dikkers valves also applies for the Two Stage Target Rock valve.
l In conclusion, the plants with Three Stage Target Rock valves may be l
able to achieve a 5% reduction in spurious SRV openings through an increased saving setpoint.
None of the p' ants can achieve any signifi-cant reduc-fon in 3RV challenges through an increaseo relief setacint.
The NUSEG-077 suggestion air refers to 1owering the operating press:.re.
But as stnad above for setp in; increases, mocest cranges are insign:fi-cant comparec to the pressure rise experienced in most overpressure transients. Thus, lowering the operating pressure by a modest amount 14
would not result in any significant reduction of S/RV challenges.
In addition such a change would result in undetermined penalties in terms of plant thermal efficiency and fuel utilization.
3.1.3.3 Offset Relief Valve Setpoints Definition - A description of this candidate modification is quoted from NUREG-0626 as follows: "The valve pressure setpoint could also be modified or offset such that fewer valves are challenged."
Discussion - Offsetting relief valve setpoints does not contribute to S/RV challenge reduction during isolation cycling since only one or two valves participate in such cycling. During the initial blowdown there could be some reduction in S/RV openings for some transients.
It is noted that small but unavoidable setpoint drifts result in a de facto offsetting even when several valves are nominally set at the same value.
3.1.3.4 Increase Main Steam Line Flow Setpoint Definition - A description of this candidate modification is quoted "com NUREG-0626 as follows: "Incr'asing the high steam line flow setpoint for main steam line isolation valve (MSIV) closure (can reduce SRV challenga and failure rates)."
Discussion - The MSIVs are designed to close when a break occurs in the main steam lines. An abnormal increase in the main steam line flow is taken as an indication of a main steam line break. High steam line flow setpoints are selected in a manner as to assure a high probability of isolation on a steam line break while keeping the probability of inadver-tent closure resulting from operational transients small. A review of the BWR experience data has revealed no instance of spurious MSIV closure resulting from plant transient events.
However, a number of inadvertent isolation events have occurred during MSIV closure surveillance testing.
These occurred when a second MSIV was closed without resetting the first MSIV that was tested. The sudden increase in steam flow in the remaining lines results in reactor isolation. The maximum reduction in SRV challenges 15
that can theoretically be obtained through an increased high steam flow setpoint is about 0.5%.
However, such a reduction may not be practical since increasing the setpoints will reduce the reliability of isolation following a main steam pipe break. A more practical approach to achieve the same goal is through reduction in MSIV test frequency, discussed in 3.1.4.4.
3.1.4 Other Candidate Modification Candidate modifications pertaining to other systems are discussed in this section.
3.1.4.1 Analog Transmitter / Trip Unit System Definition - Most operating BWRs use direct acting pressure, differential pressure and water level switches as input into the reactor protection, main steamline isolation, and emergency core cooling systems. Technical specifications for this type of process sensor typically require surveil-lance testing once a month while the plant is at power.
In the past, during the monthly surveillance tests, errors have caused scrams and challenges to relief valves.
If an improved system were installed which uses an analog transmitter and bi-stable trip unit instead of the pressure switch, the number of unnecessary scrams (and associated SRV challenges) could be reduced. The transmitter-trip unit comoination can also be designed to be highly stable and easily testable. Calibration requirements for this new system are thus greatly reduced.
(
l Discussion - The use of the analog transmitter / trip unit system would reduce the number of reactor scrams resulting from procedural and physical l
errors during surveillance tests. A 2 to Es reduction in S/RV challenges could be expected due to the implementation of this candidate rodification.
l l
l l
15 l
3.1.4.2 Improved Recirculation Flow Control System Definition - Failures in the recirculation flow electronic control systems can result in reactor isolation.
If an augmented recirculation flow control system with signal deviation alarms and signal rate alarms to detect failures in the control electronics were providsd, the signi-ficance of flow changes could be reduced. The failure detection scheme in the augmented system would cause the logic signal to change from automatic flow control to a steady recirculation flow to prevent a core flow excursion and eventual scram.
Discussion - It is estimated that approximately 2% to 6% of the S/RV challenges could be eliminated with this equipment. However, the cost and increased complexity of the control system must be evaluated further before this candidate modification can be considered feasible.
3.1.4.3 Reduce Isolations Caused by Surveillance Testing Definition - This candidate calls for developing an improved method of carrying out surveillance tests without causing inadver. ant isolations.
This may involve hardware and design changes.
In addition, reduction of surveillance testing frequency could reduce the inadvertent closures.
Discussion - A maximum of 4 to 5% reduction in S/RV challenges could be l
achieved through the implementation of this candidate modification.
3.1.4.4 Reduce MSIV Testing Frequency Definition - This candidate modification is suggested in NUREG-0737. A number of isolation events occur while the MSIV closure tests are being conducted. A reduction in the MSIV test frequency would result in a reduction in number of isolation events.
l l
17 l
l
Discussion - The frequency of MSIV tests is contained in a plant's technical specifications and generally conforms to ASME Code Section XI
~
recommendaticns. The extent of frequency reduction that is possible without impacting reliability of isolation capability should be con-sidered in the detailed design of this modification. However, the maximum benefit that could be expected is about 2 to 3% reduction in S/RV challenges.
3.1.4.5 Installation of New Relief Valve With Block Valve in Series Definition - A description of this candidate modification is quoted from NUREG-0626:
" Plants could also be modified by installing new relief valves wi.th normally open isolation or block valves that would eliminate the opening of present S/RVs that may fail to close and cannot be isolated."
Discussion - The follcwing factors would have to be considered in the implementation of this candidate modification:
1.
The suggested modification could be in violation of the ASME Code, unless some vaives are dedicated for the safety function and others for the relief function. Any modification would need to be reviewed to assure compliance with the ASME Code.
2.
The new relief valves, pipes and block valves would have to be designed for the reactor design pressure (1250 psig). Currently, the relief valve discharge flange and pioing is designed for about 600 psig.
3.
Inadvertent closure of the block valves would cause the new relief valves to 'cecome unavailable for the elief function.
This candidata nodificatica.ould act reocce the 50RV event frequency, but would reduce the o.secuence of such an event. Theoretical'y it is possible to design a system that will mitigate any future 50RV event; however, frcm a practical standpoint this may be an impossible modifica-tion to implement since there would not be sufficient room in the drywell 18
O I
of most plants to accommodate the additional piping and equipment. The large expense in terms of cost and personnel exposure requ red to implement' i
this concept is not justified when the low risk of core damage resulting from a SORV event is considered.
3.1.4.6 Earlier Initiation and Increased Flow of Emergency Core Coolant Definition - A description of this candidate modification is quoted from NUREG-0626: "Another method that could be employed is to provide additional emergency core coolant (ECC) flow to act as a heat sink (steam condenser) to accommodate the pressure increase due to swelling of the coolant.
This could also be accomplished by modifying the plant instrumentation to provide earlier ECC system initiation. The combination of increased ECC flow at an earlier time in the transient could provide the necessary heat sink to absorb the power or pressure spike before the relief valve setpoint is reached."
4 Discussion - ECC flow could not be initiated early enough by any practical means to result in any significant reduction of the number of valves that open during the initial blowdown, becaL.e of the steep rate of pressure rise following a transient.
Further, earlier initiation of ECC flow could result in ECC initiation and L8 feedwater pump trip on transients such as turbine trip (following which ECCS is not expected to initiate),
causing simultaneous loss of the preferred coolant source (feedwater) and the preferred heat sink (the main condenser). Such a modification cannot be justified.
f 3.2 Reduction of the Relative Probability of the Valve to Stick Ocen j
Many operating BWR plants are equipped with Three Stage Target Rock valves. The Three Stage Target Rock valves have exhibited a higher probability to stick open in the past than other types of valves. A detailed review of the 50RV events associated with the Three Stage Target Rock valve was carried out by General Electric and Target Rock Company, and the results have been used to identify valve modifications which improve the valve performance. Design and operational modifications 19
have been identified for the Three Stage Target Rock valve which reduce the probability of the Three Stage Target Rock valves in service to stick open.* In addition, the valve topworks have been redesigned to minimize the probability of the valve to stick open. The new design is referred to as the "two stage" design. Such valves have been installed in some operating plants. The valves thus modified are referred to as Two Stage Target Rock valves in this study.
Some operating BWR plants are equipped with Dresser Electromatic relief valves. BWR/5-6 plants are equipped with Crosby and Dikkers dual function safety / relief valves.
Assigning a normalized SORV probability factor = 1.0 for the Three Stage Target Rock valve (which is taken as a benchmark valve), the relative SORV probability factors for other valves were determined as follows:
i Two Stage Target Rock Valve
=
0.50 Dressar Electromatic Valve
=
0.25 Crosby Valve
=
0.125 Dikkers Valve
=
0.125 3.3 Reducino Causes of Sourious Blowdowns The following candidate design modifications are expected to directly affect the number of 50RVs by eliminating the causes of spurious blowdowns.
3.3.1 Eliminate Spurious Safety / Relief Valve Openings Resulting from DC Power Supply Ground Faults Defin tion - Inaovertent S/RV openings can be reduced by providing double i
pole Jingle thr:w swit:hes, or cther means of protection that oisconnect both the positive ano the negat1<e sides of the DC ccwer supply, for ener-gizing and deenergi:ing the solenoids of safety relief valves.
- Plants with improved Three Stage Target Rock valves and plants employing operational modifications will address their valve reliability on a plan -enique basis.
20
Discussion - The potential benefit of this candidata modification is the avoidance of spurious depressurization of the reactor as the result of grounding faults in the DC power supply.
It is estimated that approxi-mately one spurious relief valve opening or failure to reclose after proper opening per 50 reactor years would be eliminated by this modifi-cation.
Detailed design should assure that the new switching device will not be less reliable than the existing device in performing the functions of energizing and deenergizing the solenoid coil on demand.
3.3.2 Control of Pneumatic Supply Pressure to S/RV's.
Definition - High pneumatic supply pressure to the actuating solenoids of Target Roci: S/RVs caused one spurious blowdown in an operating plant.
Improved pneumatic supply pressure control would eliminate the cause.
Discussion - The implementation of this candidate modification would assure that this mode of spurious S/RV actuation will be eliminated.
This modificati i results in a maximum reduction of 2% in spurious blowdowns.
3.3.3 Revised S/RV Spring Setpoint. See discussion in Section 3.1.3.3.
3.3.4 More Stringent Leakage Criteria and Early Removal of Leaking Valves Definition - These candidate modifications were suggested in NUREG-0626.
"More stringent leakage criteria" is assumed here to refer to leaking safety / relief valves while in operation. "Early removal of leaking valves" refers to a planned action of removing the valves which begin to leak.
21
1 Discussion - Leaking Three Stage Target Rock valves can result in spurious blowdown. Analysis has shown that a maximum of 40 to 60% reduction in spurious operation of S/RV's could be obtained by identifying and replacing valves with high leakage. Since all valves leak to some extent, it is difficult to develop an absolute leakage criterion. Additional study is required to develop a leakage criterion which is practical and a system to detect the leakage. With the use of the Two Stage Target Reck, Crosby or Dikkers valves, the leakage is not a concern because leakage does not significantly affect the spurious blowdown probability. The implementation of this candidate modification will not reduce spurious blowdowns in the Two Stage Target Rock, Crosby and Dikkers valves.
3.3.5 Use of Two Stage Target Rock Valves Definition - The Three Stage Target Rock valves could be changed to Two Stage Target Rock Valves.
Discussion - The Two Stage design eliminates most spurious blowdown modes associated with the Three Stage Valves. A 40-60% reduction in
~~
spurious blowdowns can be achieved by changing the Three Stage Target Rock valves to Two Stage valves.
l 22
4.
MElWOOLOGY This section discusses the methodology used in this study.
4.1 Lntroduction Although the NUREG-0737 position deals primarily with the reduction of challenges to S/RVs, its clear intent is to reduce the incidence of 50RV events. Reducing challenges is only one of three approaches to reduction of 50RV events. The others are reducing the causes of spurious blowdowns and reducing the probability of S/RVs to stick open when challenged.
All three approaches are required to achieve an " order of magnitude" (factor of ten) reduction in 50RV events.
BWR/4 units equipped with Three Stage Target Rock valves were used as the basis for such judgments.
The BWR/4 with Three Stage Target Rock valves is referred to as the
" benchmark" plant in this discussion.
4.2 Aporoach A :omparison of the 50RV event frequency that can be expected over the lifetime of each BWR product line is made by multiplying the expected number of S/RV openings during a plant's lifetime by the relative proba-bility factor for the S/RV to stick open. The 50RV event frequencies thus computed for each product line were normalized to that of the benchmark plant taken as 100.
The reduction of spurious operation of relief valves was estimated based on operating experience and engineering judgment.
4.3 Probability of 5/RV's to Stick Ocen For comparing the various valves, the Three Stage Target Rock valve was taken as the benchmark valve with an assumed normalized factor of 1.0 for probability to stick open when challenged. Similar factors for other types of valves were obtained as described below.
23
4.3.1 Two Stage Target Rock A detailed review of all the 50RV events in operating plants was made, and the failure modes associated with the Three Stage Target Rock valve were tabulated. Then based on a study of the Two Stage valvo design, an assessment was made of all the failure modes that are eliminated by the Two Stage design.
Consideration was also given to any new failure modes which might develop in going from the three stage to the two stage design. With this information, a relative probability factor of 0.50 was assigned for the Two. Stage valve to stick open, when challenged.
4.3.2 Dresser Electromatic Based on a review of operating experience and engineering judgment, the Dresser valve was assigned a factor of 0.25 for its relative probability to stick open, when challenged.
i 4.3.3 Crosby and Dikkers The actual experience with the Crosby & Dikkers valves is too limited to be used for estimating the relative 50RV probability factor.
- However, since those valves are direct acting (unlike the Three Stage Target Rock Valve which is pilot operated) seat leakage is not likely to be a signifi-cant concern as in the case of Target Rock valves. Based on valve qualification test data and limited operating experience, a factor of 0.125 was assigned for their relative probability to stick open, when challenged.
4.4 Estimation of S/RV Challences The total number of 5/RV challenges expected over the cesign life of a plant was as:imated as described below for each BWR product :1re.
The total S/RV challenges curir.g a plant lifetime was taken to be the zummaticn of tr.e p ocuct of the f*equency of various design transients and ne estimated number of valve openings per occurrence of a transient. These valses were : hen normalized to the benchmark plant whose value was taken as 100.
24
4.4.1 Frequency of Transients It was assumed that each plant will experience the same number of various transients as were considered in its design basis. To estimate the impact of various design improvements on the frequency of transients, data from operating BWR plants spanning 120 reactor years of operation and approxistely 1400 reactor scram events (which include 720 S/RV challenge events) were investigated. By analyzing the data an estimate was made of the percentage by which various transient event frequencies would be modified if each of the candidata modifications discussed in Section 3 were implemented. This estimate was used to modify the fre-quency of design basis t*ansients.
4.4.2 Total Number of Valve Openings The total number of valve openings for various transients was computed by using the General Electric long-term thermal hydraulics model (SAFE and REDY codes).
The.e are many operational transients which can result in a pressure rise in the reactor vessel. The safety / relief valves will open if necessary to prevent the pressure from exceeding allowable limits.
For most of these events, the safety / relief valves will open only once.
However, there are several types of transient events which can result in a closure of the main steam isolation valves. Although a scram occurs f
immediately when the isolation valves close, the reactor continues to generate steam due to decay heat. The safety / relief valves are then the primary means of reactor pressure control. One or more valves may open with the initial pressurization following MSIV closure. These safety / relief l
valves will open when their pressure setpoints are reached and will
)
discharge steam to the suppression pool until the vessel pressure decreases to the closure setpoint of the valve.
Reactor pressure will then increase again until the lowest safety / relief valve's opening setpoint is reached.
In most instances, only one S/RV will open on subsequent actuations.
If no operator action occurs, one valve will. continue to cycle open and closed. The total number of safety / relief valve lifts is thus based on 25
o three factors--the number of transient events which result in opening of the safety / relief valves, the number of valves which open in the initial pressurization, and the number of cycles which subsequently occur.
4.4.3 Discussion of Assumptions Following are the key bases and assumptions used in the analysis.
l 4.4.3.1 The frequencies of transient events are based upon the BWR/6 design document for plant duty requirements. Overall the estimated number of relief valve openings based on the design transient frequency differed only by 13 to 21% from the estimate based on transient frequency actually experienced by the plant. Since these numbers were used only to determine the relative contribution of various modifications, this difference of 13 to 21% is not significant.
4.4.3.2 The maximum specified relief valve reclosure setpoint is used since a smaller difference between the opening and closing setpoints results in a larger number of cycles. A 25 psi blowdown per relief v&lve opening is used for pilot operated valves such as Target Rock and Dresser, and a 50 psi blowdown is used for direct-acting valves such as Crosby and Dikkers.
l 4.4.3.3 Initial plant operating conditions are at 105% nuclear boiler rated steam flow.
l 4.4.3.4 BWR/2 and 3 plants equipped with isolation condensers are assumed to be capable of avoiding relief valve cycling after the initial relief valve discharge due to a transient.
4.4.3.5 For isolation transients, subsequent single S/RV discharges continue for 30 minutas.
26
5.
RESULTS
~
5.1 Expected SORV Frequency The expected 50RV event frequency (normalized to the benchmark plant) for some of the most effective modifications are shown in Table 5.1.
The following conclusions can be reached from this table.
5.1.1 BWR/2, BWR/3 with isolation condenser, BWR/5 and BWR/6 plants are estimated to have a SORY frequency which is a factor of 10 less than the benchmark plant (BWR/4).
5.1. 2 BWR/4 plants can reduce the 50RV frequency by a factor of ten or more by implementing selected modifications from Section 3.
5.1.3 BWR/3 plants without isolation condensers can reduce the SORV frequency by a factor of ten or more by implementing selected modifi-cations from Section 3.
5.1.4 The effect of isolation condensers on plants not so equipped is shown for comparison even though they are not practical for backfit application. The effect of high steam bypass capability (here, 110%) is shown because some plants are so equipped.
5.1.5 The relative impact of each candidate modification on the S/RV challenge reduction alone is shown in Table 5.2.
It should be noted 1
that more than one candidate modification could reduce S/RV challenges by addressing a common characteristic; therefore the percentage reductions in S/RV challenge rates attributable to the candidate modifications are not necessarily additive.
- 5. 2 Excected Sourious Blowdown Frecuency Reduction The expected reduction in frequency of spurious blowdowns alone through implementation of various candidate modifications is summarized in Table 5.3.
1
~
27
~
TABLE 5.1
~
l SORV EVENT FREQUENCY j
TOTAL SORV EVENT FREQUENCY (NORMALIZED)
BWR/4 CANDIDATE w/3 Stage BWR/3 BWR/2/3 MODIFICATION Target Rock without with 4
Valve (Bench-Isolation Isolation mark Plant) Condenser Condenser BWR/5 BWR/6 (A): None 100 78 8
8 6
(B): Low Water Level 69 50 8
6 Isolation Setpoint (C): Low-Low Set Relief or 44 29 8
6 Equivalent Mancal Action (D): (B > C) 35 21 8
5 (E): Low-Low Set Relief or 11 7
2 N/A N/A Equivalent Manual Action
+ 2 Stage Target Rock Valve (F): (C) + Early Removal of 22 15 4
N/A N/A Leaky 3-Stage Target Rock Valve (G): Low Water Level Iso'; tion 9
5 2
N/A N/A
+ Low-Low Set Relief or Equivalent Manual Action
+ 2 Stage Target Rock Valve (H): (B) + (C) + Early Removal of 18 10 4
N/A N/A 3 Stage Target Rock Valve (I): 110% Steam Bypasst 88 73 4
6 4
(J): 110% Steam Bypasst 22 18 2
N/A N/A
+ 2 Stage Target Rock Valve (K): Isolation Condensert 23 8
3 4
(L): Isolation Condensert 6
2 2
N/A N/A
+ 2 Stage Target Rock Valve
- Already implemented t for comparison only N/A Not Applicable since these plants are equipoed with Crosby /Dikkers valves.
NOTES:
1.
This table shows the 50RV rce!? frequency recuction due to some of the most effect'9v cce ritetors.
2.
50RV event frequencie. ;noi n. : ted) snewn 43 ave are obtained by multiplying total S/3V chaneLges (normalized) in Table 5.2 by relative 50RV probability factor.
In the case of Two Stage Target Rock Valves the benefit in reduction of spurious blowdowns (from Table 5.3) has been included above.
28 w.
-,---,,-.--.m
- + - -
y
TABLE 5.2 S/RV CHALLENGES TOTAL S/RV CHALLENGES (NORMALI D )
BWR/4 CANDIDATE 2/3 Stage BWR/3 BWR/2/3 MODIFICATION Target Rock without with Valve (Bench-Isolation Isolation mark Plant) Condenser Condenser BWR/5 BWR/6 None 100 78 8
63 47 Low Water Level Isolation 69 50 8
48 Setpoint Low-Low Set Relief or 44 29 8
49 Equivalent Manual Action Feedwater Runback 91 69 7
58 44 Reduce surveillance Test Error ** 95 74 7
60 45 Reduce MSIV Test Frequency **
98 76 8
62 46 Feedwater Control System 89 68 7
56 45 Modification Feedwater System Improvement **
97 75 8
52 47 Turbine System Improvement **
85 67 6
53 38 Analog Transmitter / Trip Unit **
97 75 8
61 46 Improved Recirculation Flow 96 73 8
60 46 C;4. trol 27 34 Isolation Condensert 23 8
110% Steam Bypasst 88 73 4
47 28
- Already implemented
- See Note 3 t for comparison only NOTES:
1.
To obtain 50RV event frequeicy (normalized) multiply the values in the table by relative 50RV probability tactor.
2.
Relative 50RV probability factor for various valves are as follows:
3 Stage TR Valve:
1.0 Dresser Electromatic:
0.25 2 Stage TR Valve:
0.50 Dikkers & Crosby:
0.125 3.
The benefits due to various candidate modifications are not additive except where noted by **.
4.
Values shown above may vary from plant to plant depending upon utility operating practice.
29
TABLE 5.3
. REDUCTION IN SPURIOUS BLOWOOWN EVENT FREQUENCY Percentage Reduction in Candidate Modification IORV Events Acolicability Eliminate S/RV Ground Faults 1-2%
All Plants Improved Pneumatic Supply 2-3%
Plants with Target Control System Rock valves only Revise Spring Setpoint to 5%
Plants with Target Increase Simmer Margia Rock valves only More Stringent Leakage Criteria 40-60%
Plants with 3-Stage
& Early Replact ent of Leaking Target Rock Valves Valves Only Repla.ce Valve Topworks with 40-60%*
Plants with 3-Stage Two-Stage Design Target Rock Valves Only "This modification also reduces the probaDility of the valve to stick open.
See Table 5.1 for the total impact on 50RV event frequency.
~
30
6.
CONCLUSIONS Adequate core cooling is maintained in a BWR following an 50RV event even under degraded conditions.
It follows, then, that reduction of the equency of SRV events is not of great concern from the standpoint of assuring adequate core cooling.
It is concluded that BWR/2, BWR/3 with isolation condenser, BWR/5 and BWR/6 plants are expected to have a 50RV frequency which is a factor of at least ten below that for the benchmark plant. The use of selected modifications from a list of candidates car, produce a factor of ten reduction in stuck open relief valve event frequency for BWR/4 plants and BWR/3 plants without isolation condenser.
It should be noted that additional candidate modifications may exist which could reduce SORV event frequencies but have not been addressed in this report.
31
d 7.
REFERENCES 1.
NEDO-24708A (December, 1980), " Additional Information Required for NRC Staff Generic Report on Boiling Water Reactors," Sections 3.1.1, 3.2.1.
2.
NED0-24708A, Section 3.2.1.
i 3.
NED0-24708A, Section 3.2.2.
4.
NED0-24708A, Section 3.5.2.1.
5.
BWREmergencyProcedureGu[idelines,Rev.1(prepublicationform),
submitted January 31, 1981.
I i
I t
l m
32
o l
APPENDIX A Participating Utilities NUREG-0737 II.K.3.16 This report applies to the following plants, whose Owners participated in the report's development.
Utility Plant Boston Edison Pilgrim 1 Carolina Power & Light Brunswick 1&2 Commonwealth Edison LaSalle 1&2, Dresden 2-3, Quad Cities 1&2 Georgia Power Hatch 1&2 Iowa Electric Light & Power Duane Arnold Jersey Central Power & Light Oyster Creek 1 Niagara Mohawk Power Nine Mile Point 1&2 Nebraska Public Power District Cooper Northeast Utilities Millstone 1
~ ~ ~ ~
Northern States Power Monticello Philadelphia Electr,c Peach Bottom E&3, Limerick 1&2 Power Authority of the State of FitzPatrick New York Detroit Edison Enrico Fermi 2 l
l Long Island Lighting Shoreham Mississippi Power & Light Grand Gulf 1&2 Pennsylvania Power & Light Susquehanna 1&2 Washington Public Power Supply Hanford 2 System l
Cleveland Electric Illuminating Perry 1&2 Houston Lighting & Power Allens Creek Illinois Power Clinton Station 1&2 Public Service of Oklahoma Black Fox 1&2 Vermont Yankee Nuclear Power Vermont Yankee Tennessee Valley Authority Browns Ferry 1-3; Hartsville 1-4; Phipps Bend 1-2 Gulf States Utilities River Bend 33
o.
y BWR OWNERS' GROUP EVALUATION OF NUREG-0737 ITEM II.K.3.18 MODIFICATION OF AUTOMATIC DEPRESSURIZATION SYSTEM LOGIC l
l
- v i
CONTENTS
.P, age ABSTRACT 1.
INTRODUCTION 1-1 2.
ADS LOGIC OPTIONS CONSIDERED 2-1 2.1 Current Desi n 2-1 2.2 Eliminate Hi h Drywell Pressure Trip 2-2 2.3 Bypass High rywell Pressure Trip 2-2 2.4 Add Suppression Pool Temperature Trip 2-3 2.5 No High Pressure System Flow 2-4 3.
SYSTEM PERFORMANCE 3-1 3.1 Current Desi n 3-1 3.2 Eliminate Hi h Drywell Pressure Trip 3-2 3.3 Bypass High rywell Pressure Trip 3-2 3.4 Suppression Pool Temperature Trip 3-3 3.5 No High Pressure System Flow 3-3 3.6 Summary
~
3-4 4.
RELIABILITY ASSESSMENT 4-1 4.1 Reliability of ADS Initiation 4.2 Spurious and Inadvertent Actuation 4.3 Summary 5.
FEASIBILITY OF IMPLEMENTATION 5-1 l
l 5.1 Current Design 5-1 5.2 Eliminate High Drywell Pressure Trip 5-2 5.3 Bypass High Drywell Pressure Trip 5-4 5.4 Suppression Pool Temperature Trip 5-5 5.5 No High Pressure System Flow 5-7 5.6 Summary 5-9 6.
CONC'.USIONS 6-1 Figures, Table 5-1 l
APPENDIX l
A.
PARTICIPATING UTILITIES A-1 l
i l
ABSTRACT i
I A study was performed to determine the feasibility and benefits of extending the operation of the BWR Automatic Depressurization System (ADS) to include transient events which do not result in a release of steam to the drywell.
Five options, including retaining the current design,w'econsidered._Thecurrentdesign,withimplemenfationofthe Emergency Procedure Guidelines, is adequate. Howeverl an ADS modification is believed to reduce plant risk, and is therefore proposed. The results showed that the addition of a bypass of the high drywell pressure trip if reactor water level remains below the low pressure ECCS initiation setpoint for a sustained period, or elimination of the high;drywell pressure trip, are the preferred concepts. Detailed implementation will require consideration of broader scope issues, such as the final resolution of ATWS (which may affect the ADS logic, and which is specifically not considered in this study).
l l
l l
\\
l l
v p
m---
-.- -~-
,m
- e 1.
INTRODUCTION The feasibility and reliability assessment study reported herein addresses NUREG-0737 Item II.K.3.18 which states, "The Automatic Depressurization System (ADS) actuation logic should be modified to eliminate the need for manual actuation to assure adequate core cooling. A feasibility and risk assessment study is required to determine the optimum approach.
Cne possible scheme which should be considered is ADS actuation on low reactor vessel water level provided no HPCI or HPCS system flow exists and a low pressure ECC system is running. This logic would complement, not replace, the existing ADS actuation logic."
I i
i The automatic depressurization system, through selec.ted safety / relief valves,* functions as a backup to the operation of the high pressure l
coolant systems [feedwater, High Pressure Core Spray (HPCS)/High Pressure l
CoolantInjection(HPCI),ReactorCoreIsolationCooling(RCIC)/ Isolation Condenser (IC)] for protection against excessive fuel cladding heatup upon loss of coolant, over a range of steam or liquid line' breaks inside the drywell. The ADS depressurizes the vessel, permitting the operation l
of the low pressure ccolant systems [ condensate, Low Pressure Coolant Injection (LPCI),LowPressureCoreSpray(LPCS)]. The ADS is typically activated automatically upon coincident signals of low water level in i
the reactor vessel, high drywell pressure, ** and low pressure ECCS l
pumps running. A time delay of approximately 2 minutes after receipt of the signals allows time for the automatic blowdown to be bypassed if the water level is restored (or to be bypassed manually if the signals are erroneous).
The ADS can be manually initiated as well.
- A 4 plants have dedicated ADS salves.
"A fu plants do not require coincident signals.
1-1
-~.
5 For transient and accident, events which do not directly produce a high drywell pressure signal and are degraded by a loss of all high pressure coolant systems, adequate core cooling is assured by manual depressuri-zation of the reactor vessel. For these events, the operator has sufficient time to manually depressurize the reactor in order to permit operation of the low pressure ECCS in these highly degraded events. The intent of this kUREG-0737 item is to provide additional assurance of adequate core cooling for these additional events. This study evaluates the feasibility of automating the vessel depressurization for isolation events with and without a stuck open relief valve (50RV), and assesses the changes in overall plant risk resulting from such automation.
The intent of the NUREG-0737 item may be addressed in two ways: the ADS logic may be modified to assure adequde core cooling for these additional events, or the operator can be given specific guidance and training for performing manual actions under degraded conditions. Following the accident at Three Mile Island, this second course of action has been undertaken, resulting in the development of symptom-oriented Emergency Procedure Guidelines (EPG's).
Implementation of the EPGs will improve the operator response to degraded transients by giving..im explicit guidance under these conditions and a better awareness and understanding of the plant response as a result of improved training. The events in question are slow, well behaved, well understood transients which allow the operator sufficient time to actuate ADS if the situation warrants.
l In addition the operator has had extensive training in this class of events and will receive additional instructs a with the implementation of the EPGs.
i It was shown in NED0-24708, " Additional Information Required For NRC Staff Generic Report on Boiling Water Reactors," Section 3.5.2.1, that the operator has at least 30 to 40 minutes to initiate the ADS and prevent excessive fuel cladding heatup for both of the above events. This minimum time represents a " worst case" situation starting from full power with 1-2
equilibrium core exposure and complete failure of all t'he high pressure makeup systems.
Lower initial core power, low fuel exposure, control rod drive leakage flow, or partial operation of the high pressure systems would significantly increase the time available for operator action.
In addition, the operator has explicit guidance for transients under l
severely degraded conditions with the implementation of emergency proce-l dures based on the symptom-oriented Emergency Procedure Guidelines (EPG's). The symptom oriented procedures lead the operator through transients with increasing levels of degradation and give him specific guidance on when to initiate ADS if it is neaded. Thus with the imple-mentation of the new emergency procedures, the operator has an increased understanding of the system and can reliably perform the actions necessary to assure core cooling.
Transients which may require manual depressurization can be characterized by two general events:
- 1) reactor isolation with loss of normal inventory maintenance, and 2) reactor isolation with loss of normal inventory maintenance degraded by a stuck open relief valve. Both of these. events l
were considered in t.e design of the modified ADS even though the seconu 6
l event type is beyand the current design basis which assumes a single l
failure. Transients resulting in a loss of feedwater for the most part also cause a reactor isolation due to low reactor water level. Steamline breaks outside the containment result in an isolation due to several signals (e.g., high steamline flow, high steam tunnel radiation or temperature).
For transients that do not cause an isolation, the main condenser is available for depressurization and tne ADS is not required.
Therefore such events are not included in this study.
The isolation with 50RV is considered separately because the additional inventcry loss through the ocen valse increases the required high pressure makeuc flow. The additional loss also reduces the time available for the o;:er".or to manually depressurize the vessel if necessary.
l 1-3
o l
Four ADS logic modifications are considered, and the current logic is reviewed using the same basis as the modifications. These five options are evaluated as to system performance, feasibility of implementation, cost of additional design and hardware, and impact on plant operation.
Section 2 gives a detailed description of each of the logic alternatives considered. Section 3 demonstrates the acceptability of the system performance of each of the modifications. Section 4 discusses the reliability of ADS actuation with increased automation of the ADS. The advantages and disadvantages of each option and the feasibility of implementation are discussed in Section 5.
This study is devoted to the feasibility of concepts as opposed to a detailed design assessment. The goal is to determine, using simple concepts and arguments, whether or not ADS should be further automated, and if so, which conceptual design is most favorable for further develop-ment.
Detailed design implementation of any changes will require consideration of broader scope issues, such as the final resolution of ATWS(whichmt. affect the ADS logic, and which is specifically not considered in this study) and the desirability of other changes in the ADS based on recent studies in support of the Emergency Procedure Guidelines.
1-4
2.
ADS LOGIC OPTIONS CONSIDERED Five ADS logic options are considered: the current design, and four logic modifications. These four modifications are 1) elimination of the high drywell pressure trip, 2) addition of a timer that bypasses the l
high drywell pressure trip if reactor water level is low for a sustained period, 3) addition of a suppression pool temperature trip in parallel with the high drywell pressure trip, and 4) the addition of high pressure system flow measurement and logic in parallel with the high drywell pressure trip.
2.1 CURRENT DESIGN The first option to be considered is the present ADS logic design. With the implementation of the symptom-oriented EPG's, the current logic satisfies the intent of the NUREG-0737 item and its incorporation in the NSSS desi r. ineets all of the applicable design and licensing requirements.
3 It is not obvious that the advantages of further automation outweigh the disadvantages. The current cesign is thus a viable option in its own right.
Figure 2-1 shows the current ADS logic design for a typical plant. The design requires a LOCA signal consisting of concurrent high drywell pressure and low reactor water level in order to actuate the ADS. The actuation sequence depends on receipt of the high drywell pressure (2 psig) signal. Once this signal is received, it is sealed into the initiation sequence and does not reset even if the high drywell pressure subsequently clears. The next signal is low water level (low l
pressure ECCS actuation level).* When this is satisfied, the logic confirms the water level is indeed below the scram water level (to prevent spurious actuations) and starts the 120 second delay timer. The
- In :::an/ plan s this level is commonly refarrec to as " Level 1" and will be referred to as such in this report.
2-1
o,
i timer is reset if the low water level trip clears before the timer times out. The timer also allows the operator time to bypass the automatic blowdown if the conditions have corrected themselves or if the signals are erroneous. To complete the sequence, the low pressure ECCS pumps are automatically checked to provide some assurance that makeup water will be delivered to the vessel once it is depressurized.
Drywell cooling is lost for a number of plants wnen the reactor water level reaches low level (Level 1). The loss of cooling results in a heatup of the drywell air space (if the operator is unable to restore cooling) and subsequent pressurization of the drywell above the 2 psig required for ADS initiation and actuating the ADS. Thus in plants where drywell cooling is lost on low level, the current logic will act as a satisfactory backup to manual action for the events considered.
The symptom-oriented EPG's are written incorporating the current ADS logic. For the events in question, the operator is given explicit instructions on when to manually depressurize the vessel if the high pressure systems cannot maintain inventory. These instructicns are based on the conditions of vessel pressure and water level, and the availability of high and low pressure injection systems. As a result of the symptom-oriente.d nature of these guidelines, the appropriate operator actions are specified for all levels of degradation and plant conditions.
2.2 ELIMINATE HIGH DRYWELL PRESSURE TRIP The second option is simply to eliminate the high drywell pressure trip from the current logic sequence. The ADS sequence would then be activated on low reactor water level only. The remainder of the sequence remains unchanged. The effect of high drywell pressure on other safety systems, I
such as reactor scram and the ECCS that initiate on high drywell pressure, are unaffected. The logic design for this alternative is shown in Fiaure 2-2.
2-2
2.3 BYPASS HIGH DRYWELL PRESSURE TRIP The third option is to bypass the high drywell pressure requirement after a set timer delay. This is accomplished by installing a second
(" bypass") timer actuated on low water level. When this timer runs out, the high drywell pressure trip is bypassed and the ADS is initiated on water level alone. The additional logic does not affect the high drywell pressure-low water level initiation sequence for pipe breaks inside the drywell. Once the timer runs out, this option becomes the same as that discussed in Section 2.2.
The only difference is that for events which do not stoduce a high drywell pressure signal, the bypass timer gives the operator additional time to bypass the automatic blowdown if the situation is corrected or ADS is not needed for some other reason.
Figures 2-3A and 2-38 show the logic for this alternative, with the bypass timer started at either scram or low (Level 1) water level. A time delay of approximately eight minutes was chosen for preliminary evaluations.
Starting the 8-minute delay at scram water level results in the high drywell pressure trip being bypassed at about the same time as'the water level outside the shroud : reaches the top of the active fuel under the worst case conditions of an isolation event with an SORV from full power and no high pressure makeup.
If the water level recovers to the initiation level of either timer, tha.t timer is automatically reset.
The exact delay of the bypass timer is subject to a more precise evalu-ation, which is based on avoidance of excessive fuel cladding heatup using the realistic evaluation models of NED0-24708A.
It is specifically noted that the current system, which requires operator action for certain transients, is in ccmpliance with all applicable design and licensing bases. The nodification is regarded as a backup to operator action.
Starting ice bypass timer at low water level (Level 1) allows the operator the greatest time to control the system manually and still assure automatic 2-3
l i
c, depressurization in time to prevent excessive fuel heatup even under the worst case conditions described above.
For BWR/1-3, the bypass timar would be reset if the low water level trip is recovered.
For BWR/4-6, once the bypass timer times out, the bypass permissive would be sealed in and the bypass timer would not reset. This accounts for the lower Level 1 trip elevation and prevents repeated partial core uncovery.
L4 ADD SUPPRESSION POOL TEMPERATURE TRIP i
The fourth option is to add a suppression pool temperature trip in parallel with the high drywell pressure trip. The ADS initiation sequence would then be initiated by either high drywell pressure or a rise in suppression pool temperature, with the remainder of the logic unchanged.
Just as high drywell pressure is symptomatic of a loss of inventory i
inside the drywell, a rapid rise in suppression pool temperature indicates inventory loss through the relief valves or a break in the drywell.
There are two conditions that could be used to provide the pool tempera-ture permissive; when the pool temperature reaches a specified value, or if the pool heats up faster than a specified rate. The heatup rate trip would require a simple data processing system that would record the present pool temperature, compare it to the reading ten minutes previous to determine the heatup rate, and store the present information to be used later. As shown in Figure 2-4, the remainder of the logic is l
unchanged from the current design.
1 2.5 N0 HIGH PRESSURE SYSTEM FLOW The fifth option is to measure high pressure system flow (Feedwater, HPCI/HPCS, RCIC/ isolation condenser), and bypass the high drywell pressure trip if no flow is present in all of these systems. This option was identified in NUREG-0737. The remainder of the logic would remain unchanged.
Since this signal would complement the current ADS logic, the ADS is not inhibited for LOCA events if a high pressure system is operating. The additional logic is shown in Figure 2-5.
There are two methods of accomplishing the hign pressure flow measurement. The more 2-4 l
a direct method is to actually measure the flow of each high pressure system, with a minimum flow for the system (approximately full rated flow for the high pressure ECCS and about 10 percant of full feedwater) required to block the "no high' pressure flow" permissive. This method gives the greatest assurance that makeup water is reaching the vessel.
However, trips based on flow measurement may not be as reliable as desired. A theoretically more reliable but less direct measurement scheme would use pump operation and valve position to infer the lack of high pressure system operation. Because the scheme is less direct, the overall ADS actuation reliability may or may not be improved. During loss of feedwater transients, the high drywell pressure signal is bypassed and the ADS initiation sequence is started for the short time between the time feedwater is lost and the time the water level falls to the high pressure ECCS initiation trip (Level 2) and the high pressure ECCS i
start up.
During this time, blowdown would be prevented by the Level 1 trip (or the 120 second timer for BWR/1-3 because the high and low pressure ECCS start at the same water level). Once one of the high pressure systems start up, the permissive is removed and the initiation sequence is halted.
If no high pressure systems start up, level alone starts the timer and initiates ADS.
+
2-5
3.
SYSTEM PERFORMANCE This section analyzes each of the options as to whether it ensures adequate core cooling for isolations and SORV's. For these analyses it is assumed that all high pressure systems have failed and the ADS must depressurize the vessel and allow the low pressure systems to inject.
The modeling used in these analyses is the same as that used in NED0-24708.
3.1 CURRENT DESIGN The current design does not directly satisfy the above criteria because the logic does not actuate the ADS specifically for the events considered.
However, as stated earlier, the operator has 30 to 40 minutes to depres-surize the vessel under these worst case conditions and prevent core damage. This is sufficient time to assess the situation and take the necessary actions.
-In-addition to the time available to the operator to blow down the l
vessel, ADS actuation is assured for these events in plants which lose the drywell cooling on a low water level signal. The loss of drywell cooling will cause the drywell temperature to increase, and consequently the drywell pressure to rise. The drywel? pressure reaches the 2 psig setpoint required for ADS initiation in 3 to 10 minutes resulting in ADS actuation if the water level has not been restored above Level 1.
The time required for the drywell to heat up and pressurize is insensitive l
to the power level of the reactor or the ambient conditions inside and outside the containment. Thus ADS actuation would most likely occur witho# operator action within about 10 minutes after Level 1 even for events which do not directly pressurize the drywell. Analyses presented in NED0-24708 (Figure Group 3.5.2.1-33) demonstrate that adequate core cooling is assured for isolation events with the ADS blowdown delayed 10 minutes after Level 1.
Figure Group 3-1 shows the same analysis assuming an 50RV. The results shown are typical of BWR/4-6. These results bound 3-1
i BWR/1-3 because of the latter's higher ADS level trip. Because the trip is at a higher level, the resulting core uncovery is shorter and the core heatup is less.
3.2 ELIMINATE HIGH DRYWELL PRESSURE TRIP By eliminating the high drywell pressure trip, the system response to the transients considered in this study is similar to that for small LOCA events inside the containment. With a pipe break inside the drywell, the high drywell pressure trip occurs before the low water level trip.
Eliminating the high drywell pressure trip can be thought of as assuring this signal exists for all transients.
The water level response for an isolation event is bounded by small breal LOCA analyses where the majority of the inventory lost is not through the break but through the cycling of relief valves. The water level response to a stuck open relief valve is essentially the same as that shown for a small recirculation line break. Thus the break spectrum analyses provided in Safety Analysis Reports provide verification that adequate co-e cooling would be assured for this option.
3.3 BYPASS HIGH DRYWELL PRESSURE TRIP There are two cases studied for this option:
- 1) the 8-minute bypass timer started at scram water level, and 2) the 8-minute bypass timer started at low water level (the current ADS level trip).
For the first i
case the eight minute bypass timer delay plus the two minute bypass timer delay is consistent with the operator action assumed in Safety Analysis Reports.
The analyses presented in these reports for the steamline break outside the containcient demonstrate adequate core cooling is assured fer this case.
Figure Group 3-2 presents typical results for 3-2 l
o.
t l
an isolation with an SORV. The second case results in the ADS actuation occurring approximately ten minutes after low level (Level 1). The analyses and justification presented in Section 3.2 are applicable here.
3.4 SUPPRESSION POOL TEMPERATURE TRIP Since the suppression pool temperature trip performs the same function as the high drywell pressure trip, the discussion and justification presented in Section 3.2 is applicable for this option provided that the system would be designed to reliably produce a h.igh pool temperature signal before low reactor water level is reached for all events in I
question (see Section 5.4).
1 3.5 N0 HIGH PRESSURE MAKEUP FLOW j
For this modification, if no high pressure system flow is indicated, the j
high drywell signal is bypassed. Section 3.2 is applicable to this situation. For isolation and SORV events where adequate high pressure injection is indicated, the high drywell pressure trip is not bypassed and ADS is not actuated. For isolation events, any one of the~ high pressure systems alone (feedwater, HPCI/HPCS, RCIC/IC) is adequate to maintain adequate core cooling.
For an 50RV, the additional lost inventory must be made up by the high pressure system. The HPCI and HPCS systems have adequate flow capaci-l ties to make up the lost inventory. The RCIC has a much smaller capacity l
but can provide inventory makeup and in some plants can actually prevent I
The isolation condensers (IC) do not provide additional core uncovery.
makeup to replace that lost through the 50RV and cannot maintain the level.
Figure Group 3-3 shows the results for an isolation with a stuck open relief valve with only RCIC available for BWR/6. As shown for the I
plant analyzed, the RCIC has sufficient capacity to maintain the water level above the core.
Figure Groups 3-4, 3-5 and 3-6 show the same event for a BWR/4 and a BWR/3 with only RCIC and a BWR/2 with only the isolation condenser available. Because for these plants the RCIC or IC 3-3
I does not make up the inventory lost through the valve, the water level slowly falls. The depressurization of the vessel due to the SORV and the operation of the IC soon allows the low pressure systems to inject and assure adequate core cooling without ADS actuation. Thus it appears that adequate core cooling is assured by this alternative, but that conclusion would have to be confirmed by a detailed analysis if the modifications were implemented.
3.6
SUMMARY
The current logic meets all of the applicable design and licensing requirements, and in addition the current ADS logic will be sufficient for the events in question when accounting for the high drywell pressure trip resulting from the loss of drywell cooling on low water level.
Each of the four ADS logic modifications provides adequate core cooling by automating vessel depressurization for isolations and SORV events, so all are equally viable from a system performance viewpoint.
l I
3-4 I
4.0 RELIABILTY ASSESSMENT This section assesses each of the first four options described in Section 2 as to whether it reliably actuates the ADS for the events considered, and whether it increases the probability of spurious or inadvertent actuation. The fifth option (ADS permissive if no high pressure system flow is available) was not considered in this analysis since it is concluded in Section 5 that the approach is not feasible. Also included is a discussion of the expected improvement in operator reliability as a result of implementation of the EPG's and improved operator training.
4.1 RELIABILITY OF ADS INITIATION 4.1.1 CURRENT LOGIC With the current logic, the operator is relied upon to manually initiate the vessel depr:ssurization if required by failure of the high pressure injection systems to maintain level for isolations and SORV's. These events are slow, uncomplicated, and well understood, for which the operator is extensively trained and is familiar with both the equipment and the overall system response.
Following the TMI accident, reviews of emergency procedures and operator training indicated that the operator reliability could be improved for degraded situations by providing better guidance and training. The symptom-oriented EPG's were developed as a result of these reviews. The EPG's give the operator the additional guidance required for degraded situations.
Informal demonstrations of the EPG's on control room simulators using both new and experienced operators have shown a significant improvement in the reliability of operator performance under degraded condit' ions. Thus, implementation of the symptom-oriented EPG's and improved operator training in the use of the new procedures results in an improved probability that the operator will depressurize the vessel if required for the events considered.
4-1
In addition, for plants which lose drywell cooling on low reactor water level and satisfy the high drywell pressure trip as a result of the drywell heatup, a backup to operator action is provided.
4.1.2 LOGIC MODIFICATIONS The logic modifications considered either eliminate the high drywell pressure permissive or provide' instrumentation that serves as an alternate to the high drywell pressure permissive for transients that do not pressurize the drywell. This instrumentation can be designed to be more reliable than the operation of the ADS valves themselves.
Eliminating the drywell pressure trip or installing the timed bypass of the drywell pressure trip are simple changes that utilize hardware and instrumentation similar to that used in the current logic. Thus, these schemes have about the same reliability for the transients considered as the current logic has for LOCAs. The suppression pool temperature monitoring system required for the other alternative might be designed to provide roughly the same level of reliability. Thus, the overall ADS reliability is approximately the same regardless of which modification is considered.
l l
4.2 SPURIOUS AND INADVERTENT ACTUATION t
l Fault tree analyses of the various alternatives were performed in order 1
to estimate the probability of unneeded depressurization. These analyzes 1
included inadvertent manual depressurization, false signals, and testing l
and maintenance errors. The results of the studies show that the proba-bility of an unneeced depressurization is not significantly affected by the aoditional modifications to the ADS logic.
Tha crobability of inadvertent operator actuation of the ADS when d? pres-surl:atior. is not nieded 's believed to'be slightly imorouec if the s ten is automated for tne events ccnsidered. The manual inadvertent S
initiation procacili;y is higher for the :urrent ADS logic because the l
cper. :r, knowing he is responsible for manual depressurization, may ce mora aat to err in the conservative direction and depressurize -he vessel.
4-2
I The probability of spurious actuation due to equipment failure or testing /
maintenance error is believed to be slightly greater for the two logic modifications where the high drywell pressure permissive is bypassed or 1
1 eliminated. For the suppression pool temperature permissive option, the probability of spurious actuation is believed to be about the same as that for the current logic.
Because these results are based on conceptual logic designs, it is difficult to precisely quantify these effects, but it is believed that the decrease in probability of inadvertent manual depressurization and the increase in the probability of spurious actuation are approximately offsetting. The overall probability of unneeded actuation is believed to be slightly improved. Thus from the standpoint of inadvertent actuation, all the alternatives are about the same.
4.3
SUMMARY
Each of the alternatives considered reliably actuates the ADS when required, and there is no significant difference between the alternatives from the standpoint of inadvertent actuation.
4-3
5.
FEASIBILITY OF IMPLEMENTATION This section compares the advantages and disadvantages of each of the alternatives.
Included is a discussion of the practicality of each concept, the resources required for implementation, the impact on plant l
operations, and the impact on the overall plant design. A comparative.
s'ummary of the feasibility of each option is presented in Table 5-1.
In this table the current design is used as the basis for comparison.
~
Three major areas are addressed in this study: ADS performance, instal-lation and maintenance, and impact on plant operation.
5.1 CURRENT DESIGN 5.1.1 ADS Performance With implementation of the EPG's, the current ADS logic design meets the intent of the NUREG-0737 item of assuring adequate core cooling for the
--- additional transients considered, and has several advantages.
It is a system with which the operator has had significant training and experience.
In addition, the operator reliability in degraded situations will be improved with implementation of the EPG's, which give explicit instructions on when to initiate the vessel blowdown.
Isolations and 50RV's are slow, uncomolicated, and familiar transients, l
for which the operator is extensively trained and for which he is familiar with both the ecuipment response and the overall system response and behavior. Because af this familiarity, the reliability of the operator j
to perform the ~acuired actions is high, to the point of being reflexive.
Sufficier.t time 00 to 40 minutes) is available to assess the overall plant situatie.c amt initiate blowcown if required.
In addition, the current cmt;.- sitews the ocerator tna. flexibility to control the systems as require] by tN plant cor.ditions :nd symptem3.
5-1
8 O
5.1.2 Installation and Maintenance The current design forms the basis for comparison of the other four l
optiont with respect to installation and maintenance.
5.1.3 Impact on Plant Operation The current design forms the basis for comparison of the other four options with respect to impact on plant operation.
l 5.2 ELIMINATE HIGH DRWELL PRESSURE TRIP 5.2.1 ADS Performance Elimination of the high drywell pressure trip for the ADS is a simple modification that is effective in initiating the ADS if it is needed to l
assure core cooling.
If the high pressure systems are unable to maintain the water level, the ADS is actuated and the low pressure systems provide core cooling.
5.2.2 Installation and Maintenance Implementation of this modification requires only a few simple wiring l
changes with no additional hardware additions. tiaintenance and testing is somewhat easier as fewer trip circuits need to be tested and repaired.
l i
l 5.2.3 Impact on Plant Ooeration The primary drawback to this alternative is that the removal of one of the trip signals results in a slight increase in the probability of l
spurious actuation as a result of improper testing or due to spurious I
signals. This does not present a core cooling concern, since the low pressure systems would provide adequate inventory makeup; however, it does tend to decrease the plant availability, and increase the duty cycles on the vessel and containment due to unneeded depressurizations.
5-2 I
However, the probability of ADS operation when not really needed is believed to be slightly improved. The two effects are believed to be approximately offsetting.
An additional drawback is present in the earlier (BWR/1-3) plant designs having both the high and low pressure ECCS actuated at one common reactor water level. This common actuation level allows the high pressure systems about two minutes to start and restore the water level above the trip setpoint before the ADS is actuated.
If the level is not restored before the ADS timer times out, the vessel is blown down. The RCIC and isolation condensers for these plants are sized to prevent core uncovery for isolations, but they are not large enough to restore the level above the initiation setpoint and reset the ADS within the allotted two minutes.
Thus, with an isolation and loss of high-capacity, high pressure makeup, the RCIC could bring the water level under control and ADS would not be needed; however with this modification ADS would occur unless manually defeated.
Requiring it to be manually defeated is undesirable from the human engineering standpoint.
5.3 BYPASS HIGH DRYWELL PRESSURE TRIP 5.3.1 ADS Performance This option is essentially the same as the preceding one, however, the addition of the delay in bypassing the high drywell pressure trip gives the high pressure systems additional time to recover the water level and reduces the enance of undesired ADS actuation described earlier for BWR/1-3s.
Two variations are considered, one with the bypass timer started at scram water lavel and one with the bypass timer started at the icw pressure ECCS initiation level (Level 1).
5-3
The scram water level trip has the advantage of actuating,^.DS before the core is uncovered and thus minimizing core uncovery. However, since transients resulting in the water level dipping below the scram water level are fairly common, the ADS system would be challenged more frequently than with the lower level trip. An increase in the probability of spurious actuation would thus result. Starting the l
bypass timer at the lower water level (Level 1) does not present this proolem and will provide the operator additional time to assess plant conditions while still providing adequate core cooling; however, the likelihood of core uncovery before ADS actuation is increased.
It is judged that starting the bypass timer at low water level (Level 1) is preferred.
5.3.2 Installation and Maintenance The cost of this modification is low with the installation of the necessary hardware easy to perform.
The additional maintenance and surveillance is minimal as the system does not have complicated interfaces with other systems.
In general this alternative is very similar to the preceding option.
5.3.3 Imoact on Plant Operation The impact on plant. operation is about the same as that presented for -
l the previous modification. However, the addition of the bypass timer gives the operator additional time to initiate the high pressure coolant injection systems, and thus precludes unnecessary vessel blowdowns.
1 5-4
5.4 SUPPRESSION PU! TE"1ERATURE TRIP 5.4.1 pS performance The major advantage of adding a suppression pool temperature trip in parallel with the high drywell pressure trip is that a rise in suppres-sion pool temperature is indicative of an inventory loss from the reactor coolant system, analagous to the high drywell pressure signal.
Since a rise in suppression pool temperature is virtually assured for isolation and SORV events, this option automates vessel depressurization for these events while including a permissive signal in the ADS logic which would reduce the likelihood of spurious ADS actuation relative to the second option (elimination of the high drywell pressure trip). The advantages and disadvantages of that option are thus applicable here, particularly the problem of p.ecessary ADS actuation for the earlier plants.
In addition, the additional hardware required for this option is complex, reducing the reliability of this system to perform on demand. The suppression pool temperature monitoring and averaging equipment must be precise anaugh to measure the relatively slow pool heatup in order to give the ADS a permissive signal and actuate the ADS in a timely manner.
Variations in suppression pool mixing as a function of SRV discharge !
location and RHR operation raise the possibility of the temperature monitoring system " missing" the local temperature rise resulting from an SORV or detecting a non-representatively high local temperature.
Operation of the pool cooling during the initial stages of the transient does not, however, affect the initial heatup rate of the pool due to the low temperature differen.es across the iiHR heat exchangers.
In section 2.4, two approaches were suggested for proviaing the pool tamperature permisiive; measucing the pool temperature neatup rate or giving the oermissive = ce the pool temperature rezches a specified value. :teasuring the pool heatus rate recuires acd1tienal harcware c:mparec to the assoluti trip. The rate measuruent trip is less reliaole than the absolute trip, hcwever the rate measurement auts.,atically 5-5 y
.-,_,w
_ = _.
compensates for normal changes in the pool temperature. The rate measure-ment scheme can be adequately and reliably approximated by the simpler absolute trip by periodically resetting the trip to reflect a predetermined temperature difference above the actual pool temperature. A detailed analysis would have to be performed to determine an acceptable temperature rise or rate trip.
5.4.2 Installation and Maintenance The temperature measurement concerns expressed in the previous section could be reduced by installing a large number of temperature sensors and i
sophisticated averaging and monitoring equipment. Such hardware would be very expensive to purchase and install. Maintenance and surveillance testing would be complex and would increase exposure to maintenance personnel.
5.4.3 Impact on Plant Operation Due to the complexity of the system, its overall reliability is judged to be somewhat lower than that for the other options. Though this l
concept is an indication of inventory loss, this benefit is far outweighed by the disadvantages of implementation and operation.
5.5 NO HIGH PRESSURE SYSTEM FLOW 5.5.1
$5 Performance The measurement of high pressure system flow gives a fairly direct ind'
,n of the unavailability of inventory makeup flow. A lack of high pressure makeup flow would in effect verify the falling water level indication in the vessel.
In addition, this alternative does not cause the undesired ADS for the earlier (BWR/1-3) plants when the RCIC or isolation condenser are working but do not clear the ADS water level trip.
If high pressure injection systems are operating, the ADS logic would not be initiated without a high drywell pressure signal.
The high 5-6
pressure systems for these plants, however, must start up within two minutes in order to prevent ADS actuation, because the high pressure ECCS and ADS use the same water level initiation setpoint. This time limit effectively eliminates any chance the operator has'of restarting the high pressure systems and thus increases the chance of needlessly actuating the ADS.
In addition to the limited time this concept gives the operator for restarting systems, the flow measuring system is vulnerable to a high pressure system pipe break or incorrect valving downstream of the measuring point. The flow would register and no permissive signal would be generated, even if the water was not reaching the vessel. Themajordisadvantages of this option are the difficulty of determining a priori what the proper flow criterion is, and the difficulty of measuring such low flows in high flow systems.
For example, only about 3% of rated feedwater flow is required to maintain the reactor water level for isolation and SORV events.
It is difficult to accurately and reliably measure such a small flow using devicer that would not interfere with normal operation.
In addition, HPCI or HPCS normally cycle on and off as required to maintain the reactor water level.
Because of the high capacity of these systems, the water level is quickly restored and the "off" cycle is long compared to the "on" cycle, erroneously initiating the ADS sequence.
Thus the flow measurement scheme has a low probability of producing a true signal that reflects the availability of the high pressure systems.
- 5. 5. 2 Installation and Maintenance The other drawbacks of this alternative are the high cost and difficulty of installation of the hardware required for the flow measurement.
Auditional flow taos would be required to bring the present flow indications ut to safety grade requirements. Maintenance and surveillance vould be ccmoaratively difficult.
5-7 L
5.5.3 Impact on Plant Operation The reliability of the system would be governed by the reliability of the flow measuring instrumentation. The reliability of the syster might or might not be improved by inferring the lack of flow from pump operation andinje:tionvalvepositioninsteadofmeasuringflowdirectly. Spurious operation of the ADS would be more likely since for every loss of feedwater transient, the ADS sequence would be initiated for a short time during the beginning of the transient before the high pressure ECCS have been signaled to start. The ADS sequence would also be reinitiated during the subsequent cycling of the high pressure systems as they maintain reactor water level. Because of these impacts on plant operation, and the cost of installation, this option is less desirable than the first four. For these reasons this option was not addressed in Section 4.
5.6
SUMMARY
Based on the above study, the first three concepts presented (the current logic, eliminating the high drywell pressure trip, and bypassing the high drywell pressure trip) are viable options for the ADS design. The current logic, though it does not explicitly address the NUREG-0737 item, meets all of the applicable design and licensing requirements.
The operator has sufficient time to assess the plant conditions and manually depressurize the vessel if warranted.
In plants which lose drywell cooling on low reactor water level, ADS operation will. occur without manual action for isolations and 50RVs.
The fourth option (the suppression pool temperature trip) provides no additional benefit as to i
the reliability of ADS initiation for the events considered when compared to the other options and add needless complexity to the overall plant design and operation. The fifth option (the high pressure system flow measurement) is not recommended because of its impact on plant operation.
5-8
The second option, eliminating the high drywell pressure trip works well for BWR/1-6. The third option, the bypass timer, is suited for BWR/1-3, with the timer started at the ADS water level initiation setpoint. The timer should reset when the water level trip clears. This alternative is also suitable for BWR/4-6; however, the bypass timer should not reset once it has run out. Starting the timer at low water level rather than at scram water level is recommended.
Either of these options is a low cost, easily implemented means of automating vessel depressurization for outside breaks, isolations, and SORVs if required.
I i
1 e
e l
5-9
6.
CONCLUSIONS The intent of the NUREG-0737 item is to provide more assurance of adequate core cooling in the event of transients and accidents not producing a high drywell pressure signal (e.g. isolation, SORV) under conditions such that high pressure makeup systems are unable to maintain reactor inventory. The intent:may be satisfied in two ways: the ADS logic may be modified to automate the depressurization for these additional events, or the operator may be given specific guidance and training for performing manual actions under degraded conditions.
This second course of action has already been undertaken with the implemen-tation of the symptom-oriented Emergency Procedure Guidelines. The transients considered are slow and well understood, and the operator has sufficient time to assess the plant conditions and initiate the depressuri-zation.
In addition, it was shown that for plants which lose drywell cooling on low level, the current logic will act as a satisfactory backup to manual action for the events in question.
Afeasibilitystudyof!possibleADSoptionsshowedthatofthefive alterratives presented, the first three (the current design with imple-mentation of the EPG's; eliminating the high drywell pressure trip; and bypassing the high drywell pressure trip after runout of a timer started at the low pressure ECCS initiation level) were the most viable. The fourth option (a suppression pool temperature trip in parallel with the high drywli pressure trip) is also feasible; however, the added complexity I
of the system provides no additional benefit as to the reliability of ADS actuation when compared to the first three options. The fifth option (bypassing the high drywell pressure trip if low flow of high pressure injection systems is indicated) was shown to be impractical.
Of all the alternatives, addition of a bypass to the high drywell pressure trip if reactor water level remains below the low pressure ECCS initiation setpoint for a sustained period, or elimination of the high drywell pressure trip, are the preferred solutions.
6-1
This report does not attempt to demonstrate the absolute reduction in plant risk due to the ADS modification, although it is believed that a reduction will be achieved. The ADS modification is proposed because it provides more assurance of core cooling in the event of isolations, it brings the automatic system operation more closely in line with the Emergency Procedure Guidelines, and it does not increase the probability of rapid depressurization if such is not needed.
It is stressed that detailed implementation will require consideration of broader scope issues, such as the final resolution of ATWS (which may affect the ADS logic, and which is specifically not considered in this study).
l m
w m.
e 6-2
HIGH DRYWELL PRESSURE SEAL
=
IN e
LOW WATER. LEVEL (LOW PRESSURE ECCS ACTUATION) 7 CONFIRM WATER LEVEL IS BELOW SCRAM LEVEL v
120 SECOND ACTUATION TIMER
ADS ACTUATION s
- 12G SECOND ACTUATICN TDtER WILL RESET IF LOW WATER LEVEL TRIP RECOVERS BEFORE IT tit'ES OUT. THE TIMER WILL RESTART IF THE LOW LEVEL SIGNAL OCCURS AGAIN.
FIGURE 2-u CURRENT ADS LOGIC FOR A TYPICAL BWR
LOW WATER LEVEL (LOW PRESSURE ECCS ACTUATION) v CONFIRM WATER i
LEVEL IS BELOW SCRAM LEVEL u
~
120 SECOND
~
ACTUATION TIMER
ADS ACTUATION
- 120 SEC0t10 ACTUATION TIMER WILL RESET IF LOW WATER LEVEL TRIP RECOVERS BEFORE IT TIMES OUT. THE TIMER WILL RESTART IF THE LOW LEVEL SIGNAL OCCURS AGAIN.
FIGURE 2-2: FIGH 2RYWELL PRESIURE TRIP ELIMINATED
HIGH DRYWELL SCRAM PRESSURE WATER-LEVEL SEAL
=
IN g
LOW WATER LEVEL F
(LOW PRESSURE
.8 MINUTE ECCS ACTUATION)
BYPASS TIMER **
y CONFIRM WATER LEVEL IS BELOW SCRAM LEVEL u
120 SECOND ACTUATION TIMER
- 120 SECOND ACTUATION TIMER WILL RESET IF LOW WATER LEVEL TRIP RECOVERS BEFORE IT TIMES CUT. THE TIMER WILL RESTART IF THE LOW LEVEL SIGNAL OCCURS AGAIN.
- RESET SAME AS 120 SECCfiD ACTUATION TIMER.
FIGURE 2-2A*
ADO DELAYED BYPASS OF HIGH ORYWELL PRESSURE TRIP WITH BYPASS TIMER STARTED AT SCRAM WATER LEVEL
}
e HIGH DRYWELL LOW WATER LEVEL PRESSURE (LOW PRESSURE
_ECCS ACTUATION)
SEAL SEAL IN g
IN**
LOW WATER LEVEL 8 MINUTE (LOW PRESSURE BYPASS ECCS ACTUATION)
TIMER ***
u CONFIRM WATER LEVEL IS BELOW SCRAM LEVEL o
120 SECOND ACTUATION TIMER
ADS ACTUATION
- 120 SECOND ACTUATION TIMER WILL RESET IF LOW WATER LEVEL TR P RECOVERS BEFORE IT TIMES OUT. THE TIMER WILL RESTART IF THE LOW LEVEL SIGNAL OCCURS AGAIN.
SEAL IN FOR BWR.'4-6 ONLY RESET SAME AS M0 SECOND ACTUATION TIMER FOR BWR/1-3 ONLY FIGURE 2-3B: ACO OELAYED s'l? ASS OF HIGH DRYWELL PRESSURE' TRIP WITH SfPASS TIMER STARTED AT LOW WATER LEVEL
\\
SUPPRESSION POOL S E TEMPERATURE INCREASE SEAL
=
IN 9
LOW WATER LEVEL (LOW PRESSURE ECCS ACTUATION) y CONFIRM WATER LEVEL IS BELOW SCRAM LEVEL v
120 SECOND ACTUATION TIMER *
' r LOW PRESSURE ECCS PUMPS RUNNING 1
ADS ACTUATION
- 120 SECOND ACTUATION TIMER WILL RESET IF LOW WATER LEVEL TRIP RECOVERS BEFORE IT TIMES OUT. THE TIMER WILL RESTART IF THE LOW LEVEL SIGNAL OCCURS AGAIN.
FIGURE 2-4:
A00 SUPPRESSION P00L TEMPERATURE INCREASE TRIP IN PARALLEL WITH HIGH ORYWELL PRESSURE TRIP
HIGH DRYWELL PRESSURE NO FEEDWATER FLOW SEAL F:
IN LOW WATER LEVEL IP (LOW PRESSURE NO HPCI/HPCS ECCS ACTUATION)'
FLOW 1r NO RCIC/ ISOLATION I
CONDENSER FLOW CONFIRM WATER LEVEL IS BELOW SCRAM LEVEL NO CONTROL ROD DRIVE FLOW v
120 SECCND ACTUATION TIMER
'r ADS ACTUATICN
- 120 SECOND ACTUATICN TIMER WILL RESET IF LOW WATER LEVEL TRIP RECOVERS BEFORE IT TDIES CUT. THE TIMER WILL RESTART IF THE LCW LEVEL SIGNAL CCCURS AGAIN.
- MAY 3E DESIRASLE TC ADD FOR BWR/1-3 3vPASS CSH DRYWELL MESS' RE TRIP IF N0 HIGH PRES!i1RE J
FIGURE 2-5:
MAKEUP SYSTEM FLOW IS AVAILABLE
I BWR/6-218 SORV LOH PltESSullE SYSTEMS i
g,p i SYSTEM PRESSUFE x10' i
0.8
\\
cc t
I
- 0. t1 LLl (E
i D
LO i
i LO Ltj l
CC (1-i i
0.
i i ' t I i i i i_
sin
-2 0.
0.6 1.2 1.8
- 2. 4 =10' TIME
( SEC )iFIGURE 3-1.I ISOLATION Hilli SoliV. lod Pi?ESSuiiE i
AI)S ACTUATION '
SYSfEMS AVAILAULE'EVFl. OllE IO l.1ItillTI:S AI;Tl:l? I
s 2
e 2
l 2
BWR/6-218 SORV I U's l>i EsSullE SYSTEMS 60.
i LEVEL INSIDE SHROUD 2 LEVEL OUTSIDE SHROUD f
i r)
I T
1 1
ilo'
\\i'
\\,
'x 1
N
!~
w y
w
_1 LLI 20.
l ui 1
sag ic LIJ l___
Cl:
'~
Z
' O. 1 J__i._ L u._ a _
m 2
O.
0.6 1.2 1.8
- 2. 4 = 10' til UUitE 3-1.2 iSol.Al' lull HITil S0ilV. Lori PetESSuitE SYSTl!MS AVAl.l.Aul.E. ADS ACTUATIOli in..orierrim
- rro s tarrt otti:
)[
BWR/6-218 f
SORV LOed I'llESSuitE SYSTEt4S g
i FEEDWRTER x10' y 2 BCIC 3 LPCI LPCS
=
s SRV
~
1.-
U LLI U)
N
>Z CCI
=
__1 i
m LLI 0.5
-)
17 5
CL CC Z
E3
__1 LL i
O.
' ' ' ' l
s'
'8 is a
's 2
is 2
s a
s 2
sm.
-22 0.
0.6 1.2 1.8
- 2. Lix10 TIME
( SEC ) FIGuitE 3-1.3 ISOLATION d!'D' SORV LO.1 PRESSui(E SYSTEMS AVAILAULE, ADS ACTUATION '
in eiimrrp: n I: ri:st i F V F I nilF
a 2
7 BWR/6-218 SORV i
Lthe PitESSuitE SYSTEMS ggg),
i SlEAMLINE 2 ROS ij 3
SORV l
i 3
Il00.
U LLI (n
s s I
(n 3
3
.- I v
Lu 200.
'4 x
E
~
3 2.
c3
~~
\\
__J i
l LL.
~
~
O. '- L i a L L'ii L.L.. L i
2 i
i i
i we i
-2 0.,
0.6 1.2 1.8
- 2. tl=10' TIME
( SEC ) soune a-i.4 iSourion innu So,<v, um enessuae SYSf.F1I.S AV Al. l.Alst.EI ri DS,,A C..TuATI Ori A
in -
ii er -
ri..
i-
BWR/6-218 sonv Lou PitESSuuE SYSTEMS i
x10) i NAT CIRC THRU JET PUMP 1
l 4.
(_)
LLI I
Cn L
i
- E L
i al i
I
" h
- J- ' 4A L-Lu 0.
li l-G-
CC i
i r
~
f-5
['
g!
_.J LL
_y, iiiiliiii l
i i
we 2
0.
0.6 1.2 1.8
- 2. 4 x10' TIME (SEC)soune2-i.s isouvion nim soav, toa mssuae SYSfEMS AVAILAULE, ADS ACfuATioti in esernrrr.-. rvn.,rore nur
BWR/6-218 SORV l,2 Loef PilESSuilE SYSTEMS alu' VESSEL TOP e FEAD i
2 FUEL 9
0.8 u_
tb t.tj 2
1 i
~
l.i..I cr-
- D 0. 11 i-CC 2
2 2
CC UJ 13 -
lij n
F--
~
I 1 -.1-_1 _i O.
i i i i
=c
-2 O.
0.6 1.2 1.8
- 2. Lix10' TIME
( SEC )l'IGullE 3-I.6 ISOLATION sifill SORV LO.i PRESSuitE SYSTEMS AVAILAllLE, ADS ACTUATION t o H r oit rr - a r rri. t riert o. ie -
BWR/6-218 SORV 600.
Lon pusssuaE sysTEas i 00HNCOMER 2 LOWER PLENUM g
l
'2 iy i
'l i
1100.
x-CD i
i
.__I l
N i
_J t-CD i
200.
a_
__J w
i CE i
I_
g -.
2 Z
LLI 3
2 2
- 0. ' t i i i l -i i i i m
0.
0.6
'.2 1.8
- 2. 4 =10' TIME
( SEC ) FIGURE 3-1.I Is0LATION HITil SOHV, Lod PilEsSUHE 7 8 I,Ilhrh A{}4}$Elr^th bk"^
Y
BWR/6-218 scav 3
1 3
3 i
Loes,l'IfESSdRE SYSYEMS
},
CORE 2 LOWER PLENUM 3
SORV t
i O.G 4
i i.
I 0.2 l-j
~
t
}
_I 2.. - _ -- -. ~ I._
. h 3
2 CL.
_,,g gg y
3 g y
3 g y
3 g y
D O
LJ._l..d
-0.2 I I i I I WE
-2 j
0.
0.6 1.2 1.8
- 2. L1=10' TIME
( SEC ) glouae 3-i.s isouriou una s<wv, ton enessowe, 1
SYSTEMS AVAILAULE, ADS ACTUATi(W l
=_.
9 e
BWR/6-218 sOnv
[,p Lon PetESSdifE SYSTEMS x10' i SYSTEM PRESSUFE e
i 0.8
\\ S CE
~
U3 CL
- 0. tl i
ltJ tr D
U3 U's
~
1.L1 CC
~
(L i
i i
i i
~
0.
i i i i l n'
- i i i_
wo
-2 0.
0.6 1.2 1.8
- 2. tl=10' TIME
[ SEC ] suunE 3-2.i
.1Souriou unu souv, u>.. euESsui,E SYSTEMS AVAILAfiLE ADS PERMISSIVE ft fif t!IITpq aprir,s <:bos is t i:uri
~
3
~
a mm a=
E m
=>
ao C
$m*"*
O C~
cr
- mm a =e
=. m_
=s 3
m 4-
)
W OJ g$
^
'A Wa co
>. a-e W -D
.2 in 0
=
M F-
,e za n;
c.
s -o sw n
o to
= a _.,
=
wuW
=<
c
~~ W W d
w c-1 x,<
z<
cem
~
C3 0-m
. -=
<m y l=*
i
_m m >=
=M e.
.n
.,,n
. :2
.=
30
~
l
.i m
o uJ to l
e 1
Ej g's Lu r
j/
r
=._
J
_i l
/
- -)
~
e./
i
/
f l
,,,l.,,,_
.C C
o O
C C
O N
i I
.A O l
?
1 g
I
.a s
BWR/6-218 SORV k
uw paussuRE SYSTEMS i
l.5 i FEEDWATER x10' 2 BCIC i LPCI
1.
L)
LU (n
N I
03
=
=
=
__I J
LU 0.5 f
E CC Z
CJ
__.1 LL I" ' 's t i *
's 2
is 2
is 2
is 2
is 2
5m i s
-22 O.
i i 9 i 0.
0.6 1.2 1.8 2. 11 : 1 0 '
TIME
( SEC ] rioune 3-2.3 isotmon,uui soav, uw ei,eSsui<e SYSTEMS AVAILABLE, ADS PERMISSIVE
,,,c.,
,, r,......,
e e...
O
?
M 98 WW m
=>
Q 3 *=*
fA D m
= ZM fn 2
W~_
c: E T
b b
CO to e c.c O
J *A
~
fn
.53 N
W.Z p
c:
l T <
3 J a
O WL Q
- M g
(n J
'n
\\
W C
=0 L
L'.J (A CC
$.<.J F C>
- 3. H-Q O
~'
3 (A C (n T CC m<-
o C (D 3-m
=Nt
~
m CO O. m *'-
- I r
<W; e
3%~
O tn :
to >=
.-. (n :
W
'N 1m m
w=
Q l
N C
=
m u
g (D
e ma U.J l
6 l
n C6 g
~
1 a.
r
.~
1 l
-I e/
7
?T
~
,,I,,,
i
- a 1
m O
o O
l
=
O O
l E
N
~
1 1
/
l
~
~
BWR/6-218 SORV Lod PilESSullE SYSTEMS 8.
i NAT CIRC TifRU JET PUMP x10' 4.
U LLI co
(
N s
i
%Z I
I CO
__J i
W
- A
. j y-I{!
LaJ 0.
)
0-
'h
%)
CC j'
)
I i
i 2
i c)
' a
_i v
i i
~
-11.
i i i i l"i i i i m
-2 0-06
- 1. 2 1.8 2 4x10' TIME
( SEC ] aouue 3-2.,
isourion anu souv, tod r,essuae SYSTEMS AV AILAulE. ADS PEltNISSIVE
- r. e..- n i i. t cuni
I 7
g gg ei
- 7. m 2>
Q llll3 =
Oc 7n
.n U1 UJ 22-
- A
,a OJ
$,N
'G e
31
CO
>0 3 :n -
(4
<w C 2.
~
(N sO s.c
- < =
l 3
CWV n
3 m
(,,0
'A uJ, _.i at w
u
=<-
g "3
NUF C C >
O t.:!
- 'i ua a g-c 2 > u-0 O 2 < *.*
CO 3
O s
O v'.,'a ce I"* 3 ~
~
<w-y9-
_m:
U". > =
. m ".
~
o.
e.
tM in 8
n2 n
- -* m U
LLJ n
w
/
LLJ E
O n
i L
I a
i I I t t t I t i
m
(\\1 C")
=*
- C
.a O
a O
O
=
o (J 020) 26'n16'd2dW21 1
.i.'
jj A
~
2 iN F
l S
R Ml.
M e Ril x_.
2 2
E EV T
w PF S
M i
8 Y
U tS S
N
.DM 1
AA RE v
R E
2 EL R
R g.
SCR Ut i
E NE 2
i A.:I i
/
g T lT pWW i lF RV OO w AA WR nDL V
O o
n Ai '
BS L
8 o I:
i2 i ST T Mt
~
t
't i i
1 A Er t o Sn SY Sh 2
i i
2
-3 2,
ERu L
o 2
ig i) v C
E i
S
(
i E
i M
I 6
=
T L0 x
IL
~ ~ -
'O O
0 0
0
'0 0
0 2
1 6
1
>L_CI ZU I_E
~ Ea1NDt D-I L
c C
i;< :i
BWR/6-218 SDRV i
}'
Lon PHESSullE. SYSTEMS 3
3 3
i CORE 2 LOWER PLENUM 3
SORV
~
0.G 0.2 i-
.-4 3
_}
-1 2
2
,d _ 2
- f.,
1 2 3 1
2 3 4
2 3 1
2 3 1
2 CE
~3
,.3 l
-0. 2 L LLI. l LJ LL
~'
O.
0.6 1.2 1.8
- 2. tix10' TIME
( SEC ] grounE 3-2.8 isourion wim soav, toa PnessoaE SYSTEMS AVAILAULE, ADS-PEllMISSIVE l
e BWR/6-218 SORV RCIC AND LOW PRESSURE SYSTEMS 1 3 xi d3" i SYSTEM PRESSUFE l
0.8 CE U7 O-g i
i O 11 I Ll O
tg l_tJ f.T-0 1iiii o,
i i i i m
-2 0.
- 0. 6 1.2 1.8
- 2. tl =10' FIGUHE 3-3.1 ISOLATION WITil SOHV. itCI C AND LOW PatESSURE SYSTiiMS AV All.Aist.E, fl0 ADS ACTil ATruti
BWR/6-218 SOflV RCIC AND LOW PRESSURE SYSTEMS tid.
i LEVEL INSIDE Elifl0UD 2 LEVEL OUTSIDE SHROUD 110*
i-
~~
- N
%w.hsjsvvw M ws&=s.
^ :'^" = ?"^ = ?=' S
~
- ' Q __ wa l-LL.
ThF
__1 LLj 20.
LLI
-- I E8P CC
- l. L.}
i-CE
~
Z
~
0.
1 I..L.s.. L l. L L L-un
-2 0.
0.6 1.2 1.8
- 2. 4 =10' TIME (SEC)
F I GU RE 3-3. 2 ISOLATION nITil SOHV,tiCIC AND LOW PiiESSURE SYSTFHs AV All Asil F fl0 Alis ACTil ATinti
f
~~
BWR/6-218 SORV 1.5 RCIC AND LOW PRESSURE SYSTEMS x10' i FEEDHATER 2 HCIC 3 LPCI
L)
LU LO N
I CO
_J m
Lu 0.5
}-
C LT Z
i-g
.__.1 LL
-2 2
2 2
2 2
2 Iiiia O.
1 in ui i ie ie ie ie ie s<e i -s 0.
O.6 1.2 1.8
- 2. Ilx10' TIME (SEC)
F1uune 3-3.3 ys3g;,r,r or),,i,1 } p),spilv,3,y er e Agg,,131rl,y,ilESSU RE
BWR/6-218 SolW RCIC AND LOW PRESSURE S(STEMS
(;00 ~
SlEAMLINE i
2 ADS 1
SGRV i
110 0.
U l.L]
LO N
Z CD
_1 m
.i LtJ 200.
'\\
CE s
cr 9
s q
IL i
3 3
3
^
0.
L_1.h. U. l '..L L_L J _
i 2
i i
2 i
2 l
2 istC
-3 0.,
0.6 1.2 1.8
- 2. ll = 10' TIME
( SEC )FIUuetE 3-3.4ISOLATION WI'0l SOHV, WCIC AND LOW PRESSURE,
SYSI'liMS AV A ll Alli.fi, HO AOS ACTil ATION
$n a.
m tu
~
z
']
- m. =
. O esu. =. =..
m (L
T3~
m
-~
a g
m
-. a
,-~
p 3
~
n
[
oe w
a z
=_
C o-p-
w l
N u
E-c-
-=
C
=
I l
C.O u
OW
\\
x
=
m_
o
=
=-
h e
i l
s U'
$=* N
-(*.!
~
x-
--- [
]
~m
.L
- 3
.=
(
3
~
0 C.)
LLJ LO NN u_;
r
(
~
D.H
-+
_a 1
,,,,i,,,,1.-
-s
.a 5
(J35/W8i) 2169 MO l.d
BWR/6-218 SORV RCIC AND LOW PRESSURE SYSTEMS I
- 1t9
~
VESSEL TOP e FERD 2 FUEL 0.8 LL (3
Ld C
i i
i i
i i
Id 2
n:
2 2
~J 0. 11 2
i.-_.
T ir i.o O__
lb i.__.
O.
i a J l '1 i i i m
_2 D.
0.6 1.2 1.8
- 2. tix10' TIME
[ SEC 6 oui <e 2-3.6
- g g ;o g tii,,gi<v,3ngggg,,gegi,essui,e in n
BWR/6-218 SORV RCiC AND LOW PRESSURE SYSTEMS G00.
i 00HNCOMER 2 LOWER PLENUM 4
82 42 l
12 1.!
1100*
i2Nw?
i L j
__i N
t D
t-ca 200.
L1-
_1 CE I
i t--
g 0'O. ' ' ' ' I"' ' ' '.6
~'
0 1.2 1.8
- 2. tix10' TIME (SECJeroui,e3_a.7 isntArion nirii. soinv, acie Ano tow e.,essuae SYSTEMS AVAILAtil.e, No ADS ACftlATroH
BWR/6-218 SORV RCIC AND LOW PRESSURE SYSTEMS 3
a 3
3 3
a s
3
)*
i COHE 2 LOHER PLENUM 3 SORV I
0.6 i
I 0.2 I-i -,
.-_j bL I ?
i2 ia i2 2
i 2
2 1-G_
- 0..'
._t i
SAFE
-2 0.6 1.2 1.8
- 2. tix10' TIME
( SEC )FIGUHE 3-3.8 ISOLATION WITil SdRV, HCIC' AND LOW IMESSURE SYSTEMS AVA!' LADLE, NO ADS ACTU AT10tl
BWR/L1-218 SORV RCIC AND LOW PRESSURE SYSTEMS x163 i SYSTEM PRESSUPE t
O.8
^
i G:
t_,
Ln 11-i
- 0. tl s
tu OC i
D u3 s
1.d tr g
t l :i i i i im:oa-O.
i i ii we O.
0.6 1.2 1,8
~2. 4 =10' TIME (SEC)
FIGURE 3-4.1 ISOLATION WI Til SORV'. RCIC AND LOW PRESSURE
< */ r.11 f t e Att A t t P f t (*
IN1 9 f ie.
4 P ille f i'it t e-
BWR/L1-918 SORV i
RCIC AND LOW PRESSURE SYSTEMS l
60.
i LEVEL I NSIDE SHROUD 2 LEVEL [ luTSIDE SHROUD l
l i
0 t10*
N'
^
ngi
[
2
,o LL 4
TAP 1
i 1.L I 20.
LU
--J one cc L L1 t-CE
- I S
i i i l *i i i i n.J M l
0.
I i
0..
0.6 1.2 1.8
. 2. 4x10*
TIME
( SEC ) FIGURE 3-4.2 ISOLATION WITil SORV, RCIC AND LOW PRESSURE SY*;Ti~fis Ava ll API F tio Ans ACTilATints
e BWR/ l-218 SORV
)
1.5 RCIC AND LOW PRESSURE SYSTEMS x10' i FEEDdRIER 2 HPC I s LPC I
1.
L)
LtJ (n
l N
I LD
_J m
i LLI 0.5 i-CC m
i z
EJ 4
._j i
- 0. I L i ai i I i 7
'4 525 i
e is=
i s e i
s e i
s sue
-a 0.
0.6 1.2 1.8
- 2. 4x10' TIME (SEC1' FIGtJRE 3-4.3 ISol All ott 411 T81 SORV. RCIC AtlO i nti PRFSStlRF
BWR/L1-218 SORV RCIC AND LOW PRESSURE SYSTEMS 600.
i STEAMLINE 2 ADS 8
SORV t100.
L)
LLI Ln N
I CD
__J l
LtJ 200. b i-CE t:C 3
~
C) 3 (f
I s
)..,-
O. I ' ' ai. i l ;i i i i a
" ' Fi' -
i 2
i 2
i 2
i 2
sue 2
O.
0.6 1.2 1.8
- 2. tix10' TIME
( S E C ],,eese
,so<,1,o,,,1,i so. oc,c
~o <ow reessone
BWR/4-218 I
SORV i
i RCIC AND LOW PRESSURE SYSTEMS j
x10' i NAT CIRC THRU JET PUMP l
l i
4.
U LU v3 N
E C
ltt
,g g
g i
g i'
._J i
I v
3 l
8 I
I g
I I
i iti g
t-
'[
hil,fk I
l T
r
'l 1
LU 0.
I CC t
+
Q~
}
{
2 tJ o
{
~
-y.
i i i i l :( i q,,',,,
i i O.
0.6 1.2 1.8
' '. 2. 4x10' TIME (SEC)
FIGURE 3-4.5 ISOLATION WITH SORV, RCIC At40 LOW PRESSURE SYSTEMS AVAllAlt!F, tio ADS ACTilATlota I
BWR/L1-218 SORV l
RCIC AND LOW PRESSURE SYSTEMS i
l 1.2 i VESSEL TOP e HERO
- x10, i
2 FUEL
~
0.8 em L1_
LD LtJ 2
f3 N s_
i i
i i
N ItJ 2
LC A
3
- 0. ll i-s CE iC L1J n_
L1J g_.
~
O.
' ' ' ' l
"gb# '
5"'
-2_.
0.
0.6 1.2
- 1. 8,
. l2. Llul0' 4
TIME
( SEC ) FIGURE 3-4.6 ISOLATION WITH SORV, RCIC AND LOW PRESSURE-
'1-
.6 F.YMirMn ava t i e r'i r om a r e-a r Tit a v e ~'
1
BWR/L1-218 I.
SORV RCIC AND LOW PRESSURE SYSTEMS GOD' l
i DOWNCOMER i
2 LOWER PLENUM 2
12 12 2
t100
- N
^
4 I
CD
__J N
]
i i-co 200.
CL
__J CE
- C p_.
z t1J
- 0. - i i i i l ii i i i l
~
m 0.6 1.2 1.8
""2. 4 x10' D.
TIME
( SEC ) FROURE 3-4.7 ISOLATioH WITH SORV, RCIC AND LOW PRESSURE SYSTEMS AVAlt_ABLE, HO ADS ACTUATICH
.s BWR/l.1-218 1
SORV RCIC AND LOW PRESSURE SYSTEMS 1.
3 3
3 3
s CORE 2 LOWER
'LENUM s Sony-i i
i 1
i 0.6 4
i i
0.2 I-
_j I
,_2 2
l 2
1 2
1 2
i CE
- .3
~
L4
~
0 I;.
i
~
-0.2-t Lt i O.
'.6 5'"
0 1.2 1.8 2. 11 : 1 0 '
FlOURE 3-4.8 ISOLATION WITH SORV. RCIC AND LOW PNCSSONE SYSitMS AVAllAhlF. tan AOS Af' TilA T i nts
)
l BWR/3-251 SORV RCIC AND LOW PRESSURE SYSTEMS x10,2 1.
i SYSTEM PRESSURE I
i l
1 Ir 0.8 I
~.
i (n
m i
tu N
CC D
r i
Ln 07 Lu cc CL.
i
~ ' ' ' ' I 'I ' ' '.
0'O.
1 2.
3.
- 11. x10' FIGURE 3-5.1 ISOLATIOtt WITH SORV, RCIC AND l.OW PRESSURE SYSit'M9 AVA ll Alif f. i t'1 8M w TO*T'n"
BWR/3-251 SORV RCIC AND LOW PRESSURE SYSTEMS 60.
=
i LEVEL INSIDE SHROUD 2 LEVEL OUTSIDE SHROUD 2
2 1
40.
me-i t<
'. - EQ i::$:-M.a Tw J
l L1J 20.
LtJ
__J BM CC L1J 1
i-l CC
~
0'O.
SAFE
-2 1.
2.
3.
4.x10' TIME
[ S E : )
,,ou-...,
isom1 ~ m io..... ci c Amo <- e-So-SYSTEMS AVA,1.ADIE. NO ADS ACTelATION
BWR/3-25' SORV j
RCIC AND LOW PRESSURE SYSTEMS 3
U LLI cn Nr CD
_J i
Lt1 0.S i_
cc I
Cr-i L.-s s
A l
~
2 2
2 2
2
- 0. ir ' l l '" ' '
- 5 I"
'S
'5
- s
' l' 5
5"' ' 2,
-2 s 0.
1.
2.
3.
Lt. x10' ff f
b ) FIGURE 3-5.3 ISOLATION WITH SORV, RCic AND LOW PRESSURE SYSTEMS AVAll Atti f, fl0 An'i Acitf 4 Tints
BWR/3-251 SORV RCIC AND LOW PRESSURE SYSTEMS 600.
=
i STEAMLINE 2 AOS SORV 400.
L) 1.LJ Ul N
t LO T
_j v
Lu 200.
l-CE 3
[(
I
{
3
.h I
L L.
3 3
i
- ' ' ' I '..
0'O.
' ' ' ' 3 l.
_2.
.. _ 3.
ti. x10' FIGURE 3-5.4 ISOLATION WITH SORV, RCic AND 1.OW PRESSURE SYSTEttS AVAllABIE, tio ADS ACTilATinti
BWR/3-251 SORV i
RCIC AND LOW PRESSURE SYSTEMS 8.
x10' i NAT CIRC THRU JET PUMP i
l i
11.
g uj i,
i i
i' i
to i
i i
i i
in nininuinn i
i i
N i
i I
i l
1 i
i i
i i
I (M
i l
i i
ll 1
j i
i l
f
?
i e
i j
i i
i i
l I
uJ 0.
-I d '8' iLi.
W L
' L' j
{
!L
- r j
h-i o
i,i put,l \\
i a:
,1 i
\\
i i
EJ i
i 1
~
'i
[
l i
i i
l' i
i i
i
~
l muinuunu l1
-ll.
sue
-i 1 1 0.
1.
2.
3, 11.x10' ff
(
) FIGURE 3-5.5 ISOLATIOta WITil SORV. RCic AND LOW PRESSURE SYSTEMS AVAILABLE, No ADS ACTilATinta
BWR/3-251 SORV RCIC AND LOW PRESSURE SYSTEMS 9
1r x10 i VESSEL TOP e LEAD 2 FUEL 0.8 LL I
LD i
i i
x 2
gg 2
2 i
ic 4
N g
- 0. tl i
I I.
2
.tJ 1.
2 i
r
. ij
~
0'O.
I ' ' '.
~'
1 2.
3.
Lj, x10' TIME
( S E C )
,,oe c....
l
,som1,o,.
,,1.,.
...,,oc,c
,,<,,o,e s m <,,s
,,,,,, e, <,
-,,,c1.,,,,.,
i
BWR/3-251 SORV RCIC AND LOW PRESSURE SYSTEMS 600.
i DOWNCOMER I
2 LOWER PLENUM D
1 3 2 8
2 400.
s
~
r m
l
._J N
?
m 200.
e 11.
-__l E
I t-g 2
z l.L.l
~
~
e 0.
iliiii g
we
-2 0.
1.
2.
3.
- 4. x10' TIME (SEC)
FIGilRF 3-5.7 l'.ol ATlotl HI Til SoRV,- RCIC Atl0 S OW PRfSSilRE
l BWR/3-251 soav RCIC AND LOW PRESSURE SYSTEMS g~
3 3
3 3
3 i CORE 2 LOWER PLENilM s
SORV 0.6 0.2 I-
~
J 2
I?
12 12 12 12 l
2 3
33 m
g C3
~
-0.2 'I5iii we
-2 O.
1.
2.
3.
- 4. x10' TIME
( SEC ) FICURE 3-5.8ISOLAT10N WITH SORV, RCIC AND LOW PRESSURE SYSTEMS AVAlt.ABtE, tJO ADS ACTt1ATION
RNR/2 4-i ll ;'/\\
IC AND 1.0W PRESSURE SYSTEMS l
s
.ny.,
. i '. ll:.I'I PliESSUfiE
~
i
' * ~.
m, g,3._.__...._.g,_.
\\.
x
.)
s.
Ni
.. i x
i i.
\\
h ll
,\\. g....
- l. i..I N
Q.
'N O.I N.'\\
i i
'.I '8 1.t i
\\ N g
s iL qi I
i 1
0.
3 0.
f 1. F.
l.1 I.U
- 2. 4 x10 TIME
( 0f ~ l. )
i FIGUltE 3-6.l g!Ig'l,j)N glJp,,SORV,,lSOl.,4TI{}fj C()tjDIM{SljRS AND 1.ON
t
-i O
t 6
- 9 e
e i
E lm
~-
C l.
w%
==
m
=
= = '
' O..-7 r=
C r
Im
.d A ran a
V
't.
~
_-.s
=
J W
W e
.'_J C N
b lm.
E 3
g g M M
C w;~C i g ave-
=
w A b hb t~
=
O 1
(.,
J C
O l'
~
"l" 3
- s s
Z =.
51 -
l C
C.7 i
=
t
= f'
~
a me I
4=
I g
S.
eum I
N.-
N X,
1,
-s N
\\
I Z
8 O
\\
l
- C, i
d w
3 Te
=
e, N
s 3
?
6s s
I i\\ k
.\\
.l.W I
A i
( ) <
s
.s I
k 7
3 1
l Q7 w i
~
I i
-3 I
O I
l 8
e l
l
/
Z.
l i
i /
/
.r-e*
/.
=p
/
e l
f
.am q-(
l 0
E'*
- l l
t
?
i 1
I L
{
l 1.
t
~
6 j
l i
""9
_,f I
i t
t e
a r l e
C
'9 C
i C
M n.
l l
l t
g=
e.-
}
l J. r } :
i
% J *
{
-a-g n : _
W_.,'e s
t
A+
HMp
& M'bMhW Y
8 M
e I
N O
w
!G Ma
=
w W
A rp
>=
7 m
A 17 e
W N
ft:
e C
r a.
o r-G T
sm 9;
W 12--=
c s
b,2 z. +..,;a e
s s
2 r.
S.------
l
=
= - - - -
g, m
=
l Q?
~
7 e
w
~
cO m
EH 4.'se s
i 2
~w Aume H
4
\\(!
- d m
\\
1 gm m UJ w_
L.J A 1
CD.u w 2 e
es I
m
@d E
Ce. r'~
l l
l t
-lC F
e bil m
ed J-
=
I 1
9
'n
,C
-*Q m
c M
i
( 7 C
,iG-)
7i?
Ae - --
( j1 a..;
}
.m G t.::. ;
-.t vis-a I
_ ~.,. _ -, - - - -, -, -, - - - - - - - -,.., -.. - -
y
\\
i s
M e
i M,
.g C
J
~
e-i.4 C
E g'M l
2-(.
C is r
u%-
m
=
a:
D=
es 7 LM~
m tre-W CY 2'
tu..
m C
m r-m 9's
- * =
g y
-U-
=
z 2-
~
=
O.E 5._'
C.'
J I
~
\\
o C
-g C > ^g ' Z h O 5
7
- u
- - - !.. n (n m
C.~
_. e t
==
I I
~.*.
a-e M.
~
w th L*
OE R>=
l l
.y Z
c :.
ad
'm:
C..
W.ge
!e c
?A
~m C
t U8 m
l Go E!
W c4 0
LLJ E
C
.m e
I
+ -~
i yv e
O WIG
- O
/
/
/
j W.su J
I.
, a.-
e
.O O
C v
O C
r CJ
[ i a b,f i
_ - )
iv,-
l,:
- g *. i e 's'.
ti
_; 2. L'(a i. <.
5 DHR/2-?I3
.us w IC AND LOW PRESSURE SYSTEMS
- ),
xio) i i 11111 1:lliC THflu JEf PUMP i
it,
,-.. 's ll l us
-s,
~,
- I l'. t'. !
- ~ '
NN i.
=..). Yr.95 Ndd._..._. )_1_j u_i
(),
i.T Y
u n_
n a
~
E:I
__l
~
L i.
_il, ' s i l i t._tt i
0.
U.6 I2 1.8 2.11 = 1 O' we
-2 TIME (SEC)
FI Gilldi 3-6.5 IS01.ATION WITil S061V. Isol.ATION CGrilWNSl?lts AND 1.OW
e
-,we.me 4
- )
e e
f e,
e O
~
u M
N o
=
W a
' y=
m w
g
>=
N 7
a-
'A W
N V
M O,
~
a
.7 M
E 0
h
=
=
.ss O
4 1-r.
E ce O.
o t
E Q' =-
k
[ :s <
l
-u
= - -
8 O
1,= -. g """ -
V r.
s
=
e, l
l/
e.
2 g
f
=
I I
e-.
E e
1
=
l I
O fil em b<
J=
u L*,
g N
!/
J-e
)i ud u4 m.,
l
-=
=0 U
f*
t Z
t l
w
,oA
' ~
e i
l 9
f rJ i
1
/
1 y
i 1
l 4
i
~1 f,'
a.
]
9.
e I.
.c' c
=
-r d
c
_ C _.__,_ <. _ _
e
w
'M=-
e e
4#
e p%
7 c
O, N
C 2-M!
o m
w
>=
(f 'e m
n 2
I m
g e
W b
a v-u.:.
(* }
Z 0
c__ w Oi
=
a.
CN, n.
L!
l s-g.-
~~
C.
a ;, h ~
m ae
[
I"*
I
\\,,
g r g =;;:
/
O+2
?
=
z
d S.
f M:
~
CC U i
e~,
/
=-
/
O
- n t,
=
/
N e-c
/
E>
z
/
C's s
n bC I
<~
b5 8
[
- - C-
}
, p'/
s
- n.
_r
(_1 y e,im u
i i,
e i
f/
"3 i
o f
M l
e' Lt_'
/
Z I
q I
(.c.
l J o. F m
l e
i e
a f
p' I
a I
a 1
e e
j I
I l
1 1
4 y
I
.C e
e e
C-C O
C O
C ca
- ?.--,
f.i i.' c%(j s -;
li,e 3
C i. I l\\.9 9
p.
m e,
w
@e 5
O 4
e b
o 8
EO t
m C
w z
l h
40 w
C in !-
>=
e "x
2.-
3 i
O mF g
zc g
N c-S E
g-2 N!
5:
e
{-
A :
L:.J j
Er 1
3:
{-
0:
~
a.
V'.
H w
O 4L g ' =_ __ >
__ e
.e
-,a m.
.o g
~
=
- e.,
l
,a a
r
(
cn ar-N
-f 8"*e e
x.
r I
z f
O *-
6 r.
~
i h.~
_/
4,
_s O -
l i
l i
N 2
i e
i
+
I
~"g L'1.n I
I l
i l
Q~)3 2
E r
C.F l
!C l.l
.l e'
l I
s' g
l
~
i i..,
C c.-
C.O C
C C
I
/1 i.eum..
. e g
!g.
9ma
- e E
E g
E
$a$a EdE53 as
- - e = en
!e
-======35 E>r d
$2$ds5! W"
=$S d es= s8g 5 E :-
sa g28 CE<gge:rg0W"W m<3*
=
di uMW WEWCWW51Mfa":
W
$2" m
gw as Ewse-g 55 Ea r5:m 8"238 G-
"Et 5g= C$3=g
=
3 g = 5" "l"g
-W w
on gx I
E-sm
OM5 2
U "E5E E
E I!E
- E
=
323 E
m i
I 5:
C I
Eg 55 l
8l W
IE E
fod oM
=
5=
IG5 k0
=
5 5_8 3
E
=
t m
W E
E 5
5 E
2 A
M "W
g w
W I
t" O'
=
5a 58 5
EI"S WS 5
=
e==
af E
8 i2 C
SC "2MS 4
~m r
.54 3
w L 8
-52 6
5 W
==E e
t lu d25 8
8 22:
mE o
a!
0E=
C:
o rn
=We Wm 53 3 A A
A f
m m
=
5 4
r s
C I
1 I
G 8
G F
E N
A SNO I
T I
8T COL M
N N
T 0N PI G
I S
RE HTS E
I A
E PR
/AD T
S M
T R
lRA S
E A
HOE I
HE UE S
S SS T
O0 AD A
A AN iCA R
C EE E
T G
AII i
T RC R
UYI MLT N5 G
YN CN C
BIE OYN APT H
MC IM I
ALD NCI DRR I
T E
E E
, C S
S RO MFA A
A 1
ON EIL 1
E E
8 F
E LT P
F R
R A
N I
C C
8T Ei NR OSH OU HOYGN N
NE N
0N TAW IT TPSII G
IC I
RE SA I
H I
N PR U
SR WFE M
S TA T
R T3 EE ORYE Y
NN NG EU C-S RP H
ULT EA AE AN MC Al N
/
S TER C
G M8E A
LP YIPEL T
NM NT UY1 D
U DOI RDM0O YN G
G Oi5 SRE T
SUO I
R R Y U N
N N
)
O L
P I
N I
0NT F
E S
l lAR Tl I
E E
lHA EOi N
R L
ESE S
E SFAIT TNL I
MCV A
S AOU S
A E
A E
IY UNS E
RYCLL TES S
CC R
CTAEE C
E A
l SNN NN C
NI KV AWL E
SO0 IA N
ILSIE
(
R ULL Y3 C
A l
N IG I
TE N
T8O A
D N
PDl L
HT LI HAISM M1E I
YEA L
GN LT GBRSA
/D BTI OAI W
A II AS lOUER 5RE Y
RT DTN O
M LA ME iRPlC 0WE N
ASI L
T E
S 5
N F
0 F
l i
R 0
P N
N N
O O
I N
I 0
F O
I 1
T T
E E
T EO C*
RM I*
EA S
E SFA TN D
G5 MR A
S AOU A
E E
A E
T UN T
RYC TE C
CC R
CTA C l E
I L
ST 5NE NN C
NI AW P
DP 5OV IA N
IL5 X
AO A
E N
IG 1 0 Y3 E
DL TE N
T80 A-D FC
'sE OI 8TR L
iT LI HA1 M1E 5
QN LT G8R
/D 1
L Nn OAT W
A II AS I0U SRE G
RE OI DTA O
M LA ME LEP DWE D
S ASW L
ABN NA IS N
RD O
AA I
P T
M R
A O
D C
E N
N O
M C
I O
F O
I T
T UD D
E T
EO U
E R
SFA TN A
E E
1 HU R
C AOU A
GS U
E T
UN H
5 IS E
D RYC IE T
CTA Ci I
HE C
E E
R N
R NI AW W*
L EP A
ILS 8
T N
G IU Y3 E
E N
T8O A-D S
A AL T
NL T
I HAI M1E A
E N
T GBR
/D L
IE IYI W
N I
S IOU SRE R
MWP LRR O
O A
E LRP DWE C
EDT L
N M
T SPS ABN LD 0
1 D
0 t
1 i
R C
I L
U P
Q X
SE L
- E E
AR 5
L S
CN U
N A
ED 0
ST I
l 5
MO N
N Cl G
Nh N
l N
- RN NG l
A 0
AO Cl E
A%
UF5 l$
T N
i R
1 IRD l(
N 5
L T
I N E
P A
CEA C0 I
1 M
INO T
O U
AP A
A t
I T
D AT E
T C
TCu LN I
N MC E
C N
A NIB AE A
U C
N A
EG UR NR N
A L
S I0D NR N
OT A
L P
U R1I AU S
N L
O E - N MC VSG 0
TN E
I N
I CO I
E O
R DNI T0 1
A I
AC N
V U
A0S N1 i
L S
P I
R T
P N1E I
L O
HR A
U C
S I1D ID RE A
C lO M
S A
ER P
VA T
M A
S I
1 2
DP AM I
N 2
3 4
NO R
I 1
IC E
T I
R 1
r 1
z
{
A 4
A O
^
4.w Om n
w q
Y 6 sc
=
55 W
Ew
,8 k
I 02 IE" E
w EE EWt 38 ss a
I2" 5
N
J Su 355 ta
i
$W5 5-3 3
IGE 5
I C
=g u
Y
~
$m AM 5
d ag$Eaa 2%
N
$NE O
s a=
x t
5.~.
IG5 5
8 m
O l
Y 5!
EO 5
w2 3
~5" 2
~
l E.I.S.
S WQ-1 2
O o
(
u
=
5" E
i 5
i N
%.:L '
APPENDIX A Participating Utilities NUREG-0737 II.K.3.18 This report applies to the following plants, whose Owners participated in the report's development.
Utility Plant Boston Edison Pilgrim 1 Carolina Power & Light Brunswick 1&2 Commonwealth Edison LaSalle 1&2, Dresden 2-3, Quad Cities 1&2 Georgia Power Hatch 1&2 Iowa Electric Light & Power Duane Arnold Niagara Mohawk Power Nine Mile Point 1&2 Nebraska Public Power District Cooper Northeast Utilities Millstone 1 Northern States Power Monticello Philadelphia Electric Peach Bottom 2&3, Limerick 1&2 Power Authority of the State of FitzPatrick New York Detroit Edison Enrico Fermi 2 Long Island Lighting Shoreham Mississippi Power & Light Grand Gulf 1&2 Pennsylvania Power & Light Susquehanna 1&2 Washington Public Power Supply Hanford 2 System Cleveland Electric I!1uminating Perry 1&2 Houston Lighting & Power Allens Creek Illinoi's Power Clinton Station 1&2 Public Service of Oklahoma Black Fox 1&2 Vermont Yankee Nuclear Power Vermont Yankee Jersey Cent.al Power and Light Oystar Creek 1 Tannessee Valley Authority Browns Ferry 1-3; Hartsville 1-4; i
Phipps Bend 1-2 Gulf States River Bend l
l
.-.