Text
s,
.
7 (CL
.
'o
L NITED STATES
/[T ,,n
8"
NUCLEAR REGULATORY COMMISSION
$ * h]!a f 8
E
REGION 11
od
!
101 M ARIETTA sT., N.W., SUITE 3100
%<
AT LANT A, GEORGI A 33303
o
.....
OCT 171980
In Reply Refer To:
R
W
0-413/80-14
0-414/80-14
Duke Power Company
ATTN:
W. O. Parker, Jr.
Vice President, Steam Production
P. O. Box 2178
Charlotte, NC 28242
Gentlemen:
Thank you for your letter of August 25, 1980 informing us of steps you have
taken to correct the item of noncompliance concerning activities under NRC
Construction Permit Nos. CPPR-116 and CPPR-117 brought to your attention in our
letter of August 1, 1980. We will examine your corrective actions and plans
during subsequent inspections.
We appreciate your cooperation with us.
Sincerely,
'lb
g C. E. Murphy, Chief
Reactor Construction and Engineering
Support Branch
J. W. Hampton, Station Manager
cc:
D. G. Beam, Project Manager
.
.
Bc10810 OC