Forwards IE Insp Repts 50-413/80-10 & 50-414/80-10 on 800527-30 & Notice of Violation
ML19338D991
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 06/23/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19338D977 List:
References
NUDOCS 8009240302
Download: ML19338D991 (2)


See also: IR 05000413/1980010

Text

_ _.

,' )

.

y

W

/

'o

UNITED STATES

4

8

  • g

,

NUCLEAR REGULATORY COMMISSION

n

i

I

REGION 11 -

e[

o

101 MARIETTA ST N.W SUITE 3100

ATLANTA, GEORGIA 30303

JUN 2 $ 1980

In Reply Refer To:

RII:WPK

50-413/80-10

50-414/80-10

Duke Power Company

ATTN:

W. O. Parker, Jr.

Vice President, Steam Production

P. O. Box 2178

Charlotte, NC 28242

Gentlemen:

This refers to the inspection conducted by W. P. Kleinsorge of this office on

May 27 through 30, 1980 of activities authorized by NRC Construction Permit Nos.

CPPR-116 and CPPR-117 for the Catawba facility, and to the discussion of our

findings held with D. L. Freeze at the conclusion of the inspection.

,

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items. The status of these items is dis-

-

cussed in the enclosed report.

One new unresolved item resul+.ed from this inspection and is discussed in the

enclosed repc,rt. This item will be examined during subsequent inspections.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation. enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the prosisions of Section

2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions.

Section 2.201 requires you to submit to this office, within 20 days of

your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2)

corrective steps which will be taken to avoid further noncompliance; and (3) the

date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

8009240 Mb

,

,.

. _-

"

L

-

'

'

,,

,

y

.

.

.

Duke. Power Company-

-2-

the'information is proprietary, and should be prepared so that proprietary infor-

nation identified in the application is contained -in a . separate: part of the

'

document. If we ldo not hear from you in- this regard within the specified period,

.

the report will be placed in the Public Document' Room.

'

Should you have any'que~stions concerningLthis letter, we will be glad to discuss

them with you.

'

Sincerely,

.

-

.u $,

C. E. Murph ,' C

Reactor Construction and Engineering

Support Branch

y

Enclosures:

1.

Appendix A, Notice of Violation

-2.

Inspection Report Nos. 50-413/80-10

and 50-414/80-10

cc w/ encl:

J. W. Hampton, Station Manager

P. O. Box 392

Clover,;SC 29710

..

D. G.-Bear., Project Manager

P.'O. % 223

Clover, SC 29710