UNITED STATES -
8
NUCLEAR REGULATORY COMMISSION
o
$
3
E
REGION 11
101 MARIETTA ST., N.W., SUITE 3100
o
ATLANTA, GEORGIA 30303
' ' " *
SEP 021980
In Reply Refer To:
RII:
-413/80-10
50-414/80-10
/'
Duke Power Company
'
ATTN:
W. O. Parker, Jr.
Vice President, Steam Production
P. O. Box 2178
Charlotte, NC 28242
Gentlemen:
Thank you for your letter of August 19, 1980, forwarding an interim
revised response and informing us of steps you have taken to correct the
item of noncompliance concerning activities under your NRC Construction
Permit Nos. CPPR-116 and CPPR-117 brought to your attention in our
letter of June 23, 1980. We will examine your corrective actions and
'
plans during subsequent inspections.
1
We appreciate your cooperation with us.
l
Sincerely,
,
f f*
,: ,;
_
m
Charles E. Murphy , Chief
Reactor Construction & Engineering
Support Branch
cc:
D. G. Beam, Project Manager
J. W. Hampton, Station Manager