ML19316A583

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Mar 1975
ML19316A583
Person / Time
Site: Oconee 
Issue date: 04/09/1975
From:
DUKE POWER CO.
To:
Shared Package
ML19316A579 List:
References
NUDOCS 8001130088
Download: ML19316A583 (3)


Text

-

f.

'O Oconee Unit 1 t, NIT 4/9/75 DATE DOCKET NO. 50-269 OPERATING STATUS 1.

REPORTING PERIOD:

March 1, 1975 THROUGH March 31, 1975 HOURS IN REPORTING PERIOD:

744.0 2.

CURRENTLY AUTHORIZED POWER LEVEL (MWth e MAX. DEPENDAllLE CAI ACITY (Mwe-NET; 871 3.

LOWEST POWER LEVEL TO WHICH SPECIFICALL) RESTRICTED (lF ANY)(MWe-NET)

None 4.

REASONS FOR RESTRICTION (IF ANY):

THIS CL MULATIVE REPORTING PI RIOD YR TO DATE TO D ATE 503.9 578.7 10379.2 5.

HOURS REACTOR WAS CRITICAL.

0 0

0 6.

RE ACTOR RESERVE SHUTDOWN HOURS 7.

HOURS GENERATOR ON LINE.

425.9 425.9 8680.2 0

0 0

8.

UNIT RESERVE SHUTDOWN HOURS.

9.

GROSS THERMAL ENERGY 766077 766077 19003587 GENER ATED (MWH) 10.

GROSS ELECTRICAL ENERGY 264590 264590 6583290 l

GENER ATED (MWH D 11.

NET ELECTRICAL ENERGY GENER ATED 243559 229917 61 R 79 36 (MwH) 67.7 26.8 69.3 12.

REACTOR AVAILABILITY F ACTOR (1) 57 3 19 7 9R O 13.

UNIT AVAILABILITY F ACTOR (2) 37.6 12.2 47.4 14.

UNIT CAPACITY F ACTOR (3) 42.5 80.2 24.8 15.

UNIT FORCED OUTAGE RATE (4).

16.

SHUTDOWNS SCHEDULED TO BEGIN IN NEXT 6 MONTHS (STATE TYPE.DATE. AND DUR ATION OF EACH):

17.

IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE 01 STARTUP-18.

UNITS IN TEST STATUS (PRIOR TO COMMERCI AL OPE RATION) RE PORT THE FOLLO41NG.

DATE LAST D4TE FORECAST ACH'IEVED INITI AL CRITIC ALITY INITIAL ELECTRICAL POWER GENE RATION COMMERCIAL OPERATION i

i (1)

REACTOR AVAILABILITY FACTOR =

X 100 0

X l00 (2)

UNIT AVAILABILITY FACTOR

=

0 NFT ELTCTRICAL POWFR t;FNER ATFD (3)

UNITCAPACITY FACTOR

=

(4)

UNIT FORCED OUTAGE R ATE 100RS G R

LINE + FORCED OUT AGE HOURS 8 0 011300k

DOCKET NO. 50-269 UNIT oconee Unit i DATE 4/9/75 AVERAGE DAILY UNIT POWER LEVEL MONTH March, 1975 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)

DAY (MWe-net) 623 1

0 17 627 2

0 18 629 3

0 19 4

0 20 634 51 5

0 21 225 6

0 22 641 7

0 23 698 0

24 8

774 0

25 g

784

'0 26 10 781 0

27 11 772 12 4

28 238 29 715 13 291 30 590 14 664 162 31 15 387 16 DAILY UNrr POWER LEVEL FORM INSTRUCTIONS On this form, list the average daily unit power level in MWe-net for each day in the reporting month.

Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that by using maximum dependable capacity for the net electrical rating of the unit. there may be occasions when the daily average power level exceeds the 1007o line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

D C!.ET NO.

50-269 UNIT SHUTDOWNS UNIT NAMli Oconee Unit 1.

DATI!

4/9/75 REPORT MONTil March, 1975 TYPE METHOD OF F FORCED DURATION SHUTTING DOWN g

NO.

DATE S SCHEDULED (HOURS)

REASON (1)

THE REACTOR (2)

CORRECTIVE ACTIONS / COMMENTS 17 74-12-21 F

260.88 A,B 1

Reactor coolant pump seal and motor repairs; zero power physics test following refueling 1

75-03-1;.

F 13.30 A

3 Steam leak on turbine instrumentation valve 2

75-03-1:

F 6.35 A

3 Fault in ICS Delta C instrumentation 3

75-03-15 F

2.82 A

1 Turbine control oil leak 4

75-03-15 S

3.56 B

Turbine overspeed trip test (1) REASON (2) METilOD A -EQUIPMENT FAILURE (EXPLAIN) 1-MANUAL B-MAINT. OR TEST.

2-MANUAL C-REl'ULLING SCRAM

)

D-REGULATORY RESTRICTION 3-AUTOMATIC E-OPFRATOR TRAINING AND SC R AM IKENSE EXAMINATION F-ADMINISTR AllVE G-OPER AllON Al l:RROR IEXPIAIN)

Il-0TilLR (EXPLAIN) 5 75-03-2'.

F 31.17 G

3 Unit trip due to spurious pressure /

temperature trip. Unit remained off to inspect RC pump motors.

SUMMARY

.... - _..