05000364/LER-1999-001-05, :on 990621,plant Was Manually Tripped Due to Decreasing Vacuum in Condenser.Caused by Broken Steam Dump Drain Line.Broken Section of Line Was Repaired & Licensee Will Implement Addl Design Change1999-07-0202 July 1999
- on 990621,plant Was Manually Tripped Due to Decreasing Vacuum in Condenser.Caused by Broken Steam Dump Drain Line.Broken Section of Line Was Repaired & Licensee Will Implement Addl Design Change
05000348/LER-1999-002-02, :on 990527,Unit 1 Reactor Trip Occurred Following Loss of 1A SG Feedwater Pump.Caused by Personnel Error.Unit Was Stabilized in Hot Standby.With1999-06-25025 June 1999
- on 990527,Unit 1 Reactor Trip Occurred Following Loss of 1A SG Feedwater Pump.Caused by Personnel Error.Unit Was Stabilized in Hot Standby.With
05000348/LER-1998-008-01, :on 981223,reactor Vessel Support Concrete Design Bases Temperature Exceeded Due to Closed Cooling Damper.Caused by Personnel Error.Damper Opened & Secured in Position.With1999-01-18018 January 1999
- on 981223,reactor Vessel Support Concrete Design Bases Temperature Exceeded Due to Closed Cooling Damper.Caused by Personnel Error.Damper Opened & Secured in Position.With
05000348/LER-1998-007-02, :on 981106,found Several TSP Circumferential Indications & Several TSP Axial Indications Extending Just Beyond Edge of Tsp.Caused by Tube Defects.Sg Tubes Have Been Plugged or Repaired as Required1998-12-22022 December 1998
- on 981106,found Several TSP Circumferential Indications & Several TSP Axial Indications Extending Just Beyond Edge of Tsp.Caused by Tube Defects.Sg Tubes Have Been Plugged or Repaired as Required
05000348/LER-1998-006-03, :on 981124,PRF Sys Suction Damper Was Outside Design & Licensing Basis.Caused by 1976 Personnel Failure to Identify Noted Inconsistency.Scheduled Design Change in 1999 to Modify Dampers to Ensure Licensing Basis Are Met1998-12-18018 December 1998
- on 981124,PRF Sys Suction Damper Was Outside Design & Licensing Basis.Caused by 1976 Personnel Failure to Identify Noted Inconsistency.Scheduled Design Change in 1999 to Modify Dampers to Ensure Licensing Basis Are Met
05000364/LER-1998-007-01, :on 981116,ESF Actuation Occurred During DG 1000 Kw Load Rejection Test.Caused by Poor Jumper Electrical Connection.Improved Jumpers Will Be Used on Appropriate Terminals in Load Rejection Test Procedures.With1998-12-11011 December 1998
- on 981116,ESF Actuation Occurred During DG 1000 Kw Load Rejection Test.Caused by Poor Jumper Electrical Connection.Improved Jumpers Will Be Used on Appropriate Terminals in Load Rejection Test Procedures.With
05000348/LER-1998-005-03, :on 981021,automatic Start of B Train Penetration Room Filtration Occurred Due to Filling Sf Tc. Caused by Inadequate Procedure.Changed Procedure to Provide Specific Guidance for Filling SFP Tc.With1998-11-12012 November 1998
- on 981021,automatic Start of B Train Penetration Room Filtration Occurred Due to Filling Sf Tc. Caused by Inadequate Procedure.Changed Procedure to Provide Specific Guidance for Filling SFP Tc.With
05000348/LER-1998-004-03, :on 980909,turbine Trip & Consequent Reactor Trip Occurred.Caused by Reactor Protection Sys Card Failure. Failed Card Was Replaced & Unit 1 Returned to Power on 980910.With1998-09-28028 September 1998
- on 980909,turbine Trip & Consequent Reactor Trip Occurred.Caused by Reactor Protection Sys Card Failure. Failed Card Was Replaced & Unit 1 Returned to Power on 980910.With
05000348/LER-1998-003-04, :on 980816,determined That Wgdt Hydrogen & Oxygen Had Exceeded Concentration Limits,Per TS 3.11.2.5. Caused by Undetected Leak.Leak Was Identified & Isolated & Waste Gas Sys Was Returned to Svc on 980818.With1998-09-11011 September 1998
- on 980816,determined That Wgdt Hydrogen & Oxygen Had Exceeded Concentration Limits,Per TS 3.11.2.5. Caused by Undetected Leak.Leak Was Identified & Isolated & Waste Gas Sys Was Returned to Svc on 980818.With
05000348/LER-1997-003, :on 970315,determined That TS SR 4.5.3.2 Had Not Been Performed,Per Operating Procedure.Caused by Personnel Error.Verified That RHR Discharge to Charging Pump Suction MOVs 8706A & 8706B Were Closed.With1998-09-0808 September 1998
- on 970315,determined That TS SR 4.5.3.2 Had Not Been Performed,Per Operating Procedure.Caused by Personnel Error.Verified That RHR Discharge to Charging Pump Suction MOVs 8706A & 8706B Were Closed.With
05000348/LER-1998-005, :on 980315,failure to Perform Nuclear Instrumentation Surveillance Requirements Prior to Mode 2 & 3 Entry,Was Discovered.Caused by Personnel Error.Revised Applicable Procedures1998-09-0303 September 1998
- on 980315,failure to Perform Nuclear Instrumentation Surveillance Requirements Prior to Mode 2 & 3 Entry,Was Discovered.Caused by Personnel Error.Revised Applicable Procedures
05000348/LER-1998-002-05, :on 980816,SG Tube Leakage Investigation,Repair & Evaluation,Occurred.Caused by ODSCC in Two Locations on Same Tube.Operational Leak Rate Limit Requiring Plant Shutdown Has Been Administratively Reduced1998-09-0303 September 1998
- on 980816,SG Tube Leakage Investigation,Repair & Evaluation,Occurred.Caused by ODSCC in Two Locations on Same Tube.Operational Leak Rate Limit Requiring Plant Shutdown Has Been Administratively Reduced
05000364/LER-1998-006, :on 980515,containment Penetration Overcurrent Protective Device Energized.Caused by Inadequate Procedure. Motor Space Heater Breaker 2C RCP Was Promptly Opened to Restore Compliance W/Ts1998-07-0606 July 1998
- on 980515,containment Penetration Overcurrent Protective Device Energized.Caused by Inadequate Procedure. Motor Space Heater Breaker 2C RCP Was Promptly Opened to Restore Compliance W/Ts
05000364/LER-1998-001-01, :on 980328,manual Reactor Trip Was Noted.Caused by Dropped Control Rod K-2 & F-10.Affected Cable & Connectors Were Replaced During Unit 2 Twelfth Refueling Outage & Tested During Startup1998-06-11011 June 1998
- on 980328,manual Reactor Trip Was Noted.Caused by Dropped Control Rod K-2 & F-10.Affected Cable & Connectors Were Replaced During Unit 2 Twelfth Refueling Outage & Tested During Startup
05000348/LER-1998-003, :on 970315,failure to Comply W/Ts 4.5.3.2 & 3.5.2,was Determined.Caused by Personnel Error.Personnel Involved Have Been Coached Re Procedure Adherence1998-06-0909 June 1998
- on 970315,failure to Comply W/Ts 4.5.3.2 & 3.5.2,was Determined.Caused by Personnel Error.Personnel Involved Have Been Coached Re Procedure Adherence
05000364/LER-1998-004-01, :on 980420,failure to Perform Penetration Room Filtration Sys SR Was Noted.Caused by Personnel Error.Note Has Been Corrected & Initial Review of Surveillance Schedules Have Been Performed1998-05-18018 May 1998
- on 980420,failure to Perform Penetration Room Filtration Sys SR Was Noted.Caused by Personnel Error.Note Has Been Corrected & Initial Review of Surveillance Schedules Have Been Performed
05000364/LER-1998-003-01, :on 980411,SG Tube Degradation & Tube Status Were Noted During Insp.Caused by Tube Defects.Tubes Were Repaired & Plugged1998-05-0707 May 1998
- on 980411,SG Tube Degradation & Tube Status Were Noted During Insp.Caused by Tube Defects.Tubes Were Repaired & Plugged
05000364/LER-1998-002-04, :on 980405,discovered Turbine Auto Stop Trip (AST) Oil Pressure Switch Sepoints Out of TS Limits.Caused by Vibration Induced Wear.Will Replace Existing AST Switches W/More Rugged Type Pressure Switch Less Susceptible to Wear1998-05-0404 May 1998
- on 980405,discovered Turbine Auto Stop Trip (AST) Oil Pressure Switch Sepoints Out of TS Limits.Caused by Vibration Induced Wear.Will Replace Existing AST Switches W/More Rugged Type Pressure Switch Less Susceptible to Wear
05000348/LER-1997-010, :on 970523,MOV local-remote Control Circuit Wiring Discrepancies Were Noted.Caused by Cognitive Personnel Error.All Affected MOVs Were Rewired IAW Design1998-04-29029 April 1998
- on 970523,MOV local-remote Control Circuit Wiring Discrepancies Were Noted.Caused by Cognitive Personnel Error.All Affected MOVs Were Rewired IAW Design
05000364/LER-1998-001-05, :on 980328,manual Reactor Trip Due to Dropped Control Rod K-2,was Determined.Caused by Overcurrent Condition.Crdm Cable & Connectors Associated W/Rod K-2 Will Be Replaced & Rod Will Be Tested During Startup Testing1998-04-16016 April 1998
- on 980328,manual Reactor Trip Due to Dropped Control Rod K-2,was Determined.Caused by Overcurrent Condition.Crdm Cable & Connectors Associated W/Rod K-2 Will Be Replaced & Rod Will Be Tested During Startup Testing
05000348/LER-1997-003, :on 970315,failure to Comply W/Ts 4.5.3.2 & 3.5.2 Was Noted.Caused by Personnel Error.Operations Involved in Event Have Been Coached Concerning Procedure Adherence1998-04-16016 April 1998
- on 970315,failure to Comply W/Ts 4.5.3.2 & 3.5.2 Was Noted.Caused by Personnel Error.Operations Involved in Event Have Been Coached Concerning Procedure Adherence
05000348/LER-1997-005, :on 970315,failure to Perform Nuclear Instrumentation SR Prior to Mode 2 & 3 Entry Was Noted. Caused by Personnel Error.Revised All Applicable Procedures1998-04-15015 April 1998
- on 970315,failure to Perform Nuclear Instrumentation SR Prior to Mode 2 & 3 Entry Was Noted. Caused by Personnel Error.Revised All Applicable Procedures
05000348/LER-1998-001-02, :on 980217,inadequately Performed Surveillance Occurred Due to Improper Calculation of E-Bar.E-Bar & 100/E-Bar Values Were Recalculated Using Corrected Average Beta Energies for Each Unit1998-03-12012 March 1998
- on 980217,inadequately Performed Surveillance Occurred Due to Improper Calculation of E-Bar.E-Bar & 100/E-Bar Values Were Recalculated Using Corrected Average Beta Energies for Each Unit
05000364/LER-1997-004-04, :on 970910,discovered That Required Containment Atmospheric Grab Samples Had Not Been Taken.Caused by Inoperable Radiation Monitors.Declared Radiation Monitors Operable & Obtained Required Grab Samples1997-10-10010 October 1997
- on 970910,discovered That Required Containment Atmospheric Grab Samples Had Not Been Taken.Caused by Inoperable Radiation Monitors.Declared Radiation Monitors Operable & Obtained Required Grab Samples
05000348/LER-1997-014, :on 970922,discovered RCS Leak Detection Sys Inoperable.Caused by Defective Procedure in That Sys Design Criteria Were Not Adequately Incorporated Into Plant Operating Procedures.Revised Procedure1997-10-0707 October 1997
- on 970922,discovered RCS Leak Detection Sys Inoperable.Caused by Defective Procedure in That Sys Design Criteria Were Not Adequately Incorporated Into Plant Operating Procedures.Revised Procedure
05000348/LER-1997-013, :on 970818,plant Operated Outside of Design Basis Due to Control Room Exhaust Isolation Damper Being Open.Caused by Personnel Error.Revised Procedures to Ensure Dampers Are Operated within Design Basis1997-09-12012 September 1997
- on 970818,plant Operated Outside of Design Basis Due to Control Room Exhaust Isolation Damper Being Open.Caused by Personnel Error.Revised Procedures to Ensure Dampers Are Operated within Design Basis
05000348/LER-1997-011, :on 970706,TS 3.0.3 Was Entered Due to Failure to Follow Work Control Process Procedure.Operations & Maintenance Personnel Will Be Instructed on Expectations That Specific Limits Must Be Documented1997-07-31031 July 1997
- on 970706,TS 3.0.3 Was Entered Due to Failure to Follow Work Control Process Procedure.Operations & Maintenance Personnel Will Be Instructed on Expectations That Specific Limits Must Be Documented
05000348/LER-1997-010, :on 970523,Unit 1 Had Operated in Condition Outside Design Basis While in Mode 5.Caused by Personnel Error.Affected MOVs Were Rewired IAW Design1997-06-20020 June 1997
- on 970523,Unit 1 Had Operated in Condition Outside Design Basis While in Mode 5.Caused by Personnel Error.Affected MOVs Were Rewired IAW Design
05000348/LER-1996-007, :on 961107,IEEE-279 Requirements Were Not Met for Protection Channel III SG Instrumentation.Caused by Personnel Error.Implemented Administrative Controls1997-05-28028 May 1997
- on 961107,IEEE-279 Requirements Were Not Met for Protection Channel III SG Instrumentation.Caused by Personnel Error.Implemented Administrative Controls
05000348/LER-1997-006-01, :on 970401,SG Tube Degradation & Tube Status Was Reported.Caused by Defects in Tube Sheet & Expansion Transition Degradation.Sg Tubes Have Been Plugged or Repaired1997-05-28028 May 1997
- on 970401,SG Tube Degradation & Tube Status Was Reported.Caused by Defects in Tube Sheet & Expansion Transition Degradation.Sg Tubes Have Been Plugged or Repaired
05000348/LER-1997-009, :on 970430,lack of Missile Protection for Svc Water Flow Switches Occurred.Caused by Inadequate Design. Automatic Isolation Function of Isolation Valves from SW Bldg to DG Bldg,Disabled1997-05-27027 May 1997
- on 970430,lack of Missile Protection for Svc Water Flow Switches Occurred.Caused by Inadequate Design. Automatic Isolation Function of Isolation Valves from SW Bldg to DG Bldg,Disabled
05000348/LER-1997-008, :on 970423,determined Condition Existed Where Unit 1 May Have Been Operated Outside Design Basis of Plant. Caused by Personnel Error.Existing Shim Configuration on 1C SG Modified1997-05-23023 May 1997
- on 970423,determined Condition Existed Where Unit 1 May Have Been Operated Outside Design Basis of Plant. Caused by Personnel Error.Existing Shim Configuration on 1C SG Modified
05000364/LER-1997-003-03, :on 970424,failed to Perform Diesel Generator Surveillance Requirements.Caused by Procedural Inadequacy. Changed Shared Surveillance Schedule to Ensure Testing Will Be Performed for Each Individual Unit1997-05-22022 May 1997
- on 970424,failed to Perform Diesel Generator Surveillance Requirements.Caused by Procedural Inadequacy. Changed Shared Surveillance Schedule to Ensure Testing Will Be Performed for Each Individual Unit
05000348/LER-1997-007-01, :on 970422,plant Had Operated in Condition That Was Outside Design Basis Due to Degraded Cork Matl.Caused by Insufficient Routine Insps.Completed Repair of Missing Seal & Containment Wall on Unit 2 on 9704211997-05-22022 May 1997
- on 970422,plant Had Operated in Condition That Was Outside Design Basis Due to Degraded Cork Matl.Caused by Insufficient Routine Insps.Completed Repair of Missing Seal & Containment Wall on Unit 2 on 970421
05000348/LER-1997-005, :on 970315,failure to Perform Nuclear Instrumentation SRs Was Noted Prior to Mode Two & Three Entry.Caused by Personnel Error.Applicable Procedure Will Be Revised by 9705011997-04-18018 April 1997
- on 970315,failure to Perform Nuclear Instrumentation SRs Was Noted Prior to Mode Two & Three Entry.Caused by Personnel Error.Applicable Procedure Will Be Revised by 970501
05000348/LER-1997-004-01, :on 970318,safety Related 600 Volt Position Sensitive Seismic Qualification Was Not Seismically Qualified in All Positions.Caused by Personnel Error. Operating Procedures Modified1997-04-15015 April 1997
- on 970318,safety Related 600 Volt Position Sensitive Seismic Qualification Was Not Seismically Qualified in All Positions.Caused by Personnel Error. Operating Procedures Modified
05000364/LER-1997-002-01, :on 961030,inappropriate Interpretation of Penetration Room Filtration Sys Power Supply Requirement Occurred.Caused by Personnel Error.Revised Interpretation of TS 3/4.9.13 Requirements1997-04-0202 April 1997
- on 961030,inappropriate Interpretation of Penetration Room Filtration Sys Power Supply Requirement Occurred.Caused by Personnel Error.Revised Interpretation of TS 3/4.9.13 Requirements
05000348/LER-1997-002, :on 970218,discovered That SR 4160 Volt AC Breakers Not Seismically Qualified in Any Position Except in Connect Position.Caused by Personnel Error.Modified Operating Procedures1997-03-14014 March 1997
- on 970218,discovered That SR 4160 Volt AC Breakers Not Seismically Qualified in Any Position Except in Connect Position.Caused by Personnel Error.Modified Operating Procedures
05000348/LER-1997-001-01, :on 970206,TS Ventilation Sys Deficiencies Discovered.Caused by Cognitive Personnel Error.Applicable Procedures Addressing Inadequate Flow Test Revised & Responsible Person Coached on Event1997-03-0707 March 1997
- on 970206,TS Ventilation Sys Deficiencies Discovered.Caused by Cognitive Personnel Error.Applicable Procedures Addressing Inadequate Flow Test Revised & Responsible Person Coached on Event
05000364/LER-1997-001, :on 970113,nuclear Instrumentation Sys Inaccuracies Were Below 50% Power.Caused by Personnel Error. Unit Operating Procedures Have Been Modified to Specify That Nis Must Be Adjusted1997-02-12012 February 1997
- on 970113,nuclear Instrumentation Sys Inaccuracies Were Below 50% Power.Caused by Personnel Error. Unit Operating Procedures Have Been Modified to Specify That Nis Must Be Adjusted
05000364/LER-1996-004-01, :on 961214,manual Trip Occurred Due to Rod Control Sys Malfunction.Digital Step Counters Inspected & Either Modified by Adding Insulating Sleeve Over Audible Clicker Input Lead1997-01-0909 January 1997
- on 961214,manual Trip Occurred Due to Rod Control Sys Malfunction.Digital Step Counters Inspected & Either Modified by Adding Insulating Sleeve Over Audible Clicker Input Lead
05000348/LER-1996-004, :on 960620,SR Not Met for Manual SI Input Into RT Sys.Cause of Missed Surveillance Was Cognitive Personnel Error & Failure to Ensure Surveillance Test Procedure. Revised Procedures1996-12-20020 December 1996
- on 960620,SR Not Met for Manual SI Input Into RT Sys.Cause of Missed Surveillance Was Cognitive Personnel Error & Failure to Ensure Surveillance Test Procedure. Revised Procedures
05000364/LER-1996-003-01, :on 961030,determined That More than 1% of Inservice Tubes in Each SG During Eleventh Cycle Found Defective.Caused by Roll Transition Degradation,Sludge Zone Degradation & Free Span Degradation1996-12-0606 December 1996
- on 961030,determined That More than 1% of Inservice Tubes in Each SG During Eleventh Cycle Found Defective.Caused by Roll Transition Degradation,Sludge Zone Degradation & Free Span Degradation
05000364/LER-1995-002, :on 950404,increased Oxide & Deposit Coating on Fuel Was Noted During Visual Exams of Fuel Assemblies.Caused by Fuel Duty & Inherent Variability in Cladding Corrosion Process.Revised Corrosion Models1996-12-0404 December 1996
- on 950404,increased Oxide & Deposit Coating on Fuel Was Noted During Visual Exams of Fuel Assemblies.Caused by Fuel Duty & Inherent Variability in Cladding Corrosion Process.Revised Corrosion Models
05000348/LER-1996-006, :on 961008,Kaowool Fire Barrier Sys on Six Unit 1 Raceways Did Not Comply with Program Requirements. Caused by Personnel Error.Hourly Fire Watches Established & Will Remain Until Sys in Compliance1996-11-0707 November 1996
- on 961008,Kaowool Fire Barrier Sys on Six Unit 1 Raceways Did Not Comply with Program Requirements. Caused by Personnel Error.Hourly Fire Watches Established & Will Remain Until Sys in Compliance
05000348/LER-1996-005, :on 960827,valves Misalignment Occurred Due to Personnel Error in Missed Surveillance.Provided Summary of Event & Mgt Expectations to Appropriate Operations Personnel1996-09-20020 September 1996
- on 960827,valves Misalignment Occurred Due to Personnel Error in Missed Surveillance.Provided Summary of Event & Mgt Expectations to Appropriate Operations Personnel
05000348/LER-1996-003, :on 960602,actuation of ESF Equipment Occurred Due to Relay Contact Failure.Relay Replaced1996-06-27027 June 1996
- on 960602,actuation of ESF Equipment Occurred Due to Relay Contact Failure.Relay Replaced
05000348/LER-1996-002-01, :on 960529,TS Surveillance Requirements Not Met & common-cause Failure Identified.Caused by Personnel Error. Revised Surveillance Test Procedures & Modified Underfrequency Reactor Trip Circuits1996-06-27027 June 1996
- on 960529,TS Surveillance Requirements Not Met & common-cause Failure Identified.Caused by Personnel Error. Revised Surveillance Test Procedures & Modified Underfrequency Reactor Trip Circuits
05000364/LER-1996-002, :on 960422,discovered Misapplication of TS 4.4.6 Requirements Re F*.Caused by Inadequate Surveillance Test Procedure.Surveillance Test Procedure Will Be Revised1996-05-22022 May 1996
- on 960422,discovered Misapplication of TS 4.4.6 Requirements Re F*.Caused by Inadequate Surveillance Test Procedure.Surveillance Test Procedure Will Be Revised
05000364/LER-1996-001-01, :on 960408,2B DG Experienced Reduction Followed by Resumption in Speed During Auto Start Surveillance Test. Caused by Procedural Inadequacy.Dg Test Procedures Revised to Ensure Relay Actuated/Reset W/Proper Delays1996-05-0808 May 1996
- on 960408,2B DG Experienced Reduction Followed by Resumption in Speed During Auto Start Surveillance Test. Caused by Procedural Inadequacy.Dg Test Procedures Revised to Ensure Relay Actuated/Reset W/Proper Delays