ML19261B343

From kanterella
Jump to navigation Jump to search

Ack Receipt of Re NRC Position on Fee Requirements for Amends to Application Proposing Changes to ETS & Safety Tech Specs.Action Has Been Deferred by NRC So Previous Fee Payment Is Inappropriate
ML19261B343
Person / Time
Site: Millstone, Crystal River  Dominion icon.png
Issue date: 02/06/1979
From: Counsil W
NORTHEAST UTILITIES
To: Diggs R
NRC OFFICE OF ADMINISTRATION (ADM)
Shared Package
ML19261B344 List:
References
TAC-10857, TAC-11936, WGC-79-G-54, NUDOCS 7902150355
Download: ML19261B343 (1)


Text

,

IMHtTHI!AST IFFII.ITII!S I hhhhh eS""

~

m t <L := ===:c February 6,1979 WGC-79-G-54 Director of Administration U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Attn: Ms. R. M. Diggs License Fee Management Branch

Dear Ms. Diggs:

Millstone Nuclear Power Station Units 1 and 2 Proposed Revisions to Environmental Technical Specifications and to Safety Technical Specifications We have reviewed your letter of December 22, 1978 with respect to your position on fee requirements for our application of Octcber 20, 1978 for amendment to Facility Licenses DPR-21 and DPR-65. The application proposed numerous minor changes to the Environmental Technical Specifications (ETS) and Safety Technical Specifications (STS) for each unit.

The Division of Operating Reactors (0NRR) has notified us, in a letter dated December 5, 1978 (copy attached), Mr. D. L. Ziemann to Mr. W. G. Counsil, that the changes proposed in our October 20, 1978 submittal will be covered in their implementation of Appendix I Technical Specifications and reviewed concurrently with those activities. They have, therefore, deferred action on our request until that time.

Implementation of Appendix I will require extensive restructuring of both the ETS and STS, as directed by the Commission, and the changes requested on October 20, 1978 will be covered in this effart.

Since the Commission Staff has indicated that this major amendment will oe considered a Class III amendment, per the-at-tached letter dated July 11, 1978, payment of a fee at this time is inappropriate.

Subsequent to implementation of Appendix I, there may be a need to submit an ap-plication to address the remaining portions of the ETS and STS. Should any portion of our October 20, 1978 request not have been implemented, we will include those in that submittal and forward a determination pursuant to 10CFR170 at that time.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY l

d/;4'<A W. G. Cour.sil WGC/jmm Vice President cc: