ML19261A111

From kanterella
Jump to navigation Jump to search
NRC-2019-000288 - Resp 1 - Final, Agency Records Subject to the Request Are Enclosed (2018 San Onofre Unit 3 Decommissioning Funding Assurance Analysis)
ML19261A111
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/12/2019
From:
NRC/OCIO
To:
Shared Package
ML19261A098 List:
References
FOIA, NRC-2019-000288
Download: ML19261A111 (1)


Text

Datasheet 1 Decommissioining Funding Assurance Analysis As of December 31, 2017 For Plant Name: San Onofre Nuclear Gernerating Station, Unit 3 Docket Number: 50-362 DFP - 10 CFR 50.82(a)(8)(v)

(A) Cumulative Amount Spent on Decommissioning:

Amount Spent of Decommissioning Over the Previous Calendar Year:

Remaining Balance of Any Decommissioning Funds: $153,500,000 Amount Provided by Other Financial Assurance Methods: none (B) Estimated Cost of Remaining Decommissioing Activities as Stated in Most Recent SSCE update: $705,000,000 Difference Between Actual and Estimated Costs For Work Performed During Previous Year: provided Decommissioning Criteria for SSCE Basis Provided? provided (C) Any modifications to licensee's method of providing financial assurance since last report: None (D) Any material changes to trust agreements or financial assurance contracts: None DFP - 10 CFR 50.82(a)(8)(vi)

If the sum of the balance of any remaining decommissioning funds, earnings credit, and amount provided by other financial assurance methods does not cover the estimated cost to complete decommissioning, provide additional financial assurance to cover the estimated cost of completion below:

Additional Financial Assurance - N/A DFP - 10 CFR 50.82(a)(8)(vii)

(A) The total amount of dollars accumulated at the end of the appropriate year designated for managing irradiated fuel: (see below)

Licensee:  % Owned: Amount in Trust Fund:

Southern Cal Edison $1,370,900,000 San Diego Gas & Elec $412,500,000 Anaheim $52,200,000 Riverside $30,800,000 Total Trust Fund Balance $1,866,400,000 (B) The projected cost of spent fuel management until transfer of possession to DOE: $469,900,000 (C) If the funds accumulated do not cover the projected cost, provide a plan to obtain addional funds to cover the cost below:

Financial Assurance Plan - N/A Signature: NNewton Spreadsheet created by: Aaron Szabo, Shawn Harwell Date: 8/17/2015 Formulas verified by: Clayton Pittiglio