Text

e

I

UNITED STATES

8'

NUCLEAR REGULATORY COMMISSION

l

,.n

3+

c

REGION 11

' - ' '

8

101 MARIETTA sT., N.W., SUITE 310o

oY

ATLANT A, G EoRGI A 30303

g

.....

JUI.1 ' 1979

In Reply Refer To:

RII:RJH

S0-413/79-12

50-414/79-12

Duke Power Company

ATTN:

L. C. Dail, Vice President

Design Engineering

P. O. Box 33189

Charlotte, NC 28242

Gentlemen:

This refers to the inspection conducted by R. J. Hardwick of this office on

June 18-21, 1979, of activities authorized by NRC Construction Permit Nos.

CPPR-116 and CPPR-117 for the Catawba Nuclear Plant facility, and to the dis-

cussion of our findings held with D. L. Freeze at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

One new unresolved item resulted from this inspection and is discussed in the

enclosed report. This item will be examined during subsequent inspections.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with hTC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office, within 20 days of

your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2)

corrective steps which will be taken to avoid further noncompliance; and (3) the

date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

the information is proprietary, sad should be p epared so that proprietary

information identified in the application is contained in a separate part of the

document. If we do not hear frora you in this regard within the specified period,

the report will be placed in the Public Document Room.

m46 2D

79092703g4

.

.

M 1 J 7979

'

Duke Power Company

_2

~

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

.

~

[fd

E

Charles E. Murphy, Chief

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-413/79-12,

and 50-414/79-12

cc w/ enc 1:

D. G. Beam, Project Manager