ML19254B352
| ML19254B352 | |
| Person / Time | |
|---|---|
| Site: | Catawba |
| Issue date: | 07/11/1979 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Dail L DUKE POWER CO. |
| Shared Package | |
| ML19254B347 | List: |
| References | |
| NUDOCS 7909270354 | |
| Download: ML19254B352 (2) | |
See also: IR 05000413/1979012
Text
e
I
UNITED STATES
8'
NUCLEAR REGULATORY COMMISSION
l
,.n
3+
c
REGION 11
' - ' '
8
101 MARIETTA sT., N.W., SUITE 310o
oY
ATLANT A, G EoRGI A 30303
g
.....
JUI.1 ' 1979
In Reply Refer To:
RII:RJH
S0-413/79-12
50-414/79-12
Duke Power Company
ATTN:
L. C. Dail, Vice President
Design Engineering
P. O. Box 33189
Charlotte, NC 28242
Gentlemen:
This refers to the inspection conducted by R. J. Hardwick of this office on
June 18-21, 1979, of activities authorized by NRC Construction Permit Nos.
CPPR-116 and CPPR-117 for the Catawba Nuclear Plant facility, and to the dis-
cussion of our findings held with D. L. Freeze at the conclusion of the
inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with hTC requirements. This item and references
to pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions. Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is claimed that
the information is proprietary, sad should be p epared so that proprietary
information identified in the application is contained in a separate part of the
document. If we do not hear frora you in this regard within the specified period,
the report will be placed in the Public Document Room.
m46 2D
79092703g4
.
.
M 1 J 7979
'
Duke Power Company
_2
~
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
.
~
[fd
E
Charles E. Murphy, Chief
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-413/79-12,
and 50-414/79-12
cc w/ enc 1:
D. G. Beam, Project Manager
P. O. Box 223
Clover, SC 27910
1046 240