Text
'9
.
p mac
UNITED STATES
,
NUCLEAR REGULATORY Commission
y
o
REGION I
$
$
631 PARK AVENUE
f
KING OF PRUSSIA PENNSYLVANIA 19406
s...../
0
0
Docket No. 50-219
Jersey Central Power and Light Company
ATTN: Mr. Ivan R. Finfrock, Jr.
Vice President
Madison Avenue at Punch Bowl Road
Morristown, New Jersey
07960
Gentlemen:
Subject:
Inspection 50-219/79-11
This refers to the inspection conducted by Mr. L. Briggs of this office on May
7-11 and May 14, 1979 at Oyster Creek Nuclear Generating Plant, Forked River,
New Jersey of activities authorized by NRC License No. DPR-16 and to the discus-
sions of our findings held by Mr. Briggs with Mr. D. Ross and other members of
your staff at the conclusion of the inspection, and to a subsequent telephone
discussion between Mr. Briggs and Messrs. Sullivan, Jones, and Johnson on May
15, 16, 17, and 18, 1979.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter. Within
these areas, thc inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observations by the
inspector.
Our inspector also verified the steps you have taken to correct the item of
noncompliance brought to your attention in a letter dated April 4, 1979. We
have no further questions regarding the steps you are taking to correct this
item. We note that considerable work remains in this area to meet your commitment
date of October 1, 1979.
Based on the results of this inspection, it appears that one of your activities
was not conducted in full compliance with NRC requirements, as set forth in the
Notice of Violation, enclosed herewith as Appendix A.
This item of noncompliance
has been categorized into the levels as described in our correspondence to you
dated December 31, 1974. This notice is sent to you pursuant to the provisions
of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of
Federal Regulations.
Section 2.201 requires you to submit to this office,
within twenty (20) days of your receipt of this notice, a written statement or
explanation in reply including:
(1) corrective steps which have been taken by
you and the results achieved; (2) corrective steps which will be taken to avoid
further items of noncompliance; and (3) the date when full compliance will be
achieved.
.
1147
301
7910160/SW
.
.
-
.
Jersey Central Power and Light Company 2
AUG
8 1979
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosures will
be placed in the NRC's Public Document Room.
If this report contains any infor-
mation that you (or your contractor) believe to be proprietary, it is necessary
that you make a written application within 20 days to this office to withhold
such information from public disclosure. Any such application must be accompanied
by an affidavit executed by the owner of the information, which identifies the
document or part sought to be withheld, and which contains a statement of reasons
which addresses with specificity the items which will be considered by the
Conmission as listed in subparagraph (b) (4) of Section 2.790.
The information
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit.
If we do not hear from you in this regard within the
specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
)7
,
A
,
Eldon J. Brenner, Chief
Reactor Operations and Nuclear
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Inspection
Report Number 50-219/79-11
cc w/encls:
J. T. Carroll, Station Superintendent
A. Z. Roisman, Natural Resources Defense Council (Without Report)