Letter Sequence Meeting |
---|
EPID:L-2018-LLA-0233, License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-shift Staff Tables (Open) |
|
MONTHYEARML18226A1082018-04-10010 April 2018, 9 August 2018 License Amendment Request to Revise Technical Specification 5.2.2.g and Update Emergency Plan Minimum On-shift Staff Tables Project stage: Request RC-18-0091, License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions2018-08-29029 August 2018 License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions Project stage: Request ML18270A0182018-09-27027 September 2018 NRR E-mail Capture - V. C. Summer, Unit 1 - Acceptance of License Amendment Request Related to NFPA-805 Revision Project stage: Acceptance Review ML18337A4032018-12-0606 December 2018 Request for Additional Information Revise Technical Specification 5.2.2.G and Updating Emergency Plan Minimum On-Shift Staff Tables Project stage: RAI ML18355A4772019-01-0404 January 2019 Request for Additional Information Revise TS 5.2.2.g and Update Emergency Plan Minimum On-Shift Staff Tables Project stage: RAI ML19072A1442019-03-13013 March 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions Project stage: RAI ML19095A6532019-04-0404 April 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information NFPA-805 Program Revisions LAR Project stage: RAI ML19119A3652019-04-29029 April 2019 (Vcsns), Unit 1 - License Amendment Request - LAR-16-01490, NFPA 805 Program Revisions: Response to Request for Additional Information Project stage: Response to RAI ML19179A1262019-06-27027 June 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions Project stage: RAI ML19211D5102019-07-30030 July 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 (Supplement to PRA RAI 03) Project stage: RAI ML19196A2112019-08-0202 August 2019 July 23, 2019, Meeting Summary Regarding National Fire Protection Association 805 Supplement License Amendment Request Project stage: Meeting 2019-03-13
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23325A2452023-11-13013 November 2023 Enclosure 2 - Dominion Slides ML23325A2442023-11-13013 November 2023 Enclosure 1 - Attendance List ML23325A2432023-11-13013 November 2023 Regulatory Conference Summary ML23331A7892023-11-0909 November 2023 Nov. 2023 Enviro Scoping Meetings Related to the V.C. Summer Subsequent License Renewal Application Meeting Summary ML23171A9172023-06-20020 June 2023 Summary of Meeting Concerning the V.C. Summer Nuclear Station, to Discuss Annual Assessment for Period Jan 1, 2022 Through December 31, 2022 ML22270A2042022-09-30030 September 2022 Summary of Meeting Regarding a Potential Request to Modify the Reactor Vessel Surveillance Capsule Withdrawal Schedule for VC Summer ML22151A3332022-05-31031 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting Regarding the V.C. Summer Nuclear Station, Docket No. 50-395, Meeting Number 20220449 ML21131A1612021-05-11011 May 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Virgil C. Summer Nuclear Station, Docket No. 50-395; North Anna Power Station, Docket Nos. 50-338 and 50-339; and Surry Power Station, Docket Nos. 50-280 and 50-281, Meeting ML20213B1672020-08-13013 August 2020 July 23, 2020, Summary Regarding Second Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request ML20181A0052020-07-13013 July 2020 June 24, 2020, Summary Regarding Pre-Application Meeting to Discuss Proposed Technical Specification Task Force-425 License Amendment Request (EPID-L-2020-LRM-0049) ML20105A1482020-04-10010 April 2020 Public Meeting Summary Virgil C. Summer Nuclear Station ML19196A2112019-08-0202 August 2019 July 23, 2019, Meeting Summary Regarding National Fire Protection Association 805 Supplement License Amendment Request ML19123A1332019-05-0101 May 2019 Public Meeting Summary - V.C. Summer Nuclear Station, Docket No. 50-395 to Provide Opportunities to Discuss Annual Assessment of V.C Summer Nuclear Station with the Public for Period of January 01, 20018 - December 31-2018 ML19086A0272019-04-12012 April 2019 April 4, 2019, Meeting Summary Regarding Pre-application Meeting to Discuss Two Proposed Relief Requests ML18144A1482018-05-24024 May 2018 Public Meeting Summary - Virgil C. Summer Nuclear Station Docket No. 50-395 ML18068A0272018-03-22022 March 2018 Summary of March 15, 2018, Pre-Application Meeting with South Carolina Electric and Gas Company to Discuss a Future NFPA-805 Amendment (EPID-L-2018-LRM-0015) ML17103A5222017-04-12012 April 2017 Annual Assessment Meeting Summary 2017 ML15126A1962015-05-0505 May 2015 April 16, 2015 Public Meeting Summary - Category 1 - Virgil C. Summer Nuclear Station Units 2 and 3 Annual Assessment ML15119A5102015-04-29029 April 2015 Meeting Summary with Members of the Public Concerning the Annual Assessment of of Virgil C. Summer Nuclear Station, Unit 1, in Blair, S.C ML14106A4762014-04-16016 April 2014 End of Cycle 2013 Public Meeting Memo ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13199A1772013-07-31031 July 2013 Summary, June 20, 2013 Category 1 Meeting with South Carolina Electric and Gas Company, to Discuss Voluntary Fire Protection Risk Initiative Self-Assessment ML13123A1472013-05-0303 May 2013 Summary of Category 1 Public Meeting with South Carolina Electric and Gas,Virgil C. Summer Nuclear Station, Units 2 and 3, Annual Assessment ML13119A4112013-04-29029 April 2013 Summary of Category 3 Public Meeting, Virgil C. Summer Nuclear Station, Unit 1, Annual Assessment ML13098A8442013-04-11011 April 2013 Summary of Meeting with South Carolina Electric & Gas to Discuss Proposed Emergency Plan Changes ML12157A0452012-06-0404 June 2012 5/24/2012 - Summary of Category 3 Public Meeting - Virgil C. Summer Nuclear Station Unit 1 Annual Assessment and NRC Construction Oversight of Units 2 and 3 Combined Licenses ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML11152A0802011-06-14014 June 2011 Summary of March 31, 2011, Meeting with South Carolina Electric and Gas Company to Discuss NFPA-805 License Amendment ML1115204542011-06-0101 June 2011 Summary of Public Meeting with South Carolina Electric & Gas Co., V. C. Summer to Discuss the NRC Reactor Oversight Process and Annual Assessment ML1023804682010-08-26026 August 2010 08/18/10 Summary of Meeting NRC Initial Exam Writer'S Workshop ML1016704282010-06-17017 June 2010 Meeting Summary Notice ML0930005732009-11-0505 November 2009 Summary of September 14, 2009, Public Conference Call to Discuss Responses to Generic Letter 2004-02 Requests for Additional Information ML0923803922009-08-26026 August 2009 08/11-12/2009-Summary of Meeting Re 2009 Us NRC Initial Exam Development Workshop ML0911000692009-04-17017 April 2009 Summary of Meeting with Public/Open House to Discuss NRC Reactor Oversight Process and the Annual Assessment of the Virgil C. Summer Nuclear Station ML0835204162008-12-16016 December 2008 Public Meeting Summary, Virgil C. Summer Nuclear Station, Docket No. 05-395 IR 05000395/20075022007-07-30030 July 2007 Summary of Public Meeting - Virgil C. Summer Nuclear Station, to Discuss Significance on Apparent Violation Documented in Inspection Report 50-395-07-502 ML0713500592007-05-11011 May 2007 Summary of Public Meeting with South Carolina Electric & Gas Company to Brief the Licensee'S Post Outage Review of Refueling Outage 16 at Virgil C. Summer Nuclear Station IR 05000395/20070022007-04-30030 April 2007 IR 05000395-07-002; on 01/01/2007 - 03/31/2007 for South Carolina Electric & Gas Company; Virgil C. Summer Nuclear Station, Integrated Inspection Report and Annual Assessment Meeting Summary ML0627605282006-10-24024 October 2006 September 13, 2006, Summary of Meeting with South Carolina Electric & Gas Re Generic Letter 96-06 (TAC No. M96872) ML0627800022006-10-0404 October 2006 Summary for Meeting Between NRC and South Carolina Electric & Gas Company Refueling Outage 16 at Virgil Summer ML0621305672006-08-0101 August 2006 Summary of 07/19 - 07/20/2006 Meeting - 2006 Initial Exam Development Workshop ML0609601222006-04-0303 April 2006 Summary of Meeting with South Carolina Electric & Gas Company to Discuss the Results of the Root Cause Evaluation for the High Failure Rate on the January 10, 2006, Operator Licensing Initial Written Examination ML0601705522006-01-17017 January 2006 Comment Card Responses During January 9 Through 10, 2006, NRC Public Workshop ML0600304322005-12-30030 December 2005 Public Meeting Summary - Oct. 18, 2005 Category 1 Public Meeting-Summer, Docket # 50-395 ML0509704712005-04-0707 April 2005 Meeting Summary - Public Meeting - Virgil C. Summer Nuclear Power Station ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents ML0331404862003-11-0606 November 2003 ,Summary of Public Meetings to Discuss the Draft Supplement 15 of the Generic Environmental Impact Statement for the Renewal of the V. C. Summer Nuclear Station Operating License ML0328101292003-10-0606 October 2003 Summary of Post-Refueling Outage Meeting ML0328002772003-10-0606 October 2003 Closed Meeting Summary Between Usnrc/South Carolina Electric & Gas Co. to Discuss Sensitive Safeguards Information ML0224601912002-08-29029 August 2002 Summary of Meeting with Virgil C. Summer Nuclear Station, Post - Refueling Outage Meeting 2023-06-20
[Table view] |
Text
August 2, 2019 LICENSEE: South Carolina Electric & Gas, Inc. (SCE&G)
FACILITY: Virgil C. Summer, Unit 1
SUBJECT:
VIRGIL C. SUMMER, UNIT 1 - JULY 23, 2019, MEETING
SUMMARY
REGARDING NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) 805 SUPPLEMENT LICENSE AMENDMENT REQUEST (EPID L-2018-LLA-0233)
On July 23, 2019, a Category 1 public teleconference call was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of South Carolina Electric & Gas Company (SCE&G, licensee) and its contractor, Jensen Hughes, to discuss technical issues related to the licensee's proposed response to U.S. Nuclear Regulatory Commission (NRC) June 27, 2019, Request for Additional Information (RAI) for PRA RAI 03 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19179A126).
The public meeting notice and agenda, dated July 9, 2019 (ADAMS Accession No. ML19196A066), are available in the NRC Public Meeting website. A list of participants is provided in Enclosure 1.
Public Conference Call During the meeting, SCE&G stated they plan to respond to the June 27, 2019, RAI, utilizing option (ii):
(ii) Alternatively to part (i), provide updated risk results in Table PRA RAI 03-1 of letter dated May 22, 2019 that uses the system time window for operator action to trip RCPs based on the FPRA RCP seal failure model accepted in the safety evaluation associated with Amendment No. 199, and discuss how the updated risk results align with the risk acceptance guidelines of Regulatory Guide 1.205. Propose a mechanism that ensures an NRC-accepted RCP seal failure model is used in the FPRA for self-approval of post-transition changes.
The licensee stated that they plan to revise the Human Error Probability (HEP) for Reactor Coolant Pump (RCP) trip from 60 minutes to 20 minutes as approved in Amendment No. 199.
The licensee stated that they are pursuing the below areas of PRA refinement to meet the risk acceptance guidelines of Regulatory Guide 1.205:
- 1. Amount of water available for seal injection (i.e., RWST draindown).
- 2. More extensive circuit analysis and refined cable locations related to loss of seal cooling, RCP trip, etc.
- 3. Existing fire and other procedures and HRA treatment for refinements.
- 4. More refined main control board (MCB) fire scenarios for specific failure modes and locations. The licensee stated they are considering utilizing the draft NUREG-2178, Refining and Characterizing Heat Release Rates from Electrical Enclosures During Fire, Volume 2, Fire modeling guidance for electrical cabinets, electric motors, indoor dry transformers, and the main control board.
The NRC staff provided the below feedback that was discussed at the meeting, and sent to the licensee on July 30, 2019, as a supplement to the June 27, 2019, PRA RAI 03 (ADAMS Accession No. ML19211D510).
Supplement to Option (ii) [based on July 23, 2019, teleconference discussion]:
Describe in sufficient detail any additional changes to the VCSNS PRA models (i.e.,
internal events, internal flooding, seismic, and fire) in support of the updated risk results that were not described in the LAR dated August 29, 2018, as supplemented by letters dated April 29, 2019 and May 22, 2019.
Explain and justify whether the changes are PRA maintenance or PRA upgrades as defined in ASME/ANS RA-Sa-2009, Section 1-5.4, as qualified by Regulatory Guide 1.200, Revision 2.
For all PRA changes that constitute a PRA upgrade, state if a peer review has been performed for any PRA upgrades in accordance with an NRC-accepted process. As applicable, provide the open facts and observations (F&Os) characterized as findings associated with this peer review and explain how the F&Os were dispositioned to Capability Category II for this application.
If a peer review was not performed for PRA upgrades, propose a license condition such that prior to implementing self-approval of post-NFPA-805 transition changes:
PRA upgrades will be appropriately peer reviewed and any finding-level F&Os are closed in accordance with an NRC-accepted process (e.g., focused-scope peer review, F&O closure review, direct submittal to the NRC), and, Confirm that the updated transition change-in-risk estimates for this application align with the risk acceptance guidelines of Regulatory Guide 1.205.
SCE&G stated they will submit a response to the June 27, 2019, RAI by August 12, 2019, that will include a description of the PRA refinements, a proposed schedule for submitting a complete response to the June 27, 2019, RAI, and justification for the extended period of time beyond the 30 days RAI response time allowed by regulation.
Regarding the licensees consideration of utilizing draft NUREG-2178, the NRC staff notes LIC-109, Revision 2, Acceptance Review Procedures (ADAMS Accession No. ML16144A521),
states, Unapproved guidance may be used as the basis for a proposed change, however, the licensee must supply all information necessary (i.e., plant-specific justification and technical basis) to support the change.
No regulatory decisions or commitments were made during the meeting. There were no members of the public on the call.
/RA/
Shawn Williams, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-395
Enclosure:
List of Attendees cc: Listserv
ML19196A211 OFFICE DORL/LPL2-1/PM DORL/LPL2-1/LA NRR/DRA/APLB/BC DORL/LPL2-1/BC DORL/LPL2-1/PM NAME SWilliams KGoldstein MReisi Fard MMarkley SWilliams DATE 7/30/19 8/1/19 8/1/19 8/2/19 8/2/19 LIST OF PARTICIPANTS JULY 23, 2019, PUBLIC CONFERENCE CALL WITH SOUTH CAROLINA ELECTRIC & GAS REGARDING NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) 805 SUPPLEMENT LICENSE AMENDMENT REQUEST Nuclear Regulatory Commission Staff Shawn Williams JS Hyslop Todd Hilsmeier Mehdi Reisi Fard Ed Miller Ching Ng Tomy Nazario Cruz Eliza Hilton Ellery Coffman Philipp Braaten Licensee Participants Sara Beth Dalick, SCE&G Jody Galloway, SCE&G Ken Leonelli, SCE&G Jim Stanley, SCE&G Craig Sly (Dominion)
Lauren Lopez (Dominion)
Usama Farradj (Jensen Hughes)
Andy Ratchford (Jensen Hughes)
Guy Ragan (Jensen Hughes)
Frank Hope (Jensen Hughes)
Vincent Rubano (Jensen Hughes)
Pierre Macheret (Jensen Hughes)
Enclosure