Letter Sequence Request |
---|
EPID:L-2020-LLE-0050, Township of Lacey'S Petition for Leave to Intervene and Hearing Request (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARML18312A2512018-11-0808 November 2018 Township of Lacey'S Petition for Leave to Intervene and Hearing Request Project stage: Request ML18324A6382018-11-16016 November 2018 Comments from the Concerned Citizens for Lacey Coalition Regarding the Oyster Creek Nuclear Generating Station Application for Direct Transfer of License Project stage: Request ML18337A4192018-12-0303 December 2018 Applicants' Joint Answer to Township of Lacey Project stage: Request ML19009A3262019-01-0707 January 2019 Comments from the Concerned Citizens of Lacey Coalition on Oyster Creek Nuclear Plant License Transfer Project stage: Request ML19008A4942019-01-15015 January 2019 Post-Shutdown Decommissioning Activities Report - NRC Presentation at Public Meeting on January 15, 2019 Project stage: Request ML19009A1712019-01-15015 January 2019 Post-Shutdown Decommissioning Activities Report, NRC Public Meeting January 15, 2019 Project stage: Request ML19009A3432019-01-15015 January 2019 Holtec Slides PSDAR Meeting 1-15-19 Project stage: Request ML19032A0732019-01-31031 January 2019 Comment (1) from Anonymous on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19046A0172019-02-13013 February 2019 Comment (2) from Anonymous on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19051A0192019-02-20020 February 2019 Watch Petition to Intervene and Hearing Request Project stage: Request ML19051A1142019-02-20020 February 2019 Commonwealth of Massachusetts' Petition for Leave to Intervene and Hearing Request Project stage: Request ML19057A1882019-02-24024 February 2019 Comment (3) of Anonymous Individual on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19057A1902019-02-24024 February 2019 Comment (4) from Anonymous Regarding Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19057A5692019-02-25025 February 2019 Comment from Jim R. Garb on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19060A2282019-02-26026 February 2019 Comment from Henrietta Cosentino on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19059A0232019-02-27027 February 2019 Comment (5) of Rebecca Chin on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19065A1802019-03-0101 March 2019 Comment (6) of David Noyes Supporting Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19070A1762019-03-0101 March 2019 Comments from Carolyn Barthel on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1612019-03-0101 March 2019 Comments from Chris Riger on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A1872019-03-0101 March 2019 Comment (7) of Henrietta Cosentino on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19060A2272019-03-0101 March 2019 Comment from the Associated Industries of Massachusetts on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1672019-03-0202 March 2019 Comments from Irene Paine on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1662019-03-0202 March 2019 Comments from Gertrude Carter on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1622019-03-0202 March 2019 Comments from David Agnew on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A2582019-03-0202 March 2019 Comment from James Sinclair on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A2572019-03-0202 March 2019 Comments from William Stewart on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1682019-03-0303 March 2019 Comments from Joan Holt on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1752019-03-0303 March 2019 Comments from Betsy Smith on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1742019-03-0303 March 2019 Comments from Barbara Clark on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1722019-03-0303 March 2019 Comments from Alex Bally on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1712019-03-0303 March 2019 Comments from Nicola Blake on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1702019-03-0303 March 2019 Comments from Lillia Frantin on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1692019-03-0303 March 2019 Comments from Lesley Phillips on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19064B3302019-03-0303 March 2019 Comment from James B. Lampert on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A1922019-03-0303 March 2019 Comment (9) of James B. Lampert on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19065A1882019-03-0303 March 2019 Comment (8) of Mary Gatslick on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19070A1642019-03-0303 March 2019 Comments from Diana Maher on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A1932019-03-0404 March 2019 Comment (10) of J. B. Lampert on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19065A1962019-03-0404 March 2019 Comment (11) of Guy Page on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19072A3122019-03-0404 March 2019 Comments from Guy Page on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19072A3142019-03-0404 March 2019 Comments from Commonwealth of Massachusetts on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1772019-03-0404 March 2019 Comments from Catherine Berkey on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19064B3312019-03-0404 March 2019 Comments from the Cape Downwinders and Boston Downwinders on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19064B3322019-03-0404 March 2019 Comment from Pilgrim Watch on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19064B3452019-03-0404 March 2019 Comment from Pine Dubois on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19070A1652019-03-0404 March 2019 Comments Received from Concerned Citizens of Massachusetts on the Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment (NRC-2018-0279) Project stage: Request ML19065A1982019-03-0404 March 2019 Comment (12) of Brad Ferland on Pilgrim Nuclear Power Station; Consideration of Approval of Transfer of License and Conforming Amendment Project stage: Request ML19109A1772019-04-17017 April 2019 Response to NRC Request for Additional Information Project stage: Response to RAI ML19114A5192019-04-24024 April 2019 Motion of the Commonwealth of Massachusetts to Supplement Its Petition with New Information Project stage: Request ML19129A4732019-05-0909 May 2019 Watch Motion to Supplement Its Motion to Intervene and Request for Hearing, Biodiversity (05.09.19) Project stage: Request 2019-02-25
[Table View] |
|
---|
Category:Legal-Motion
MONTHYEARML20079J1802020-03-19019 March 2020 Unopposed Motion of the Commonwealth of Massachusetts to Correct a Previously Filed Declaration ML20035C7562020-01-30030 January 2020 1-30-20 Entergy Motion to Intervene (DC Cir.)(Case No. 20-1019) ML20031D4332020-01-29029 January 2020 1-29-20 Reply to Response to Motion to Dismiss (DC Cir.)(Case No. 19-1198) ML19347D4152019-12-13013 December 2019 Motion of the Commonwealth of Massachusetts to Amend Its Petition with New Information ML19303B4252019-10-28028 October 2019 Transport Room (Motion for Stay Pending Appellate Review)(Dc Cir.)(Case No. 19-1198) 10-28-19 ML19295E6852019-10-16016 October 2019 Entergy Motion to Intervene (DC Cir.)(Case No. 19-1198) 10-16-19 ML19247E5092019-09-0404 September 2019 Motion of the Commonwealth of Massachusetts for a Twenty-Two Minute Enlargement of Time to File Its Stay Application and Supporting Appendix ML19247B4312019-09-0303 September 2019 Application of the Commonwealth of Massachusetts for a Stay of the Effectiveness of the NRC Staff Actions Approving the License Transfer Application and Request for an Exemption to Use the Decommissioning Trust Fund for Non-Decommissioning ML19246A0322019-09-0303 September 2019 Watch Motion to Stay Staff Order of August 22, 2019 Granting Exemption ML19246A0332019-09-0303 September 2019 Watch Motion Under 10 C.F.R 2.1327 to Stay Staff Order of August 22, 2019 ML19230A0212019-08-18018 August 2019 Reply of the Commonwealth of Massachusetts in Support of Its Motion for an Enlargement of Time to File an Application to Stay a Nuclear Regulatory Commission Staff Order Approving the License Transfer Application ML19227A0682019-08-15015 August 2019 Emergency Motion of the Commonwealth of Massachusetts for Clarification of the Commission'S August 14, 2019 Memorandum and Order ML19227A3982019-08-15015 August 2019 Emergency Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File an Application to Stay a Nuclear Regulatory Commission Staff Order Approving the License Transfer Application ML19213A3132019-08-0101 August 2019 Motion of the Commonwealth of Massachusetts to Stay Proceeding to Complete Settlement Negotiations ML19129A3732019-05-0909 May 2019 Commonwealth of Massachusetts' Reply in Support of Motion to Supplement Its Petition with New Information ML19129A4732019-05-0909 May 2019 Watch Motion to Supplement Its Motion to Intervene and Request for Hearing, Biodiversity (05.09.19) ML19114A5192019-04-24024 April 2019 Motion of the Commonwealth of Massachusetts to Supplement Its Petition with New Information ML19091A1892019-04-0101 April 2019 Watch Reply to Applicant'S Answer Opposing Pilgrim Watch Petition for Leave to Intervene and Hearing Request ML19077A2092019-03-18018 March 2019 Notices of Appearance of David R. Lewis, Anne R. Leidich, and Susan H. Raimo ML19077A2762019-03-18018 March 2019 Unopposed Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File Its Reply ML12257A3392012-09-13013 September 2012 Filed Copy - Joint Motion to Amend Briefing Schedule - Massachusetts V NRC - 1st Cir 12-1404 and 12-1772 ML12195A0802012-07-13013 July 2012 Notice of Appearance for Joseph A. Lindell for ESA Roseate Term ML12157A1872012-06-0505 June 2012 Notice of Appearance from Joseph A. Lindell on Entergy Nuclear Operations, Inc., (Pilgrim) ML12137A2582012-05-16016 May 2012 Notice of Appearance for Joseph A. Lindell ML12136A5172012-05-15015 May 2012 NRC Staff'S Unopposed Motion for an Extension of Time to Respond to Jones River Watershed Association and Pilgrim Watch'S May 14, 2012, Request to Reopen, for a Hearing and to File New Contentions ML12132A4682012-05-11011 May 2012 Motion to Strike ML12097A2222012-04-0505 April 2012 Entergy Motion to Strike Petitioners' Affidavit and Portions of Petitioners' Reply ML11357A2092011-12-23023 December 2011 Commonwealth of Massachusetts' Motion to Reply to NRC Staff and Entergy Oppositions to Commonwealth Appeal of LBP-11-35 ML11290A1812011-10-17017 October 2011 Commonwealth of Massachusetts Motion to Reply to NRC Staff Answer to Massachusetts Request to Stay Commission Decision on Pilgrim Watch Appeal or in the Alternative to Strike Reference to Massachusetts Expert ML11258A0262011-09-15015 September 2011 Commonwealth of Massachusetts Amended Motion to Reply to NRC Staff and Entergy Oppositions to Commonwealth Motion to Supplement Bases to Its Contention ML11256A3042011-09-13013 September 2011 Commonwealth of Massachusetts Motion to Reply to NRC Staff and Entergy Oppositions to Commonwealth Motion to Supplement Bases to Its Contention ML11235B0962011-08-23023 August 2011 Applicant'S Motion for Issuance of Renewed License ML11223A2842011-08-11011 August 2011 Commonwealth of Massachusetts Motion to Supplement Bases to Commonwealth Contention to Address NRC Task Force Report on Lessons Learned from the Radiological Accident at Fukushima ML1115303402011-06-0202 June 2011 Commonwealth of Massachusetts' Motion to Admit Contention and, If Necessary, to Re-Open Record Regarding New and Significant Information Revealed by Fukushima Accident ML1115303442011-06-0202 June 2011 Commonwealth of Massachusetts' Conditional Motion to Suspend Pilgrim Nuclear Power Plant License Renewal Proceeding Pending Resolution of Petition for Rulemaking to Rescind Spent Fuel Pool Exclusion Regulations ML1113905722011-05-19019 May 2011 Commonwealth of Massachusetts Motion to Reply to Entergy'S Answer Opposing Commonwealth'S Joinder in Petition to Suspend the License Renewal Proceeding for the Pilgrim Nuclear Power Plant and Request for Additional Relief ML1113905702011-05-19019 May 2011 Commonwealth of Massachusetts Motion to Reply to the Answers of the NRC Staff and Entergy in Opposition to the Commonwealth of Massachusetts Motion to Hold Licensing Decision in Abeyance Pending Commission Decision Weather to Suspend the Pi ML1112203262011-05-0202 May 2011 Commonwealth of Massachusetts Motion to Hold Licensing Decision in Abeyance Pending Commission Decision Whether to Suspend the Pilgrim Proceeding to Review the Lessons of the Fukushima Accident ML1102407012011-01-24024 January 2011 Entergy'S Motion to Strike Portions of Pilgrim Watch'S Reply to Entergy'S and the NRC Staff'S Answers Opposing Pilgrim Watch'S Request for Hearing on a New Contention ML1101306682011-01-13013 January 2011 Entergy'S Motion in Limine to Exclude from Evidence Pilgrim Watch'S Sama Remand Pre-Filed Testimony and Exhibits ML1100503302010-12-30030 December 2010 Entergy Request for Change in Hearing Date ML1035004002010-12-13013 December 2010 Pilgrim Watch Request for Hearing on a New Contention: Inadequacy of Entergy'S Aging Management of Non-Environmentally Qualified (EQ) Inaccessible Cables (Splices) at Pilgrim Station ML1032103122010-11-0404 November 2010 Pilgrim Watch Request Extension Submit Affidavits ML1027800452010-10-0404 October 2010 NRC Staff'S Answer to Pilgrim Watch Motion Regarding ASLB Refusal to Respond to Pilgrim Watch'S Motion for Clarification ML1027300422010-09-22022 September 2010 Pilgrim Watch Motion Regarding ASLB Refusal to Respond to Pilgrim Watch'S Motion for Clarification ASLB Order (Sept 2, 2010) ML1025803182010-09-0909 September 2010 Pilgrim Watch Motion for Clarification ASLB Order (Sept. 02, 2010) ML1017301822010-06-16016 June 2010 Motion Requesting Leave to File Response to Judge Paul B. Abramson Decision on Recusal Motion (June 10, 2010) ML1015404252010-05-26026 May 2010 Pilgrim Watch Request for Permission, and Reply to NRC Staff'S Response to Pilgrim Watch Motion to Disqualify Judge Abramson ML1014500892010-05-24024 May 2010 NRC Response to Pilgrim Watch Motion to Disqualify Judge Paul B. Abramson ML1015404242010-05-24024 May 2010 Pilgrim Watch Request for Permission, and Reply to Entergy'S Opposition to Pilgrim Watch Motion to Disqualify Judge Abramson 2020-03-19
[Table view] |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of Docket No. 50-293 & 72-1044 LT Entergy Corporation Pilgrim Nuclear Power Station License Transfer Agreement Application PILGRIM WATCH MOTION TO SUPPLEMENT ITS MOTION TO INTERVENE AND REQUEST FOR HEARING - BIODIVERSITY (05.09.19)
Pilgrim Watch requests further to supplement its Motion to Intervene and Request for Hearing filed February 20, 2019, its Reply to Petitioners filed April 1, 2019, and its Motion to Supplement filed May 3, 2019 with new and significant information regarding biodiversity, under 10 C.F.R. § 2.323.
Specifically, Pilgrim Watch asks to supplement the record by adding (1) the Summary for policymakers of the global assessment report on biodiversity and ecosystem services of the Intergovernmental Science-Policy Platform on Biodiversity and Ecosystem Services, https://www.ipbes.net/sites/default/files/downloads/spm_unedited_advance_for_posting_htn.pdf, issued by the United Nations Intergovernmental Science-Policy Platform on Biodiversity and Ecosystem Services (IPBES) on May 6, 2019, and (2) a United Nations statement, https://www.un.org/sustainabledevelopment/blog/2019/05/nature-decline-unprecedented-report/,
1
issued on the same day. The report summary was approved at the 7th session of the IPBES Plenary meeting 29 April-4 May) in Paris.
On May 6, 2019, the New York Times described the report: 1 Humans are transforming Earths natural landscapes so dramatically that as many as one million plant and animal species are now at risk of extinction, posing a dire threat to ecosystems that people all over the world depend on for their survival. The 1,500-page report, compiled by hundreds of international experts and based on thousands of scientific studies, is the most exhaustive look yet at the decline in biodiversity across the globe and the dangers that creates for human civilization. A summary of its findings, which was approved by representatives from the United States and 131 other countries, was released Monday in Paris. The full report is set to be published this year. Unless nations step up their efforts to protect what natural habitats are left, they could witness the disappearance of 40 percent of amphibian species, one-third of marine mammals The Summary and United Nations Statement are relevant to Pilgrim Watchs contentions set forth in its Motion to Intervene.
They are particularly relevant to some of Pilgrim Watchs bases for contention 2, e.g., that the potential environmental impacts of decommissioning are not bounded by previous environmental impact statements (Motion to Intervene, p. 91) and that new and significant information not considered in those previous statements required Entergy and Holtec to submit a Supplement to Applicants Environmental Report with their license transfer application (10 C.F.R. §51.53(d)). (Pilgrim Watch Reply to Applicants Answer Opposing Pilgrim Watch Petition for Leave to Intervene and Hearing Request, p. 32.)
1 New York Times, Humans are Speeding Extinction and Altering the Natural World at an Unprecedented Pace, Brad Plumer, May 6, 2019 (https://www.nytimes.com/2019/05/06/climate/biodiversity-extinction-united-nations.html) 2
The new information in the Summary and Statement provide evidence that Holtecs and Entergys assertions that the proposed direct transfer has no environmental impact (LTA, p. 20) and that the environmental impacts associated with planned PNPS site specific decommissioning are are bounded by the previously issue environmental impact statements (Holtec PSDAR, p 20, see also pp 3, 21-25, 29, 31-38) are incorrect. See, e.g. By the numbers-Statistics and Facts from the Report section of the UN Report.
It seems abundantly clear that NRC and other federal and state authorities must reassess the environmental impacts in the IPBES report. The UN reports are new and provides significant information showing that neither the GEIS, SEIS nor the Fact Sheet included in the 2016 draft NPDES permit for PNPS bounded the environmental impacts that Holtec and Entergy relied upon in its LTA and PSDARs.
The IPBES report also ties directly to Pilgrim Watchs Contention 1, insufficiency of funds.
The report is likely to lead to the conclusion that assurance that fewer pollutants are left on the site likely would will result in the expenditure of more funds and that these additional needed funds should be part of the cost estimate. PWs Motion to Intervene showed, at 20, that Holtecs assumption that only 0.03% of the DTF will remain after decommissioning means the DTF will not be sufficient if any of Holtecs cost estimate assumptions are too low, or if Holtec Pilgrim and HDI incur any of the multitudinous additional costs that are not considered in the PSDAR or DCE.
The new information is material to the outcome of this proceeding. The new information impacts whether the license transfer application should be granted or denied. In the Matter of Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Units 2 and 3) Docket Nos. 50-336-LR, 50-423-LR ASLBP No. 04-824-01-LR July 28, 2004, p. 7. Bases and fact support the motion.
3
This Motion is timely. The new information became available on May 4, 2019 in Paris and May 5 in the U.S. press, this Motion is being filed on May 10, 2019, only four to five days later.
Pilgrim Watch conferred with the Applicants on May 9, 2019. Counsel for the Applicants indicated that they oppose this Motion. Pilgrim Watch also conferred with the Commonwealth. The Commonwealth replied that it does not intend to oppose the motion.
For the above reasons, Pilgrim Watch requests that the Commission grant this Motion and consider this new information in connection with its consideration of the Pilgrim Watchs pending Petition and Reply filed in order to best protect the public health, safety and financial interests of the Commonwealth.
Date: May 9, 2019 Signed (electronically) by Mary Lampert Pilgrim Watch, director 148 Washington Street Duxbury, MA 02332 Tel. 781.934.0389 Email: mary.lampert@comcast.net 4
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of Docket No. 50-293 & 72-1044 LT Entergy Corporation Pilgrim Nuclear Power Station License Transfer Agreement Application CERTIFICATION OF SERVICE Pursuant to 10 C.F.R. § 2.305, I certify that copies of Pilgrim Watchs Motion to Supplement Its Motion to Intervene and Request for Hearing has been served upon the Electronic Information Exchange, the NRCs e-filing system, in the above-captioned proceeding, on May 9, 2019.
Date: May 9, 2019 Signed (electronically) by Mary Lampert Pilgrim Watch, director 148 Washington Street Duxbury, MA 02332 Tel. 781.934.0389 Email: mary.lampert@comcast.net 5