Shearon Harris Nuclear Power Plant UFSAR Chapter: 17 Amendment 61 Page i of i 17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION........................... 1 17.2 DELETED BY AMENDMENT NO. 46........................................................................... 1 17.3 DELETED BY AMENDMENT 61.................................................................................. 1

Shearon Harris Nuclear Power Plant UFSAR Chapter: 17 Amendment 61 Page 1 of 1 17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION The PSAR QA program was implemented for the original plant design and construction activities.

17.2 DELETED BY AMENDMENT NO. 46 17.3 DELETED BY AMENDMENT 61 The description of the Quality Assurance Program is contained in the Duke Energy Corporation Topical Report Quality Assurance Program Description Operating Fleet, DUKE-QAPD-0001-A.

That Topical Report follows the format and content guidance of NUREG-0800 Section 17.3 except it is based on ANSI N18.7-1976 in lieu of ANSI/ASME NQA-1 and NQA-2.

Topical Report DUKE-QAPD-0001-A is incorporated by reference into the UFSAR.

Shearon Harris Nuclear Power Plant UFSAR Chapter: 17 Amendment 61 Page 1 of 1 TABLE TITLE N/A THERE ARE NO TABLES FOR CHAPTER 17

Shearon Harris Nuclear Power Plant UFSAR Chapter: 17 Amendment 61 Page 1 of 1 FIGURE TITLE N/

THERE ARE NO FIGURES FOR CHAPTER 17