NRR E-mail Capture - Three Mile Island Nuclear Station, Unit 1 - Acceptance of Requested Licensing Action License Amendment Request for Changes to Tendon Surveillance Program Technical Specifications
ML18297A043
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 10/24/2018
From: Justin Poole
Plant Licensing Branch 1
To: Mascitelli F
Exelon Generation Co
References
L-2018-LLA-0255
Download: ML18297A043 (3)


Text

NRR-DMPSPEm Resource From: Poole, Justin Sent: Wednesday, October 24, 2018 9:03 AM To: Mascitelli, Francis J:(GenCo-Nuc)

Cc: Danna, James

Subject:

THREE MILE ISLAND NUCLEAR STATION, UNIT 1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST FOR CHANGES TO TENDON SURVEILLANCE PROGRAM TECHNICAL SPECIFICATIONS (EPID L-2018-LLA-0255)

SUBJECT:

THREE MILE ISLAND NUCLEAR STATION, UNIT 1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST FOR CHANGES TO TENDON SURVEILLANCE PROGRAM TECHNICAL SPECIFICATIONS (EPID L-2018-LLA-0255)

By letter dated September 20, 2018, Exelon Generation Company, LLC submitted a license amendment request for Three Mile Island Nuclear Station, Unit 1. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal and discussions during the pre-licensing meeting on September 13, 2018, the NRC staff has estimated that this licensing request will take approximately 155 hours6.458 days <br />0.923 weeks <br />0.212 months <br /> to complete. The NRC staff expects to complete this review by October 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Thanks.

Justin C. Poole Project Manager NRR/DORL/LPL I U.S. Nuclear Regulatory Commission (301)415-2048 1

2 Hearing Identifier: NRR_DMPS Email Number: 637 Mail Envelope Properties (Justin.Poole@nrc.gov20181024090200)

Subject:

THREE MILE ISLAND NUCLEAR STATION, UNIT 1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST FOR CHANGES TO TENDON SURVEILLANCE PROGRAM TECHNICAL SPECIFICATIONS (EPID L-2018-LLA-0255)

Sent Date: 10/24/2018 9:02:40 AM Received Date: 10/24/2018 9:02:00 AM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:

"Danna, James" <James.Danna@nrc.gov>

Tracking Status: None "Mascitelli, Francis J:(GenCo-Nuc)" <Francis.Mascitelli@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2915 10/24/2018 9:02:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: