NUREG-1350, Vol. 30, Information Digest 2018-2019, Section 7, Appendix B
ML18226A126
Person / Time
Issue date: 08/14/2018
From: Couret I L
Office of Public Affairs
To:
Meyd, Donald
Shared Package
ML18226A101 List:
References
NUREG-1350 V30
Download: ML18226A126 (1)


Text

112 Applicant Docket Number TypeSubmittal Date Design Site StateExisting Plant?Date Accepted Status Combined License (Construction and Operating)Nuclear Innovation North America, LLC 05200012 &

05200013 COL 9/20/07 ABWRSouth Texas Project, Units 3 and 4 TXYes 11/29/07 COL Issued 02/09/2016Tennessee Valley Authority (TVA)05200014 &

05200015 COL 10/30/07 AP1000Bellefonte, Units 3 and 4 AL No 1/18/08Withdrawn-12/02/2016Dominion Virginia Power 05200017 COL 11/27/07 ESBWRNorth Anna, Unit 3 VAYes 01/28/08 COL Issued 06/02/2017 Duke Energy Carolinas05200018 &

05200019 COL 12/13/07 AP1000Lee Nuclear Station, Units 3 and 4 SC No 2/25/08 COL Issued 12/19/2016 Progressive Energy05200022 &

05200023 COL 2/19/08 AP1000Shearon Harris, Units 2 and 3 NCYes 4/17/08 Suspended-05/02/2013Southern Nuclear Operating Co.05200025 &

05200026 COL 3/31/08 AP1000Vogtle, Units 3 and 4 GAYes 5/30/08 COL Issued 02/10/2012South Carolina Electric and Gas05200027 &

05200028 COL 3/31/08 AP1000V.C. Summer, Units 2 and 3 SCYes 7/31/08 COL Issued 03/30/2012 AmerenUE 05200037 COL 7/24/08U.S. EPRCallaway, Unit 2 MOYes 12/12/08Withdrawn-10/19/2015Duke Energy Florida05200029 &

05200030 COL 7/30/08 AP1000Levy County, Units 1 and 2 FL No 10/6/08Withdrawn-04/26/2018DTE Electric Company 05200033 COL 9/18/08 ESBWRFermi, Unit 3 MIYes 11/25/08 COL Issued 05/01/2015Luminant Generation Co.05200034 &

05200035 COL 9/19/08 US-APWRComanche Peak, Units 3 and 4 TXYes 12/2/08 Suspended-03/31/2014Entergy 05200036 COL 9/25/08 ESBWRRiver Bend, Unit 3 LAYes 12/4/08Withdrawn-06/14/2016 PPL Bell Bend 05200039 COL 10/10/08U.S. EPRBell Bend (1 Unit)PAYes 12/19/08Withdrawn-09/22/2016Florida Power and Light05200040 &

05200041 COL 6/30/09 AP1000Turkey Point, Units 6 and 7 FLYes 9/4/09 COL Issued 04/12/2018 Design Certi~cationAREVA NP 05200020 DC 12/11/07U.S. EPR N/A N/A N/A 2/25/08Suspended-03/27/2015Mitsubishi Heavy Industries 05200021 DC 12/31/07 US-APWR N/A N/A N/A 2/29/08Applicant Delayed

-Not ScheduledKorea Electric Power Company and Korea Hydro and Nuclear Power 05200046 DC 12/23/14 APR 1400 N/A N/A N/A 3/4/15Scheduled Toshiba Corporation 05200044 DC 10/27/10 ABWR N/A N/A N/A 12/14/10Withdrawn-12/30/2016GE-Hitachi Nuclear Energy 05200045DC 12/7/10 ABWR N/A N/A N/A 2/14/11 ScheduledNuScale Power LLC 05200048DC 01/6/17 NuScale N/A N/A N/A 3/23/17 Scheduled Early Site Permit PSEG Site 05200043 ESP 5/25/10Not yet announced PSEG Site NJYes 8/4/10Issued 05/06/2016TVA Clinch River SMR Site 05200047 ESP 5/25/10Not yet announced Clinch River Site TN No 1/12/17 Scheduled APPENDIX B New Nuclear Power Plant Licensing Applications Notes: Withdrawal was requested for Calvert Cliffs, Grand Gulf, Nine Mile Point, Victoria County, Bellefonte, and Callaway (COL and ESP). On July 31, 2017, a decision was announced by South Carolina Electric & Gas (SCE&G) to cease construction on V.C. Summer nuclear power plant, Units 2 and 3 , and by letter dated December 27, 2017, SCE&G requested withdrawl of the corresponding COLs; NRC action is still pending. In September 2017, Duke Energy announced cancellation of William States Lee nuclear power plant, Units 3 and 4 project. As of June 2018, Nuclear Innovation North America submitted a letter requesting that the COLs for South Texas Project, Units 3 and 4, be withdrawn.

Data are current as of May 2018; the next printed update will be in August 2019. NRC-abbreviated reactor names listed.