ML18190A203

From kanterella
Jump to navigation Jump to search
Notification of NRC Triennial Heat Sink Performance Inspection (05000298/2018003) and Request for Information
ML18190A203
Person / Time
Site: Cooper Entergy icon.png
Issue date: 07/06/2018
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Dent J
Nebraska Public Power District (NPPD)
Farnholtz T
References
IR 2018003
Download: ML18190A203 (7)


See also: IR 05000298/2018003

Text

July 6, 2018

Mr. John Dent, Jr.

Vice President-Nuclear and CNO

Nebraska Public Power District

Cooper Nuclear Station

72676 648A Avenue

P.O. Box 98

Brownville, NE 68321

SUBJECT: COOPER NUCLEAR STATION - NOTIFICATION OF NRC TRIENNIAL HEAT

SINK PERFORMANCE INSPECTION (05000298/2018003) AND REQUEST

FOR INFORMATION

Dear Mr. Dent:

On August 20, 2018, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite

portion of the Triennial Heat Sink Performance inspection at the Cooper Nuclear Station.

This inspection will be performed in accordance with NRC Baseline Inspection Procedure (IP) 71111.07, Heat Sink Performance, by two inspectors from the NRCs Region IV office

for one week.

In order to minimize the impact that the inspection has on the site and to ensure a productive

inspection, we have enclosed a request for documents needed for the inspection. The

documents have been divided into three groups.

  • The first group lists information necessary for our initial inspection scoping activities.

This information should be available to the lead inspector no later than July 23, 2018.

By July 25, 2018, the inspector will communicate the initial selected set of approximately

two to four risk-significant heat exchangers.

  • The second group of documents requested includes those items needed to support our

in-office preparation activities. This set of documents, including the calculations

associated with the selected heat exchangers, should be available no later than

August 6, 2018. This information should be separated for each selected component,

especially if provided electronically (e.g., folder with component name that includes

calculations, condition reports, maintenance history, etc.). During the in-office

preparation activities, the inspectors may identify additional information needed to

support the inspection.

  • The last group includes the additional information above as well as plant specific

reference material. This information should be available to the inspectors on

August 13, 2018. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the inspectors as the documents are

generated.

J. Dent 2

It is important that these documents be as complete as possible, in order to minimize the

number of documents requested during the preparation week or during the onsite inspection.

All requested documents are to be for the time period from the onsite inspection period back to

the last Triennial Heat Sink Performance inspection. If nothing addressing a request was done

in that time period, then the request applies to the last applicable document in the previous time

period.

We have discussed the schedule for this inspection activity with your staff and understand that

our regulatory contact for this inspection will be Thomas Forland of your licensing organization.

If there are any questions about this inspection or the material requested, please contact the

lead inspector, Wes Cullum, by telephone at 817-200-1563 or by e-mail at

Wes.Cullum@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

This letter, its enclosure, and your response will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No: 50-298

License No: DPR-46

Enclosure: Triennial Heat Sink Performance Inspection Request for Information

cc: Electronic Distribution

Request for Information

Triennial Heat Sink Performance Inspection

Cooper Nuclear Station

Inspection Report: 05000298/2018003

Inspection Dates: August 20 - 24, 2018

Inspection Procedure: IP 71111.07, Triennial Heat Sink Performance

Lead Inspector: Wes Cullum, Reactor Inspector

I. Information Requested by July 23, 2018:

1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting Safety-

Related Equipment, heat exchangers in order of risk significance.

2. Copy of heat exchanger performance trending data tracked for each GL 89-13 heat

exchanger.

3. List of corrective action program documents (with a short description) associated with

GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling, or heat exchanger

testing, for the previous 2 years or since the last heat sink performance inspection.

4. Copy of any self-assessment done on any of GL 89-13 heat exchangers done since last

heat sink performance inspection.

5. System health report(s) and maintenance rule system notebooks for all the GL 89-13

heat exchangers.

6. Copy of your responses for GL 89-13.

II. Information Requested by August 6, 2018:

1. For the specific heat exchangers selected:

a. Copies of the two most recent completed tests confirming thermal performance for

those heat exchangers which are performance tested;

b. Copy of system description and design basis document for the heat exchangers (as

applicable);

c. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the operation for

the selected heat exchangers;

d. Copy of the Updated Final Safety Analysis Report (UFSAR) sections applicable for

each heat exchanger; and

Enclosure

e. Provide a list of calculations with a description which currently apply to each heat

exchanger.

2. A schedule of all inspections, cleanings, maintenance, or testing of any plant heat

exchanger to be done during the onsite portion of the inspection.

3. Copies of procedures developed to implement the recommendations of GL 89-13,

(e.g., the GL 89-13 Heat Exchanger Program description).

4. Pages from the UFSAR for the GL 89-13 Heat Exchanger Program.

5. Maximum GL 89-13 heat exchanger inlet temperatures that still allow full licensed power

operation of the nuclear reactor. Please provide the documents that state these limits

(e.g., UFSAR or Technical Requirements Manual (TRM)) and the operating procedures

that ensure these limits are not exceeded.

III. Information Requested by August 13, 2018:

1. For the specific heat exchangers selected:

a. Provide the Design Basis Documents and Updated Final Safety Analysis Report

pages for the selected heat exchangers;

b. Copy of the design specification and heat exchanger data sheets for each heat

exchanger;

c. Copy of the vendor manuals including component drawings for each heat exchanger;

d. Copy of the calculation which establishes the limiting (maximum) design basis heat

load which is required to be removed by each of these heat exchangers;

e. Copy of the calculation which correlates surveillance testing results from these heat

exchangers with design basis heat removal capability (e.g., basis for surveillance test

acceptance criteria);

f. Copy of the calculations or documents which evaluate the potential for water

hammer or excessive tube vibration in the heat exchanger or associated piping;

g. List of engineering-related Operator Workarounds/Temporary Modifications for these

heat exchangers since the last Heat Sink Performance Inspection;

h. Copy of the evaluations of data for the two most recent completed tests confirming

the thermal performance of each heat exchanger;

i. Documentation and procedures that identify the types, accuracy, and location of any

special instrumentation used for the two most recently completed thermal

performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow

instruments or temperature instruments). Include calibration records for the

2

instruments used during these tests;

j. Copies of those documents that describe the methods taken to control water

chemistry in the heat exchangers;

k. Copies of the documents that verify the structural integrity of the heat exchanger,

e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection

results;

l. The cleaning and inspection maintenance schedule for each heat exchanger for the

next 5 years;

m. Copy of the document describing the inspection results for the last two cleaning and

inspection activities completed on each heat exchanger;

n. Copy of the document which identifies the current number of tubes in service for

each heat exchanger and the supporting calculation which establishes the maximum

number of tubes which can be plugged in each heat exchanger;

o. Copy of the document establishing the repair criteria (plugging limit) for degraded

tubes which are identified in each heat exchanger; and

p. Information regarding any alarms which monitor on-line performance.

2. For the ultimate heat sink (UHS):

a. Maintenance or inspection of inaccessible below-water portions of the UHS system

including results of underwater diving inspections and assessments of sediment

intrusion and/or removal of sediment; and

b. Documentation of inspections to verify no structural damage to intake structures that

would indicate loss of structural integrity and/or capacity.

3. For the safety-related residual heat removal (RHR) service water and diesel generator

cooling water systems (DGCWS):

a. Copies of the pipe testing and/or inspection program procedures, and the latest

completed surveillances and tests verifying structural integrity of the piping;

b. History during the last 3 years of any through wall pipe leak on the system and the

disposition documentation; and

c. Copies of the procedures to monitor, assess, and disposition active through wall pipe

leaks, including structural evaluations and/or planned corrective actions.

If the information requested above will not be available, please contact Wes Cullum as soon as

possible.

3

Inspector Contact Information:

Wes Cullum Chad Stott

Reactor Inspector Reactor Inspector

817-200-1563 817-200-1526

Wes.Cullum@nrc.gov Chad.Stott@nrc.gov

Mailing Address:

U.S. NRC, Region IV

Attn: Wes Cullum

1600 East Lamar Blvd.

Arlington, TX 76011-4511

4

ML18190A203

SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002

By: WLC Yes No Publicly Available Sensitive

OFFICE RI:EB1 C:EB1

NAME WCullum TFarnholtz

SIGNATURE /RA/ /RA/

DATE 07/02/2018 07/06/2018